Capacity Verification Model, 031523
Capacity Verification Model, 031523
Capacity Verification Model, 031523
Tier 2 Readiness
Have you ensured that your subtier suppliers are prepared for production?
Are subcomponent PPAP's, PV information and R@R information available and confirmed? X
Production Representation
Is the product being manufactured at the production site in the production environment? (I.e. using the production
tooling, gaging, process, materials, operators, environment, and performed at the required production speed) X
Does the actual process flow agree with the process flow diagram? Ensure it represents the entire process from
receiving through shipping. X
Quality Systems
Is all in-process documentation, such as SPC and work instructions in place? X
Has the process been 'fail-safed' by operation to prevent defective product from moving to the next operation?
X
Is Non Conforming product controlled so it can not move to the next operation/ rework procedures? X
Does the actual process conform with the process control plan? X
Are permanent production operators trained to perform the production operation, part checks and statistical
monitoring as outlined on the process control plan? X
Are all production checking fixtures complete, with acceptable measurement system studies (i.e. gage R&R)
performed? X
Have any PV tests been performed and if so did they meet the requirements? n/a
Are all processes conforming to the production control plan specifications? X
12b Scheduled Preventive Maintenance / shift hours 0.17 0.17 0.17 0.17 0.17
12c Tooling Change Over / shift hours 0.00 0.75 0.75 0.00 0.00
13 Shifts / day (3 shifts is standard) shifts 3.00 3.00 3.00 3.00 3.00
14 Days / week (5 days is standard) days 5.00 5.00 5.00 5.00 5.00
15 Weeks / year (48 weeks is standard) weeks 48.00 48.00 48.00 48.00 48.00
16 Number of lines, presses, etc. units 1.00 1.00 1.00 1.00 1.00
18 % of line for XYZ Customer parts (Allocation %) % 100% 100% 100% 100% 100%
19 Quoted Production Rate pcs/hour 225.0 155.0 140.0 275.0 140.0
II - Supplier Quoted Capacity Data
19a Cycle time (for informational purposes only) seconds 8.0 23.0 14.0 12.0 11.0
19b Cavities (for informational purposes only) # per tool 1.0 1.0 1.0 1.0 1.0
27 Trial run duration (8hrs is default) hours 8.00 8.00 8.00 8.00 8.00
28 Total parts produced pcs 955 955 955 955 955
III - RUN at RATE Results
35 Reason text
Comments