Professional Documents
Culture Documents
Concept Select Report - REFERENCE ONLY
Concept Select Report - REFERENCE ONLY
Compression TLP
Topside Concept Select Report
Project Ormen Lange Compression TLP
Document Revision 02
ECCN EAR 99
Restricted
ECCN: EAR 99 Deminimus
This document is made available subject to the condition that the recipient will neither use nor disclose the contents except as agreed in
writing with the copyright owner. Copyright is vested in Shell International Petroleum Company.
© Shell International Petroleum Company 2011. All rights reserved.
Neither the whole nor any part of this document may be reproduced or distributed in any form or by any means (electronic,
mechanical, reprographic, recording or otherwise) without the prior written consent of the copyright owner.
Ormen Lange Compression TLP - Topside Concept Select Report Revision: 02
Revision History
Table of Contents
1. INTRODUCTION 11
2. PROCESS ENGINEERING 13
2.1. Concept select design basis 13
2.2. Subsea scope summary 17
2.3. Topside process description 22
2.4. Topside design conditions 29
2.5. Compression configuration / strategy 33
2.6. Cooling requirements 35
2.7. Process safeguarding 40
2.8. Operational considerations 43
2.9. Water handling 45
2.10. Hydrate formation mitigation and MEG storage 46
2.11. Sand handling 50
2.12. Utilities systems 52
2.13. Materials selection 59
3. MECHANICAL - ROTATING EQUIPMENT 63
3.1. Design conditions 63
3.2. Gas analysis 63
3.3. Base case design conditions 63
3.4. Sensitivity 1 design conditions 65
3.5. Sensitivity 2 design conditions 65
3.6. Sensitivity 3 design conditions 65
3.7. Selected design conditions for concept select phase 65
3.8. Compressor configuration 66
3.9. Compressor design 66
3.10. Compressor type selection 66
3.11. Compressor mechanical design 66
3.12. Compressor operation strategy 68
3.13. Compressor rebundling strategy 68
3.14. Compressor driver selection 71
3.15. Gas turbine compressor driver design 71
3.16. Offshore power generation 74
3.17. Compression system availability 75
3.18. Fuel gas consumption and CO2 emissions 82
3.19. Onshore power generation (power from shore) 86
3.20. Weights and dimensions 86
3.21. Condensate export pumps 95
3.22. Condensate recycle pumps 102
3.23. Seawater lift pumps (hazardous system) 107
3.24. Essential seawater lift pumps (non hazardous system) 111
3.25. Fire water pumps and drivers 115
3.26. Sub main / emergency generation 119
3.27. Pedestal cranes 121
3.28. MEG injection pump 125
3.29. Air compressor package 129
3.30. LP fuel gas booster compressor 131
4. MECHANICAL - PIPING AND LAYOUTS 135
4.1. General 135
4.2. Power from shore option 139
4.3. GT drive option 149
Tables
Table 3-1 Gas Composition for Compressor Design 63
Table 3-2 Design Conditions 65
Table 3-3 Sensitivity 2 Design Conditions 65
Table 3-4 Sensitivity 3 Design Conditions 65
Table 3-5 GT Driven Compressor Mechanical Design Details 67
Table 3-6 Electric Motor Driven Compressor Mechanical Design Details 67
Table 3-7 GT Driven Centrifugal Compressor Shaft Power Design 67
Table 3-8 Electric Motor Driven Centrifugal Compressor Shaft Power Design 68
Table 3-9 Nozzle velocity details - Sensitivity 2 – 64 million Sm3/d Compressor design 69
Table 3-10 Nozzle velocity details - Sensitivity 3 – 60 million Sm3/d Compressor design 70
Table 3-11 Gas Turbine Site rating details 72
Table 3-12 Compressor Gas Turbine Driver Selection 72
Table 3-13 LM2500+G4 operating margin 73
Table 3-14 Emotor driver operating margin 74
Table 3-15 Estimated Electrical Load list for Offshore PowerGen 74
Table 3-16 PowerGen Gas Turbine Site rating details 74
Table 3-17 Power Generation Gas Turbine Driver Selection 75
Table 3-18 Availability Study Configuration Cases 76
Table 3-19 Reliability, Availability and Production Efficiency results 77
Figures
Figure 1-1 Floating Concept Key Features 12
Figure 2-1 Mid-Case Production Profile 13
Figure 2-2 PQ Curve (Discharge pressures based on 90 bar(a) at Nyhamna) 14
Figure 2-3 Mid Case – Production Rate vs. Pressure 15
Figure 2-4 In-field Flow line Arrival Temperatures vs. Time 16
Figure 2-5 Blended Arrival Temperatures vs. Time 16
Figure 2-6 Ormen Lange Template Positions 18
Figure 2-7 Existing installation of A and D Templates 19
Figure 2-8 Final Installation with TTR Template and Flowlines 21
Figure 2-9 Inlet Riser/Flexible Jumper Arrangement 22
Figure 2-10 Riser Bay PDMS Snapshot 23
Figure 2-11 Sketch of Riser Bay Layout (plan view) 24
Figure 2-12 Ormen Lange Floating Compression Control Scheme 27
Figure 2-13 Ormen Lange Floating Compression Safeguarding PFS 31
Figure 2-14 Single Stage Compression Discharge Temperature Profile 33
Figure 2-15 Required Polytropic Head (Mid-Case Profile) 34
Figure 2-16 Extract from General Electric (GE) Proposal showing Re-Wheeling Approach 35
Figure 2-17 Mid-Case Power Requirements 35
Figure 2-18 Mid-Case Profile Cooling Demand 37
Figure 2-19 Mid-Case Profile Compressor Discharge Temperatures 38
Figure 2-20 Compression Power Required to Produce Mid-Case (with and without suction cooling) 39
Figure 2-21 Platform Layout showing Flare Stack in NE Corner 42
Figure 2-22 Minimum Pipeline Flow vs. Landing Pressure 45
Figure 2-23 Condensed water content in gas as a function of reservoir pressure for typical wells 46
Figure 2-24 Hydrate Formation Temperature Upstream of Inlet Separation 48
Figure 2-25 Hydrate Formation Temperature Downstream of Inlet Separation 49
Figure 2-26 Proposed Drains System Configuration 54
Figure 2-27 Ormen Lange Floating Compression Materials Selection Diagram 61
Figure 3-1 Vertically Split Back-to-Back Centrifugal Compressor Design 66
1. Introduction
This report is an update of the Ormen Lange Floating Compression concept selection report, issued in
October 2009 (37-1Y-NS-X15-00012) (Ref: 100). At that point a Tension Leg Platform (TLP) was
recommended and this was endorsed by an interim VAR 3. This updated concept selection report provides a
more comprehensive description of the TLP topside functionality and configuration based on more mature
design information and the process design also reflects the latest subsurface models. A brief description of the
overall concept is shown below but this report details only the topside concept. For a complete description of
the selected concept it needs to be read in conjunction with the Subsea (37-1B-NN-P15-00001 03M) and
Substructure (37-1Y-NS-X15-00032) Concept Selection Report (Ref: 63 and 99).
The selected floating compression concept for Ormen Lange is a steel TLP.
The design export gas capacity for the TLP is 60 million Sm3/d. This is delivered by 2 x 50% gas compression
trains each comprising two stages of compression. The compressor drivers will either be local Gas Turbines
(GTs) or electric motors (EM), with power supplied from the grid via a power cable form shore. The export
gas pressure from the platform will be in the range of 130-160 bar(a) depending on throughput. An onshore
arrival pressure at the Nyhamna plant of 90 bar(a) is assumed based on future third party field production
assumptions through Nyhamna.
The floating facility is fed by eight top-tensioned risers; two from each subsea template. A flexible jumper
connects each riser to the platform. Gas and bulk liquid is separated in the inlet separators prior to gas
compression. Condensate/ Mono Ethylene Glycol (MEG) from the separators is pressure boosted via pumps
to the associated Second Stage compressor discharge.
The facility is safeguarded by a 30 million Sm3/d flare system and the topsides is configured in a modular
arrangement with four major perimeter modules, a central riser bay module and a living quarters/helideck
module. A dedicated skiddable rig is provided on the topsides to perform riser installation. The platform will
be will be permanently manned.
The TLP is located in around 868 m water depth, approximately 600 m west of the existing trunk lines. The
TLP hull [including hull systems] weighing ca. 35,000 MT will be held to the seabed by four tendons per
column, each tendon founded on a large diameter driven pile. The TLP will support twelve 16” diameter
mono-bore carbon steel top-tensioned risers. The risers are tied back to a riser base template with suction pile
foundations. The riser base template provides the tie/backs to the subsea flow lines.
The subsea systems associated with the floating facility include one 16” diameter carbon steel flow line per
riser. There are eight import flowlines and four export flowlines in total:
Four import flowlines arrive from the south: two connected to Template A and two connected to tie-in points
on the infield flowlines from Template D. Four import flowlines arrive from the north: two connected to
Template B, and potentially another two connected to tie-in points on the infield flowlines from the mid-north
template.
Four export flowlines connect downstream at hot-tap points on the 30” trunk lines. An umbilical is provided
for controlling the Subsea Isolation Valves (SSIVs) on each flowline, and in the case of the sub-concept using
electrical drive motors, an electrical power cable extending from Nyhamna provides power from shore (refer
to Figure 1-1).
2. Process Engineering
This section describes process design work carried out for the Ormen Lange Floating Compression concept
select phase. Technical decision work is primarily documented within KDL’s, technical information notes
(TINs), and philosophy documents (safeguarding and control); these have been referred to where applicable.
To determine the associated compression suction and discharge pressures for the Mid-Case profile, a pressure-
flow (PQ) curve was generated (see Figure 2-2); “system” pressures refer to the pressures at the top of the
import and export risers. The “system out” pressures are based on IPM model predictions of export pipeline
backpressure, the suction/“system-in” pressures are calculated based on a compression power of 77 MW and
a compression adiabatic efficiency of 80%.
160
140
80
60
40
20
0
0 10000 20000 30000 40000 50000 60000 70000
MSm3/d
160 9
8
140
7
Pressure (bara), Flow MSm3/d
120
Compression Ratio
6
100
5
80
Suction Pressure 4
Discharge Pressure
60
Gas Export MSm3/d 3
40 Compression Ratio
2
20 1
0 0
2016 2018 2020 2022 2024 2026 2028 2030 2032 2034 2036
Year
It can be seen from Figure 2-3 that single export pipeline operation is expected to commence in early 2022
(green spike), and that compression ratio will become limiting from around 2027.
2.1.2. Template flow contributions
Figure 2-1 shows the flow profiles from individual templates over time. It can be seen that post-2018 the flows
from the A and D templates make up the majority of the production, these templates have broadly similar
production profiles. The production rates from B and C templates are also quite similar, but contribute less
than A and D.
2.1.3. Arrival temperatures
Refer to Figure 2-4.
OLGA has been used estimate the floater arrival temperatures, a “U” value of 25 W/m2°C was assumed for
this work. Early in floating compression, the A and B template fluids arrive at significantly hotter temperatures
than C/D due to their relative shorter distance from the platform. By 2030 production from all templates is
arriving within a closer temperature range (-4 to 12°C).
The arrival manifold arrangement provides the flexibility to route any riser to either inlet separator, the
operating temperature of each separator will therefore depend on the wells lined up. Figure 2-5 shows the
average arrival temperature assuming full mixing of all production (blue line), also shown is an extreme case
where hot A/B production is produced segregated from cold C/D (red and green lines).
60
50
Template A
B Template
40
C Template
D Template
30
Deg C
20
10
0
2016 2018 2020 2022 2024 2026 2028 2030 2032
-10
Year
60
50
Homogeneous Mix
A/B seg
40
C/D Seg
30
Deg C
20
10
0
2016 2018 2020 2022 2024 2026 2028 2030 2032
-10
Year
Gas is currently exported to Nyhamna via 2 x 30” pipelines, the end of each pipeline is connected via a pigging
loop template. Each production templates is comprised of multiple wells producing to 2 x 20” production
manifolds. Any well can be lined up to either 20” manifold. Each 20” template production header is tied into
one of the 30” export pipelines. In the case of the D template, 2 x 15 km flowlines are run from the template
Pipeline End Modules (PLEMs) to local PLEMs adjacent to each 30” export pipeline. Figure 2-7 shows the
current installation of the A and D templates. B is similar to the A template hook-up although it connects to
the pipelines via the pigging loop template.
To tie the A and B templates back to the floater, new connections will be made from each 20” template
production header (non-utilised header end) to two new PLEMs (with a piggable branch for pig
launcher/receiver (PLR) connection). From each PLEM, a new 16” carbon steel flowline will be run to Flow
Line End Terminations (FLETs) (with isolation valve) local to the subsea Top Tensioned Riser (TTR)
template, 16” tie-in spools with diverless connectors connect the FLETs to the TTR template. The TTR
template will contain 12 riser slots (eight import/ four export), and is effectively a mirror image of the riser bay
on the floater above.
For the D template, two new in-field flowlines will be tied into the existing PLEMs (adjacent to the export
pipeline tie-ins). These flowlines will also be run to two new FLETs (with isolation valve) adjacent to the TTR
template. The C template will be tied-back in the same manner as D, although it approaches from the North.
All eight new in-field flowlines and risers have been taken as 16” NB for topside design, however the size of
the C flowlines may only be 12” NB. Furthermore it is also possible that C may be taken over the B template
(the manifold design of the pigging loop template can permit this). In this event only six infield risers would
need to be installed. Based on predicted velocities there may also be scope to reduce the size of the A/B/D
16” import risers (FEED Optimisation).
The concept is based on a thin carpet of rock in the flowline sections where the lines are not in free spans.
This is in order to achieve maximum cooling of the gas from a compression efficiency point of view; the
requirement for rock carpets is not finalised. The flowlines are in general lying exposed on the seabed. Pre and
post-lay seabed intervention is required by excavation and rock dumping to ensure flowline integrity and
foundations for FLETs, PLEMs and spools.
Subsea Safety and Isolation Valves (SSIVs) will be provided for all in-field risers (to be confirmed by
Quantitative Risk Assessment (QRA) study); these SSIVs would be located within the subsea TTR template.
The main purpose of the SSIVs is to isolate potential gas backflow in case of e.g. riser rupture at the TLP. The
SSIVs are remotely operated via an umbilical connection from the TLP.
Four 16” NB export risers will be installed on the floater, based on predicted velocities there may be scope to
reduce the size of the export risers (FEED Optimisation).
There are one pair of risers allocated to each 30” main export pipeline. The export risers connect to the subsea
TTR template and then connect to four adjacent FLETs. 16” tie-in spools with diverless connectors connect
the FLET to the TTR template. From the FLETs, new 16” NB pipeline sections of around 600 m will run to
four new PLEMs (with one piggable branch for PLR connection) located adjacent to the existing 30”
pipelines. The PLEMs are welded to and installed with the flowlines. The flowlines are in general lying
exposed on the seabed. Pre- and post-lay seabed intervention is required by excavation and rock dumping to
ensure flowline integrity and foundations for FLETs, PLEMs and spools. Each PLEM will be tied-into the
associated export pipeline by hot-tap.
The location of the export flowline SSIVs is not finalised and is subject to the outcome of QRA study work.
These will either be located within the TTR subsea template, or alternatively will be located at the PLEMs local
to the export pipeline tie-ins. It may be desirable to locate the SSIVs local to the main export pipelines to
protect from the full inventory of the trunk line to Nyhamna being discharged beneath the platform (e.g. due
to dropped object), however this requires an additional longer umbilical(s).
The subsea TTR template riser slot arrangement will “mirror image” the layout of the topside riser bay. The
export risers are allocated to the centre block of four slots. The A and D templates will utilise the Southern
block of four slots, while the B and C risers will take the Northern block of four. The final envisaged subsea
layout is shown in Figure 2-8:
A MEG injection point is provided between each riser ESDV and inboard ESDV to allow pressure
equalisation prior to opening the riser ESDV; a flexible connection will be required to each MEG injection
point. All inboard ESDVs will have a smaller bore bypass line to allow pressure equalisation prior to opening,
and riser/pipeline depressurisation. MEG injection may also be required during depressurisation to prevent
hydrate formation.
Above each inboard ESDV is a blinded-off flange which can be used to allow connection of a temporary
vertical pig launcher/receiver (PLR); the temporary PLR will be installed on the upper deck and connected to
the afore-mentioned flange via a deck hatch. The riser and inboard ESDVs will be used to isolate the riser
during the installation.
Downstream of each topside jumper is a PLR bypass valve (normally open) which is used to direct flow
through the PLR during pigging operations. The kicker line ties in downstream of this valve, this line is likely
to require a flexible connector which will run along the underside of the riser bay roof and up through the
same deck-hatch referred to above (TBC). A connection to flare downstream of the kicker line take-off allows
depressurisation of the in-field flowline and riser to the platform flare system; note that this is not part of the
emergency depressurisation sequence.
Each import flowline then splits in two, with one connection to each separator inlet collection manifold.
Actuated routing valves allow Operations to select which separator collection header they want to route
production to. Each separator collection manifold is comprised of 2 x 24” (TBC) parallel headers which run
down either side of the riser-bay, these then common-up into a main 30” (TBC) separator inlet line. Figure
2-10 shows a Plant Design Management System (PDMS) screenshot of this arrangement (note that this is not
up-to-date with latest steelwork/piping and is intended to give an impression of relative layout only). Figure
2-11 shows a plan view layout sketch.
Export
Crossover
Valve
FI
C1 B1
X1 Y1
X2 Y2
D1 A1
D2 A2
The arrival separator pressure is regulated by a pressure controller which controls the speed of the associated
compressor driver (both compression stages are off a common drive shaft), the separator pressure floats on
the compressor suction. A connection from each separator gas outlet to flare is provided. A PIC/ Pressure
Control Valve (PCV) will vent gas to flare in the event of high separator pressure. The separator flaring facility
is primarily provided to facilitate kicking-off low pressure wells in later life and to aid with commissioning.
For the local power generation design option, a fuel gas take-off will be provided downstream of the separator,
this will be used for the first four years of operation. Beyond this date it will become necessary to take fuel gas
from downstream of the first stage compressors. Refer to section 2.12.4 for details of the fuel gas system.
Separated MEG and condensate enter the condensate export pumps (P-2001 A/B/S) where the pressure is
boosted to export conditions, these are 3 x 50% multi-stage variable speed drive pumps. P-2001S will act as a
common spare and can be lined up to either separator. Each pump is sized for a design flow of 113 m3/h and
1,020 m head in early life, however in around 2023 a cartridge change-out will reduce the capacity to around
55 m3/h and increase the head to around 1,400 m.
The separator level controller is split-ranged to the pump variable speed drive and a Level Control Valve
(LCV). It is envisaged that the LCV will normally modulate to control level, with the driver speed being step
changed when the control valve moves out-with a specified stroke range. Over time the pump driver speed
will steadily increase in line with the compression ratio. A standard minimum flow spillback loop is provided
upstream of the LCV and is routed back to the arrival separator inlet.
2.3.3. Compression
Refer to PFSs 37-1Y-NS-C72-00003/4 (Ref: 70) and KDL_SPh3-FI-04-03 Single or Multi-stage Compression
(Ref: 31).
Two-stage compression is needed to deal with the required compression ratio in later life, both compression
stages will however be installed from day one. Vendor proposals are based on both stages sharing a common
housing and driven off a common shaft. The re-wheeling philosophy is discussed in Section 2.5.
Gas from each arrival separator enters a First Stage Compressor Suction Scrubber (V-2701/2801). These are
approx. 3.2 m ID x 5.3 m vertical vessels which have SMSM internals (or equivalent). In the suction scrubbers
any condensed liquid or carryover is removed. The clean gas is sent to the first stage compressor where its
pressure is boosted to between 50 bar(a) – 105 bar(a) depending on the profile year. The temperature of the
gas leaving the First Stage Compressor can vary significantly and is a function of arrival temperature,
compression ratio and well line-up; it is expected to be around 60°C in early life, increasing to around 120°C
(based on max compression ratio of three).
The first stage compressor discharge gas is cooled in the First Stage After-cooler (E-2701/E-2801) to around
25°C; direct seawater cooling is employed. E-2701/2801 are sized for 20 MW, which satisfies both the process
cooling requirement and the recycle cooling duty. As the anti-surge recycle line is taken downstream of the
discharge cooler an additional hot gas bypass may be required to protect the compressor against sudden surge
(TBC). Because all the gas (with the exception of inter-stage fuel gas) from the stage one compressor enters
the stage two compressor, it may be possible to install a common anti-surge recycle line around both stages
(FEED optimisation). To avoid excessively cold temperatures downstream of the anti-surge control valve
(ASCV), a temperature controlled bypass facility is provided around the after-cooler to upstream of the ASCV
(requirement TBC).
