Professional Documents
Culture Documents
ILP 2 Progress As at 2024.02.19
ILP 2 Progress As at 2024.02.19
Antony ) 19-Feb-24
Description chainage length Total Section B chainage length Total Section B Overall Progress
202+450 188+077 14.37 Km % 188+077 176+605 11.472 Km % Km %
Dismantling 202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.85 100%
Jungle Clearing 202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.85 100%
Clearing &
202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.85 100%
Grubbing
Initial Formation 202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.85 100%
Initial Survey 202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.85 100%
Design 202+450 188+077 14.37 14.37 100% 188+077 177+500 10.58 10.58 92% 24.95 96%
Cable Trench
202+450 193+500 8.95 8.95 62%
Excavation
Cable Trench Pipe
202+450 197+000 5.45 5.45 38%
Laying and
Cable Trench
Cover Slab Placing
Service Ducts 9.00 9.00 100% 8.00 8.00 100% 17 100%