CALCULATION OF NET PRESSURE IN THE HEEL SLAB

pmax = 68.03 kN/m2


pmid = 22.46 kN/m2 Eqn. 38
pmin = -3.17 kN/m2
Pv = 77.55 kN/m2 FSTEM + FBASE + FSOIL Eqn. 39
f1 = 55.09 kN/m2 Pv - pmid
f2 = 80.73 kN/m2 Pv - pmin

w1 = 1.80 m
MWALL = 116.9365248 kN-m Moment at the face of the wall
Mu = 187.0984397 kN-m Design Moment
Rmz = 3.901053766 N/mm2
% steel ρ = 0.010146081 Steel ratio
2
Ast = 2221.991805 mm
s= 50.90 mm

PROVIDE: 12 mm dia. bars at 50.00 spacing

CHECKING FOR SHEAR

V = 122.237208 kN Total shear at wall (f1+f2)/2*b2 Eqn. 40


Vu = 0.6698 N/mm2 Design Shear Stress
Vc = 0.7937 N/mm2 Allowable Shear Stress SAFE!

c) Design of Toe slab (Bottom Reinforcement)

t2 = 300.00 mm Thickness at base slab


db = 12 mm Diameter bar used
cc = 75 mm Clear cover to the main bar
d.eff. = 219 mm Effective depth Eqn. 28

CALCULATION OF NET PRESSURE IN THE TOE SLAB

pmax = 68.03 kN/m2


pmid2 = 25.31 kN/m2 Eqn. 41
pmin = -3.17 kN/m2
W2 = 35.25 kN/m2 FBASE
f3 = 9.94 kN/m2 W2 - pmid2
f4 = 38.43 kN/m2 W2 - pmin
f5 = #DIV/0! kN/m2 (f3-f4)/b2*(d.eff/1000)+f4