NO Price Estimaton for gujarat site Qty Price Total


1 Fixing of Industrial On / Off Push buttons with emergency locable type-80 240 Nos 200 48000
2 Motors Less than 1 HP: /Glanding & Termionation -44 132 Nos 160 21120
3 Motors less than 5 HP/Glanding & Termionation-58 174 Nos 180 31320
4 Motors 10 HP to 40 HP/Glanding & Termionation-34 102 Nos 250 25500
5 Motors of 150 HP:/Glanding & Termionation-1 3 Nos 780 2340
6 Motors of 215 HP:/Glanding & Termionation-3 9 Nos 880 7920
7 Field 200 I/Os for Instruments & Valves (3 Terminal per Instrument) 600 Nos 12 7200
8 Field 400 I/Os for Field JBs (3 Terminal per Instrument) 1200 Nos 12 14400
9 Panel 200 I/Os for Instruments & Valves (3 Terminal per Instrument) 600 Nos 12 7200
10 Panel 400 I/Os for Field JBs (3 Terminal per Instrument) 1200 Nos 12 14400
11 Cable Tray Stucture Fixing /Mounting (Actuals ) 60 Mtr 200 12000
12 Cable Tray Support Fabrication / Site (Price Per /KG) 1200 Mtr 120 144000
13 Cable Tray Laying (Per Meter)Up to 5HP /Instruments 160 Mtr 75 12000
14 Cable Tray Laying (Per Meter)Up to 40HP & Above 80 Mtr 168 13440
15 Cable Laying (Per Mtr) Up to 5HP /Instruments 120 Mtr 25 3000
16 Cable Laying (Per Mtr) Up to 40 HP & Above 140 Mtr 85 11900
Total 375740
Onward & Return Travel @ Actuvals
Stay @ Actuvals (4-5) persons estimated for the job