Gas leaving the first stage compressor after-cooler arrives at the second stage suction scrubber V-2702/2802.
These are approx. 2.75 m ID x 5.0 m vertical vessels with SMSM internals. The clean gas is sent to the second
stage compressor which boosts the gas pressure to 130-160 bar(a) (subject to profile year). The second stage
after-cooler E-2702/2802 is sized for 20 MW, this ensures that export gas is cooled to less than 60°C and also
provides the second stage compressor recycle cooling duty. To avoid excessively cold temperatures
downstream of the anti-surge control valve ASCV, a temperature controlled bypass facility is provided around
the after-cooler to upstream of the ASCV (requirement TBC).
Liquid leaving the first and second stage suction scrubbers in each train is routed to a liquids collection header.
The first stage scrubber liquid is pumped to the header by P-2701/2801 (A/B), whereas the second stage
scrubber liquid will flow under pressure differential (on/off level control is envisaged for all suction
scrubbers). The liquids collection header contains a crossover valve, in normal operation this will be closed
and the liquids originating from a given compression train will be routed back to the associated inlet separator,
however the crossover valve can be opened to allow all liquid to be routed to either separator, or equally to
both.
Downstream of the second stage aftercooler is a PCV and associated discharge pressure controller. In normal
operation the PCV will be fully open (or bypassed) and the second stage compressor discharge pressure will
float on the export pipeline backpressure. The discharge PCV will be used to maintain backpressure on the
compressors if the export pipeline is at low pressure e.g. at start-up; it will also be used at start up to feed
forward gas to export in a controlled manner.
Liquid from the condensate export pump (P-2001A/B) is injected downstream of the second stage
compressor. It is desirable to have a homogeneous mix of gas/liquid upstream of the export manifold to limit
the potential for mal-distribution of liquids to the risers (refer to Ref: 59). The liquid will be injected as a mist
as far as possible.
2.3.4. Export manifold arrangement and risers
Refer to PFS 37-1Y-NS-C72-00005 (Ref: 39).
The cooled gas and recombined liquid is sent to the export manifold. This is comprised of two headers which
run the length of the well bay, each header is connected to 2 x 16” export risers (which both tie into the same
30” export pipeline), refer to Figure 2-11. A crossover valve connects these headers, but in normal operation
this is closed such that all the gas from each compression train is routed to only one 30” export pipeline, the
reasons for this line-up are discussed in Section 2.8. Operations can choose to open the crossover valve in
order to split all the gas equally to all risers or to direct it to specific risers, such as may be necessary during
later life when only a single 30” export pipeline is in use (refer to Section 2.8.1). Non-Return Valves (NRVs)
are installed on either side of the export manifold crossover valve. Without the NRVs the two 30” export
pipelines would effectively be linked with the potential for significant flow from one to the other as a result of
pressure equalisation.
For the GT-drive option, fuel gas import connections are installed on the downstream side of the NRVs. The
GTs will not be dual-fuel design to improve emissions, and therefore once the reservoir pressure drops below
around 40-50 bar(a), either fuel gas booster compression or fuel gas import from the export pipelines will be
required for start-up; at this stage the design base case is fuel gas import.
Tie-in points are included on each export header to allow for possible future gas recirculation from the export
header back to the template in-field flow-lines (see Figure 2-11). Gas recirculation may be necessary to mitigate
low in-field flowline velocities in later life (refer to Section 2.8.4).
The design of the export risers is fundamentally the same as the import risers. These will also be 16” NB.
2.3.5. Topside compression bypass lines
Refer to KDL SPh3-FI-01-05 Floater Inlet and Export Manifolding Configuration (Ref: 15).
A bypass facility will be provided around each separator/compression train. The bypass lines will allow arrival
fluids from each inlet separator manifold to be sent directly to the export header. As a result of the layout of
the riser bay (see Figure 2-11) the bypass lines will be relatively short connections with a remotely actuated
isolation valve(s).
These are primarily provided for use during commissioning and give the facility for continued partial
production in the event of a loss of compression.
2.3.6. Metering
Refer to Metering Philosophy (Ref: 65).
FLARE Note 1
FUEL GAS
TO EXPORT PIPELINE 1
A/S A/S TC
XC TC XC
PC
PT TT TC PC TO EXPORT PIPELINE 1
HOLD 1 TC
FT PT TT
FT PT TT PT TT
PC
FI
FI Note 1
E-2702
E-2701
SC
TEMPORARY PIG
LAUNCHER/RECEIVER
V-2702 K-2701
V-2701
K-2701
2nd STG
1st STG
Gap Control Kicker Line
Gap Control
LC
V-2001A LC
Suction
Crossover
LC
Valve
FLARE
P-2701 A/B Discharge
Crossover
Valve
FC FC FI
XI
P-2001A
PI TI
Pigging bypass
valve XI
E-2802
ESDV
E-2801
Note 1
MEG
K-2801
K-2801 V-2802
V-2801 2nd STG
1st STG
PI
V-2001B
TO EXPORT PIPELINE 2
Riser
ESDV
P-2801 A/B
P-2001B
FI
TO EXPORT PIPELINES
BDV
80 145 bara
both trains
BDV
FLARE
145
FUEL 60
GAS 2500# RISER A
ESDV 80 (HOLD 1) 1500# EXPORT PIPELINE 1
60 60
180 80
SP = 190
barg SP = 75 °C
SP = 130 barg SP = 130 bara (Note 3) ESDV
SP = 100 bara (Note 3) SP = 115°C RISER B
TSHH
PS HH
PSHH TSHH
PSHH EXPORT PIPELINE 1
P SHH
SP = 150 °C
SP = 150 °C E-2702
E-2701 25 25 TSHH
900# 1500# TSHH
165 130
110 130 180 120 241 180
60 60 V-2702
150 180
80 120 V-2701
2500# (HOLD 1) TEMPORARY PIG
160 60
LAUNCHER/RECEIVER
241 80
LSHH 110 K-2701 (2nd)
80 K-2701 (1st ) 150
900# 1500# LS HH
145 Kicker Line
25 25 25
ESDV
60 80 120 LSLL
120
V-2001A
900# 1500# LSLL 120 80 110
Suction 60 60 145 150
Crossover
80 80 120
Valve ESDV
145 900# 1500# ESDV
FLARE
80 150
145 241
60
80
P-2701A/B
Export
LSLL 60 Crossover Flexible
80 Valve
900# 1500# 150 ESDV
80 150 FSLL PS HH
241
145 241 1500#
TE 5
ESDV
P-2001A
ESDV
P SHH TSHH
P SHH Pigging bypass
PSHH TS HH
PSHH valve Flexible
E-2802
E-2801 TSHH
Inboard
TS HH
ESDV
V-2802
V-2801
MEG
LSHH
K-2801 (2nd)
K-2801 (1st) LSHH
V-2001B ESDV
LS LL
60 160
LSLL
TO RISER B 80 241
(EXPORT PIPELINE 2)
ESDV Riser
ESDV ESDV
P-2801A/B
LSLL
ESDV
FSLL PSHH
ESDV
P-2001B
TO EXPORT PIPELINES
60 60
80 80
arator.
Ormen Lange Compression TLP - Topside Concept Select Report Revision: 02
160
5
140
120 4
Compression Ratio
100
Deg C
3
80
Single Stage Discharge Temp
60 2
Homogeneous Suction Temp
Compression Ratio
40
1
20
0 0
2017 2018 2019 2020 2021 2022 2023
Year
It can be seen from Figure 2-14 that in late 2022 the single stage discharge temperature exceeds 150°C,
therefore sometime prior to this, multi-stage compression with inter-cooling will be required. At this time the
average floater arrival temperature is <20°C, therefore suction coolers will not help postpone this date.
2.5.3. Compression installation strategy
As shown above, multistage compression is not required until around 4-5 years into floater life. The project
strategy is however to install both compression stages from “Day 1”, with the aim of avoiding future heavy
lifts. This applies to both compression trains. Vendor proposals have been based on this design approach.
Note that the concept of installing 2 x 50% single stage compressors and switching these to an in-series set-up
in later life was considered in KDL_SPh3-FI-04-03 (Ref: 31). However the expected production deferment
associated with the reduction in volumetric capacity could be significant, and this option has been ruled out.
2.5.4. Re-wheeling requirements
Figure 2-3 shows the Mid-case profile compression suction and discharge pressures over time. Assuming an
equal compression ratio across each stage for all years, Figure 2-15 shows the compressor polytropic head
requirement over time.
18000
Compressor Differential Head
16000
14000
12000
10000
Head (m)
6000
4000
2000
0
2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
Year
Figure 2-15 Required Polytropic Head (Mid-Case Profile)
Based on vendor proposals, a re-bundle of both compressor stages is expected in 2022. Figure 2-16 shows an
extract from GE’s proposal showing the flow vs. head requirements across platform life (NB: inconsistencies
between this and Figure 2-15 relate to the fact that vendors calculated suction pressures based on actual
installed motor powers). The red bubble represents the first bundle configuration of each stage, both trains
would be run with this configuration until 2022. Re-wheeling would then take place in 2022 in order to cover
the operating points up until 2029 (blue bubble). Beyond this date only a single train is required to deal with
the production rates (pale blue bubble). Refer to Section 3.13.
2.5.5. Driver power and IPM modelling
Figure 2-17 shows the Mid-case calculated compression powers based on UniSim simulation of each year. The
calculated powers are somewhat less than the 77 MW assumed in IPM modelling. This is mainly because
UniSim models the effect of inter-cooling on overall compression efficiency. The powers in Figure 2-18 are
unlikely to be achievable for either the GT Drive or E-motor options based on vendor proposals. Each GT
driver is expected to be site rated to around 32 MW, with mechanical losses the shaft power will be less. For
the PfS option, the electric motors are each likely to be 36 MW rated, but will again deliver less with
mechanical losses accounted for.
The result of the above is that the suction pressures predicted by the PQ curve in Figure 2-2 are optimistic.
This means that for the Mid-case there would be a shorter plateau and a general deceleration in production.
For the purposes of concept select, the impact of this is that vessels have been sized slightly conservatively at
this stage. It is recommended that during the BFD engineering phase, IPM production profiles are re-run
incorporating compressor vendor proposal feedback.
Figure 2-16 Extract from General Electric (GE) Proposal showing Re-Wheeling Approach
Total Power
70
50
40
30
20
10
0
2016 2018 2020 2022 2024 2026 2028 2030 2032 2034 2036
Year
80.00
Total Compression Cooling Demand
70.00
60.00
50.00
Cooling (MW)
30.00
20.00
10.00
0.00
2016 2018 2020 2022 2024 2026 2028 2030 2032 2034 2036
Year
Figure 2-18 Mid-Case Profile Cooling Demand
2.6.3. Exchanger design duties
The peak compression cooling load per train is around 34 MW. Ideally as much of this cooling as possible
would be done with the inter-cooler (E-2701/2801) as the colder the inlet temperature to the Second Stage
Compressor, the more efficient second stage compression becomes. The following are however design
constraints:
1. Minimum achievable cooling temperature may be around 25°C (TBC).
2. First and second stage after-coolers must be large enough to provide the compressor recycle duties.
In full recycle the compressor cooling duty matches the shaft power delivered by the driver, both first and
second stage compressors are on a common shaft. It has been assumed for concept work that each
compressor stage will have its own recycle loop. Without mechanical losses, the GT option motor is site rated
to approx 32 MW, while the E-motor is site rated to around 36 MW. Preliminary compressor vendor curves
indicate that this power would be apportioned roughly 50/50 to each compressor stage in normal operation.
The maximum recycle power is not known at this stage, however clearly it cannot exceed the motor power.
Considering the above requirements, for preliminary design purposes a design duty of 20 MW has been
conservatively assumed for both the first stage and second stage after-coolers (both trains).
2.6.4. Requirement for first stage compressor suction cooling
Suction cooling could either be installed upstream of the inlet separators, or on the gas stream upstream, of
1st stage compression. The primary reasons for installing suction would be:
1. To limit the discharge temperature from the first stage compressor discharge to within materials design
temperature limits, normally 150°C for new Shell designs.
2. To improve the efficiency of overall compression.
The blue line in Figure 2-19 shows the expected 1st Stage Compressor discharge temperature over time (note
that post-2027 the trend levels and then drops-off with falling arrival temperature). On the basis of the
temperatures shown, suction cooling is not required for materials/integrity reasons.
140
Compressor Discharge Temperatures
120
100
80
Deg C
Stg 1 Discharge
Stg 2 Discharge Temp
60
40
20
0
2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
Year
70
60
50
Total Power Required with cooling
Power (MW)
30
20
10
0
2016 2018 2020 2022 2024 2026 2028 2030 2032 2034 2036
Year
Figure 2-20 Compression Power Required to Produce Mid-Case (with and without suction
cooling)
Figure 2-20 shows that suction cooling only adds any significant value in the first three years. The economics
of accelerated production during this period are difficult to calculate, however the following are
considerations:
1. Mid-case production is capped to 60 million Sm3/d in accordance with the current Ormen Lange Plan
for development and operation (PDO), this negates to a large extent any production acceleration benefit
during 2018/2019. Furthermore there is already excess power available when “on-plateau”. On this
basis the effect of suction cooling would be to extend the plateau slightly and also provide some
acceleration off-plateau. However a key point is that by 2020 the average arrival temperature is 28°C and
rapidly falling, therefore the returns diminish away quickly. It cannot be known at this stage if the PDO
will change in the future.
2. The major benefits of suction cooling are reduced fuel gas / emitted CO2 and some plateau extension.
Ref: 75 has previously looked at the economics of installing suction cooling vs. reduced fuel gas and
CO2 emissions (2008 profiles). On the basis of these factors alone suction cooling was not justified.
3. A design objective for the Ormen Lange floater is minimum facilities and manning.
Suction cooling - segregated production operating mode:
The A and B templates are located closer to the floater location, whereas C and D are further away. As a result
production from A and B will arrive relatively hotter (see Figure 2-4).
The FTHPs of the D wells, are also higher than from A/B/C. In spite of this the latest IPM simulations show
no benefit in processing D segregated, this is primarily because D production is forecast to be significantly less
than 50% of total production in all reservoir realisations.
In spite of the above, lining up wells to deliberately create a hot train and cold train could improve the
economics of suction cooling. This approach would increase the period for which suction cooling was
beneficial, and also improve the amount of cooling possible. Furthermore only a single suction cooler would
be needed. See recommendation 2 below.
Suction cooling recommendations:
1. On the assumption of an average arrival temperature to both trains, by inspection, suction cooling will
not provide a step change in achievable production, rather perhaps 2-6% over a window of two to three
years, and only if the PDO is changed to accommodate rates above 60 million Sm3/d.
While the economics have not been calculated, the additional equipment and OPEX is not viewed as
justifiable bearing in mind the drive for minimum facilities and manning.
It is recommended however that for now the conceptual design makes weight and space allowance for
suction coolers, as this issue will be looked at further in FEED.
Deliberately lining up a hot train and cold train has the potential to improve the argument for suction
cooling. Only a single suction cooler would be required, this could be manifolded such that it could be
lined up to either compression train.
2. Deliberately lining up a hot train and cold train has the potential to improve the argument for suction
cooling. Only a single suction cooler would be required, this could be manifolded such that it could be
lined up to either compression train.
It is recommended that further analysis of this scenario is carried out in FEED.
3. The risk of hydrate formation in suction coolers needs careful assessment. Direct seawater cooling could
result in low skin temperatures and it may be necessary to temper the seawater through recycling or
other means. Locating suction coolers upstream of the arrival separators should help protect against
hydrates as the presence of MEG significantly suppresses the hydrate formation temperature. However
this location will result in a higher design duty and possibly a higher design pressure, furthermore there
may be process control advantages in locating suction coolers upstream of 1st stage compression and
using these for recycle cooling. These design aspects to be looked at in FEED.
The flare system will have a continuous N2 purge. This results in lower greenhouse gas emissions than
continuous purging with fuel gas. A continuously lit flare will not be used, thereby eliminating emissions from
pilot gas. The flare ignition package will be a ballistic type ignition package driven by compressed air or
nitrogen. This will be activated by either high pressure in the Flare Knockout (KO) Drum or high gas flow.
A cold Low Pressure (LP) vent system will be used to vent nitrogen purge gas from compressor seals and flash
gas from the drainage systems.
2.7.2. Flare stack design
The flare system design capacity is set by emergency depressurisation which requires a peak rate of
30 million Sm3/d, refer to Section 2.7.4 below.
A vertical flare stack will be situated on the NE corner of the upper deck. This location is dictated by the
prevailing wind direction. Figure 2-21 shows the position of the flare stack and Flare KO drum relative to the
overall topsides. The acceptable radiation limit during emergency depressurisation is 4.73 kW/m2
(API RP 521 (Ref: 103) / ISO 23251 (Ref: 108)) taken from the nearest manned location. Fire Radiation
Explosion and Dispersion (FRED) analysis indicates that on this basis a flare stack height of 105 m is required
based on a design capacity of 30 million Sm3/d.
2.7.3. High Pressure (HP) flare header and KO drum sizing
Preliminary sizing calculations indicate that a 24” flare header and stack will be required for the design rate of
30 million Sm3/d. A horizontal KO drum with preliminary dimensions of 5.5 m ID x 13.75 m T/T is required.
The operating pressure in the KO drum at the peak flaring rate would be approximately 8 bar(a). The design
pressure of the drum has been set at 11 bar(a).
2.7.4. Emergency depressurisation philosophy
See Ref: 73 for details.
The emergency depressurisation system will be based on simultaneous and automatically initiated
depressurisation of the entire plant. Sequential depressurisation would require equipment in adjacent fire zones
to be protected by a combination of layout, firewalls, fire-proof installation, drainage and deluge. This
approach is not usually practical on an offshore platform.
Activation of emergency blowdown will be automatically initiated by the Fire and Gas (F&G) system.
Sufficient time for sectionalising valves to close will be allowed for before opening of blowdown valves. Full
platform depressurisation shall also be possible from the Central Control Room (CCR).
The emergency depressurisation criteria has been taken as depressuring to 100 psi in 15 minutes based on
API 521 (Ref: 102) guidance. This gives a peak flare load of 30 million Sm3/d.
Alternatively the total gas produced could be allowed to be shared among all the export risers. This might be
desirable if only one compression train is operating in order to minimise pipeline backpressure and maximise
production. A consideration in doing this however is the potential for an uneven split of gas and MEG to each
export line (see Ref: 59), operational experience in conjunction with use of the mitigations above may be
required to assess whether this is feasible.
As this crossover valve will effectively link the two export pipelines, to avoid full pressure equalisation
between them, two NRVs will be installed on either side of the crossover valve.
Export liquids crossover valve:
In the event that only a single compression train is in use with both separators, this crossover facility allows
the total liquid from both separators to be injected into the discharge of the online Second Stage Compressor.
The design intent is to create a homogeneous mixture of gas and all liquid prior to the flow splitting to the
risers.
2.8.2. Late life well start-up
In late field life it may be necessary to “kick wells off” to a lower arrival pressure than can be achieved by the
compressors. As there is no test separator this would be done by de-pressuring one of the main separators to
low pressure (note that in late life there may effectively be a spare separator). The separator and infield
flowline would be depressurised and, the produced gas routed to flare until stable well flow is established.
Each separator has a flare connection and PIC/PCV specifically for this purpose.
2.8.3. Fuel gas supply
The following is not applicable to the PfS option. Refer also to Utilities Section 2.12.4.
A fuel gas supply pressure of approx. 40 bar(a) is required for the compressor GTs (vendor to confirm). In
early life fuel gas will be taken from the gas leaving the arrival separators as these vessels will operate at
pressures higher than this until sometime between 2021-2022. After this date fuel gas will be taken from the
discharge of the first stage compressors which should operate at >50 bar(a) even in late life. Note that if a
common anti-surge recycle design is utilised for both compressor stages, the impact of drawing fuel gas inter-
stage should be assessed.
A third fuel gas supply connection will be taken from each export header downstream of the crossover valve
NRVs. This is intended for start-up fuel gas import. The GTs will not be dual fuel design in order to minimise
emissions, therefore either fuel gas booster compression or gas import from the export pipelines will be
required. This decision is not closed out yet.
