Professional Documents
Culture Documents
Lecture 04 DESIGN PRINCIPLES & PRACTICE OF SUBSTATION and Location
Lecture 04 DESIGN PRINCIPLES & PRACTICE OF SUBSTATION and Location
1
1/10/2024
Milkias B.
Adama Science and Technology University, Department of Electrical Power & Control Engg. School of Electrical Engineering & Computing
1/10/2024
Milkias B.
PLANNING
POWER SYSTEM
4
OUTLINE
▪ 1. FUNDAMENTALS
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
Introduction
Planning & economics
▪ 2. Load data and Forecasting
▪ 3. Power quality and Reliability analysis
▪ 4. DESIGN PRINCIPLES & PRACTICE OF SUBSTATION
Substation sizing and spacing
Substation location
Effect of changing load density
Effect of changing primary voltage
Cost interaction of substation size and spacing vs primary voltage
and load density
▪ 5. Power System Quality Analysis
Project evaluation
Financing
Project phases
Key points
▪ 6. UNIT COMMITMENT
Unit commitment
Spinning reserve
Priority list method/Merit order scheduling
1/10/2024 Milkias B. 5
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
4.
1/10/2024
Milkias B.
DESIGN PRINCIPLES AND
PRACTICE OF SUBSTATIONS
6
4. DESIGN PRINCIPLES AND PRACTICE OF SUBSTATIONS
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
▪ The major points which help to optimize planning in close evaluation of ones
interrelationship with the others are as follows:
1. substation spacing in the system,
2. size and number of substations,
3. sub-transmission voltage and design, and
4. distribution feeder voltage and design.
Therefore, determining the most cost-effective design involves evaluating the
transmission-substation-feeder system design as a whole against the load pattern, and
selecting the best combination of transmission voltage, substation transformer sizes,
substation spacing, and feeder system voltage and layout.
1/10/2024 Milkias B. 7
▪ In design interrelationships, how the cost, electrical performance and
reliability of the example system change as the characteristics of its
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
1/10/2024 Milkias B. 8
2.1 Substation Size and Spacing
◦ The set of substation service areas for a T&D system must "tile" the utility service
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
territory, covering all locations where there is any demand, and each substation must
have sufficient capacity to serve the load in its service area.
For instance, six substations serving an area of 108 square kilometres, evenly
spaced in a hexagonal pattern 4.56 kilometres apart. Each serves 18 square
kilometres with a peak load of 58.5 MW (65 MVA), with 81 MVA capacity, for an
80% utilization rating. If the capacity of each substation were doubled, to 162
MVA, each could serve twice the area - 36 square kilometres - and only half as
many substations would be needed. Area, and load, increase with the square of the
spacing, so doubling the capacity and area served will result in an increase of 41%
in permissible substation spacing, in this case from 4.56 to 6.45 kilometres.
1/10/2024 Milkias B. 9
▪ Interactions and impacts of changing substation size: One way to
change the capacity of the substations in a system is to vary the number of
transformers of a standard size used in each. Another option for varying the
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
capacity and hence the potential service area of a substation is to vary the
size of the transformers while keeping their number constant. Here
regarding about cost impact, the cost of any level is lower if larger
transformers are used to attain a capacity figure.
The installed cost of a 54 MVA transformer is almost always substantially less than twice that of a
27 MVA transformer, so that even a larger savings is effected by increasing capacity to 162 MVA
by using three 54 MVA transformers instead of six 27 MVA units. Thus, a 54 MVA transformer,
installed, would cost $1,350,000 rather than the $1,550,000 cost of two 27 MVA units.
(two transformers), each serving a peak load of 43.3 MVA. Each now
serves only 66% as much area, and the feeder system emanating from it
must distribute only 66% as much load.
dss:
Where fv is the fixed cost at voltage V, sv is the slop of the cost in the linear range, F is the total
length of feeder routing (F=A*r), dss is the avergage distance b/n substations , A is area served,
L is load served(L=A*M), M= load density(MW/mile sq.), r = feeder route density (mile/mile
sq.)
The required reach for feeders in a distribution system will be roughly .75
times the substation spacing.
1/10/2024 Milkias B. 11
Cost of the feeder system on a per
MW basis increases linearly up to the
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
1/10/2024 Milkias B. 13
The feeder system has an opposite economy of scale.
