Professional Documents
Culture Documents
Adding Inline Components-Imp-TRNC03401-10001
Adding Inline Components-Imp-TRNC03401-10001
Adding Inline Components-Imp-TRNC03401-10001
This workbook is designed for use in Live instructor-led training and for OnDemand selfstudy.
The explanations and demonstrations are provided by the instructor in the classroom, or in the OnDemand
eLectures of this course available on the Bentley LEARN Server (learn.bentley.com).
This practice workbook is formatted for on-screen viewing using a PDF reader.
It is also available as a PDF document in the dataset for this course.
TRNC03401-1/0001
Course Description
This is the third of five courses for the OpenPlant PID CONNECT Edition User.
This workbook contains exercises to place a control station, then replace the valves of the control station. Next, the user will place pipeline
insulation and place inline components. Then the user will place a drain line and a reducer which will change the data of the pipeline. Finally,
the user will move an inline component and change the actuator of a control valve using OpenPlant PID CONNECT Edition.
Learning Objectives
Place a Control Station
Replace Valves
Place a Reducer
Change an Actuator
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 2
Installing the OP Training Project
A PID has been provided for your convenience. You will need to place this PID into the WorkSet directory shown below.
6. Select Instruments > Instrument Galleries > Control Valves from the ribbon menu.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 4
7. Select Control Valve from the Component Gallery and place on pipeline L103. The following
dialog opens.
a. Select Gate as the Valve Type and Diaphragm Actuator as the Actuator type.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 5
The Gate Control Valve dialog opens.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 6
The Place Instrument Oval Annotation dialog opens.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 7
Exercise 02: Placing Gate Valves
In this exercise we will add the gate valves to the control station.
1. Select Piping > Piping Galleries > Valves from the ribbon menu.
a. Click OK.
2. Place the gate valve on the pipelines downstream of the control valve.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 8
Exercise 03: Drawing a Bypass Line
In this exercise we will draw the bypass line around the control valve.
2. Select Tools > Managers > Drawing from the ribbon menu.
a. Select the Settings tab.
b. Clear the Tag Dialog Prompt.
Note: This will temporarily disable the tag dialogs while we place a bypass line.
c. Click OK.
4. Expand the Piping > Piping Galleries > Piping from the ribbon menu.
5. Select Minor from the Component Gallery, the Place Pipe Run dialog opens.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 9
6. Draw the minor line as shown below bypassing the control station.
7. Select Tools > Managers > Drawing from the ribbon menu.
a. Select the Settings tab.
b. Set the Tag Dialog Prompt.
c. Click OK.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 10
Exercise 04: Adding the Bypass Valve
In this exercise you will add a globe valve to the bypass line.
1. Select Piping > Piping Galleries > Valves from the ribbon menu.
Note: You may need to move the globe valve size annotation to below the valve for clarity.
5. Select Element Selection, to end the command.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 11
Exercise 05: Place another Control Station
In this exercise we will place a second control station.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 12
Exercise 06: Placing Reducers
In this exercise we will add reducers between the gate valves and the control valve. Adding reducers will change the
properties of the pipe and the valves.
1. Select Piping > Piping Galleries > Fittings from the ribbon menu.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 13
You may have to expand the details.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 14
e. Click Apply Spec Change in the InRun Spec Validation dialog. The properties of the control valve have changed and require a new
spec.
6. Place a second reducer on the pipeline between the control station and the gate valve on the right.
a. Select the top HTF-FG-BG108-EX-OPM, P2.
b. Click OK.
c. Expand the Operating Conditions category.
d. Select 4” from the Size list.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 15
5. Click OK.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 16
Exercise 07: Replacing Valves
In this exercise we will replace the gate valves with plug valves.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 17
Exercise 08: Placing Check Valves
In this exercise we will place check valves near the pumps.
2. Select Piping > Piping Galleries > Valves from the ribbon menu.
3. Select Check.
4. Insert a check valve on the P-100 discharge line.
Note: If your pipelines does not fall on a grid line, change the locks to Axis and Nearest prior to valve placement.