2.8.4. Gas recirculation
Gas is exported to Nyhamna via 2 x 30” 120 km export pipelines. When the export gas rate in a pipeline falls
to below a critical flow, unstable production and large liquid surges when ramping up from low flow can
occur. Figure 2-22 shows the relationship between minimum flow required and landing pressure. For a landing
pressure of 90 bar(a), the minimum pipeline flow required is approx 20 million Sm3/d. Note that these are
conservative values which can likely be challenged during actual operation.
Based on Figure 2-22 in around 2023 it is forecast that production will be reduced to one export pipeline only
in order to maintain the required flow. Later in life (perhaps around 2027), gas recirculation from Nyhamna
may also be required to maintain minimum flow in the single export pipeline. The redundant export pipeline
would be used to send the gas from Nyhamana. The effect of both these actions is that the floater export
pressure tends to remain high despite falling net production as shown in Figure 2-3.
Similarly, the in-field flowlines may also be at risk of excessive liquid hold-up at low velocities. Tie-ins will be
provided on each export gas header to allow future gas recycling around each template. In this scenario all
subsea template wells would be lined up to only one in-field flowline, with the other flowline being used to
send platform gas back to the template.
10
T yp ic a l D -w e ll
Condensed water content m3/MSm3 gas
T yp ic a l A w e ll
T yp ic a l B w e ll
8 T yp ic a l C w e ll
0
0 50 100 150 200 250 300 350
R e s e rvo a r p re s s u re [b a ra ]
Figure 2-23 Condensed water content in gas as a function of reservoir pressure for typical wells
MEG injection points will also be provided on high risk sections of the topside process for possible hydrate
remediation, however these will rely on temporary hook-up of MEG injection facilities.
200
190 Hydrate formation temperature
180 upstream of separators (I.e. Including
MEG)
170
160
150
140
130
120 FC-005 type 1 Hydrate
Pressure [bar]
70
60
50 Normal Operating range
40
30
20
10
0
-30 -25 -20 -15 -10 -5 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70
Temperature [C]
200
190
180
170 Arrival temperatures of gas from
160 C and D templates through field
Hydrate formation temperature life
150
upstream of separators
140
130
120 Hydrate formation temperature 2017 FC-005 type 1 Hydrate
Pressure [bar]
20
10
0
-30 -25 -20 -15 -10 -5 0 5 10 15 20
Temperature [C]
During start-up MEG will be injected downstream of the riser ESDVs for pressure equalisation prior to
opening of the riser ESDV. During depressurisation of the flowlines / risers it may also be continuously
injected.
• Expectation level for sand production (P50) is: 20 µm particle size, 35% quartz at 3 ppm wt continuous
production.
• Design case (worst case) for sand fines production is: 44 µm particle size, 100% quartz at 5 ppm wt
continuous production.
• In the event of a gravelpack failure:
Partial Failure: Particle Size: 150 µm
Mineralogy: 100% quartz
Rate: 50 ppm wt
One of the largest risks, is that when the production system downstream the well is shut in, this could lead to
settle-out of sand at the low points (e.g. at the base of the risers). If the design of the system caters for shut-
down of the flowline and riser system, a mechanism is required, so that fluid flow (either forward or reverse)
can be maintained, in order to avoid formation of sand-plugs during settle-out.
2.11.4. Assessment of requirement for dedicated topside sand removal system
For longer periods of high level sand production, preliminary calculations have shown that the following
concentrations may be tolerable without the need for sand removal upstream of the inlet separator, provided
facilities are designed optimally in terms of material specification, equipment specification and line sizing to
maintain minimum velocities to avoid deposition but ensure erosion rates are within acceptable levels:
< 1,600 ppm at 150 microns particle size
< 400 ppm at 890 microns particle size.
The system is not expected to produce continuous quantities of sand and fines. A dedicated handling system is
therefore not required.
2.11.5. Recommendations
It is recommended that the floating compression system incorporates sand monitoring and sampling points on
the flowlines and condensate lines in order to provide additional safeguarding against the effects of sand.
The floating compression system should be designed or have an operating philosophy, such that sand plugs in
flowline riser bases resulting from gravel pack failure can be avoided or flushed out. This should be looked at
in more detail in FEED.
2.12.1.2.Essential users
Within the non-hazardous seawater cooling users system, most of the users are identified as “Essential
services”, these include:
1. HVAC
2. Power generator
3. Sub-main generator
4. Firemain pressurisation.
Based on this in the event of process shutdown or loss of power, the non-hazardous seawater lift pumps must
continue to run. This will be achieved by connecting the non-hazardous seawater pumps to the emergency
diesel power generation system.
(Note that the air compressor and emergency generator will be air cooled and thus independent of the
platform power and cooling systems.)
2.12.1.3.Specific Design Features
Electro-chlorination:
The electro-chlorination system will be designed to treat the seawater systems so that the continuous residual
concentration (equivalent free chlorine) is 0.5 ppm (vol/vol), see Section 2.12.8.2.
Minimum flow protection:
The seawater pumps will be of fixed speed type. The minimum flow should be controlled on flow (as advised
by Norsok) not pressure (following the Shell DEP would lead to minimum flow protection on pressure).
Filters:
Either 2 x 100% filters or 1 x 100% filter with online backwash shall be installed within each seawater system.
Shutdown valves:
The gas coolers will be equipped with shutdown valves on the seawater side to enable isolation in case of tube
rupture or hydrocarbon leakage into the system.
Layout requirements:
The proposal is to have electro-submersible pumps within a pump caisson for both seawater systems. In
accordance with Norsok where seawater is used for process cooling it is recommended to dump seawater to a
caisson at a higher elevation than the high point in the seawater system. By applying this solution the use of a
dump valve is avoided and the potential for vacuum is reduced.
2.12.2. Drains System
2.12.2.1.Open Drains System
Refer to PFS 37-1Y-NS-C72-00013 (Ref: 43).
The open drain system has been designed in accordance with Norsok standards by adopting the following
design features:
• Two completely segregated systems are installed to collect drainage from both hazardous and
non-hazardous areas.
• The hazardous drains are also segregated by the use of firewater seal boxes. This prevents the spread of
fire from one fire area to another.
HP Flare
Knockout
Drum To Atmospheric /
Cold Vent
LT
To Process
(Inlet Separators)
To reclaimed
oil sump
LT N2
LT
Non -
Hazardous
Hazardous
Drains
Drains
LT
Non -
Hazardous
Hazardous
Clean water Areas Drains
Areas Drains Clean water
overboard Sump overboard
Sump
20 m3
Closed Drains Vessel TOTE TANKS (HOLD)
The open drains from non-hazardous areas and from hazardous will be completely segregated. This avoids the
possibility of liquids or vapours from hazardous areas migrating to non-hazardous areas. From Ref: 11, the
Open Non-Hazardous Drain (ONHD) may be routed to a dedicated non-hazardous caisson or to a collection
tank. Among the main advantages given for collection tanks rather than caissons are: reduced cost, easier
access and maintainability and the possibility to measure the discharge flow and quality. A main disadvantage is
potential for accumulation of solids in the vessel. It is not anticipated however that there will be a large
quantity of solids collecting in the system, therefore a collection sump (30 m3) is proposed (T-5601).
The water collected in the ONHD collection tank will be discharged overboard, an oil skimming pump will be
provided in the sump tank; no produced water treatment system is proposed. Sampling points will be provided
so that the quality of the water being discharged may be monitored. As the quantities of drains water are
generally small in comparison with typical produced water, there is normally no requirement to install on-line
continuous metering or quality measurement.
The skimmed hydrocarbons from the ONHD tank will be routed to the Open Hazardous Drain (OHD)
sump. An actuated valve and NRV are likely to be required to protect against backflow, a positive
displacement pump may also be a requirement to again limit any backflow.
The design of the (OHD) system will be similar to the ONHD. A separate collection sump T-5602 (also
30 m3) will collect the drain fluids. Clean water will be dumped overboard, skimmed oil will be sent to the
Closed Drains Vessel V-4301, similar backflow protection to that stated above for the ONHD skimming line,
will be required. In accordance with Norsok standards, the hazardous open drain will be continuously purged
with nitrogen in order to prevent ingress of oxygen into the tank.
2.12.2.2.Closed Drains System
Refer to PFS 37-1Y-NS-C72-00012 (Ref: 42).
In the floater design there is no LP flare system and depressurisation will take place via the HP flare system
(although it may be possible to achieve some depressurisation within the process). During maintenance
campaigns, when condensate is drained from depressured vessels, a closed drains drum with some pressure
capability is seen as a better and safer alternative than utilising a hazardous open drain to atmospheric tank.
Any line connecting a process vessel to the closed drains system will have positive isolation.
Closed drain drum (V-5701) design
The closed drains drum will be sized in order to drain down the process vessels on the platform, assuming that
these have been emptied to the low low liquid level. This would require a hold-up capacity of around 20 m³;
there may be scope to reduce this in FEED by optimisation around drainage/shutdown management.
The closed drains drum is vented via the atmospheric vent header. Shell DEP (Ref: 11) requires a minimum
design pressure of 3.5 bar(g) for the “closed drains drum”. This eliminates the risk of a rupture in the event of
a deflagration.
The closed drains drum will be emptied by the Closed Drain Drum Pump P-5701A/B, this will route fluids to
the Flare KO drum which is the lowest pressure part of the process. From the Flare KO Drum the liquid is
pumped back to the main inlet separators.
An option to pump out the closed drains drum to tote tanks which can be lifted to a support vessel will also be
included in the design.
2.12.3. Flare and vent system
Refer to PFS 37-1Y-NS-C72-00014 (Ref: 44).
A single flare system is proposed without flare recovery facilities. An atmospheric vent is included in the
design for venting of the closed drains vessel and compressor seal gas.
Flare gas recovery facilities have not been included. The hydrocarbon content in the seal gas from the
compressors is likely to be negligible in normal operation. The quantity of hydrocarbons resulting from leaking
relief valves is also likely to be very small. From a Greenhouse gas emissions and Energy Efficiency
perspective the continuous running of a recovery compressor is likely to create more CO2 emissions than will
be saved by recycling the gas back into the fuel gas system (refer to Ref: 67).
The flare system will have a continuous nitrogen purge in order to avoid a potentially explosive composition
due to air ingress. Using nitrogen as the purge gas will result in lower greenhouse gas emissions than
continuously purging with fuel gas. This analysis takes into account the CO2 emitted per kg of N2 produced
and also the effect of emitting methane directly to the environment (which has the effect of 22 times the
equivalent amount of CO2).
Flare metering will be used to monitor the flow of hydrocarbon emissions from the HP flare system. As the
flare will be continuously purged with nitrogen the metering system would be required to differentiate between
nitrogen and hydrocarbon.
The flare ignition package will be a ballistic type ignition package driven by compressed air or nitrogen. The
design of the flare and vent system is discussed further in the Safeguarding philosophy (Ref: 73).
2.12.4. Fuel gas system
Refer to PFS 37-1Y-NS-C72-00015 (Ref: 45) and Ref: 71.
This unit is not required for the “power from shore” design option. Design work carried out for the fuel gas
system is summarised in Ref: 71. This work was based on 2009 production profiles, however the required
platform power was similar ballpark to that required by latest profiles. In FEED this should be formally
updated. In Ref: 71 the arrival pressure assumed upstream of fuel gas letdown (120 bar) was higher than
expected for latest design data (80 bar(a)). This is likely to reduce the pre-heating duty stated below (to be
updated in FEED).
Key design aspects are summarised below:
• The fuel gas system shall have sufficient volume to enable a smooth changeover to an alternative fuel
source. 30 seconds of hold-up time above PSLL has been provided. Fuel gas scrubber dimensions are
approximately 1,450 mm ID x 3,100 mm T/T. There are no specific Norsok or Shell guidelines on the
minimum required hold-up capacity time.
• Actual superheating requirements will be determined by turbine vendor, and are typically 20°C to 30°C
above its water dew-point and 25°C to 35°C above its hydrocarbon dew-point. In design work it was
assumed the fuel gas will be superheated by 20°C by H-4501A. A duty of around 350 kW is estimated in
Ref: 71. Shell DEP requires at least 20°C superheating of the fuel gas.
• Fuel Gas Filter. A dedicated filter separator has been provided on the fuel gas supply to each gas turbine
at the turbine skid limit. Shell requirements are similar.
• Process shutdown valves. Process shutdown valves are required at the following locations: in the main
supply line to the fuel gas system and in all fuel gas supply lines to the gas turbines. Similarly, Shell
requires an automatically operated ESDV on each fuel gas line to each user prior to entering a safe area.
The line between the ESDV and the fuel gas user should be automatically depressurised on shutdown.
In addition to the above requirements, pre-heating is required to protect against hydrate formation upon
pressure letdown. Ref: 71 estimated a pre-heating duty of 450 kW.
The fuel gas system will be spared such that there will be 2 x 100% trains. This redundancy is installed in order
to maximise overall availability. It may be possible to justify a single fuel gas scrubber vessel, with sparing
installed on the pre-heater and super-heater. This is an optimisation for FEED.
2.12.5. Inert gas system
Refer to PFS 37-1Y-NS-C72-00016 (Ref: 46).
The inert gas system has been designed to supply nitrogen for the following users:
• Compressor seals
• Flare header purging
• Atmospheric vent header purging
• Hazardous Open Drains Sump
• Utility stations
• MEG Storage blanketing (TBC).
The system has been designed for a total capacity of 350 Sm³/h. The main nitrogen user will be the gas
compressor seals which require a normal flow of approximately 120 Nm³/h total flow.
The system is designed to provide a nitrogen purity of 97 vol% at design capacity of 350 Sm³/h. This satisfies
Norsok requirements of 97 vol% at normal operation and 95 vol% at peak flowrate.
The inert gas plant should, because of the risk of a non-breathable/suffocating atmosphere, be located in a
naturally ventilated area. Oxygen rich gas shall be ventilated to a location where personnel have no access.
Critical consumers, such as the compressor gas seals, need to have a separate back up such as from Nitrogen
bottles. Low priority users such as the utility stations will be automatically shut off favouring high priority
users.
2.12.6. Diesel system
Refer to PFS 37-1Y-NS-C72-00017 (Ref: 47).
The system has been designed to treat raw diesel and meet the specification of the following users:
• Firewater pumps/generators
• Emergency Generators
• Sub-main generators
• Life boat stations and utility stations.
Deck cranes will be powered by electric driven motors rather than diesel driven motors.
The design consists of the following features as recommended by Norsok:
• four days storage capacity with continuous consumption
• minimum flow protection for centrifugal pumps
• day tanks for large consumers
• filtration and water removal
• 2 x 100% diesel transfer pumps
• 2 x 50% raw diesel tanks (75 m³ each)
• 1 x 100% treated diesel tanks (50 m³).
Continuous consumption is based on 2 m³/h of diesel. The diesel requirements for each of the firewater pump
generators, emergency and sub-main generators is approx. 0.63 m³/h. Therefore, the total storage capacity of
200 m³ equates to more than 13 days of storage capacity (assuming only the emergency generator was in
operation). With reference to Shell’s code of practice document on diesel oil systems for offshore installations
(Ref: 13), typical designs in the North sea are based on between 8 and 11 days of diesel storage. Therefore, a
total storage capacity of 200 m³ is adequate.
2.12.7. Compressed air system
Refer to PFS 37-1Y-NS-C72-00018 (Ref: 48).
The compressed air system will supply clean, dry, oil free air to the following users:
• Air operated instruments and valves
• Purging of electric motors
• Nitrogen generation package
• Living quarters
• Plant air utility stations for use of air tools.
A capacity of approximately 2,734 Nm³/h is required. Concept select work has assumed 3 x 50% Atlas Copco
ZT 200 machines, each capable of supplying 1,711 Nm³/h.
The air is dried to a water dew point of –40°C within the air drier package D-6301 A/B. Norsok standards
require that the air be dried to a water dew point of –25°C within the air drier, however Shell DEP requires –
40°C in order to be 10°C below the lowest expected ambient temperature.
From Norsok, in case of low system pressure, low priority users such as plant air should be automatically shut
off favouring higher priority users such as instrument air. The design will shut off the supply to the plant air
system first when the pressure drops to 8.5 bar(a) (normal operating pressure is 9.5 bar(a)). Production users
such as purge air to electric motors will be supplied with air until the pressure in the system drops to 7.5 bar(a).
The safety critical items such as the flare ignition package, living quarters and instrument air have the highest
priority and will remain supplied with air until full platform shutdown occurs when the air pressure reaches
5.5 bar(a) (The flare ignition package should also have an independent back-up supply).
The air receiver V-6301 (2.6 m ID x 4.6 m T/T) is sized to provide 5 minutes of instrument air at operating
pressure. The hold-up time is based on the supply to the safety critical users only. Norsok standards require a
5 minute hold-up time but do not specify that the hold-up time applies only to safety critical items.
The receiver is sized to allow for a flow of approximately 650 Sm³/h between 7.5 bar(a) and 5.5 bar(a). The
critical user flowrate has not yet been identified so it is not clear whether this is sufficient.
The Shell Code of Practice (Ref: 75) states that the sizing of the receiver shall be based on the design quantity
of utility air required. The design flow of Utility air has been estimated as 2,394 Nm³/h. This would result in a
much larger receiver vessel, 3.4 m ID x 9.6 m T/T.
The size of the air receiver will have to be reviewed in FEED when more information is available on the
required flowrate of critical users and Norsok requirements are clarified. An additional wet air receiver
VL-63-0002 is required as advised by the vendor Atlas Copco. The capacity of this vessel is 6 m³.
Sparing requirements given by Norsok are as follows:
• Two compressors are required to meet the total air requirement
• Instrument air will be supplied with 100% sparing for air drying.
Both of these requirements are met by the current design. In accordance with Shell guidelines (Ref: 75) each
drier package will contain two driers, one operating and one in regeneration/stand-by mode.
2.12.8. Chemical injection
Refer to PFS 37-1Y-NS-C72-00019 (Ref: 49).
2.12.8.1.MEG Injection
Refer to Section 2.10 for details. A 50 m3 MEG Storage tank T-4401 (operating volume) and injection pumps
will be provided. It is envisaged that MEG will be topped up via a supply vessel. Nitrogen blanketing of the
MEG storage tank is assumed (TBC). As this will be of process quality, there is the potential for oxygen
ingress into the MEG. However since topside MEG would be injected only intermittently and at low volumes
this may not be a concern (to be reviewed in FEED).
(Note that cryogenic nitrogen is used at Nyhamna for blanketing to minimise the potential for oxygen ingress
into the process due to the adverse impact of magnetite fouling of the production system and disruption of the
forced precipitation of iron carbonate in rich MEG storage.)
2.12.8.2.Additional Chemicals
It is not known at this stage exactly which chemicals will be required for the process however, possible
chemicals required are as follows:
• Demulsifier
• Scale Inhibitor
• Biocide.
These will be stored in a common compartmentalised tank (T-4402) with downstream electrically driven
positive displacement pumps.
The electro-chlorination system will be designed to provide a continuous design dosing concentration
(equivalent free chlorine) of 2.0 ppm (vol/vol). The sodium hypochlorite will be added to the seawater intake
as per Norsok standards (Ref: 117). The maximum residual concentration (equivalent free chlorine) in the
seawater will be 0.5 ppm (vol/vol).
2.12.9. Fresh water system
Refer to PFS 37-1Y-NS-C72-00020 (Ref: 50).
2.12.9.1.Capacity of the freshwater system design
The freshwater system produces both potable and service water to be used on the floating compression
station. The potable water capacity has been based on 80 persons with a rate of 300 L/day/person. This
equates to 24 m³/day.
The capacity of the potable water pumps P-5301 A/B, is 25 m³/h (2 x 100%). This is much higher than the
average daily consumption of potable water and will cater for peak loads. (This allows for a 27 person shift
change based on shower usage of 15 L/min per person).
As per the potable water system, the service water pumps will be capable of producing 25 m³/h to cope with
peak loads. The service water system will supply the following users:
• Utility stations
• Diesel centrifuges (TBC)
• Chemical injection system.
The service water design capacity has been taken as 30 m³/day for concept select, however it is known that
there should be scope to reduce this in FEED.
2.12.9.2.Comparison of design with Norsok standards
The design of the fresh water system complies with Norsok standards (Ref: 117). As per Norsok standards the
system is designed as follows:
• The Potable water is sterilised in a Ultraviolet (UV) steriliser
• The fresh water is dosed with hypochlorite upstream of the potable water tanks
• Imported fresh water will also be dosed with sodium hypochlorite and pass through a UV steriliser
• Separate storage tanks are supplied for potable and service water
• The water will be in continuous circulation in both systems in order to prevent freezing in the lines
• Potable water storage (2 x 60 m³) is designed for six days storage at average daily demand. This exceeds
the Norsok requirement which calls for four days storage
• The service water tanks (2 x 100 m³) are designed for more than six days supply. These are probably
oversized and in FEED storage volume may be reduced (optimisation).