Larger substations, and the greater area that their feeder systems most
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
capacity to put at each one are the strategic moves in power delivery
planning. For although substations themselves represent a minority of
system cost, they define the overall character of the T&D system.
They are the meeting place between transmission and distribution, a clue
in itself to their importance. But more important, their locations define
the end points of delivery need at the transmission system, as well as the
starting points for the feeders at the distribution level.
This last is particularly important, for the selection of a poor site from
the feeder standpoint can increase the cost of the T&D system by a great
deal.
1/10/2024 Milkias B. 15
The substation level, like other levels of a power delivery system, must
cover the entire system. Power delivered to each customer must come
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
Each substation area consists of the part of the service territory that the
substation serves, its area covered by the feeder system emanating from
its low-side buses.
1/10/2024 Milkias B. 16
For any existing or planned substation, there is a best location for it in
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
Occasionally, these two locations are identical, but usually they are
slightly different. Regardless, usually the economic aspect rules
determination of location.
The optimal location for a substation from the cost standpoint is almost
never the lowest cost site (i.e., cheapest land), but is instead the best
overall compromise between all the cost elements involved in the
substation - land cost, site preparation cost, cost of getting transmission
in and feeders out, and proximity to the loads it is intended to serve.
1/10/2024 Milkias B. 17
The perpendicular bisector rule of identifying a substation
service area identifies the set of all points equidistant between a
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
While simple, this method in one form or another was used to lay
out a majority of substations currently in use worldwide.
1/10/2024 Milkias B. 18
Modem substation sitting computer programs use accurate analytical
approaches that build upon the concept's guiding rule: serve load from
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
Serving each customer from the nearest substation assures that the
distribution delivery distance is as short as possible, which reduces
feeder cost, electric losses costs, and service interruption exposure.
1/10/2024 Milkias B. 19
Suppose that the substation in figure above is moved one mile to the west,
while still being required to serve the hexagonal (shaded) area identified as
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
its service territory in that figure (i.e., that area's boundaries and territory will
not change).
The major cost impact affected by this change in location would be on the
feeder system. The new site means the substation is closer to some loads
(those to the west), and farther from others (those on the east side of its
service territory).
MW mile = load density length of edge (distance moved )
2
1/10/2024 Milkias B. 20
Certainly, if distribution planners were forced to move a substation away
from its theoretical optimum location, they should make whatever
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
adjustments they could do the rest of the system layout in order to reduce
the cost impact as much as possible.
One option is to change the service area of the substation and its
neighbours, rather than leave them fixed, as was the case considered
above.
The substation in the figure is moved one mile west, and its
service area boundaries are "re-optimized" to minimize overall
impact on the feeder system, slightly changing substation service
area shape (but not its area, although the areas of its neighbours
do change). All substation boundaries in this system satisfy the
perpendicular bisector rule, optimal in a situation where load
density is uniform and there are no geographic constraints.
2. Small deviations (less than 1/3 mile) in the actual substation site from the
center feeder cost create insubstantial cost increases. (A 1/3 mile
difference in the previous condition carries a cost impact of $37,000, less
than 1% of the substation's cost and less than .2% of the sub-
transmission-substation-feeder cost.)
3. Large deviations in actual site location from the center of feeder cost are
very expensive - moving the substation in the previous example 1.2 miles
(6,400 feet) costs $1,000,000.
1/10/2024 Milkias B. 22
4. Whenever non-optimal sites must be accepted, planners should re-plan the
associated service area boundaries and feeder network for the substation
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
6. T&D systems with higher primary voltage are less sensitive to deviations in
their substation location.
7. T&D systems with higher load density are therefore sensitive to deviations
in their substation locations.
1/10/2024 Milkias B. 23
4.3 Effect of Changing load density
When density is doubled, a substation whose capacity was previously
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
sufficient to serve an X mile radius around It now can serve only an X/1.41
radius. The same radius as before can
associated equipment.
The resulting impact of voltage level on the feeder system cost versus substation
spacing diagram (at the base example system density of 3.25 MW/mile2). The curve
for a 25 kV feeder system is plotted along with that for 12.47 kV.
