SECTION -B (Mr. Bandula ) SECTION -A (Mr.

Antony ) 19-Feb-24
Description chainage length Total Section B chainage length Total Section B Overall Progress
202+450 188+077 14.37 Km % 188+077 176+605 11.472 Km % Km %

Dismantling 202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.85 100%

Jungle Clearing 202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.85 100%
Clearing &
202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.85 100%
Grubbing
Initial Formation 202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.85 100%

Initial Survey 202+450 188+077 14.37 14.37 100% 188+077 176+605 11.47 11.47 100% 25.85 100%

Design 202+450 188+077 14.37 14.37 100% 188+077 177+500 10.58 10.58 92% 24.95 96%

202+450 188+077 14.37 187+250 177+450 9.80

Final Formation &


14.37 100% 9.80 85% 24.17 93%
Join Survey

202+450 196+600 5.85 187+250 177+450 9.80

196+000 193+500 2.50

193+200 188+077 5.12


Initial ABC 13.47 94% 9.80 85% 23.27 90%

202+450 196+900 5.55 186+550 185+350 1.20

196+020 194+000 2.02 182+750 180+100 2.65

192+900 191+700 1.20


ABC Final &
8.77 61% 3.85 34% 12.62 47%
Density

Cable Trench
202+450 193+500 8.95 8.95 62%
Excavation
Cable Trench Pipe
202+450 197+000 5.45 5.45 38%
Laying and
Cable Trench
Cover Slab Placing
Service Ducts 9.00 9.00 100% 8.00 8.00 100% 17 100%

Precast Box 3.00 2.00 67% 1.00 1.00 100% 3 83%

Insitu Box - - 100% 1.00 1.00 100% 1.00 100%