TO EXPORT PIPELINE 1
Duplex
Duplex 22% Cr
22% Cr LTCS
Note 1 + 3mm
Note 1
Duplex CA
Duplex 22% Cr Duplex Duplex 22% Cr E-2702 TO EXPORT PIPELINE 1
22% Cr 22% Cr
E-2701
FLARE
16 clad
Discharge
Crossover
Duplex 22% Cr Valve
Duplex 22% Cr
P-2001A LTCS + 3mm
Duplex CA
22% Cr
A XI
LTCS + 3mm CA
E-2802
ESDV
E-2801
Carbon Steel + 6mm
V-2001B
TO EXPORT PIPELINE 2
P-2801 A/B
P-2001B
Carbon Steel + 6mm
TO EXPORT PIPELINES
case, a 60 million Sm3/d condition, reducing to 3.3 million Sm3/d, using a decreasing inlet pressure from 75 bar(a) to a minimum of 14.6 bar(a).
eration efficiency and resultant CO2 emissions. See Table 3-2.
4 million Sm3/d condition, reducing to 3.3 million Sm3/d, using a decreasing inlet pressure from 75 bar(a) to a minimum of 14.6 bar(a). See Table 3-3
o 74 MW of electrical power offshore to drive two electric motor compressor trains. This available power enables a lower inlet pressure to be utilised in early field life. This design
n Sm3/d, using a decreasing inlet pressure from 70 bar(a) to a minimum of 14.6 bar(a).
d power from shore power generation and resultant reduced CO2 emissions. See Table 3-4.
d to be uneconomic; therefore a 2 x 50% unspared compression trains have been selected as the optimum configuration for the floater concept. Refer to document 37-1Y-NS-M15-
on & Driver Selection Study (Ref: 94) for further details.
d using the design conditions detailed in Sensitivity Case 2 and Sensitivity Case 3. Vendor information and internal design tools have been used to define the compressor designs.
driven options are radial barrel type (vertical split), single casing design two stage back-to-back centrifugal compressor designs, suitable for up to eight impellers. An illustration of a
or design is detailed below in Figure 3-1.
-Gen (Ref: 4). Design margins are applied to the compressor shaft power. A standard 2% for a gearbox, an API margin of 4% and a DEP margin of 10% are applied to calculate the
e 3-8 for further details.
ve an identical operation strategy. Two compressor trains are required from years 2018 to 2029 and one train from 2031 onwards.
he compressor requires to be re-bundled twice over the field life, increasing the number of impellers from two per stage to four per stage. The compressor is a single casing back to
and eight impellers respectively. The compressor wheel diameters also increase in years 2022.5 to 2029 In years 2031 to 2034 the impeller wheel diameters are again reduced to
Ormen Lange Compression TLP - Topside Concept Select Report Revision: 02
The compressor and gearbox are both the same configurations in years 2018 to 2029. In years 2031 and 2034
the gearbox is required to be changed to increase the speed of the compressor. An additional re-bundle and
speed change is used to reduce the compressor recycling, this would also be an alternative operation mode if
the third re-bundle was not completed.
3.13.1. Nozzle velocities sensitivity 2
At a 64 million Sm3/d flow rate, 75 bar(a) inlet, utilising a 2 x 50% compressor system design, the compressor
nozzles velocities are detailed below in Table 3-9 over the field life.
GT
POINT Section Vin Vout
S1 32 32
2018
S2 27 28
S1 32 32
2019
S2 26.8 28.1
S1 32 31.6
2020
S2 26.5 27
S1 32.3 30.8
2021
S2 25.9 25.3
S1 31.6 29.11
2022
S2 24.5 23.12
S1 27.5 21.8
2023
S2 16 14
S1 30.4 27
2025
S2 17 13.1
S1 27.7 18
2027
S2 14.3 10
S1 36 21
2029
S2 15.9 9.2
S1 21 17
2022.5
S2 14.1 14.1
S1 27 15.7
2031
S2 11.45 6.85
S1 17.6 10.86
2034
S2 8 4.6
Table 3-9 Nozzle velocity details - Sensitivity 2 – 64 million Sm3/d Compressor design
The maximum nozzle velocity acceptable for a GE centrifugal gas compressor is 38 m/s.
3.13.2. Nozzle velocities sensitivity 3
At a 60 million Sm3/d flow rate, 70 bar(a) inlet, utilising a 2 x 50% compressor system design, the compressor
nozzles velocities are detailed below in Table 3-10 over the field life.
VSDS
POINT Section Vin Vout
S1 34.5 35.4
2018
S2 29.6 29.2
S1 34.6 35.2
2019
S2 29.6 29.17
S1 33.2 33.4
2020
S2 28.4 26.5
S1 34.36 33
2021
S2 28.2 26
S1 33 30.9
2022
S2 26.4 24
S1 30 22.5
2023
S2 17.7 15
S1 34.3 23.5
2025
S2 18.45 13.4
S1 30.7 19.3
2027
S2 15.6 10.11
S1 36 21
2029
S2 15.8 9.2
S1 22.2 18.8
2022.5
S2 15 14.3
S1 27 15.7
2031
S2 11.45 6.85
S1 17.6 10.86
2034
S2 8 4.6
Table 3-10 Nozzle velocity details - Sensitivity 3 – 60 million Sm3/d Compressor design
The maximum nozzle velocity acceptable for a GE centrifugal gas compressor is 38 m/s.
3.13.3. Gas turbine driven option centrifugal compressor design details
The gas compressor has been designed as per DEP 31.29.40.30-Gen (Ref: 5) to operate over the production
profile provided for the Ormen Lange floater. See Table 3-3 for further details.
The compressor is capable of turning down from plateau production of 64 million Sm3/d to 3.3 million Sm3/d
utilising two compression stages.
The compressor inlet pressure has been determined by the Integrated Production System Model (IPSM)
reservoir model, which has been used to predict each year of reservoir production. Using the flow rates
predicted by IPSM the discharge pressures have been determined from the resultant back pressure on the flow
lines.
In early field life the inlet pressures have been optimised at 75 bar(a) to fully utilise the available driver shaft
power. After year 2023, the available driver shaft power has not been optimised, as a minimum inlet pressure
of 14.6 bar(a) has been provided as a minimum.
The first stage inlet gas is not trimmed cooled by inlet coolers, the gas temperature is reduced by the distance
of the risers and flow lines the gas travels on the seabed. The seabed temperature is approximately -2°C,
therefore natural cooling occurs. As a result in early field life the gas inlet temperature is predicted to be 31°C,
reducing to 4°C in late life.
The second stage of compression is trimmed cooled by direct seawater cooling to 25°C constantly over the
field life.
Year 2023.5 is a high pipeline pressure scenario which may occur if a single flow line philosophy is used from
2023 onwards. This case will be determined in future studies.
This compressor design also requires a high polytropic efficiency of greater than 80% up to year 2023 to
enable the flow rate to be maintained by the selected drivers, therefore the compressor vendor design with the
highest polytropic efficiency has been chosen. The chosen compressor design operates at speeds between
9,905 rpm and 5,755 rpm to maintain a high polytropic efficiency, therefore a speed increasing gearbox is
required.
The Gas Turbine design has been completed to DEP 31.29.40.30-Gen (Ref: 5). Norsok R-001 (Ref: 118) has
also been consulted for the gas turbine design and has no further performance limitations. In summary the gas
Turbine DEP design margins are:
Gas Turbine Inlet Loss 2%
Gas Turbine Exhaust Loss 2%
Gas Turbine Waste Heat Recovery Units (WHRU) Loss 2%
Gas Turbine Unrecoverable Loss 5%
Using the information above, the DEP site rated GE LM2500/PGT25+G4 is site rated at approximately:
- 31,355 kW “New and Clean”
- 29,161 kW. “Time Degraded”.
Refer to Table 3-12 for further details. Information has been provided by GE detailing the
LM2500/PGT25+G4 to be capable of greater than 33,000 kW, however this calculation is not to a full DEP
specification, therefore has not been fully utilised in this stage of the design.
Manufacturer Model ISO Performance New & Clean Performance Time Degraded
Power Heat Rate Efficiency Power Heat Rate Efficiency Power Heat Rate Efficiency PT Speed
kW kJ/ kWh % kW kJ/ kWh % kW kJ/ kWh % (rpm)
GE Oil & Gas PGT 25+G4/ DLE 34,302 8,719 41.3 31,355 9,392 38.3 29,161 9,580 37.6 6,100
Total GE LM2500+G4
Compressor site "New &
shaft power Clean"
Requirement Shaft Power Number of Power
2x50% trains Available Trains Margin
Case / Year kW 2x50% trains kW required Available %
3,000 kW 6,919 kW
Conceptual study factor 1.35-1.4 (Norsok E-001) x 1.4 4,049 kW 9,340 kW
The Gas Turbine design has been completed to DEP 31.29.40.30-Gen (Ref: 5). Norsok R-001 (Ref: 118) has
also been consulted for the gas turbine design and has no further performance limitations. In summary the gas
Turbine DEP design margins are:
Manufacturer Model ISO Performance New & Clean Performance Time Degraded Performance
Power Heat Rate Efficiency Power Heat Rate Efficiency Power Heat Rate Efficiency
kWe kJ/ kWh % kW kJ/ kWh % kWe kJ/ kWh %
Solar Turbines Mars 100 10,664 11,090 32.5 10,153 11,598 31.0 9,443 11,830 30.4
The Solar Mars 100 at a “New and Clean ” condition currently does not meet the 2 x 100% power generation
train requirements, however after removing the 10% power margin the driver is suitable. A 2 x 100% power
generation system has been selected to meet the DEP N&1 sparing requirements.
The power generation gas turbines have been designed to operate on gas only and not on diesel to reduce the
NOX emissions and diesel consumption. Submain and emergency diesel engines are currently being used for
black start and normal operations restarts.
Table 3-19 shows the average through-life measures for system reliability, system availability and system
production efficiency.
It can be seen that for all Cases 1 (motor drives) the system reliability is 98.26% and for all Cases 2 (gas turbine
drives) it is 98.00%. Therefore based on the expected equipment performance the motor driven compressors
are 0.26% more reliable than gas turbine driven compressors.
The system availability for all Cases 1 is 96.72% and for all Cases 2 it is 94.94%. The difference of 1.78%
comprises the 0.26% reliability difference from above, and the balance of 1.52% due to the higher
maintenance requirement for the gas turbine driven compressors.
Once the available feedstock is taken into account (as expressed by production efficiency, PE%) there is an
improvement in moving from 2 x 50% to 3 x 33% and to 4 x 25%. This is because as the feedstock reduces
below the design capacity the remaining trains can replace some of the capacity lost by the train suffering an
outage. In effect the 2 x 50% nominal trains are 2 x 50+% trains. The effect is more marked for the gas
turbine driven compressors than the motor driven compressors as there is more lost capacity to recover.
The results for Case SC1, where heat is recovered from the exhausts of the 2 x 50% gas turbine compressor
drives and converted to power using an Organic Rankine Cycle (ORC), are no different from those for Case
2A (2 x 50% gas turbine drives), as the heat recovery unit and ORC unit have no effect on the performance of
the gas turbines.
In Case SC2 where the gas turbine compressor design capacity is nominally 2 x 32 million Sm3/d, at the very
outset an outage of one compressor results in the remaining compressor operating at effectively 53.3%. This
gives a small increase in reliability and availability performance over Case 2A (2 x 50% [30 million Sm3/d]).
However, there is a quite large increase in the Production Efficiency (PE) of 0.61%.
In sensitivity Case SC3 (2 x 50% motor drives with Power from Shore, assuming no submarine cable failures)
the electrical supply is more reliable than using offshore based power generation and so the reliability and
availability are higher than for Case 1A. It is to be expected that the PE would also be slightly higher than Case
1A, but it is shown to be better than Case 1C (4 x 25% motor drives). This stems from the power of the
motors drives being 35 MW for Case SC3 compared to 30 MW for Case SC3 resulting in a higher capacity for
Case SC3.
For Case SC3a (2 x 50% motor drives with Power from Shore, including submarine power cable failures) the
reliability and availability are the worst of all cases at 96.18% and 94.81% respectively. However, the PE is
better than for Case 2A (2 x 50% GT drive). It is suggested that because of the dramatic impact of the rare
cable failures due to the non-redundant submarine supply cable, that a thorough assessment be made to reduce
the impact either by introducing redundancy or managing the risk.
3.17.1. Production
Table 3-19 gives an appreciation of the relative performance of the various configurations. The final decision
on which configuration to adopt will need to be taken on the basis of a through-life economic assessment
(and, in relation to Case SC3, an assessment of the issues surrounding the integrity of the submarine power
supply). The input to the economic model should therefore be the expected production for each year of the
project. Figure 3-4 shows the through-life expected production for all cases. It can be seen that the results for
each case track each other closely and that by 2023 (the year after the first compressor re-wheel), the amount
of variation is reduced.
The economic model will use a discounted cash flow methodology which gives more weight to early-life
production. It is therefore appropriate to examine the early-life portion of the production curves as shown in
Figure 3-5.
Figure 3-5 Through Life expected production for all configurations years 2018-2020
Case 1C provides the best production (green dashed line, 4 x 25% motor drives). The second best is Case SC3
(red dotted line, 2 x 50% motor drives, PfS). However, this does not include for subsea power cable failures
and should be reconciled with Case SC3b (black dotted line, 2 x 50% PfS CF).
It is to be noted that the plots for Case 1A (2 x 50% motor drive, blue dashed line) and Case 1B (3 x 33%
motor drive, yellow dashed line) overlap each other. This is unexpected given the separation seen between the
Case 2 plots and it is therefore recommended that the bypass profiles be reviewed.
As with the production plot, in early-life the best PE is exhibited by Case 1C (4 x 25% motor drive) followed
closely by Case SC3a (2 x 50% motor drive PfS). However, after the 2022 compressor re-wheel Case SC3a
performs better than Case 1C for a number of years. Otherwise with the exception of Case SC3a (which
includes cable failure for the subsea electrical supply case), the PEs for early years are very similar.
Figure 3-7 shows the results for the gas turbine drive Cases 2A, 2B and 2C and SC2. The sharp drops relate to
the following:
2022 Compressor Re-wheel
2024 50 k Gas Turbine Inspection
2027 Compressor Major Overhaul
2029 Compressor Re-wheel.
Again the 4 x 25% configuration (Case 2C) shows the best PE and in the early years all other cases have a
similar PE. However, the plot for Case 2C in 2023 is inconsistent with the shape of the other plots; this
warrants a review of the bypass profiles.
It is to be noted that discounting Case SC3a (which includes cable failure for the subsea electrical supply case)
in the early years, the PEs for the electric drive cases do not go below 92.5% whereas the PEs for the gas
turbine drive cases do not go below 91.5%, a 1% difference.
3.17.3. Definitions
Reliability = (operation time + standby time) / (total time - prev. maint. time)
Reliability disregards preventive maintenance.
Availability = (operation time + standby time) / total time
Availability includes preventive maintenance. Both the above measures relate to system times only and do not
include the effect of changing feedstock.
Effective Capacity = capacityi * (fraction of time spent at capacityi)
Effective capacity expresses the effect of the times the system is at various capacity levels on the available
feedstock.
Production Efficiency (PE) = Effective Capacity / Feedstock Capacity (also referred as Maximum
Capacity).
The 2 x 50% export compressor gas turbines are estimated to produce 3.8 million tonnes of CO2 over the field life. The 2 x 100% power generation gas turbines are
estimated to produce 0.89 million tonnes of CO2 over the field life.
Lambda 3.115
Criteria
The 2 x 50% export compressor gas turbines are estimated to produce 2,749 tonnes of NOX offshore over the
field life. The 2 x 100% power generation gas turbines are estimated to produce 581 tonnes of NOX offshore
over the field life.
3.18.4. GT driver SO2 emissions
As Ormen Lange gas has no H2S content no SO2 is anticipated to be produced as part of the combustion
process.
Table 3-24 Estimated Electrical Load list for Power from Shore
Ormen Lange Compression Platform Upstream Major Projects Power from Shore
Electrical Load List 37-1Y-NS-E19-00003 Rev02 Based on MEL Re v07
Tag No. Service Duty/ SWBD Output Installed Effici- Pow er Em ergency Norm al production Rem arks
St.By. Pow er Pow er ency Factor Mode Mode
P-2001C CONDENSATE EXPORT PUMP Duty 369.0 450.0 95 0.85 0 0 1 388 241 Freq. Converter RECEPTION FACILITIES
K-2701 GAS COMPRESSOR VSDS Unit A Duty 35000.0 37433.0 93.5 0.962 0 0 1 37,433 10,699 COMPRESSION
K-2801 GAS COMPRESSOR VSDS Unit B Duty 35000.0 37433.0 93.5 0.962 0 0 1 37,433 10,699 COMPRESSION
P-5001A SEAWATER LIFT PUMP Duty 700.0 790.0 95 0.85 0 0 1 737 457 Utilities
P-5001C SEAWATER LIFT PUMP Duty 700.0 790.0 95 0.85 0 0 1 737 457 Utilities
P-5002A ESSENTIAL SEAWATER PUMP A Duty 200.0 225.0 95 0.85 1 211 130 1 211 130 Utilities
A-4401 MEG INJECTION SKID Duty 220.0 250.0 95 0.85 0.5 116 72 Utilities
K-6301A AIR COMPRESSOR SKID A Duty 255.0 300.0 95 0.85 1 268 166 1 268 166 Utilities
K-6301B AIR COMPRESSOR SKID B Duty 255.0 300.0 95 0.85 0 0 1 268 166 Utilities
Z-1003A ROV LAUNCH STRUCTURE St.By 400.0 400.0 95 0.85 0 0 0 0 SUBSEA SUPPORT
X-4001A SOUTH PEDESTAL CRANE St By 480.0 480.0 95 0.85 0 0 0 0.5 253 157 Mechanical Handling
2,147 kW 85,237 kW
Conceptual study factor 1.35-1.4 (Norsok E-001) x 1.4 2,898 kW 88,867 kW Assumes comp load fixed
2146.8 1.4 only applied to load excluding compressors
Weights and dimension of a Gas Turbine Driven Power Generation Skid are:
Table 3-26 Solar Mars 100 GT Driver PowerGen weights and dimensions
Weights and Dimensions Solar Mars 100 Power Generation Skid
Length 14.6.0 m
Width 2.8 m
Height 11.5 m
Gas turbine power generator (dry approx) 120,000 kg
Gas turbine power generator (operating) 120,000 kg
GT air intake system Inc
Exhaust system Inc
Ventilation system Inc
UCP Inc
Mineral lube oil system Inc
Synthetic oil system Inc
For further information refer to Figure 3-10.
As this is a production critical service, a common spare train has been has been selected (three pumps total).
• Base plate
• Drain / Seal piping
• Control Panel
• Electro-submersible pump
• Submersible pump electric motor with cable
• Submersible pump non return valve
• Rising main
• Air vent valve/vacuum breaker
• Pump inlet screen
• Ion-exchange anti-marine fouling system
• Material of pump etc in contact with the seawater to be Super Duplex stainless steel.
Table 3-33 Hazardous System Seawater Lift Pump weights and dimensions
Weights and Dimensions of Hazardous System Seawater Lift Pump
Length of pump and motor 4.2 m
Width of pump and motor 0.7 m
Rising main / casson - length / width 30 / 0.75 m
Pump and motor weight (dry/ operating approx) 5,100 kg/ 7,000 kg
Cable/adapter/flap valve / anti fouling (dry approx) 500 kg
• Electro-submersible pump
• Submersible pump electric motor with cable
• Submersible pump non return valve
• Rising main
• Air vent valve/vacuum breaker
• Pump inlet screen
• Ion-exchange anti-marine fouling system
• Material of pump etc in contact with the seawater to be Super Duplex stainless steel.
Table 3-34 Essential Seawater Lift Pumps (Non Hazardous System) Specifications
Essential Seawater Lift Pumps (Non Hazardous System) Specifications
Pump UPA 300-94/3 + UMA 250D 190/22
Rated speed 2,920 rpm
Flow rate 375 m3/h
Stages 3
Pumping temp 20
Density 1,030 kg/m3
Discharge pressure (centre line of nozzle) 8.25 bar(g)
Total head 110
NPSHr 9.2 m
% 77
Pump rating 180 kW
Pump materials Wetted Parts - UNS S32760
Motor rating 180 kW, 690 v, 50 Hz
Cable 50 m
Riding main dia (w/o cable) 0.3 m estimated
Cable supports inc
NRV inc
Vent valve 2”
Anti fouling system Marin anti fouling system
Initial enquires have been made, mainly to establish an equipment weight, dimensions and cost, the CAT
C280-8 Marine Diesel Generator Set specifications.