The vast majority of line segments in a feeder system are very lightly loaded. Therefore,
at small substation spacings - those dominated by fixed costs -overall feeder system cost
increases because of the higher fixed cost of 25 kV feeder hardware. This occurs over
most of the viable range of substation spacing - the capability of 25 kV to carry load and
reach greater distances at lower cost does not pay off until beyond eight miles spacing.
1/10/2024 Milkias B. 26
4.5 Cost interaction of substation size and spacing vs primary voltage
and load density
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
If load density is high enough, then 25 kV is more economical than 12.47 kV.
Now, the curves cross at just over two miles substation spacing, instead of at
eight miles, as at 3.25 MW/mile2.
For any substation spacing beyond two miles, the higher primary voltage
provides superior overall system economy. Based on the information, optimum
substation spacing and size can be determined.
1/10/2024 Milkias B. 27
Total cost of T&D system utilizing 34.5 kV, 25 kV, or 12.47 kV as primary
distribution voltage, as a function of substation spacing, at 6.50 MW/mile load
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
density.
The 25 kV voltage is now more economical than 12.47 kV for all but very
small substation spacing. However, 34.5 kV is not the most economical at any
spacing.
The cost behaviour shown here is representative of all but very rare, extremely
strange power systems. However, different systems will have slightly different
quantitative characteristics than shown here; the curves given here should not
be used as design rules of any utility system. Rather, planners should use the
principles shown here to develop similar analysis of their own system.
1/10/2024 Milkias B. 28
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
1/10/2024
Milkias B.
29
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering Electric Power/ Transformer Sub station
Circuit breaker
Higher availability through 10,000 times proven chamber
1-9 slide – P 76-81 Understanding_Electric_Power_Systems_0471446521
SUBSTATIONS
• They provide a location where transformers can be connected to feed power into
the sub transmission or distribution systems.
• They provide a location where transmission lines can be de-energized, either for
maintenance or because of an electrical malfunction involving the line.
There are a number of designs used for substations. however, there are elements
common to all:
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
• Bus − the electrical structure to which all lines and transformers are connected.
- open air and enclosed type.
• Protective relays
- monitor the voltages and currents − The relays actuate circuit breakers.
• Circuit breakers
➢ capable of interrupting the flow of electricity to isolate either a line or a transformer.
➢ extinguishing the arc that forms using a variety of technologies such as oil, vacuum,
air blast or sulfur hexafluoride (SF6).
➢ These fault current levels can be 20 or 30 times larger than the current flow under
normal operating conditions, that is, thousands of amperes.
➢ Circuit breakers also allow lines or transformers to be removed from service for maintenance.
• Transformers
➢ To connect facilities operating at two different voltage levels.
➢ On load and Off load or both Tap changing at the higher voltage side
➢ An autotransformer, which is used when facilities at nearly the same voltage are to be connected
• Disconnect switches
➢ Used to open a circuit when only “charging” current present is due.
➢ To connect or disconnect circuit breakers or transformers which are not carrying load current.
• Lightning arrestors
➢ To protect transformers and switchgear from the effects of high voltage due to lightning stroke or
a switching operation.
➢ To flashover when the voltage at the transformer exceeds a pre-selected level which is chosen by
the station design engineers to coordinate with the basic insulation level of the transformer (BIL).
• Metering equipment
➢ To measure line and transformer loadings and bus voltages so operating personnel can ensure that
these facilities are within acceptable limits.
• Shunt reactors
➢ To control high voltages that occur especially at night due to the capacitive effect of lightly loaded
transmission lines.
➢ to reduce or control the high voltages that can occur when a sudden loss of a block of customer
load occurs.
➢ The windings, insulation and the external tank are similar to those used for transformers.
• Series reactors
➢ Installed in a transmission line to increase the impedance of the line, to decrease current levels
in the event of short circuits, or to reduce its loading under various operating conditions.
• Shunt capacitors
➢ To provide mVArs to the system to help support voltage levels.
• Series capacitors
➢ To reduce the effective impedance and the electrical angle between the sending and the receiving
parts of the system of a long transmission line and enabling more power to flow over the line
and increasing stability limits..
