PROVINCE OF BATANGAS
Municipality of Cuenca
Scope of Work :
A. Materials:
200 bags Portland Cement P 222.00 44,400.00
25 cu.m ¾ crushed stone 950.00 23,750.00
13 cu.m sand 650.00 8,450.00
132 pcs 12 mm Ø def std bar 165.00 21,780.00
140 pcs 10 mm Ø def std bar 105.00 14,700.00
120 pcs 9 mm Ø def std bar 95.00 11,400.00
22 pcs. ¼ ordinary plywood 335.00 7,370.00
23 kls. C. w. nails assorted size 80.00 1,840.00
17 kls. # 16 G.I Tie Wire 80.00 1,360.00
900 bd. Ft. 150 – 2x3x12 coco lumber 22.00 19,800.00
Materials P 154,850.00
Labor 47,150.00
Equipment 8,000.00
Direct cost P 210,000.00
O.C.M 21,000.00
Mark up 21,000.00
V.A.T 30,240.00
Item Cost P 282,240.00
Unit Cost P 11,350.00/ cu.m
A. Materials:
200 bags Portland Cement P 222.00 44,400.00
26 cu.m sand 650.00 16,900.00
2793 pcs. # 5 CHB masonry blocks 8.50 23,740.50
136 pcs 10 mm Ø def std bar 105.00 14,280.00
7 kls. # 16 G.I Tie Wire 80.00 560.00
Materials P 99,880.50
Labor 29,919.50
Equipment 5,000.00
Scaffolding Rental 3,000.00
Direct cost P 137,800.00
O.C.M 13,780.00
Mark up 13,780.00
V.A.T 19,843.20
Item Cost P 185,203.20
Unit Cost P 860.00/ sq.m
A. Materials:
53 pcs. G.I Pipe sht 2 x 2 3/16 angular bar or equivalent P 720.00 38,160.00
12 pcs 1 ½ x 1 ½ x 3/16 angular bar 450.00 5,400.00
60 pcs C-purlins 2 x 3 w/ stiffener 500.00 30,000.00
14 pcs. 12 mm plain sag rod 235.00 3,290.00
16 kls welding rod 120.00 1,920.00
223 L.m Long soan Rib-Type 0.50 mm or equivalent 295.00 65,785.00
1650 pcs. text screw 2.90 4,785.00
9 pcs Ridge roll pre-painted or equivalent 400.00 3,600.00
600 pcs, blind rivets 1.10 660.00
Materials P 153,600.00
Labor 40,400.00
Equipment 7,000.00
Direct cost P 201,000.00
O.C.M 20,100.00
Mark up 20,100.00
V.A.T 28,944.00
Item Cost P 270,144.00
Unit Cost P 1,386/ sq.m
A. Materials:
220 sq. ft steel casement window w/ 3/16 transparent glab P 250.00 P 55,029.22
3 pcs. silicon sealant 350.00 1,050.00
3 pcs. panel type door (main door) 4,500.00 13,500.00
3 pcs. hollow core flush door 2,500.00 7,500.00
24 pcs. door loose pin hinges 35.00 840.00
6 pcs. door lock 450.00 2,700.00
3 pcs. 0.90 x 2.10 door jamb 2 x 5 1,500.00 4,500.00
3 pcs. 0.70 x 2.10 door jamb 2 x 5 1,350.00 4,050.00
Materials P 89,169.22
Labor 17,830.78
Direct cost P 107,000.00
O.C.M 10,700.00
Mark up 10,700.00
V.A.T 15,408.00
Item Cost P 143,808.00
Unit Cost P 1,386/ sq.m
.
Total Estimated Cost of Project P 749,952.00
S A Y P 100,000.00
Prepared by:
ROMEO A. HERNANDEZ
Municipal Engineer
Assisted by:
PILAR ANDREA E. DIMACULANGAN
M. P. D. C.
Approved by:
CELERINO A. ENDAYA
Municipal Mayor
NAME OF PROJECT : REPAINT OF COOPERATIVE BUILDING (EVERLAST)
LOCATION :PINAGTONGULAN LIPA CITY, BATANGAS
Scope of Work:
I - PAINTING WORKS
A. Quantity: 1.00 lot
I - Labor:
one (1) construction foreman @ P 850.00 /day for 24 days P 20,400.00
six (2) skilled labor 750.00 /day for 24 days 36,000.00
Sub-Total P 56,400.00
S A Y P 82,880.00
Prepared by:
SONNY MACASAET
Paint Contractor