WORK BREAKDOWN STRUCTURE

Stilt House
Construction

Pre- Structural and Interior Work Final Construction


Foundation
construction Exterior Work and Finishes Phase

Define scopes and Excavate for Construct floor Mechanical, Electrical, Final Building
objectives foundation footing system (joists, and Plumbing Inspections
subfloor)

Assemble project Install drainage and Install fixtures and Final assessment
team utility trenches Erect wall framing appliances with clients
(studs, sheathing)

Pour concrete Install flooring, Site Cleanup


Obtain permits and
footings interior doors, and
approvals Install roof framing,
trim
decking, exterior
sheathing, weather
barrier, and siding Project closeout
Conduct land survey Build foundation
walls Install insulation and
drywall

Clear and excavate Install windows and


site Waterproof exterior doors
foundation walls Install paints and
finishes