Form of Inspection Report as per Schedule-II

[ Refer Regulation-32 & 45 of CEA (Measures relating to Safety & Electric Supply) Regulations, 2023 ]

FORM-III
(Installations of voltage exceeding 650V)

Report No. : 119/23-24


Date of Inspection by Electrical
: 14 Mar 2024
Inspector
Date of Last Inspection : -
1. Consumer No. : -
2. Voltage and system of Supply:-
(i) Voltage : 11 KV
(ii) No of Phases : 3 PHASE
(iii) AC/DC : AC
3. Name of Consumer/Owner : GE DSSC
4. Address of Consumer/Owner : GE DSSC Wellington
5. Location of the premises : S/S No 2
6. Particulatrs of Inspection : Periodic Inspection
Make Ser No Capacity Voltage Location
(a) TRANSFORMERS :
(i) Indo-Tech IT-5872 of the year 315 KVA 11KV/433V S/S No 2
2004
(ii) ITL 7585 of year 1992 300 KVA 11KV/433V S/S No 2
(iii) NEC RY 2175/1 of year 100 KVA 11KV/433V S/S No 2
1972
(iv) Kirloskar Electric Co XDG001/01 of year 315 KVA 11KV/433V S/S No 2
2019
(b) HT BREAKERS: VCBs
(i) Kirloskar (Incoming - 0512P024 400 Amps 12 KV Sub Stn No 2
01 Outgoing -04 Nos)

(ii) Schneider/HVX-X 5218-2020-21 800 Amp 12 KV


(c) OTHER EQPTS:
(i) Five Number of Two Pole Structure with one GoD (in Use) 11 KV 02 Nos TNEB

(ii) One Number of Four Pole Structure with one GoD (in use) 11 KV Sub Stn No 2
(d) Total connected load kW : 750 kW

7. General conditions of the Installation:-


The manned Sub-Station with S/S buildings having VCBs and Outdoor yard having Transformers & GoDs is
observed in good functional state. Regulation wise points observed as under with respect to the indoor and
outdoor installations shall be rectified on priorty:-

S No Regulation No Requirements Report


As per Chapter-II
1 Regulation -3 Is the register of the designated persons properly made and kept up to
date duly attested ? No

A record having the names of persons designated to operate and carry out the work on the electrical
apparatus is to be maintained. And that the designated persons shall possess a certificate of
competency or electrical work permit and the same shall be ensured by GE.

2 Regulation -5 Whether Electrical Safety Officer as required under the Regulation is


designated ? No
Report No. 119/23-24 Page 1 of 19
S No Regulation No Requirements Report
As per Chapter-III (General Safety Requirement)
3 Regulation -14 (i) Is/are there any visible sign(s) of overloading in respect of any
apparatus ? No

(ii) Whether any unauthorised temporary installation exists ? No


(iii) Whether the motors and controlling equipment are being over
hauled periodically and record kept of the same in register ? Yes

(iv) Whether the transformer oil samples are being tested periodically
and results recorded in a register ? Yes,

Record in register is to be maintained.


(v) Whether suitable lightning arrestors have been provided near the
transformers for protection against lightning ? No

Lightning Arrestors are required to be installed necessarily for tranformer's safety.

(vi) Whether earth resistance is being measured periodically once a


year and results recorded in a register ? Yes,

Earth Resistance shall necessorily be measured in dry season. It is to be ensured that Earth Resistance
Register is regularily checked by AGE E/M and GE.
(vii) Any other defect or condition which may be source of danger. If
yes, please explain ? No

(viii) Whether operation and maintenence date has been clarified,


catergoized and computerized for prompt and easy retrieval ? Yes,

computorization is to be done for easy retrieval.


(ix) Whether residual life assessment and life extension programs are
being under taken for instalations or equipments of voltage exceeding
650V ? ( Applicable for installation or equipments more than 15 years Yes
old)
(x) Whether all required type and routine test at factory done for
equipments. Deficiency and discrepancies in above test report and NA, being periodic
results, if any, shall be reported. inspection

(xi) Are there deficiencies in construction with refernce to Indian


Standard requirements? Please specify. No

4 Regulation -15 Give report on the condition of service lines, cables, wires, apparatus
and such other fittings placed by the supplier/owner of the premises. If Satisfactory,
not satisfactory, give details.

5 Regulation -16 Whether suitable cut-outs/CBs provided by the supplier at the


consumers premises are within enclosed fire proof receptacle ? Yes

6 Regulation -17 (i) Whether switches are provided on live conductors ? Yes
(ii) Whether indication of a permanent nature is provided as per
regulation so as to distungish earthed conductor or earthed neutral Yes
conductor from the live conductor ?
(iii) Whether a direct line is provided on the neutral in the case of single
phase double pole iron clad switch/CBs instead of fuse ? Yes

7 Regulation -18 (i) Whether earthed terminal is provided by the supplier ? Yes
(ii) General visible condition of the earthing arrangement ? Satisfactory
8 Regulation -19 (i) Are live parts in building inaccessible ? Yes
(ii) Whether readily accesible switches have been provided for
rendering them dead ? Yes
9 Regulation -20 Whether " Danger Notices" in Hindi and the local language of the
district and of a design as per relevant Indian Standard are affixed Yes,
permanenetly in conspicuous position ?
But sufficient Danger Notice Plates to be provided
Report No. 119/23-24 Page 2 of 19
S No Regulation No Requirements Report
10 Regulation -21 (i) Whether the practice of working on live lines and apparatus is
adoped? If so, have the safety measure been adopted as per No
Schedule-I ?
(ii) Whether insulating floor or mats confirming to IS-15652: 2006 have
been provided ? Yes