The engine ratings provided by the vendor were completed under standard conditions and not “SITE” rated
for Ormen Lange. The engine performance will therefore increase when site rated. During the next design
phase this system will be defined in more detail. Refer to Figure 3-18 for further information.
Table 3-49 Fuel Gas Booster Compressor Package weights and dimensions
Fuel Gas Booster Compressor Package Weight and Dimensions
Skid length 5.1 m
Width 2.6 m
Height 3m
Dry weight 50,000 kg
Operating weight 55,000 kg
4.1. General
• Layout developed in accordance with
o EP Projects Layout Development Procedure GEN-EPA-M18-00001-001-A02 (Ref: 15)
o PDMS Model Specification GEN-EPA-M19-00003-001-A01 (Ref: 20)
o Norsok standard L-002 Piping design, Layout and Stress Analysis (Edition 3) (Ref: 115)
o Norsok standard S-001 Technical Safety (Edition 4) (Ref: 119)
o Preliminary Process Flow Schemes – no issue date (Ref: 51)
o Preliminary Equipment List 60 million Sm3/d, Reference Case – GT Drive Option.
37-1Y-NS-C19-00001 Revision 07 (Ref: 68)
o Preliminary Equipment List 60 million Sm3/d, Reference Case – Power from Shore Option.
37-1Y-NS-C19-00002 Revision 07 (Ref: 69)
• Refer to Figure 4-1 below for general layouts of the TLP and modules.
The size and layout of the hull has been developed and supplied by Rijswijk. The PDMS model is to be
updated following recent changes in the hull dimensions, which will also reduce the sizes of the
modules, but only by approximately 1 m in length. The topsides layout has developed from an
Integrated Deck arrangement to Modular in order to increase the potential number of construction yard
locations. The size and layout of the topsides modules have been developed based upon the size
restrictions dictated by the hull support locations. Minor local modifications have been carried out by
Exploration & Production (EP) Projects, such as local access/extension platforms, mezzanine deck in
the Utilities section, and support framework for separators.
The main platform modules are:
o RB – Riser Bay
o GC – Gas Compression
o HU – Hull
o LQ – Living Quarters
o PM – Power Module
o US – Utilities South
o UT – Utilities.
• The predominant wind and current direction determines the location of the LQ and gas compression
facilities. The LQ should be located upwind of the gas compression and power generation exhaust
stacks to reduce the impact of fumes and possible gas clouds affecting the LQ and the Temporary
Refuge (TR) within it. Any smoke/fumes or gas clouds would be blown away from the LQ/TR under
most wind conditions.
• The predominant current comes from the West, which influences the location of the platform cranes
and locations of supply boats. Should a supply boat loose power, the predominant waves would drive
the vessel along the side of the platform and then clear, rather than into the platform leading to damage
to the hull, or the risers.
• However, the lifeboats adjacent to the LQ, which will be accessed directly from the TR, must face
upwind to reduce the possibility of smoke affecting the personnel in the event of an evacuation. This
results in the lifeboats being launched into the predominant waves, which may lead them to being driven
back under the hull should their engines fail.
The type and size of lifeboats has not been finalised as yet, but only two suppliers are known to comply
with the Norsok requirements – Schatt Harding and Norsafe. A typical lifeboat with a compliment of
70 personnel has been included in the model to provide the required N+1. This is based upon
approximately 120-130 personnel being on-board during the commissioning phase.
Two further lifeboats are included on the East side of the platform to provide a means of evacuation
during normal operation for a crew working in the gas compression module. Two lifeboats are required
for the N+1 requirement, and 70 person lifeboats are required due to the drop height. Smaller capacity
lifeboats require a much lower drop height, which would result in them being located within the splash
zone.
Platform orientation has been determined to be true North. The factors affecting this orientation are the
wind and wave direction but also the seabed topography and available sites to install piles for the TLP,
and available routes for the subsea pipelines.
• The Piping layouts show only the large bore systems, based upon preliminary PFS. The layouts would
need to be developed in FEED, as the Process Engineering Flow Scheme (PEFS) becomes available, as
not all isolation valves are shown.
• Preliminary access and escape routes have been included in the model.
• The type and size of the cranes has yet to be finalised but a suitable crane has been included in the
model. The type, height, capacity and reach are adequate for the material handling requirements of the
platform, but a further review and a Mechanical Handling Study will be conducted during FEED.
• Cable trays and lighting systems have not been included in the model. Preliminary pipe racks for the
large bore production manifolds have been included but no other pipe racks are shown.
• All the seawater, firewater and service caissons are located on the outside of the columns as per the
latest guidance from Rijswijk. The caissons must be installed close to the columns of the platform in
order for supports to be provided, and so local extension platforms are required to reach firepumps and
allow access/maintenance, as these are located out with the main deck space. The depth of
drains/sewage caissons relative to firewater/seawater lift caissons is to be checked in FEED as no
guidance was found during Concept Select.
• All the equipment identified on the equipment list has been included, except for the hull systems that
are not part of topsides scope, and minor safety items such as hose reels, hydrants, safety showers and
miscellaneous fire fighting equipment cabinets. Ballast pumps/caissons have been included as these are
installed/accessed via the topsides.
• Stair towers are located at each corner of the TLP to allow access to all levels. The top of the Riser Bay
sits above the top deck of the surrounding modules and access has been provided at the North and
South ends of this module.
• Each module will have one fixed corner, with two that allow movement in one direction. The corner
opposing the fixed support will allow movement in two directions. The locations of the supports has
been determined by the Hull engineers, with the fixed support being located on the outside of the
columns so that maximum support is provided should a riser jet fire weaken the inside face of the
column.
There are two layout options, one with Power from Shore via an electric cable, and the second with
local power generation using two generators. The electric motors are replaced with GT drives for the
local power option.
• The Central Control Room will be integrated into the main deck of the Utilities module, allowing a
degree of pre-commissioning / commissioning activities to be completed prior to deck sail away from
the fabrication yard. The living quarters will be fabricated elsewhere by a specialist fabricator and
installed on top of the Utilities module later. The LQ sits on top of the CCR, and the stairway between
them will be sealed to allow personnel to move between the LQ and the CCR. This also provides a link
between the CCR and the Temporary Refuge area within the LQ for evacuation to the lifeboats if
required.
• A seascape is provided on the lower deck level near to the LQ for emergency evacuation, but would not
normally be deployed. The model shows this escape route down to the sea level and is for information
only.
• A Man Overboard Boat (MOB) is included, and is located above the workshop in the Utility area, as per
the Norsok requirements. This MOB must be visible from the crane cab.
• A goods lift is included in the Utilities Module through the workshop to allow transportation of smaller
items of equipment between decks without transferring to the deck edge where laydown areas will be
provided and serviced by the platform cranes.
• To save deck space and allow efficient layouts, storage tanks are located within the decks in the Utility
areas for non-hazardous services. This concept would need to be reviewed and agreed early in the
FEED process.
• A number of electrical equipment items are located in the module, along with battery rooms, HV&AC
and two of the four firepumps. The seawater filters for the cooling water system are within the Utilities
module, located on the lower deck. The battery rooms and local equipment rooms (LERs) are located
on the mezzanine deck, North of the CCR.
• A workshop is located between the LQ and the West blastwall, on the top deck. The goods lift passes
through this workshop to the roof, which can also be used as a laydown area for equipment. A jet fuel
package is located at one end of the roof, and must be protected from swinging objects. Jet fuel is
pumped to the top of the LQ where the dispensing package is located. The location and operation of
the jet fuel system is to be reviewed in FEED.
• One of the two firepumps at the SW column is located on a deck extension, with the caisson being
supported from this module. The module support arrangement has a sliding support at this location,
and so module displacements must be identified to ensure the firewater caisson is not subjected to
excessive lateral loads at the column guides.
• The NW corner would be fixed. However, there will need to be expansion loops in the pipework
crossing from the Utilities module to the Power Generation and the Utilities South, but as this pipework
will contain services and not process pipework, the design temperatures will be relatively low and
therefore the size of the expansion loops will be limited.
4.2.2. Gas Compression Module (65 x 28 x 12)
• The inlet manifolds are routed around the North edge of the East blastwall and tie-in to dedicated inlet
separators. Any slugs of liquid are dealt with in this vessel and the initial liquid separation is also carried
out at this point. Pumps are located beneath the separators on the lower level to pump any liquids back
into the export header.
The height of the Inlet Separator must provide 7 m NPSH to the condensate pumps, although details of
liquid levels are not available. A worst case scenario has been adopted where the lowest liquid elevation
is assumed to be at the bottom tan line of the vessel. The inlet nozzle height then falls within the deck
beams, which would result in the inlet pipework turning within the beams to align with the nozzle. As
spades will probably be required at the inlet nozzle for isolation purposes the inlet nozzle must be
located above the deck for access. The vessel is shown supported from support ring around the vessel,
which sits on the top deck. This allows the inlet pipework to be installed above the deck level and allows
access to inlet nozzle. The vessel protrudes through the deck and can be seen from the level below,
effectively hanging through the deck. Gas outlet nozzle deflections are minimised with this support
arrangement.
• The two electric driven gas compressors are located on the top deck of the module. Oil for the
compressor seals is routed to a storage tank and pump set which is to be gravity fed from the seals and
so must be located underneath the compressor. To avoid excessive pipe runs between decks, the seal
unit is hung beneath the top deck and is accessed via ladders from the top deck. The compressors are
located on the top deck as they are too large to fit in between decks, to ensure they are freely ventilated
to avoid a build up of gas should a leak occur, and to allow access by both platform cranes in case of
maintenance.
The two scrubbers associated with each train are located to the South of each compressor, with the two
discharge coolers located above. The Process requirements are for the outlet of the coolers to fall to the
scrubbers. The compressor second stage discharge is routed through the second cooler and then the two
headers runs back along the blast wall to the Riser Bay. At this point they join a common header but are
separated by a normally closed cross-over valve. This allows the discharge from one train to be routed
to one pipeline, and the other to the second pipeline, allowing different flow and pressures in each
pipeline.
• The MEG storage and injection skid is located in the Gas Compression module as a dedicated chemical
injection skid is not required for the TLP, and so the MEG is located in a hazardous area.
• The lower deck of the module contains all the pumps associated with the separators and scrubbers, and
the flare knock drum to ensure a fall in the flare pipework. The flare tower is located on the North end
of the module, with the ignition package beneath it.
The Flare height (105 m above the top deck to the tip) is based upon preliminary information, and it
may be possible to reduce the height with further work in FEED. This could reduce the crane height, as
a minimum distance will be required from the crane operator’s cab to the flare tip.
• In case of emergency, two additional lifeboats and a TR on a mezzanine deck have been included. If the
escape tunnel is not included in the final layout, these lifeboats will be the only means of escape if there
were an incident in the Riser Bay cutting off the escape route back to the TR in the Utilities module.
However, this results in the need for a full lifeboat crew to be stationed at the TR whenever personnel
are in the Gas Compression module. This is not a practical approach and so further work on the QRA is
required during FEED.
• Drains tanks and pumps are included in the lower deck beams.
• The NE corner of the module will be fixed, and so the manifold pipework that will run from between
the Riser Bay and the Compression modules may require expansion loops to accommodate the relative
displacements. The extent of these loops will be determined during FEED.
4.2.3. Riser bay module (45 x 40 x 19.5)
• The underside of the lower deck is to be 2.5 m above the top of column, and has been set by Rijswijk to
ensure the modules are not in the splash zone or subject to water damage from water run-up at the
columns. The deck beams are 1.5 m deep except for the centre sections of the Riser Bay which are 2 m
to accommodate the loads from the TTRs. As the underside of the deck is to be the same for all
modules, the top of steel for the lower deck level in the Riser Bay must be 500 mm above that of the
surrounding modules. This is not ideal when considering escape routes and movement of equipment as
walkways linking the Riser Bay to the other modules will be inclined.
Norsok (L-001, section 4.1) (Ref: 114) states that deck levels should be at the same elevation as far as
possible and that transportation routes should not contain steps or thresholds, section 4.3.4. Norsok
S-002, table B.1 (Ref: 120) advises that the maximum height difference in one step in access ways is
350 mm. At least two steps would be required for a 500 mm height difference, or the walkway would
need to be inclined at approximately 10°. ISO 14122-1 (Ref: 107) states that the preferred access is from
the same level, where this is not possible then a suitable ramp shall be used with an angle of pitch less
than 10° but with a maximum of 3° for handcarts and other manually wheeled vehicles, a maximum of
7° for motorised vehicles. (Maximum of 20° for walking but no tools or items are to be carried.) The
mechanical handling study should take into account the difference in deck height when considering the
movement of materials and equipment in and out of the Riser Bay. It may be that the platform crane is
required for each activity carried out in the Riser Bay, irrespective of the size/type of equipment to be
moved. A suitable laydown area at each end of the Bay is to be included in the layout.
As part of the Riser Bay review to reduce weight, the centre steelwork sections may be reduced to 1.5 m,
in which case the deck levels of all modules will become the same. Suitable access ways will be provided
and the need for additional laydown areas at the ends of the module will be reduced. This work is
currently on-going and deck levels will be determined prior to the start of FEED.
• Inlet production manifolds down each side of the Riser Bay are 24” 1500#, and combine to run in 30”
pipework on the North side of the Riser Bay Module, which may cause problems with procurement of
flanges. As a result, hubs are included in the PDMS model as these are more readily available than
flanges (dimensional details of flanges above 24” have been removed from the relevant standards as they
are not used, i.e. Magnetic Stainless Steel (MSS) SP-44). Hubs also offer reduced weight and space
advantages. Hub connections are also shown at the inlet separators and exchangers. Compact flanges are
available through the Ormen Lange (OL) onshore pipe specs, and are to Norsok standard L-005
(Ref: 116). All large bore connections would need to be reviewed in FEED to confirm the standard to
be used.
• The location of the blast walls has been determined by the layout of the Riser Bay equipment and
pipework, and the location of the main deck beams in the structure that will provide the support to the
blast walls.
• The risers for the Tension Leg Platform are located in the centre of the platform. The four Northern
risers and four Southern risers are inlet risers from the subsea templates, with the four central risers
being the export lines. This arrangement results in minimal line crossings subsea, reducing costs.
Installation of the rigid risers is via a rig located above the riser bay and is covered in another section of
this report.
The dimensions of the riser bay may be reduced to 40 m x 34 m, as a more compact layout is being
developed. This will assist with the installation of the module at the construction yard. The final
dimensions are determined by a number of factors but are limited by the design of the Upper Column
Frame (UCF) and hull. The Riser Bay is supported on a UCF which rests on the four columns of the
hull and has a knee brace at each leg.
The risers are spaced at 7 m in the E/W direction and 6 m in the N/S in the compact layout, which
allows a central truss to run along the length the module, providing the support.
The 16” flexible jumpers connect the riser to the inlet manifolds that run along each side of the riser
bay. These allow the displacement of the riser and isolation valves relative to the platform deck and the
fixed manifolds. Each riser is supported by six hydraulic cylinders that are then supported by stools
located on the main deck. This Top Tensioned Riser system (TTR) allows the platform to move around
the rigid risers. The jumpers have a minimum bend radius of 3.81 m (Wellstream flexible based upon a
quasi-static application 1.25 x Styrene-Butadiene Rubber (SBR)), and allow for a vertical displacement of
approximately 1.31 m up and 1.087 m down from the null position. The 16” flexible jumpers are
installed in a “U” shape and tie-in to inlet manifolds on each side of the bay.
Jumper replacement is not expected during the life of the platform, but sufficient space has been
allowed to assist in their removal and hatches will be retained in the top deck to allow jumper
replacement. The platform crane and local rigging will be required to install the jumpers in the first
instance, and change them out if required.
There will be two inlet sub-manifolds installed on each side of the riser bay as each riser is to be routed
to two main manifolds. These manifolds allow different pressure regimes to operate at the same time.
The two A sub-manifolds connect and are routed to one inlet separator, and the two B sub-manifolds
are routed to the second separator.
There are two isolation valves on the riser, an isolation valve at the topsides tie-in and a further valve at
each of the manifold connections. This allows double valve isolation for each jumper should it require
replacing, and allows the platform to remain producing should any jumper or riser require isolation.
• The tensioner ring is to be accessible in all weather conditions except the 10,000 year storm case. As a
result, the elevation of the tensioner cassette is relatively high and requires a substantial support
structure to accommodate the loads imposed upon it. Installation heights (riser flooded) and nominal
positions have been checked and the maximum displacements modelled to ensure the lower of two
valve access platforms, connected to the riser, will not clash with the tensioner cassette during extreme
movement. (This arrangement includes a 0.61 m installation tolerance for the risers.) Access will be
required to this platform, which may be in the form of ladders that will protrude passed the cassette
support frame. Permanent ladders will provide access to the top of the fixed cassette, and between the
two access platforms, but personnel would need to step from the static ladder on the stool to the
“moving” valve access platform. This would need to be reviewed in FEED as there are Safety issues
with transferring between moving equipment items. Access ladders have been included within the
PDMS model to indicate the potential layout.
As the platform moves under extreme weather conditions, the rigid risers will move relative to the
platform deck. The risers will rotate approximately 6° from vertical (from the centralising cassette) when
viewed from the deck of the TLP and the layouts have been reviewed to ensure there are no clashes due
to this movement. Lateral displacements at the jumper connection have been confirmed as +/-1.03 m in
the North/South direction, and +/-0.82 m in the East/West direction.
• The SSIVs on the subsea template beneath the TLP are located at the skid edge, and sufficient space is
available within the Riser Bay to install skid beams and winches to allow removal of the valves and
actuators from the topsides.
4.2.4. Power Module (58 x 18.5 x 12)
• A number of the transformers associated with the power cable are located in this module, as are
electrical LERs and transformers, not essential to LQ operation.
• The North platform crane is supported from this module and additional laydown area has been
allocated on the top deck. The lower deck includes deck extensions for Remote Operated Vehicle
(ROV) containers and control equipment that may be used during installation of the risers.
• One of the two firepumps at the NW column is also located on a deck extension. The caisson will be
supported from the extension platform. The module support arrangement has a sliding support at this
location, and so module displacements must be identified to ensure the firewater caisson is not
subjected to excessive lateral loads at the column guides.
• The diesel treatment and storage system is located on the lower level, with the storage tanks located
within the lower deck.
• A hose loading station is located on the lower deck level.
• The flare metering and oxygen analyser packages are located on the top deck to the East end the
module, local to the flare tower.
• The NE corner will be fixed.
4.2.5. Utilities South Module (58 x 18.5 x 12)
• This module contains the escape tunnel that connects the Gas Compression module to the Utilities
module and the Temporary Refuge. A QRA has shown that the escape tunnel and two lifeboats are not
required, but the final decision on which system should be employed has not been made and so the
layout carries both options. Access to the escape tunnel can be made from each of the three modules it
runs through, and will be installed with full lighting, HV&AC and public announcement (PA) systems.
• The South platform crane is supported from this module and additional laydown area has been allocated
on the top deck. A paint store is located to the West side of the top deck. The lower deck includes deck
extensions for ROV containers and control equipment that may be used during installation of the risers.
• One of the two firepumps at the SW column is also located on a deck extension. The caisson will be
supported from the extension platform. The module support arrangement has a fixed support at this
location and so lateral displacements between the hull and the topsides module is not a concern.
• However, the supports at corners of this module and the Gas Compression are sliding and as there will
be process cooling and firewater lines crossing between them, there is the potential for expansion loops
in this area.
• The non-hazardous drains sump and pumps are located in this module, within the lower deck structure.
As mentioned above, the bottom of steel for all the lower deck must be the same elevation and no
equipment is to protrude beyond this level. As such, the type of pumps and sump arrangement will need
to be reviewed in FEED to ensure this solution is acceptable.
• Potable water storage tanks and pumps are located within the lower deck structure. The
electro-chlorination package is situated near to the potable water tanks.
• The nitrogen generation package, air compressors and receivers, and air driers are all located on the
lower level of this module.
• A hose loading station is located on the lower deck.
