SECTION -B (Mr. Bandula ) SECTION -A (Mr.

Antony ) 16-Feb-24
Description chainage length Total Section B chainage length Total Section B Overall Progress
202+450 188+077 14.37 Km % 188+077 176+605 11.472 Km % Km %

Dismantling 202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.845 100%

Jungle Clearing 202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.845 100%
Clearing &
202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.845 100%
Grubbing
Initial Formation 202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.845 100%

Initial Survey 202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.845 100%

Design 202+450 188+077 14.37 14.37 100% 188+077 177+500 10.58 10.58 92% 24.95 96%

202+450 196+700 5.75 179+450 177+500 1.95

196+100 188+077 8.02 183+700 179+600 4.10


Final Formation &
13.77 96% 9.10 79% 22.87 88%
Join Survey
187+000 183+950 3.05

0.00

202+450 197+360 5.09 179+450 177+500 1.95

197+210 196+700 0.51 183+700 179+600 4.10

196+100 193+570 2.53 179+450 177+500 1.95


Initial ABC 13.44 94% 8.00 70% 21.44 82%
193+390 188+077 5.31

202+450 200+800 1.65 181+700 181+200 0.50

200+900 198+300 2.60 185+950 185+350 0.60

ABC Final &


4.25 17% 1.10 10% 5.35 13%
Density

Service Ducts 9.00 8.00 89% 8.00 8.00 100% 16 94%

Precast Box 3.00 2.00 67% 1.00 1.00 100% 3 83%

Insitu Box 0.00 0.00 100% 1.00 1.00 100% 1.00 100%