5. Click Cancel on the EX-OPM spec dialog..
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 18
6. Click OK on the Check Valve dialog.
9. Select Gate.
10. Place the flanged gate valve downstream of the check valves.
11. Click OK on the Gate Valve dialog.
12. Select Element Selection, to end the Gate Valve command.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 19
Your drawing should now appear similar to the figure below.
13. Place an additional Gate Valve on the suction line of each pump.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 20
Exercise 09: Placing Inline Fittings
In this exercise we will place a strainer and add miscellaneous valves to the PID.
1. Select Piping > Piping Galleries > Fittings from the ribbon menu.
2. Select Y-Strainer.
3. Place the strainer downstream of the gate valves as shown.
4. Window into an area around the heat exchangers EX-100 and EX-100A.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 21
5. Place a Gate Valve on the pipeliness entering and exiting the exchangers as shown below.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 22
8. Using the center handle, pull down to straighten the pipeline.
9. Place a Plug Valve on pipeline BG108 leaving the vessel.
10. Select Instruments > Instrument Galleries > Control Valves from the ribbon menu.
a. Select Control Valve from the Component Gallery the following dialog opens.
b. Select a Ball from the Valve Types list.
c. Select a Cylinder Operator from the Actuators list.
4. Place the valve upstream of the plug valve.
Note: The actuator is now ghosted on your cursor for you to place.
5. Place the actuator stem on the top of the ball valve bubble.
a. Select BALL CONTROL VALVE, FLANGE, RAISED-FACE, 150LB in the Spec dialog.
b. Click OK.
c. Tag the valve ESV-100 with a Service of FG and a System of H.
d. Click OK.
5. Place the instrument bubble.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 23
Exercise 10: Placing Pipeline Insulation
In this exercise we will place insulation on the pipelines.
1. Window into the area around the Heat Exchangers EX-100 and EX-100A.
2. Select Piping > Piping Galleries > Pipe Services from the ribbon menu.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 24
Your drawing looks as shown below.
L106 2
L108 2
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 25
Exercise 11: Miscellaneous Valves
In this exercise we will finish placing valves.
1. Window into the area in the lower left corner of the drawing where pipeline L100 enters the sheet.
2. Place a flanged Gate Valve on the line.
3. Select Piping > Piping Galleries > Fittings from the ribbon menu.
4. Place the Open Figure 8 Blind just downstream of the gate valve.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 26
Exercise 12: Moving a Valve
In this exercise we will move a valve.
3. Grab the center handle and slide left or right along the pipelines.
4. Release in a new location.
The valve will move and it will break the line at the new location.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 27
Exercise 13: Placing a Drain Line with Valve
In this exercise we will be adding a drain line between the check valve and the pump.
Note: You may need to edit the piping and valves to make room for the new drain line.
1. Window into the area around the pumps P-100 and P-100A.
2. Select Tools > Managers > Drawing from the ribbon menu.
a. Select the Settings tab.
b. Clear the Tag Dialog Prompt.
c. Click OK.
4. Expand the Piping > Piping Galleries > Piping from the ribbon menu.
5. Select Vent/Drain.
6. Place a drain line on the pipeline of the suction side of the pumps as shown.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 28
7. Select Element Selection.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 29
Exercise 14: Placing a Valve by Endpoint
In this exercise we will place the valve by its endpoint.
The valve is highlighted by it’s end point instead of it’s center point.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 30
7. Place a flanged gate valve on the drain line.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 31
Exercise 15: Move the Drain Lines
In this exercise we will move the drain lines to make room for a reducer.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 32
Exercise 16: Placing a Reducer
In this exercise we will place reducers near the pumps.
Note: You may need to perform simple editing to perform the next exercise by stretching or moving the pipelines,
pumps and valves.
1. Select Piping > Piping Galleries > Fittings from the ribbon menu.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 33
Exercise 17: Moving the Reducer
In this exercise we will move the reducer.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 34
Exercise 18: Adding a Valve Actuator
In this exercise we will add and a valve actuator.
1. Select the Gate Valve on pipeline L100 at the left edge of the sheet.
2. Right-click and select Properties from the context menu.
3. Select the General Info category.
4. Select Handwheel from the Actuator Display Label field.
The valve has updated to show the Handwheel.
Copyright © 2018 Bentley Systems, Incorporated DO NOT DISTRIBUTE - Printing for student use is permitted 35