4.2.6. Nyhamna modifications
• Additional electrical equipment is required at Nyhamna, and following a review of the site drawings an
area to the North of the plant has been identified as a possible location for this equipment. The area was
used for the pipeline construction and testing, and is adjacent to the existing pipelines. The electrical
cable could be run alongside these pipelines as the route has already been surveyed.
Access to the new equipment would be via the existing roads, and equipment could be brought to site
by either road or boat, and offloaded on the construction jetty. Figure 4-4, Figure 4-5, Figure 4-6 and
Figure 4-7 below show the location of the new equipment.
Table 5-1 Inlet Separator and First Stage Suction Scrubber - Summary Details and Weights
Inlet Separators Compressor Suction Scrubbers
Carbon Steel QT Steel Carbon Steel QT Steel
Internal Diameter (mm) 3,400 3,400 3,200 3,200
T/T Length (mm) 9,000 9,000 5,300 5,300
ASTM Material Grade A516 Gr. 70 A533 Cl.2 A516 Gr. 70 A533 Cl.2
Design Stress (N/mm2) 170 252 155 252
Wall Thickness (mm) (1) 155 105 170 105
Dry Weight (tonne) 187 136 137 90
Op Weight (tonne) 236 185 158 112
Test Weight (tonne) 270 222 182 138
Note 1: Wall Thickness includes a 5% allowance for re-inforcement around nozzles and 5 mm allowance
for the alloy cladding.
5.1.3. Discussion
The calculated wall thicknesses for the original design conditions were approaching the limit of what can be
manufactured and several specialist vessel fabricators and a material supplier were approached to determine
whether fabricating the vessels was feasible.
The main area of concern was the ability of the fabricators to guarantee the toughness properties of the plate
and forging material at the minimum design temperature. The forging material outlined above has a high
Nickel content and is not suitable for sour service due to the NACE limitation on Nickel.
Although the vessel thicknesses have reduced with the lower design pressure, there are several areas that
require resolution during FEED to ensure that no major issues arise during the Execute phase. These include
Post Weld Heat Treatment (PWHT) effects on material strength and cladding; stainless steel cladding
specification and method (explosive bonding, weld overlay, weld technique etc); manufacture of heads (one
piece, crown and petal, avoidance of intersecting nozzle welds on heads);
The design conditions need to be confirmed to allow the vessel thicknesses and material selection to be
finalised. The current material selection is at the upper limit of thickness for high strength quenched and
tempered material. A small increase in the design pressure and/or vessel diameter may require a change to
carbon manganese steel which would result in a significant increase in the wall thickness and weight for the
vessels. The minimum design temperature has a significant influence on the permissible material thickness as
achieving the required impact properties in thicker sections of plate is more difficult.
The following table details the fabricators who have been approached together with their responses.
Table 5-2 Inlet Separator and First Stage Suction Scrubber - Vessel Fabricators’ Responses
Vessel Fabricator Response
The enquiries were based Dimensions ID = 3.2 m, T/T=10 m,
on the earlier vessels design
criteria Design Pressure = 200 bar(g), Temperature = -46/+100°C
Material: ASTM A533 Gr.2 or equivalent with clad/overlay.
Estimated wall thickness = 140 mm (based on allow. stress 252 N/mm2)
ATB Riva Calzoni ATB had initial concerns regarding the minimum design temperature and
Location: Italy plate thickness, but did seek advice from their plate supplier (Industeel).
Contact: Salvatore ATB has since provided a budget quotation for supplying all four vessels
Poddighe fabricated in high strength QT steel. The proposed shell thickness is
Tel: +39 030 2581236 120 mm(1) based on a design stress of 263.8 N/mm2.
E-Mail: salvatore.poddighe An e-mail was issued to ATB on 16/04/09 with several queries relating to
@atbrivacalzoni.com design temperature, proposed plate supplier, PWHT, cladding technique, etc.
Response outstanding.
Belleli Declined to offer a budget quotation. Equipment deemed too small for
Location: Italy them.
GE Oil and Gas Declined to offer a budget quotation. This type of fabrication process is not
Location: Italy included within their product range, which is mainly focused on heavy wall
reactors manufactured by forged rings.
Hans Leffer Hans Leffer claim to be very experienced in manufacturing high strength
Location: Germany QT steel vessels, but recommend limiting the maximum material thickness
Contact: Peter Nicklaus to 100 mm. They have proposed a design stress of 247 N/mm2.
Tel: +49 6897 793302 It is worth noting that Leffer has previously supplied vessels at 121 mm Wall
Table 5-3 Inlet Separator and First Stage Suction Scrubber - Plate Supplier Responses
Plate Supplier Response
Industeel Industeel has confirmed that both steel grades can be supplied as follows:
Location: France
Contact: ASTM A516 Gr.70 Carbon steel delivered quenched and tempered;
Cedric Chauvy Maximum thickness = 215 mm
Tel: +33 477 832560 Ceq = 0.45%;
E-Mail:
ASTM A533 Gr.C Class 2 High strength quenched and tempered steel:
Maximum thickness = 140 mm
PWHT = max 600°C for 9 hours
CVN = 40J/28J @ -46°C
5.1.4. Conclusion
The inlet separators and compressor suction scrubbers can be manufactured from carbon steel (ASTM A516
Gr.70) or high strength quenched and tempered steel (A533 Class 2).
Based on discussions with the material suppliers and vessel fabricators, the following selection criteria was
identified in the Technical Information Note (TIN) and adopted earlier in the project for the vessel material:
a. High strength quenched and tempered (QT) steel where the calculated wall thickness is less than or equal
to 100 mm.
b. Carbon steel (up to a maximum thickness of 215 mm) where the calculated wall thickness for high
strength QT steel exceeds 100 mm.
However the criteria is based on the feedback of one fabricator which has not been substantiated and the plate
supplier and other fabricators have guaranteed the material properties up to a thickness of 140 mm limit.
Vendor feedback suggests that the cost differential between the two material options is small which leaves
weight as the deciding factor. The vessel wall thicknesses are at the current material selection criteria limit but
it’s recommended that the inlet separators and suction scrubbers are manufactured from High strength
Quenched and Tempered steel to minimise the vessels’ weight.
The following equipment weights have been used within the master equipment list:
Table 5-4 Inlet Separator and First Stage Suction Scrubber - Equipment List Weights
Inlet Separators Compressor Suction
Scrubbers
Dry Weight (tonne) 139 93
Op Weight (tonne) 188 115
During FEED, the material selection for the vessels and associated metallurgical issues need to be fully
resolved to guarantee the plate and forging material and mechanical properties and identify acceptable vendors
for plate supply and vessel fabrication.
operation, shell and tube heat exchangers have been selected for these coolers. A secondary consideration was
that if problems were experienced with operation of the compact PCHEs, installing replacement shell and tube
exchangers would be cost prohibitive, if not impossible due to the lack of available space.
The shell and tube exchanger proposed by Hans Leffer is a fixed tube sheet design which offers the most
economic solution with numerous exchangers of this type operating satisfactorily in the North Sea. However,
to maintain the option to change exchanger type in the future, a withdrawal volume has been included in the
PDMS model at present. The exchanger type needs to be reviewed in conjunction with the seawater treatment
facilities and filtration before the final selection is made.
5.2.1. Design conditions
The design pressure and temperature of the gas compressor aftercoolers are:
5.2.2. Materials
Titanium has been selected for all seawater wetted parts (shell, tubes and tubesheet(s)). Carbon steel is suitable
for the channel end(s).
5.2.3. Dimensions and weights
Only one budget quotation was received for the gas compressor aftercoolers. This was submitted by Hans
Leffer who proposed a BEM fixed tube exchanger (details shown below).
In addition, four off thyristor control panels are required for controlling the heaters / super-heaters. No
dimensions or weights have been received for these items. They will be located remote from the skid within a
local equipment room.
Table 5-10 Fresh Water Maker Package - Summary Details and Weights
Reverse Osmosis
Dimensions and weights of the fuel gas dispending package have been taken from the equivalent package
located on Shearwater, which can supply up to 13.7 m3 of aviation fuel per hour.
The Shearwater platform is located 200 km East of Aberdeen, while the Ormen Lange field is located 130 km
West of Kristiansund. The jet fuel supply package located on Shearwater can accommodate four off tote tanks
each containing 2.7 m3 of aviation fuel. The Ormen Lange package has been down-sized to accommodate
three off tote tanks, which takes account of the shorter distance.
The dimensions, weights and power requirements of the packages are as follows:
6. Topsides Structure
6.1. Structural arrangement
The earlier conceptual study work recommended that an integrated deck was the preferred option for the TLP
floating compression solution. Further to this, it was suggested that consideration should be given to an
alternative modular deck arrangement as used on Shell’s recent Gulf of Mexico (GOM) TLPs such as Mars B.
Further structural work was thus undertaken to assist in identifying the technical implications of such an
arrangement on the Ormen Lange platform concept.
Based on the existing dimensions for the proposed TLP hull, an alternative arrangement of five modules that
could be supported by the hull was developed to allow the layout engineers to develop a suitable equipment
layout. This arrangement utilises a central module to support the risers, manifolds and installation rig while
four perimeter modules support the process and utilities equipment, and the living quarters.
The potential switch from an integrated to a modular deck requires that an upper column frame (UCF) be
incorporated into the hull to carry the squeezing/prying forces between the column tops. This frame includes
four vertical diagonal braces down to the TLP legs to carry the weight of the central module and riser tension
forces.
There are various advantages and disadvantages to the modular option relative to the integrated deck, both
technical and commercial, but only the technical matters are discussed in this section.
Advantages:
• The squeeze/pry forces from the hull are carried by the UCF. This potentially reduces the structural
weight of the deck modules and allows the design to be performed independently.
• The use of the UCF provides strength and support to the columns during the temporary and transport
conditions prior to deck installation reducing the need for temporary strengthening.
• Reduced ballasting capability since float-over installation avoided.
Disadvantages:
• The separate modules are more reliant on their individual support points leading to a less robust design
in the event of loss of local hull strength due to a jet fire.
• Heavy lift crane vessel required for module installation.
The relative merits of the two options were discussed in more detail in the key decision document
(SPh3-Fl-04-08 (Ref: 54)) that recommended the adoption of a modular deck arrangement.
Figure 6-1 Weight Estimates from Equip List 09b TLP Onshore Power: TLP Modular Algorithm
Algo and TLP Integrated Algo
It was concluded that weight in itself was not a considerable driver in selecting between the two deck
concepts.
NTE and the CoG limits previously defined. The trends of the estimated payloads are included in the
following figures.
Figure 6-2 Payload Estimate Trend - Local Power Figure 6-3 Power from Shore
Currently the Local GT power payload estimate is 30,980 tonnes and the Power from Shore option estimate is
30,881 tonnes, compared to the NTE of 31,000 tonnes. The location of the CoG is also within the current
limits as indicated in the figures below, although for the Power from Shore option it is approaching its
Western limit.
Figure 6-4 Horizontal Movement of CoG Figure 6-5 Variation in Vertical CoG
No analysis or design for the separate LQ module or for the flare tower has yet been performed.
The proposal as developed is based on option C. This allows all the common facilities to be incorporated in
the LQ building with no temporary duplication of plant or equipment, and requires the lowest initial footprint.
In practice it is envisaged that a compromise between B and C may prove to be the optimum solution.
6.5.3. LQ floor area
The total area required to accommodate the envisaged initial manning (for option C) is projected to be
approximately 4,000 m2, equating to just over 30 m2 per person. At this stage the Norsok CDS 101 table
entitled “Living Quarters Programme” has not been presented. The input data remains too fluid and requires
more clarity on manning levels and for the option development strategy to be agreed. The LQ weight estimate
is directly driven by the required floor area and volume. It is included within the overall weight estimate of the
platform.
6.5.4. LQ location
The overall location and external configuration of the LQ on the platform is already substantially determined
by high level requirements including crane and laydown locations, wind direction, helideck operational
requirements, optimum lifeboat locations, need for personnel protection, production risks, and blast
considerations. The LQ has not been designed to be located within the deck structure due to the shortage of
space within the utility module area.
6.5.5. LQ layout configuration
The current internal configuration provides justification of the required footprint, the required overall floor
area size and the overall weight estimate of the LQ. The layout demonstrates the relationship of the required
facilities and its external interfaces to facilities outside of the LQ module boundary; interfaces for personnel,
goods and services. These are, typically, the personnel entrances, the helideck, lifeboat locations, laydown
locations, crane access, stairtowers, and the location of services interfaces with the rest of the platform. The
layouts seek to present a viable configuration in the relationship of the LQ to the rest of the platform.
Within the boundary of the LQ itself, the location of the various facilities will be substantially dictated by the
external interfaces but with the option C layout there remains the flexibility to configure the functions to
different locations within that boundary. For the stated manning levels, the required size of the facilities will
not change much from the proposed areas allowing the optimum internal operational relationships to be
reconfigured or developed further in subsequent stages of the design.
Facilities provided outwith the LQ
For the purposes of clarity the following personnel areas are located outwith the LQ:
• Control Room: This is located directly below (along with some associated office space) and
accessible by the main stair and from the stair NE (dirty) stair.
• Escape Tunnel: In addition to the usual access routes to the LQ there is an escape tunnel, enclosed
within the deck, leading directly to the LQ NE Stair.
• Plant Room: The HV&AC air supply could come from an integrated common plant room with
the topsides HV&AC supply, with waste extract only located at the LQ.
Blast Wall
Although the Riser Bay will be enveloped on two faces with blast walls, the LQ itself will also have its own
defined level of blast resistance. The protection will extend upwards from the Control Room within the Utility
Deck below the LQ and across the exposed faces of the LQ above the weather deck level providing additional
blast protection to the TR.
Cabins
To keep the overall size and weight of the LQ down and to minimise the need when demanning for
mothballing some areas and for brownfield scope, one strategy is to incorporate a large number of two person
cabins that can, after commissioning, be used as one man cabins for the longer term.
Medical suite
The medical facilities are currently shown on Level 3. There are alternative views on the preferred operational
location but the facility can readily be located in Level 1 resulting in other facilities (such as recreation) moving
to an upper level. The allocated floor area remains largely the same irrespective of location.
6.5.6. Drawings
The following drawings have been prepared to illustrate the concept layout.
Brief descriptions of the process overview, telecommunications options, operations and maintenance
philosophies for Ormen Lange Phase 2 Floating Compression are provided within this document and their
impact on the SAS design is identified and these form the context in which this document has been developed.
• Ergonomically designed (CCR) and HMI displays will be provided, including large screen presentations
of the process, safety status and alarms requiring immediate operator attention. These shall also provide
a detailed visual process overview and Closed Circuit Television (CCTV) information
• Advanced alarm management, online visualisation and decision support
• Fall-back mechanisms for single sensor failure to maximise production availability
vendor’s remote office) to assist in fault diagnosis, systems updates. etc. All remote access shall be secure,
auditable and comply with existing Norske Shell’s IT policy and DACA security arrangements.
The SAS architecture and IT security arrangements shall be DACA compliant as per DEP 32.01.20.10-Gen
and the diagram below.
DACA Internet
Access
Access
Manager
Manager
Asset Mgt Historian Clients
PCAD
PCAD
Gateway CCR
PAS
CONTROL BUS
Fiscal Special *
HMI Control APPS Gateway IPF
Metering Monitoring
FIELD BUS
Version: 2.0
Attachment 2 – Ormen Lange Floating Compression Flow Control Schematic provides an overview of the
proposed control scenario.
7.6.3.1. Application of Modern Technologies and Processes
It is a recognised that there are Shell initiatives which all future projects must comply with unless otherwise
approved.
The two examples of these applicable to this project are Foundation Fieldbus,(FF), which involves the
implementation of advanced digital technology within the PCS, and Main Automation Contractors (MAC)
agreements in which all SAS components (i.e. PCS, ESD and F&G systems) are supplied from a single
nominated vendor.
Both of these issues are addressed in 37-1Y-NS-I15-00003 – Control and Automation Philosophy and the
application of these will be further developed during the design phases of this project.
7.6.3.2. Interfaces With Other Systems
In line with the existing 37-1A-102-00001 - Ormen Lange Automation Philosophy the following
communication interfaces will be applied for as required data exchange between the SAS and other equipment
packages:
• Modbus (serial communication)
• Profibus (serial communication)
• OPC (ethernet communication)
Again, this issue is addressed in 37-1Y-NS-I15-00003 – Control and Automation Philosophy and development
and application of these will be determined during the design phases of this project.
7.6.4. Safety systems
The offshore SAS consists of the ESD, PSD and FGS systems, each of which shall be designed to function
independently from, but interact with, each of the others.
The onshore SAS shall be upgraded to reflect the offshore installation and all associated onshore
modifications. It shall operate independently from the offshore systems but shall have the capability to
generate offshore shutdowns. As part of this, screen operated equivalents of the offshore hardwired PSD and
ESD pushbuttons shall be available to enable remote activation from onshore when the SAS is in remote
operations mode.
Attachment 3 provides a brief outline of the Safeguarding Process Flow Schematic.
The principal objectives of the safety system are:
• Prevention of harm to personnel
• Prevention of harm to the environment
• Protection of facility and equipment
Norsok S-001 requires, at the highest level, a function to be available at the Critical Action Panel (CAP) to
disconnect power to the ESD logic solvers, allowing activation upon failure of programmable logic.
The standard also requires safety systems to be designed for survivability such that Dimensioning Accidental
Loads (DALs) shall not cause loss of safety systems functions or local escalation.
7.6.4.1. Emergency Shut Down (ESD) System
The purpose of the ESD system is to monitor nominated process parameters and react accordingly to prevent
escalation of abnormal conditions into a major hazardous event, thereby limiting the extent and duration of
any such events that do occur.
The ESD system shall be designed for automatic sensing of abnormal conditions and automatic reaction by
shutting down and/or isolating the platform, the pipeline and equipment and, where appropriate,
depressurising the installation in a timely manner.
All instrumented protective functions in the ESD system shall meet or exceed SILs assessed in accordance
with the (IPF) classification methodology prescribed in DEP 32.80.10.10 – Classification and Implementation
of Instrumented Protective Functions and Norsok Standard I-002 – Safety and Automation Systems (Ref: ).
The ESD functions shall be arranged in a tree-structured hierarchy, in that a high level of ESD shall initiate
lower levels including PSD. All interactions between ESD, PSD, F&G and PCS shall be clearly identified on
Cause and Effects diagrams which will be generated during design.
The ESD system shall operate independently of the control system, with the required interfaces to other
systems again being identified and addressed during design.
The ESD logic solver shall, as a minimum, be certified as a SIL 3 safety system by a reputable certifying body
in accordance to IEC 61508, with all ESD outputs being fail-safe.
The survivability of the platform ESD and field components for all considered fire and explosions scenarios
shall be addressed during design. The ESD system shall not be dependent on local equipment rooms with
locations less safe than the CCR.
7.6.4.2. Process shutdown (PSD) system
The PSD system shall be designed to automatically shut down the production facility, either partly or
completely, as required to prevent abnormal process states from developing into hazardous events.
The PSD shall be designed as a safety system independent from the control system. The system shall have
built-in redundancy, with online diagnostics and allow for online replacement of the Central Processor Unit
(CPU).
The PSD system shall meet or exceed SIL levels assessed in accordance with the IPF classification
methodology prescribed in DEP 32.80.10.10 Classification and Implementation of Instrumented Protective
Functions.
The logic solver (firmware) compliance with IEC 61508 shall be documented i.e. certified/type approved by a
reputable certifying body. The logic solver software shall be protected against illegal access from external
sources.
The logic solver and essential utilities of the PSD system shall be located in a protected area that withstands
systems dimensioning accidental loads.
7.6.4.3. Fire and gas system (FGS)
The FGS shall be designed to monitor all air spaces where a fire or hazardous accumulation of flammable
mixture or toxic gas may occur and to automatically detect these events, alert personnel and initiate timely
executive actions in order to prevent or minimise escalation of the event.
The fire and gas detection system shall comply with the detailed requirements specified in DEP 32.30.20.11 –
Fire, Gas and Smoke Detection Systems (Ref: 8) and Norsok Standard I-001 – Field Instrumentation
(Ref: 111). The FGS shall comply with the minimum SIL requirement as specified in OLF Publication 070 -
Application of IEC 61508 and IEC 61511 in the Norwegian Petroleum Industry and meet or exceed SIL
assessment requirements as prescribed by the DEP.
The number, type and location of detectors shall be optimised using Company approved Fire and Gas
detector mapping software in accordance with the above DEP.
