Turbine start up sequence control

CMD ON Turbine Sequence SGC

Step 101

Command: SGC Control oil supply on


Feedback: 1) SGC Control oil pumps on & EHA oil
SP
2) SLC all ESV's & Control valves ON &
OL VLV ON
Step bypass: ESV open/TSLLE>56%

Step 102

Command: No command
Feedback: 1) Condenser pre.<0.6 kg/cm2
2) IPBP trip not operated
3) CEP-1/2 dish. Pre >17 kg/cm2
4) CW pressure > 4 kg/cm2

Step 103

Command: 1) LPBP Control ON


2) ASM ON

Feedback: 1) LPBP Control ON


2) ASM ON
3) Water injection control ON

Step bypass: 1) HRH pr > 15 kg/cm2


2) Turbine speed > 49.5 S-1
Step 104

Command: 1) SLC drains ON


2) SLC warm up drains ON
3) HP exhaust temp. control Auto &
ON
Feedback: 1) SLC WARM UP drains ON
2) SLC drains ON
3) HP exhaust temp. control Auto ON
4) HP exhaust temp. control ON.

Step bypass: 1) HRH pr > 15 kg/cm2


2) Turbine speed > 49.5 S-1

Step 105

Command: No command
Feedback: 1) All ESV closed
2) All CVs closed
3) CRH NRV 1 & 2 closed

Step bypass: 1) ESV open/TSLLE>56%


2) TSLLE>56%/Position setpoint
Turbine>0%
3) Generator load >10%

Step 106

Command: No command
Feedback: 1) Turbine trip system A&B no trip
2) One OVEF ON
3) Lube oil cooler outlet temp>35 deg c
4) SLC drains NO FAULT

Step 107

Command: 1) SLC warm up control off


2) Drain before HP CV-1 closed.
3) Drain before HP CV-2 closed.

Feedback: 1) SLC warm up control off & drain


before HPCV-1 & 2 closed

Step bypass: 1) ESV open


Step 108

Command: No command
Feedback: 1) L.steam flow >10% & steam before
HPBP>30 K
2) Steam before IPBP > 30 K
3) DT >X1, < X2 & > X3
4) Drain before ESV open
5) Drain before HPCV -1 & 2 not closed.
6) Condenser pre. < 0.5 kg/cm2
7) Turbine speed > 0.25 S-1
8) Step 5 completed
9) Step 6 completed
Step bypass: 1) Wall temp. HPCV-1 & 2 <100 deg C
2) ESV open/TSLLE >56%.
3) Turbine speed > 690 rpm

Step 109

Command: TSLLE raised


Feedback: TSLLE position >56%

Step 110

Command: No command
Feedback: 1) HPESV-1 opened
2) HPESV-2 opened
3) IPESV-1 opened
4) IPESV-2 opened
5) LPESV-1 opened
6) LPESV-2 opened

Step 111

Command: No command
Feedback: 1) Gland steam pressure control auto
2) Gland steam pressure < 1.06 kg/cm2
& > 1.04 kg/cm2
3) One OVEF ON
4) SLC Drain no fault
Step 112

Command: No command

Step 113

Command: SLC Warmup control ON


Feedback: 1) HPC temp > 450 deg C, LSTM FL>15 &
Bypass LS
2) DT >X4,
3) DT >X5,
4) DT >X6,
5) Drain before HPCV -1 & 2 > 2% &
Bypass
6) Turbine speed >15 rpm
7) Steam before LPBP SH >30 K
8) Step-11 permit fulfilled
9) HP casing DT top bottom not high
10) Condenser pressure trip not operate
11) Load setpoint >10 %
12) Steam purity < 0.5 us/cm
13) Drain before HPCV -1 & 2 not closed
14) One OVEF ON

Step bypass: Turbine speed >11.5 S-1

Step 114

Command: Turbine speed setpoint raised


Feedback: Turbine speed reference > 690 rpm

Step 115

Command: Tno coomand


Feedback: Turbine speed> 630 rpm

Step 116

Command: No command
Feedback: CRH X7 satisfied & casing flange
temp. 60 degc & DT HPS
surface/mean <12 deg c & upper
margin > 30 k

Step bypass: 1) Wall temp. HP casing >250 deg C


2)Turbine speed > 2994 rpm
temp. 60 degc & DT HPS
surface/mean <12 deg c & upper
margin > 30 k

Step bypass: 1) Wall temp. HP casing >250 deg C


2)Turbine speed > 2994 rpm
Step 117

Command: 1) Turbine speed set point raised


2) SLC warm up control off
3) Drain before HPCV -1 & 2 closed
Feedback: Turbine speed SP>3015 RPM

Step 118

Command: No command
Feedback: Turbine speed > 2940 rpm
Step bypass: Generator breaker ON

Step 119

Command: AVR auto


Feedback: AVR auto

Step 120

Command: Excitation field breaker closed


Feedback: Generator voltage >95% & excitation
brkr closed & AVR auto.

Step bypass: Generator breaker ON

Step 121

Command: No command
Feedback: 1) CRH X8 checked
2) Upper margin > min
3) Synchroniser on AUTO

Step 122

Command: synchronise on
Feedback: Generator breaker ON

Step 123

Command: TSLLE raised


Feedback: TSLLE >100 %
Command: TSLLE raised
Feedback: TSLLE >100 %

Step 124

Command: Power setpoint raised


Feedback: Step 24 waiting time finished
Step bypass: Generator load >10%

Step 125

Command: Start up check back


Feedback: 1) Generator breaker ON
2) Step 25 activated.
3) Turbine speed > 2970 rpm.
Step-101

Command SGC Control oil supply on


Feedback 1) SGC Control oil pumps on & EHA oil SP
2) SLC all ESV's & Control valves ON & OL VLV ON
Step bypass ESV open/TSLLE>56%

Step-102

Command No command
1) Condenser pre.<0.6 kg/cm2
2) IPBP trip not operated
Feedback 3)CEP-1/2 dish. Pre >17 kg/cm2
4) CW pressure > 4 kg/cm2

Step-103

1)LPBP Control ON
Command
2) ASM ON
1) Condenser pre.<0.6 kg/cm2
2) IPBP trip not operated
Feedback 3)CEP-1/2 dish. Pre >17 kg/cm2
4) CW pressure > 4 kg/cm2