Checklist (Documentary Requirements) - Updated
Checklist (Documentary Requirements) - Updated
02 Performance Security / Parent Company Guarantee bank guarantee or stand-by L/C (from list of accredited banks)
03 Advance Payment Security (if applicable) bank guarantee or stand-by L/C (from list of accredited banks)
04 Official Request for Advance Payment (see above) to accompany the submission of Advance Payment Security
Rationalized Bill of Quantities & DUPA as required re-align the BOQ to balance the rates
Detailed Work Programme / Project Execution Plan including Procurement Plan (if any)
Temporary Works incl. Temporary Toll Facilities, Permits & Trafic Management
Work/Inspection Forms / Permits & Clearances On Construction-related permits, see Bid Docs Schedule Template
Notes: Ideally, requirements shall be fully complied at least 14 days upon issuance of the Letter of Award. Rationalized BOQ, Performance Security and Work Programme are top priorities.
Regular Coordination Meetings shall be established. If necessary, a Steering Committee that convenes at least monthly to resolved critical issues can be formed.
The above list is not exhaustive or restrictive. Any document or requirement not indicated but is necessary to be provided by the Contractor shall be complied accordingly.
Bonds and Insurances are prescribed to be coordinated with the corporate insurance advisor or insurance broker.
Highlighted items can be done concurrently or in parallel with all site preparations and not dependent or not affected by any permits or clearances to be secured by the Contractor.
These items are contractual matters and are not dependent on construction issues.