Details of the final siting and location of detectors, fire areas and allocation of fire protection skids shall be
incorporated in the dedicated HMI graphics and displayed in the CCR
The survivability of the platform FGS and field components for all considered fire and explosions scenarios
shall be demonstrated. The FGS shall not be dependent on local equipment rooms in locations less safe than
the CCR.
7.10. Metering
The need for metering of flare gas and fuel gas consumption has been identified as a result of CO2 tax
regulations. Norsok standard I-104 (Ref: 113) classifies flare gas and fuel gas measurement as Class C and
Class B metering systems with uncertainty limits of ± 5% and ± 1.8% of standard volume respectively.
Ultrasonic flow meters are recommended for these applications as they provide the necessary accuracy and
rangeability required.
A dedicated document 37-1B-NS-I15-0003 – C&A Metering Philosophy (Ref: 65) has been produced for
guidance during the design phase on all metering installations.
FUEL GAS
FUEL GAS
FLARE
FUEL GAS
TO EXPORT PIPELINE 1
FI
TIC PIC
TO EXPORT PIPELINE 1
HOLD 4 TIC
FT
FT
PdT FI
PdT
HG-27-HOLD
HG-27-2001
SC VG-27-HOLD
VG-27-2001
TEMPORARY PIG
LAUNCHER/RECEIVER
KA-27-HOLD
KA-27-1001
Kicker Line
Suction
LSLL
A-20-1001 Crossover
LSLL
Valve
LIC
FLARE
Discharge
Crossover
PA-27-2001A/B Valve
FIC FIC
PA-20-1001A/B
FI
Pigging bypass
valve
HG-27-HOLD
HG-27-2001
ESDV
VG-27-2001
VG-27-2001
MEG
KA-27-HOLD
KA-27-2001
A-20-2001
LSLL
LSLL
TO EXPORT PIPELINE 2
LIC
Riser
ESDV
FIC FIC
PA-20-2001A/B
FI
TO EXPORT PIPELINES
FLARE
FLARE
TYP COMPRESSOR TYP
TYP TYP RELIEF both trains
both trains
P both trains FLARE both trains 235 bara (HOLD 1, 2)
TYP FLARE FIRE
h trains FIRE
both trains 160 bara
BDV
80 145 bara
FLARE
145
BDV
FUEL 60
GAS RISER A
ESDV 80 2500# 1500# EXPORT PIPELINE 1
60 60
180 80
SP = 200
barg SP = 75 °C
SP = 130 barg
SP = 130 barg SP = HOLD ESDV
SP = 100 bara (Note 3) TSHH RISER B
PSHH
PSHH TSHH
PSHH EXPORT PIPELINE 1
PSHH
SP = 150 °C
SP = 150 °C HG-27-HOLD
HG-27-2001 TSHH
900# 1500# TSHH
110 110 160 130
110 130 150 160 180
60 60 241
VG-27-HOLD
VG-27-2001 150 180
80 120 2500# (HOLD 3)
130 25 160 60 TEMPORARY PIG
Increase to 180 120 LAUNCHER/RECEIVER
LSHH 241 80
160 bara? 110 KA-27-HOLD
80 KA-27-1001 900# 1500# 160
145 Kicker Line
25 25
Suction ESDV 25
60 80 120 LSLL
120
A-20-1001 Crossover
Valve 900# 1500# LSLL 120 80 110
60 60 145 160
80 80 120
145 900# 1500#
FLARE
80 150
145 Discharge
60 241 ESDV
ESDV Crossover
PA-27-2001A/B Valve
80
LSLL
60
Flexible
80
900# 1500# ESDV
150
80 FSLL
150 241
145 241 PSLL
1500#
ESDV
PA-20-1001A/B
ESDV
PSHH TSHH
PSHH Pigging bypass
PSHH TSHH
PSHH valve Flexible
HG-27-HOLD
HG-27-2001 TSHH
TSHH
Inboard
ESDV
VG-27-2001
VG-27-2001
MEG
LSHH
KA-27-HOLD
KA-27-2001
A-20-2001 ESDV
LSLL
60 160
LSLL
TO RISER B 80 241
(EXPORT PIPELINE 2)
Riser
ESDV
ESDV
ESDV
LSLL
ESDV
FSLL
PSLL
ESDV
PA-20-2001A/B
TO EXPORT PIPELINES
60 60
80 80
r.
8. Metering
8.1. Introduction
This section describes the work carried out to provide guidance on the selection of the most applicable
solutions for flow metering of the process streams, as identified in the attached metering Process Flow
Diagram (PFD).
In addition to the requirements to standard of equipment across both existing and new installations, the
recommendations contained within this section also take into account the project philosophy to construct the
offshore topsides in modular form at various different locations.
The intent of this document is to establish the requirements for flow measurement for each of the identified
process streams, determine the required accuracy for each installation and provide recommendations on the
appropriate applicable technologies. Each of the metering installations will be interfaced to the PCS for
monitoring and report generation. It is not intended that this all process streams are addressed but only the
major streams as identified in the attached PFD.
In addition to process requirements, metering shall be provided for flare gas and fuel gas as required for CO2
tax purposes. The existing onshore at Nyhamna shall be provided with access to all metering information via
the PCS communications network for remote comparison and report generation.
Notes
1 The above accuracy figures do not apply to the installed sensor but to the overall “presented” result.
2 Whilst it is not anticipated that fiscal metering will be required for this installation, accuracy
requirements for this are included in the above table for clarity.
8.2.2. Typical Examples of In-Line Instruments
The following are some typical examples of instrumentation used for process fluids metering. Note that this is
a typical list only and meters will be selected during FEED based on application and requirements.
8.3. Background
Development of the process fluids metering recommendations has taken into account the process design and
operational requirements. All metering shall be interfaced to the PCS, with required data being transmitted to
the Nyhamna onshore PCS.
8.3.1. Process overview
From the Main Concept Select Report, which was produced by Process as part of the Main Concept Select
Study, the floating compression design is based on the optimised configuration of two arrival separators and
two compression trains. Combined with the design of the inlet manifold, this will allow flow from any riser to
be directed to either of the separators and thus different wells may be processed at different arrival pressures.
This is as shown in Figure 8-1 Overall Process Flow Scheme.
Each of the topsides trains is designed to control the import of combined well fluids, separate the liquid and
gas phases, followed by compression of the produced gas and boosting of the liquid pressure. The gas and
liquids are then recombined and transported via a multiphase pipeline to the Nyhamna onshore plant for
further processing. The incoming water will be treated with mono ethylene glycol (MEG) to suppress hydrate
formation in the infield pipelines and the combined water and MEG transported to onshore along with the gas
and liquid hydrocarbons.
Provision will be provided for future installation of gas recirculation facilities to each of the subsea templates
as gas lift may be required later in field life to maintain fluid velocities, although this facility is not presently
shown on the process flow schematic in Figure 8-1.
FLARE Note 1
FUEL GAS
TO EXPORT PIPELINE 1
A/S A/S TC
XC XC
PT TT TC PC TO EXPORT PIPELINE 1
HOLD 1 FT PT TT
PT TT PT TT TC
PC FT
FI Note 1
E-2702
E-2701
SC
TEMPORARY PIG
LAUNCHER/RECEIVER
V-2702 K-2701
V-2701
K-2701
2nd STG
1st STG
Gap Control Kicker Line
Gap Control
LC
2001A LC
Suction
Crossover
LC
Valve
FLARE
P-2701 A/B Discharge
Crossover
Valve
FC FC FI
XI
P-2001A
PI TI
Pigging bypass
valve XI
E-2802
ESDV
E-2801
Note 1
MEG
K-2801
K-2801 V-2802
V-2801 2nd STG
1st STG
PI
001B
TO EXPORT PIPELINE 2
Riser
ESDV
P-2801 A/B
P-2001B
FI
TO EXPORT PIPELINES
Design life for the floating compression system is 30 years and target availability is 97.5%. For flow assurance
purposes, facilities for the detection of produced formation water will also be provided at topsides.
8.3.2. Process Control
Pressure and temperature within the arrival separators will be controlled at 80 bar(g) and a maximum of 80°C
respectively, with bulk separation of gas and liquids taking place within these vessels. Note that the separators
will be elevated by approximately 5 m to provide the required NPSH to the condensate export pumps.
In normal operation, each separator will be lined up to a dedicated process train consisting of separator,
suction scrubbers, compressors, water and condensate handling, aftercoolers and associated ancillary
equipment.
Gas flows will be measured at the suction of the first and second stage gas export compressors K-2701 and
K-2801 for the provision of inputs to the compressor anti-surge controls. During operating modes where the
suction crossover line will be open, these inputs will also allow calculation of the flow through the crossover
line. Note that it has yet to be determined whether a dedicated anti-surge bypass control loop for each
compressor is optimal or a single combined loop around both compressor stages would be the best solution.
Process control of the process will be via the PCS with interfaces to the ESD, PSD and F&G systems as
required.
8.3.3. Metering applications
Based on the Measurements Accuracy Requirements Table in Section 8.3.1 above, most process control
measurement will be to Class C but for identified metering requirements as listed below, installations shall be
to Class B (i.e. Liquids better that 2% and gas better than 3%). Note that there are no identified requirements
for Class A (Fiscal Standards) for these installations. Each metering installation shall consist of instrumentation
as detailed in the Typical Examples of In-Line Instrumentation Table in Section 8.3.2 above.
The identified metering requirements are based on Figure 8-1, with the philosophy that the process fluids will
be measured at various stages of both their individual and co-mingled states as follows.
1. Subsea metering will be provided as part of the subsea scope using Roxar multiphase meters. These are
already installed on existing subsea templates A, B and D and will be fitted on template C when installed
as part of this project. These meters have proven very successful on the existing installations with an
accuracy of +/- 5%.
2. The following shall apply to each of the process trains:
• The combined produced liquids will be measured on the discharge of the arrival separators
VA-20-1001 / 2001 respectively, downstream of the export condensate pumps minimum flow
take-off point. As liquids from the compressor suction scrubbers are recycled through the arrival
separators, and the meter will be installed downstream off this, this will ensure that only the total
flow of liquid to the export header from each separator is measured and the recycled volumes will
not be included.
• An additional flow meter will be installed at the export pump discharge for minimum pump flow
protection. Whilst the export pumps will be VSD, the spillback facility will be useful during start-
up, and when operating at turn-down or under process upset conditions.
• Gas from the arrival separators (VA-20-1001 / 2001) will be measured prior to the suction
scrubbers to give total imported gas.
• Gas flows will again be measured at the suction of the first and second stage gas export
compressors (KAG-27-1001 / 2001) for the provision of inputs to the anti-surge controls. One of
the main advantages from this measurement is that when operating in process train load sharing
mode, which requires the suction crossover line to be open, the flow in this crossover line may be
calculated. Note that it has not yet been determined whether a dedicated anti-surge bypass control
loop for each machine is optimal or a single combined loop around both stages is preferable.
• Gas will be measured immediately upstream of where the gas and liquid are recombined. A
significant advantage of this measurement is that when operating in process train load sharing
mode, which requires the suction crossover to be open, the flow in this crossover line can be
calculated by difference. In addition, it will also monitor the export gas flow leaving each
compressor train.
3 During FEED, consideration will be given to a leak detection system by comparison of appropriate
inputs.
4 Provision will be provided for the future of metering of gas recirculation to each of the subsea
templates, as this may be required later in field life in order to maintain fluid velocities.
5 Detection of produced formation water will be provided by the installation of water in oil in conjunction
with Coriolis mass flow meters with density measurement for comparison purposes. Sampling facilities
will be provided at various locations on the process facilities to enable the source of this water to be
determined.
6 Wet gas flow metering will be provided in the main bypass lines around each of the compression trains.
7 The need for metering of flare gas and fuel gas consumption has been identified as a result of CO2 tax
regulations (Norsok standard I-104 (Ref: 113) classifies flare gas and fuel gas measurement as Class C
and Class B metering systems with uncertainty limits of ± 5% and ± 1.8% of standard volume
respectively. Thus total gas to flare will be metered at the flare gas header and fuel gas will be measured
and accumulated to give a record of total gas use as fuel.
The measurement of the recombined flows by the use of multiphase flow meters in the final discharge
headers, immediately before these enter the subsea pipelines, was considered but is not considered
necessary for this installation.
Review and update of the on-shore metering at Nyhamna associated with this and other future projects
is being addressed by others and is specifically outwith the scope of this project.
Again, if required, pressure and temperature inputs for corrected volume or mass flows will be provided, either
from dedicated field transmitters or from process control instrumentation, if installed in appropriate locations.
8.4.3. Water in oil metering
For the detection of produced formation water within the hydrocarbon liquids, it is recommended that a
water-in-oil detector be installed, possibly in conjunction with a Coriolis mass flow meter with density
measurement for comparison purposes. Sampling facilities will be provided at various locations on the process
facilities to enable the source of this water to be determined.
8.4.4. Wet gas measurement
In order to allow measure production to proceed through either train in any cases where gas compression is
either not yet completed or is not operational, wet gas flow metering will be provided in the main bypass lines
around each of the compression trains. It is proposed that multi-phase flow meters be installed for these
applications with make and model being determined during FEED.
Table 9-1 Electrical Load List – 60 million scm/d Reference Case – GT Driven
Compression/Generation
Table 9-2 Electrical Load List – 60 million scm/d Reference Case – Power from Shore (PfS)
The Shell HSSE & SP Control Framework defines a Major Hazard as those hazardous substances, activities,
operations or conditions which are assessed as having a Consequence Severity of five or risk ranking of High,
as defined in the Shell Control Framework “Risk Assessment Matrix” (RAM). Table 2 shows the Major
Hazards identified for the Floater options [Shell Document Number 37-1Y-NS-F15-00012, Major Hazards
Identification Report, Revision 02E, May 2009 (Ref: 89)]:
Description Applicable to
MH
SS TLP Hybrid
MH-1 Topside Process Facility (Gas & Condensate systems, Fuel Yes Yes No
Gas)
Hydrocarbon
under pressure Loss of topside hydrocarbon containment from
compressors, separator vessels, piping and manifold
systems, when ignited, results in fire/explosion.
MH-4 Collision with third party vessel (supply, fishing, merchant Yes Yes Yes
vessels)
Ship Collision
MH-5 Incorrect ballast, loss of buoyancy, extreme weather, Yes Yes Yes
capsize, mooring failure, water leakage.
Loss of
Stability
MH-6 Earthquake, failure of load bearing members, extreme Yes Yes Yes
weather.
Structural
failure
In the management of MHs, further work will be required during subsequent project phases, e.g. bow-tie
analysis, finalisation of the physical effects modelling and the QRA, and finalisation of the performance
standards for the Safety Critical Elements.
As required by Norsok the following defined situation of hazard and accident (DSHA) have been identified
for the TLP [Shell Document Number 37-1Y-NS-F15-66010, TLP QRA, Revision 01R, February 2011
(Ref: 92)]:
DSHA 1 Hydrocarbon leak
1.1 Hydrocarbon leak in process areas
1.2 Leakage from risers and flow lines below/near TLP
DSHA 2 Acute oil leaks
2.1 Acute discharge of chemicals
System Definition
Hazard Identification
Risk Risk
Acceptance Criteria Reducing Measures
Frequency Consequence
Analysis Analysis
Risk Picture
Risk Analysis
Risk Estimation
Risk Evaluation
Risk Assessment
Table 10-3 GIR per area - Major accidents originating at the TLP
Combining the personnel distribution in the different areas with the GIR values per area gives the total GIR
for each group as presented in Table 10-5.
The results show that GIR values for all groups on the TLP are well below the criteria. GIR is however within
the ALARP region for all groups (10>GIR>0.1 per 10,000 yrs) and risk reducing measures should therefore
be identified.
The main contributors to the GIR values are helicopter transportation, occupational accidents and
fires/explosions resulting from process and riser leaks.
10.8.2. PLL and FAR values
The risk to personnel can also be expressed as PLL which is the annual number of fatalities and FAR which is
fatalities per 108 working hours. These risk measures represent the average fatality risk for all personnel for one
year of operation.
The average FAR for personnel on TLP is estimated to be 3.4. The contributions to the FAR value from
different accidents are presented in Table 10-6 and in Figure 10-3. The main contributors are the same as for
the GIR values.
Table 10-6 PLL and FAR - contribution from different accident categories
FAR per accident PLL (per year) FAR % of total FAR
Process accidents 2.3E-03 0.62 18 %
Riser accidents 2.0E-03 0.54 16 %
Ship collision 9.1E-04 0.25 7%
Ballast accidents 5.5E-04 0.15 4%
Occupational accidents 2.6E-03 0.70 21 %
Extreme weather 2.1E-04 0.06 2%
Dropped objects 1.1E-05 0.003 0.1 %
Helicopter collision3 4.6E-07 negl. -
Helicopter transportation4 3.8E-03 1.05 31 %
Total PLL and average FAR 1.2E-02 3.4 100 %
The PLL and FAR values have also been estimated for each main area. The results are presented in Table 10-7
and Figure 10-4.
Table 10-7 PLL and FAR per main area - major accidents originating at the TLP
6.0
FAR per Area
5.0
4.0
FAR
3.0
2.0
1.0
0.0
LQ Utility AreaRiser Bay Area
Process Area TransportWork accidents Average
• RPNs are installed on the Forward and Aft side of the TLP. This is where the two main cranes are
located on this facility [Email from Errol Callais (Auger Offshore Installation Manager) to Victor Ojabo,
10/02/11 (Ref: 15)].
• A yearly preventative maintenance is performed on the nets both visual and by Remotely operated
underwater vehicle inspections [Email from Errol Callais (Auger Offshore Installation Manager) to
Victor Ojabo, 10/02/11 (Ref: 15)].
• RPNs are still in place and remain in good condition [Email from Ronald Entzel (Senior Operations
Readiness Engineer) to Victor Ojabo, 07/02/11 (Ref: 16)].
• There has been one reported incident in which a vessel lost Delivery Point (DP), drifted and “bumped”
gently into one of the nets with no damage to the TLP, vessel or nets [Email from Errol Callais (Auger
Offshore Installation Manager) to Victor Ojabo, 10/02/11 (Ref: 15)].
Based on the effectiveness against protecting the centrally exposed risers from errant vessels and operational
experience of them on other TLPs it is recommended that RPNs are base case for Ormen Lange TLP.
10.11.6. Storegga slide (landslide)
The risk for a major subsea mudslide is negligible based on results from a former study considering the Ormen
Lange field development. However, the slide risk assessment study [Lund J.K. et al: "Slide Risk Assessment in
the Ormen Lange Field Development Area", SPE 86703, Society of Petroleum Engineers, 2004 (Ref: 122)]
reveals that the frequency for a shallow slide is in the area of 10-5 per year. This may represent a threat to the
stability of the platform. It is, therefore suggested to conduct further studies on the effect of shallow mud slide
on the anchoring system of the TLP.
10.11.7. Lifeboats
Project held meetings with two vendors concerning lifeboat design standards, both were carrying out a gap
analysis against DNV-OS-E406 [DNV Offshore Standard DNV-OS-E406, Design of Free Fall Lifeboats,
April 2010 (Ref: 106)] to ensure compliance against it.
The lifeboat drop height from the TLP is approximately 33 m, therefore the larger lifeboats must be used to
withstand the resultant impact energies from this drop height.
Maximum personnel on board will be 140 during commissioning. As Norsok requires N+1, three 70 capacity
lifeboats will be provided at the LQ. If Eastside lifeboats are provided the maximum foreseeable requirement
for escape from the process area would be during compressor maintenance work when there could be 12-
15 personnel in the process module. Therefore as N+1 must also be provided on the East side, two
70 capacity lifeboats would be provided.
Further work will be carried out on this during Define to ensure correct lifeboats are selected which comply
with DNV-OS-E406.
10.11.8. Explosion analysis
A detailed probabilistic explosion analysis in the process area including Computational Fluid Dynamics
simulations and equipment count on P&IDs will be conducted during Define to verify the explosion DAL
specifications made during Select.
10.11.9. Vessel collisions
The Petroleum Safety Authority Norway issued a note which stated they expect there to be reasonable
agreement between performed collision analyses and actual experienced collisions on the facilities on the
Norwegian shelf. To satisfy this requirement the QRA Visiting Ship Collision Assessment used a 7,500 tonnes
displacement supply vessel to reflect the fact that vessel size is continuously increasing.
The COAST database should be referenced during Define to identify the ship traffic in the Ormen Lange area,
and update the ship collision assessment if necessary.
Present Value (NPV) is assisted by the use of an Availability / Reliability model, an Activity Based Cost Model
(ACBM) and Criticality considerations.