• Phase angle regulating transformers
➢ To control power flow through a transmission line
• FACTS (Flexible ac Transmission Systems)
➢ Increased power transfer capability, rapid voltage control, improved system stability, and
mitigation of sub-synchronous resonance
It should include:
C) 1 ½ CB
station
2x Sectionalizer CB and
4x Disconnector Switch
yard
2x Disconnector with
earthing blade
2x Regulated step up
Transformer
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
substation:
Schematic diagram of the step up transformer
Schematic diagram of the step up transformer
substation:
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
3x
ORC
533000
/500
TVV-1200-2
1200 MVA
24 kV
300 MVA
TRDNC 20kV
40000/35
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering Schematic diagram of the supply system for self usage at generating station, 6kV:
33-220 kV
Reserve
transformer
for
6 kV self usage
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering at generating station, 6kV:
Schematic diagram of the supply system for self usage
Schematic diagram of the step up transformer substation:
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
Schematic diagram for self usage(0.4 kV) at the power plant rated 300 MW
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
330 0.1
330 / / 0.7 kV
3 3
Busbar arrangement 2 AC – 600/72 Mark 839 - 74
❑ To select a structural scheme (quantity, type and rating of main power transformers with
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
their connection).
❑ To select electrical diagram of the distribution yard of all voltage values.
❑ To select power supply scheme for auxiliaries including quantity, type and rating of
transformer for self usage.
❑ To calculate short circuit current which enable for selection of electrical apparatus and cables,
and selection of technical and economical mechanism for faulty(S.C) conditions.
❑ The existing cable lines size which are supplied from low voltage side should be
preliminarily chosen.
❑ To select the electrical apparatus circuit breakers disconnectors fuses and instrumental
transformers(CT & VT) and decide the content of measuring devises. All instrument
transformers should be selected by voltage rating, class of accuracy, continuous
load current and connection system.
Substation Layouts
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
❑ Security of supply
- Category 1 No outage necessary within the substation for either maintenance or fault;
- Category 2 Short outage necessary to transfer the load to an alternative circuit for maintenance
or fault conditions;
- Category 3 Loss of a circuit or section;
- Category 4 Loss of substation;
❑ Extendibility
- for future extension work.
❑ Short circuit limitations
❑ Maintainability
❑ Land area
❑ Operational flexibility ❑ Cost
❑ Protection arrangements
ALTERNATIVE LAYOUTS
Single busbar
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
Busbar faults will only cause the loss of one circuit. Circuit
breaker faults will involve the loss of a maximum of two
circuits.
Full mesh
ALTERNATIVE LAYOUTS
Ring
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
Double busbar - Transfer bus the most popular open terminal outdoor substation
arrangement throughout the world.
❑ By the given data, to draw the axis X and Y plan and indicate the centre of electrical
load of each load (factory or district)
❑ On the bases of the dimensions of the plotted territory , to select the scale(mactive , mreactive)of the
load which is oriented to the max. and min. suitable radius- Rmin; Rmax.
Qmin
mactive. p =
Pmin
; m = ;
Rmin
2
reactive. p
R 2
min
Pmax Pmax
mactive. p = =
; active. p R 2 ;
m
R 2
max
max
❖ The value of “m” can be rolled to the full no. and applied for active and reactive loads.
❑ To determine the radius of the circles of all active and reactive loads of the
consumers.
P
Ractive. p = ; Rr .i = 2 10−2 Qi ;
mactive. p
Where, Rmin and Rmin – the radius of the active and reactive load, km;kW/km2
P ; Q – the active and reactive load of the consumer, kW and kVar
mactive; mreactive – the scale for active and reactive load, kW/km2 or kVar/km2
If only P and Cos φ are given Q = Ptg
Selection of location for Distribution Substation
Finding of load centre coordinates
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
PX i i PY i i
X a0 = i =1
n
; Ya 0 = i =1
n
; Centre A (Xa0 ;Ya0) – location of the main Distr.SS
P i P
i =1
i
i =1
QY
n
Q X i i i i
X r0 = i =1
n
; Yr 0 = i =1
n
; Centre B (Xr0 ; Yr0) – location of the Comp.
equipment.
