PROGRES KERJA

PEKERJAAN TOWER TRIANGLE BLOK 4

September 2023 Oktober 2023


No. Jenis Pekerjaan Volume Satuan Bobot
1 2 3 4 1 2 3 4
I TOWER 65 METER

1 Tower Triangle 50x50 Medium 1 inch 40.00 mtr 18.95% 3.79% 3.79% 3.79% 3.79% 3.79%
2 Tower Triangle 40x40 Medium 1 inch 25.00 mtr 9.21% 1.84% 1.84% 1.84% 1.84% 1.84%
3 Roll Slenk Baja Anti Karat 5.00 roll 15.79% 3.16% 3.16% 3.16% 3.16% 3.16%
4 Jarum Keras No.12 66.00 pcs 1.74% 0.35% 0.35% 0.35% 0.35% 0.35%
5 Baut Tower 5/8 66.00 pcs 0.35% 0.07% 0.07% 0.07% 0.07% 0.07%
6 Klem Slenk No.6 445.00 pcs 0.47% 0.09% 0.09% 0.09% 0.09% 0.09%
7 Pondasi Samping (Tarikan) 6.00 btg 4.74% 1.18% 1.18% 1.18% 1.18%
8 Pondasi Angkur Tengah 1.00 bh 1.05% 0.26% 0.26% 0.26% 0.26%
9 Semen 20.00 Zak 0.84% 0.84%
10 Pasir 1.00 Rit 1.41% 1.41%
11 Koral 1.00 Rit 1.32% 1.32%
12 Papan Cor 10.00 Lbr 0.11% 0.11%
13 Paku 1.00 kg 0.02% 0.02%
14 Jasa Mendirikan Tower + Pondasi 65.00 mtr 23.95% 23.95%

I ANTI PETIR

1 Penangkal Petir Merk Thomas R120M 1.00 bh 3.42% 0.86% 0.86% 0.86% 0.86%
2 Stick Ground Rood 16 mm original 8.00 btg 5.05% 1.26% 1.26% 1.26% 1.26%
3 Kabel BC 25 mm Eterna 40.00 mtr 1.26% 0.32% 0.32% 0.32% 0.32%
4 Kabel BCC 70 mm Eterna 66.00 kg 5.42% 1.35% 1.35% 1.35% 1.35%
5 Box Panel 30x40 1.00 bh 0.21% 0.05% 0.05% 0.05% 0.05%
6 Esolator dan Busbar 1.00 Set 0.05% 0.01% 0.01% 0.01% 0.01%
7 Skun 70 (Ori) 2.00 bh 0.11% 0.03% 0.03% 0.03% 0.03%
8 Skun 35 (Ori) 8.00 bh 0.23% 0.06% 0.06% 0.06% 0.06%
9 Begel 5/8 8.00 bh 0.19% 0.05% 0.05% 0.05% 0.05%
10 Pemasangan Anti Petir (tanam stick dan pengukuran) 1.00 ls 1.05% 0.26% 0.26% 0.26% 0.26%

I TRANSPORT

1 Transport Tower Banjarmasin - Rantau 1.00 Ls 3.08% 0.44% 0.44% 0.44% 0.44% 0.44% 0.44% 0.44%

Total 100%
Pajak ( 11 % ) Ra 29.52% 31.41% 33.29% 44.48% 58.47% 72.46% 86.45% 100.00%
Grand Total Ri 30.02% 32.41% 34.29% 45.48% 60.00%
Dev 0.50% 1.00% 1.00% 1.00% 1.53%

CV EBY TRIANGLE
Benny Effendy
Direktur