A. MATERIALS:
C. INSPECTION:
a. Check for the brand and dimension of the materials to that of the given
specifications.
b. Check for straightness of the wall angles and secondary ceiling. It
should also be properly leveled so as to avoid unnecessary curvatures on
the gypsum board when the latter is installed.
c. Check for the anchors.
d. The frame should not wave when pushed.
e. Check for the presence of the necessary electrical wirings and fixtures
prior to fixing of the gypsum board.
f. Check for the deformations on the gypsum board prior to fixing.
g. Check the locations of the necessary cut-outs for the utilities (electrical
and plumbing installations).
h. Spacing of metal furring must be 0.4-0.6 meter apart.
i. Spacing of screws shall be from 200mm to 300mm on centers.
j. Finished paint should not show any joint line.
D. EXECUTION:
CEILING INSTALLATION
F. SAFETY MEASURES: