Professional Documents
Culture Documents
Progress 2024.02.16
Progress 2024.02.16
Antony ) 16-Feb-24
Description chainage length Total Section B chainage length Total Section B Overall Progress
202+450 188+077 14.37 Km % 188+077 176+605 11.472 Km % Km %
Dismantling 202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.845 100%
Jungle Clearing 202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.845 100%
Clearing &
202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.845 100%
Grubbing
Initial Formation 202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.845 100%
Initial Survey 202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.845 100%
Design 202+450 188+077 14.37 14.37 100% 188+077 177+500 10.58 10.58 92% 24.95 96%
0.00
Insitu Box 0.00 0.00 100% 1.00 1.00 100% 1.00 100%