The RAM base case model for the TLP has predicted;
• 95.7% availability for the 2 x 50% Electric Motor (EM) driven compressors and offshore power
generation
• 95.9% availability for the 2 x 50% EM driven compressors and onshore power generation.
The summarised results contained in the RAM model report (Doc No. GS.09.51414 (Ref: 21)) also shows the
result for each compression configuration case and how it supports the selection of the 2 x 50% EM driven
compressor. The availability % represents the expected actual capacity of the TLP production system over the
19 years field life.
An integrated model for the Integrated Production System will consider the reliability requirements to meet
the contractual gas supply obligations from Ormen Lange and Norske Shell availability and reliability
aspirations. Additional sensitivities will be done during FEED and Detailed Design to confirm the predicted
reliability numbers. During FEED the system sensitivity in terms of incremental availability / reliability needs
to be assessed and offset against Life Cycle costs.
Capacity
Capacity and turndown requirements will primarily depend upon contract and market conditions, and
availability requirements. The floating compression platform option is required to provide uninterrupted gas
supply to the onshore gas treatment facility at Nyhamna. Each item of equipment should be studied for its
ability to handle as wide a range of operating conditions as possible in order to minimise equipment count and
maximise flexibility.
Turndown philosophy
In general, turndown should be possible down to 25% of normal maximum throughput, without loss of
functionality. The shutdown philosophy will incorporate equipment recycle where possible and warm-up and
blow down will be avoided where risk considerations permit.
Turndown will be considered for all main utilities including power – this should also take into consideration
the ability to systematically manage power/load shedding.
There should be some means of pressurising the facility after a complete shutdown to facilitate a rapid start up
(use of Nitrogen and/or backflow from export trunk line).
Control and automation
In order to achieve the ambition of a second generation Integrated Operations Framework as outlined in the
(draft) OLF guidelines on “Integrated Operations for new projects”, an integrated control and safeguarding
system (hull, topsides and onshore treatment facilities) shall be developed. This will help to realise Smart Fields
operation, centralised real-time measurement, monitoring, control and safeguarding for gas compression,
liquid handling, power generation, utilities system operations and development planning.
The process control system will be part of the SAS. This allows remote monitoring and remote set point
control capabilities of appropriate parameters of the hull, facilities and subsea wells systems from both
offshore CCR and the Onshore CCR at Nyhamna. These parameters and levels of authority will be further
defined as part of a Control and Monitoring Philosophy during FEED. The business case for the upgrade of
the existing Multi-Purpose Dynamic Simulator used by Norske Shell will be further developed during FEED.
Production measurement and surveillance
Metering is required to fulfil a number of functions driven by regulatory, industry and internal requirements.
The metering functions relate to process control, sales quantity, and hydrocarbon accounting. Consistent with
a need to simplify facilities, metering equipment will be minimised to that deemed necessary to effectively
manage the business:
• Metering devices, flow conditioning equipment and ancillaries designed to meet the necessary level of
accuracy only.
• Sensors provided for real time condition and performance monitoring of critical equipment (e.g.
compressors) and for process performance monitoring.
• Sampling points with appropriate connections must be provided at key points throughout the process,
utilities and export system.
• All hydrocarbon sample points will be equipped with connections to drains and/or flare.
Operability and maintainability
The principle of minimum manning/intervention applies, with routine activities carried out during daytime
only. Apart from the design requirement for automation and remote monitoring and control, the normal
approach to be adopted shall be towards:
• Lay-out and spacing with segregated modules/locations and the possibility for easy expansion if
required.
• Easy and Safe access and facilities (e.g. skid-beams) to allow for modular change-out of components (no
in-situ major repair and/or overhaul of major equipment).
• Use of equipment standard to the rest of the existing operation as much as possible. Operability and
Maintainability will be particularly critical during Start Up and Shut operations, taking also into
consideration any potential problems with flow-assurance.
The Project should aim to select as much as possible similar types and makes of equipment to those existing:
• Reduce the need for different types of spare parts and hence minimises stockholdings.
• Allow interchange ability of equipment.
• Realise contract management advantages in equipment procurement.
The sparing philosophy will be based on Reliability and Availability Modelling. This study will be used to
determine the most optimum-sparing configuration to achieve the required availability in order to meet the
requisite production targets. A spares policy, compatible with the availability requirements of the Ormen
Lange future compression and Norske Shell, shall be established. Analysis of the requirements will be based on
reliability centred maintenance techniques taking into consideration replacement time and lifecycle costing for
each of the components. This shall also be one of the primary selection criteria for major machinery and
equipment purchase.
3. Provide a Microwave radio link from the platform to the Norwegian mainland at Gamlemsveten as the
primary link with a Very Small Aperture Terminal (VSAT) satellite system as backup.
4. A fibre optic cable embedded in a power cable providing power from onshore to the platform. Backup
will be provided via a satellite system.
The recommended solution to provide broadband communications links from the platform to the Nyhamna
control room is option three – a microwave radio primary link with satellite backup.
less critical than for a Semi-sub as no active ballasting is required (to compensate for weather or sea state) once
the installation is permanently installed (except in circumstances such as damage conditions or during major
lifting operations). It might therefore be possible to make the case successfully that the marine systems could
be operated remotely during steady state operations but it is too early to conclude this and further work will be
required during the Define phase to fully assess this in consultation with the appropriate Norwegian
authorities.
The cost implication of the NUI mode of operation for the floater has been evaluated for additional
deferment per year, field personnel cost per year and logistics cost per year. The Unit Operating Cost (level 2
estimate +25 / -15%) for the floater operation in the NUI mode is estimated at 0.25$/Barrels Oil Equivalent
(BOE) compared to 0.42$/BOE for minimum manning of the facilities. This significant reduction is mainly
due to reduction in logistics (flights and vessels) cost and personnel cost.
The cost and manning changes to achieve NUI operating mode will have some positive and negative cost
implication. The overall impact is a savings of about US$2.15 million/yr at US$50/BOE. However a
sensitivity run shows a loss of about US$3.77 million/yr at US$70/BOE. The overall impact on availability of
unmanning the platform is a reduction of about 0.2% of the average availability calculation for the platform.
The overall conclusion for the comprehensive NUI assessment is:
a) Since there is no known FOI with hydrocarbon processing and rotating equipment where remote
control and operation technology for marine systems has been successfully implemented, it is
considered unproven and therefore not recommended for the Ormen Lange floater platform NUI.
b) Carryout a full facility RAM study for the selected floater configuration and demonstrate the sensitivity
for the Normally Unattended Installation operating mode.
c) Review the Ormen Lange floater facilities operation risk profile to include the impact of operating in a
Normally Unattended Installation mode.
d) The Unit Operating Cost (level 2 estimate +25 / -15%) for the floater operation in the NUI mode is
estimated at 0.25$/BOE compared to 0.42$/BOE for minimum manning of the facilities.
e) The cost and manning changes to achieve NUI operating mode will have some positive and negative
cost implications. The overall impact is a savings of about US$2.15 million/yr at US$50/BOE and loss
of about US$3.77 million/yr at US$70/BOE.
f) A review of offshore host facilities in operation has shown that though NUI had been considered in a
number of oil and gas development projects around the world there were none found to have
successfully operated a floater NUI facility with compression and offshore power generation as
proposed in the Ormen Lange Future Compression floater.
g) Since there is no known FOI with hydrocarbon processing and rotating equipment where remote
control and operation technology for marine systems has been successfully implemented, it is
considered unproven and therefore not recommended for the Ormen Lange floater at this stage in the
project development phase. This is however an opportunity that will be further explored in the Define
phase.
h) The overall impact on availability for unmanning the platform is a reduction of about 0.2% of the
average availability calculation for the platform.
11.5. Logistics
A full pre DG3 Logistics, Infrastructure and Resources Assessment (LIRA) report has been prepared as part
of the concept selection study. Logistics accounts for between 15% and 20% of Project costs. It is also
responsible for 50% of the HSE Risk. The Ormen Lange Gas Compression Floater Concept project
requirements are evaluated against existing facilities used for the Logistics and Infrastructure Operations in
Mid Norway. The experience, facilities and learnings from Draugen and Ormen Lange Drilling Support
activities will be fully exploited and built into the logistics strategy.
The total amount of activity increase for Ormen Lange floater is estimated at 15% over current support
activities for Draugen, and two Exploration/Development Rigs. The movements of materials, equipment, and
staff should be coordinated and optimised and where possible the existing pool of Vessels, Helicopters, Base
facilities and Contracts should be used based on synergies and economics. CAPEX vs. OPEX Tradeoffs
should be reviewed in line with expected activities and production over the life cycle cost of the project and
where required, permanent facilities should be constructed to last the project life.
A number of Risks and Opportunities were identified as part of the LIRA study and these are listed below.
This will form the basis for further work in the Define phase.
Main Logistics Contraints/Limitations:
• Adverse Winter working conditions (improve working conditions)
• Helicopter Crew Change Operations (increase in Helicopter Passenger Miles)
• Supply base facilities (immediate need for expansion)
• Contractor Support Facilities (review and tender for additional services)
• Large overseas imported items seek Norwegian Customs ruling on exemptions before placing the
orders for long lead items (i.e. vessels, equipment modules, gas turbines etc).
OPEX Cost
120,000,000 160,000,000
140,000,000
100,000,000
120,000,000
80,000,000
100,000,000
60,000,000 80,000,000
60,000,000
40,000,000
40,000,000
20,000,000
20,000,000
0 0
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
Contingency Faciltiy
Logistic Support Bases Overhead
Sub Sea TA and Core Maintenance
TAX Annual Production Prod (BOE)
The scope of the OPEX estimate includes all direct and indirect expenditures related to the operation of the
assets for the floater base case option during the estimated operating period. The estimate does not include
any revenues, rejuvenation/abandonment costs and CAPEX to sustain gas production nor any OPEX
associated with pre-start activity. It should be noted that this is an incremental project, which extends the life
of an existing field with a well established support and management structure already in place.
All activities relevant to the OPEX estimate have been considered (See Figure 11-2 below). In addition to
Production and Maintenance (routine maintenance and plant turnarounds/offshore interventions) these
comprise HSE, IT, Human Resources (HR), Finance, Supply and Logistics, Marine and Business Management.
As an additional facility to an existing venture, the support organisation is largely in place already. The model
will capture any incremental support manpower requirement that is directly linked to the new facility as well as
the increases due to the requirement for a facility operations crew. All staff will be assumed to be local
Norwegian staff with manning levels taken from the manning strategy developed for the base case of the
project. An initial manning level 30% higher will be used for the first two years with a reference date of 2018
where the manning will be as in the project plan then decreasing to 85% to simulate the mature operations
state. Additional manpower has been assumed for turnaround/ major shutdown periods.
Methodology
An Asset/Activity model was constructed using the Ope$t ® software to enable a systematic itemised build-up
of the estimate. All cost elements have been categorised as manpower, services, materials, tools or CAPEX.
Risk Areas
The following risks were identified during the case building.
• Alignment and scheduling of major shutdown events in line with availability studies and changes to
unplanned shutdown data.
• Project requirement to review and possibly change Technical, Economical, Commercial, Organisational
and Political (TECOP) review for contingency.
• Waste costs are based on an estimated total waste volume and should be updated as a higher degree of
certainty is gained.
• CO2 tax is based on Norwegian Rates for 2010/11 across the life of the operate phase. Therefore any
changes in the tax rate will affect the model estimate.
• NOX Tax is currently not included in the model as this may be better captured in the economics model
so that the tax rate can be more easily tracked.
• Power Tariff cost change in relation to gas price cannot be estimated across the life of the operate
phase, therefore presenting a risk to the estimate result.
37-1Y-NS-C19-00001
Equipment List 60MSm3d Reference Case GT Driven Option 2x50% Rev07m.xlsx
EXCEL FILE TO BE REPLACED BY LIVLINK HYPERLINK (HOLD)
37-1Y-NS-C19-00001 24/03/2011
High Strength
duction GC 3.40 9.00 9.1 139.0 188.0 145 2000000 Mangiarotti quotation 10/04/09
Carbon steel
14 suction
Sulzer Quotation 03/12/10
duction GC 4.6 1.4 1.4 6.4 8.4 9.4 sulzer 369 450 143 150 10 - 60 -10 / 80 C6 112.9 m3/h 1,800,000
GSG 80-260 / 11 BB5
discharge
Ormen Lange Compression TLP - Topside Concept Select Report Revision: 02
A summary topsides weight for the equipment used in the GT Driver TLP concept option is detailed below.
At present these are estimated design weights from vendor quotations or calculations. The final topsides
equipment weights will be determined in FEED and details design phases.
• Reception facilities
• Compression
• Utility
• Safety
• Electrical power generation and distribution
• Control and automation
• Subsea support
• HVAC
• Risers
• Mechanical handling
• Hull systems.
The hull systems equipment are located in the TLP legs and are therefore are considered for final topsides
weight and cost estimates. The hull systems electrical requirements are taken into account in the electrical
loads.
Full details of the Power from Shore TLP option equipment list is attached below:
37-1Y-NS-C19-00002
Equipment List 60MSm3d Reference Case Power from Shore Option 2x50% Rev07M.xlsx
EXCEL FILE TO BE REPLACED BY LIVLINK HYPERLINK (HOLD)
A summary topsides weight for the equipment used in the Power from Shore TLP concept option is detailed
below. At present these are estimated design weights from vendor quotations or calculations. The final
topsides equipment weights will be determined in FEED and details design phases.
This information is being provided as input only to assist the development of the final CAPEX cost report.
13. Conclusion
The topside design for the TLP has evolved significantly since the last report was issued in late 2009. The key
changes to highlight are:
• The process design has been expanded to now include two stages of compression to cater for the
revised subsurface conditions and a desire to achieve lower abandonment pressure at the wells to
maximise UR.
• The topside layout has been re-configured into a modular arrangement to simplify the technical
interface with the Hull.
• Extensive reviews have been carried out to ensure that we have a robust equipment list and suitable
allowances and contingencies added to make sure we have a robust weight and CoG estimate for the
global analysis.
• The overall topside dimensions have been aligned with the latest Hull dimensions.
• Extensive IPSM studies have been performed to optimise the topside design in terms of flow and
compression power.
• Availability and reliability studies have been performed on the whole OL production system to optimise
the compressor configuration and inform the sparing philosophy.
• Detailed QRA studies have been performed to quantify the overall TLP risk picture and also identify
risk mitigation opportunities to be work further in the next phase.
• Operations personnel have been fully engaged in the development of the concept at all stages.
• The PDMS model has been developed to a high degree, including detailed modelling of the topside/hull
interfaces.
Overall the proposed topside concept is now at a relatively mature stage. The subsea and substructures
concepts are at a similar level of definition and the interfaces are well understood and documented.
There are still a number of concept optimisations to be performed between now and the start of FEED. Some
of this will be done as part of the BfD preparation in Q2 2011 and some might be left to early FEED
depending on the level of definition required to make the decision. One key decision still outstanding is the
selection of local power of PfS. This decision will need to be made prior to start of FEED.
The next step in the development of the topside design is the preparation of a BfD. This will be done
according to PG08 and is estimated to be complete by the end of Q2 2011. The focus will then shift to FEED
planning and this phase of work is currently planned to commence on the 1st Sept 2011.
14. Abbreviations
ACBM Activity Based Cost Model
BEM TEMA Exchanger Nomenclature (“B” Bonnet (Integral Cover); “E” One Pass
Shell; “M” Fixed Tubesheet like “B” Stationary Head)
DP Delivery Point
dP Differential Pressure
EM Electric Motor
FF Foundation Fieldbus
GC Gas Compression
GE General Electric
GT Gas Turbine
HC Hydrocarbon
HP High Pressure
HR Human Resources
HU Hull
HV High Voltage
ID Internal Diameter
IO Integrated Operations
IT Information Technology
KO Knockout
LP Low Pressure
LQ Living Quarters
LV Low Voltage
NTE Not-to-exceed
OL Ormen Lange
PA Public Announcement
PD Pressure Differential
PE Production Efficiency
PM Power Module
PQ Pressure Flow
RB Riser Bay
RV Ranking Value
SMS Schoepentoeter-mistmat-swirldeck
SMSM Schoepentoeter-mistmat-swirldeck-mistmat
SV Screening Value
TR Temporary Refuge
UR Ultimate Recovery
UV Ultraviolet
WE Well Engineering
WT Wall Thickness
15. References
Regulations
1. Norwegian Maritime Directorate’s Regulation No. 687, 9 May 2003
2. Regulations relating to measurement of petroleum for fiscal purposes and for calculations of CO2 tax
(The measurement regulations), The Norwegian Petroleum Directorate, 1 Nov 2001.
Codes of Practice (EA), Engineering Procedures (EM) and Engineering Standards (ES)
12. EA/010, Engineering Reference Document, code of practice, Design of Utility Air Systems for
Offshore Installations
13. EA/013, Engineering Reference Document, code of practice, Design of Diesel Oil Systems for
Offshore Installations
14. EA/041, Engineering Reference Document, code of practice, Drainage systems for Offshore
Installations, Rev 1.
Miscellaneous
15. Email from Errol Callais (Auger Offshore Installation Manager) to Victor Ojabo, 10/02/11
16. Email from Ronald Entzel (Senior Operations Readiness Engineer) to Victor Ojabo, 07/02/11
17. EP2005-0310
18. GEN-EPA-E13-00030-001, HSE Action Close Out Procedure, Revision A01, October 2005
19. GEN-EPA-M18-00001-001-A02, EP Projects Layout Development Procedure
20. GEN-EPA-M19-00003-001-A01, PDMS Model Specification
21. GS.09.51414, RAM model report
22. HSE Case (Volume 3: HEMP Requirements, Tools and Techniques)
23. KDL OL-1,06.08.03.02, Materials Selection
24. KD SPh3-FE-04-04, Start-up Chemical Injection Storage on Facility
25. KDL SPh3-FI-01-05, Floater Inlet and Export Manifolding Configuration
26. KDL SPh3-FI-01-06
95. 37-1Y-NS-S15-00011, Floating Compression TLP Concept - Weight, Payload & CoG Estimates for
Topsides
96. 37-1Y-NS-S15-00026, Floating Compression TLP Concept - Modular Deck Structural Analysis Report
97. 37-1Y-NS-T15-00001-01, Ormen Lange Broadband Telecommunications Concept Study
98. 37-1Y-NS-X02-00008, Design Pressure Ormen Lange Future Compression Project Select Phase, Rev
05, August 2010
99. 37-1Y-NS-X15-00032, Ormen Lange Phase II, Floating Compression Select Phase, TLP Floating
Systems Concept Summary Report
100. 37-1Y-NS-X15-00012, Ormen Lange Floating Compression concept selection report, October 2009
101. 37-1YB-NN-P15-00001, Ormen Lange Compression TLP Subsea Report, Rev 02, Feb 2011.
Industry Standards
102. API 521
103. API RP 521
104. Application of IEC 61508 and IEC 61511 in the Norwegian Petroleum Industry, OLF Publication 070
105. CAA CAP 437, Offshore Helicopter Landing Areas – Guidance on Standards
106. DNV-OS-E406, DNV Offshore Standard, Design of Free Fall Lifeboats, April 2010
107. ISO 14122-1
108. ISO 23251
109. NHT-I52-00049, Safety and Automation Systems – Supplement to I-002
110. NORSOK standard C-004, Helicopter Deck on Offshore Installations
111. NORSOK standard I-001, Field Instrumentation
112. NORSOK standard I-002, Safety and Automation Systems
113. NORSOK standard I-104, Fiscal Measurement Systems for Hydrocarbon Gas
114. NORSOK standard L-001
115. NORSOK standard L-002, Piping Design, Layout and Stress Analysis (Edition 3)
116. NORSOK standard L-005
117. NORSOK standard P-100, Process Systems, Edition 3, Nov 2010
118. NORSOK standard R-001
119. NORSOK standard S-001 Technical Safety (Edition 4)
120. NORSOK standard S-002
121. NORSOK standard Z-013
122. SPE 86703, Society of Petroleum Engineers, Slide Risk Assessment in the Ormen Lange Field
Development Area, 2004.
16. Holds
PART 3 – PROCESS ENGINEERING
1. Section 2.3.1 Import risers and inlet manifold arrangement
2. Section 2.3.3 Compression
3. Section 2.4.2 Inlet separators and first stage suction scrubbers
4. Section 2.4.3 First stage compressor and inter-stage design pressure
5. Section 2.12.5 Inert Gas System
6. Section 2.12.8.1 MEG injection
7. Section 2.12.9.1 Capacity of the freshwater system design
PART 15 - ABBREVIATIONS
PART 16 - REFERENCES