Q
i =1
i Q
i =1
i
Where,
Xa0 ;Ya0 – coordinate of the active electrical load centre
Xr0 ;Yr0 – coordinate of the reactive electrical load centre
Selection of location for Distribution Substation
Given data: Topology* 3 x 2 km with power loads consumers (1 div. = 0.1 km)
Number of consumers
Parameters
Load 1 Load 2 Load 3 Load 4 Load 5
P, kW 100 160 1000 400 25
X, km 0.6 1.45 2.4 1.55 0.4
Y, km 1.45 1.25 0.9 0.55 0.4
Cos φ 0.7 0.75 0.9 0.8 0.6
Find: a) Determine the coordinates of active electrical load centre
b) Determine the coordinates of reactive electrical load centre
c) Plot the given data on the load topology graph.
Solution:
a) Plotting the electrical load centers of each consumer on the load topology, with scale of mg=0.2km/cm.
(Fig.1)
b) Calculating the radius of a circles of active and reactive load of each consumer using the above scale.
c) Calculating the scale for active load (ma) using the above scale
Taking the lowest load(load-5) radius Ra5= 0.1km, thenmactive. p =
Pmin = 25/3.14*0.12=796≈800 kW/km2
;
Rmin
2
P3 1000
And we find the highest load (load 3)radius using ma; Ra.3 = m ; = = 0.63 km
a .3 3.14 800
if the max. load Ra3is possible to plotted on the topology, then the scale is accepted for the rest of active
load to plot their radius, Pi
Ra.i = ; Ra.i = 2.10−2 Pi ;
ma
* Topology: means a relationships between linked elements: the relationships between parts linked together in a system such as a distribution
or a computer network (formal).
Selection of location for Distribution Substation
d) Calculating the reactive load of each consumer using the following relation:
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
where,
tg φ – the angle which can be found using cos φ the the value will be collected on the output
data table.
e) Calculating the radius of a circles for reactive loads with the same scale, i.e mr= 800 kVar/km2
using −2
Rr .i = 2 10 Qi
PY i i
100 1.45 + 160 1.25 + 1000 0.9 + 400 0.55 + 25 0.4
Ya 0 = i =1
= = 0.88 km.
n
100 + 160 + 1000 + 400 + 25
P
i =1
i
Therefore , the distribution sub station will be allocated near by point A (2 ; 0.88).
n
Q X i i
102 0.6 + 141 1.45 + 480 2.4 + 300 1.55 + 33 0.4
X r0 = i =1
= = 2.3 km;
n
102 + 141 + 480 + 300 + 33
Q
i =1
i
n
QY i i
102 1.45 + 141 1.25 + 480 0.9 + 300 0.55 + 33 0.4
Yr 0 = i =1
= = 0.88 km.
n
102 + 141 + 480 + 300 + 33
Q
i =1
i
Therefore , the synchronous compensator will be allocated near by point B (2.3 ; 0.88).
Selection of location for Distribution Substation
Fig.1. Load Topology of all group of consumers
Active load
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
Reactive load
Selection of location for Distribution Substation
Output data
Number of consumers
Parameters
Load 1 Load 2 Load 3 Load 4 Load 5
P, kW 100 160 1000 400 25
Ra , km 0.2 0.25 0.63 0.4 0.1
Cos φ 0.7 0.75 0.9 0.8 0.6
tg φ 1.02 0.88 0.48 0.75 1.33
Q , kVar 102 141 480 300 33
Rr , km 0.22 0.24 0.44 0.35 0.11
Answer: Point A (2; 0.88) will be the place where the DSS is to be located and centre of active load.
Point B (2.3; 0.88) will be the place where the Comp. is to be located and centre of reactive load.
Selection of location for Distribution Substation
Variant
Cos φ1 P2, kW Cos φ2 P3, kW Cos φ3 P4 , kW Cos φ4 P5 , kW Cos φ5
P1 , kW
(X2 , Y2) (X3 , Y3) (X4 , Y4) (X5 , Y5)
(X1 , Y1)
Selection of location for Distribution Substation
Abat
Hawassa University, Institute of Technology Department of Electrical & Computer Engineering
Atnafu
Hussen
Edmialem
Teke
Abat
Atn
Huss
Edmi
Teke
Any Question??
?
Any Question ?
Any Question ?
?
Any Question ?
? ? ?
? ?
? ? ? ?
?Any Question ? ? 1/10/2024 Milkias B.
73
73