(iii) Whether identification of panel has been provided on the front and
the rear of the panel ? No

Clearly visible Identification at the front & rear of the panels is to be done.
11 Regulation -23 Whether flexible cables used for portable or transportable equipment
(For portable/ covered under the regulation are heavily insulated and adequately
transpoetable Yes
protected from mechanical injury ?
apparatus)

12 Regulation -24 State the condition of metalic coverings provided for various
conductors. (For cables protected by bituminous materials) NA

13 Regulation -26 Whether the circuits or apparatus intended for operating at different
(Distinction of circuits) voltage(s) are distinguishable by means of indication(s) of permanent Yes
nature ?
14 Regulation -28 Whether all circuits and apparatus are so arranged that there is no
(Accidental charging of danger of any part(s) becoming accidentally charged to any voltage
circuits)
Yes
beyond the limits of voltage for which it/they is/are intended ?

15 Regulation -29 (i) In the case of generating stations/enclosed sub-stations/switching


sub-stations, whether fire buckets filled with clean dry sand been
conspicuously marked and kept in convenient situations in addition to Yes,
fire extinguisher suitable for dealing with electric fires ?

But Fire buckets with dry sand & Fire Extinguishers are required to be kept and maintained in
siffucient quantity .
(ii) Whether First Aid boxes or cupboards conspicuously marked and
properly equipped are provided and maintained at generating stations /
enclosed sub-stations / enclosed switching sub-stations / Electrical No
Maintenance vehicles except in case of unattended installations ?

First Aid Box with adeqate medicines is required to be kept and maintained.
(iii) Is adequate staff trained in First Aid Treatment and fire fighting ? No,
Regular training in liason with Stn HQ is required to be imparted.
16 Regulation -30 (i) Whether instructions in English or Hindi and the local language of
the district and where Hindi is the local language, in English and Hindi,
for the resuscitation of persons suffering from electric shock have been NO, to be provided
affixed in a "conspicuous place" ?

(ii) Are the persons mentioned in this regulation able to apply


instructions for resuscitation of persons suffering electric shock ? No

Regular training in liason with Stn HQ is required to be imparted.

As per Chapter-IV (General conditions relating to supply and use of electricity)


17 Regulation - 36 Leakage on premises : State insulation resisitance between conductors
and earth in Mega Ohms >1000 M Ohms

18 Regulation - 37 (i) Whether a suitable linked switch or circuit breaker, or a emergency


tripping device is placed near the point of commencement of supply so
as to be readily accessible and capable of being easily operated to Yes
completely isolate the supply ?

Report No. 119/23-24 Page 3 of 19


S No Regulation No Requirements Report
(ii) Whether suitable linked switch or a circuit breaker to carry and
break the full load current is provided on the secondary side of a Yes
transformer ?
(iii) Whether every distinct circuit is protected against excess electricity
by means of suitable circuit breaker or cut outs ? Yes
(iv) Whether linked switch or circuit breaker or emergency tripping
device is provided near the motor or other apparatus at Voltage
exceeding 650V but not exceeding 33KV for controlling supply to the Yes
motor or apparatus ?
(v) Whether adequate precautions are taken to ensure that no live parts
are so exposed as to cause danger ? Yes

19 Regulation- 39 (i) Whethe clear space of 100cm is provided in front of the main switch
board ? Yes

(ii) Whether the space behind the switch board exceeds 75cm in width
or is less than 20cm ? >75cm

(iii) In case the clear space behind the switch boards exceeds 75 cm,
State whether a passage way from either end of the switch board to a Yes
height of 1.80 meters is provided ?

Passage/space is always required to be always kept cleared of obstructions.

As per Chapter-VI (Safety provisions for electrical installations & apparatus of voltage exceeding 650V)
20 Regulation- 46 (i) Whether all conductors and apparatus including live parts thereof are
inaccesible ? Yes
(ii) Whether all windings of motors or other appparatus are suitably
protected ? Yes
(iii) Whether the separation wall or fire wall between apparatuses or
consumer premises, in a substation or a switching station with
apparatus having more than 2000 litres of oil are installed, have been NA
provided as required under the regulation?

(iv) Where 9,000 litres or more oils used in any one oil tank, has
provisions been made for draining away or removal of oil which may NA
leak or escape from such tank(s) ?
(v) Whether suitable firefighting system as per the regulation has been
provided ? Yes, but inadequate

(vi) Whether trenches inside sub-station containing cable are filled with
non-inflammable material or completely covered with non-inflammable Yes
slabs ?
(vii) Are conductors and apparatus so arranged that they may be made
dead in sections for carrying out work thereon ? Yes

21 Regulation- 47 Whether protections and inter-locks have been provided ? Give details Yes, SLD to be
of the protection scheme & their settings. provided
22 Regulation- 50 (i) Have all non-current carrying metal parts associated with the
(Connection with installation been effectively earthed with the earthng system or mat by Yes
earth for apparatus of two seperate & district connections ?
>650V)
(ii) Is the earth wire free from any mechanical damage ? Yes
(iii) Has the neutral point at the transformer and generator been
earthed by two separate and distinct connections with earth ? Yes

(iv) Have the metal casings or metallic coverings containing or


protecting and electric supply line or apparatus been properly earthed
and so joined and connected across all junction boxes as to make good Yes
mechanical and electrical connection throughout their whole length ?

Report No. 119/23-24 Page 4 of 19


S No Regulation No Requirements Report
(v) Whether earthings has been properly executed and has been Yes,
tested? If yes, give value of earth resistance. 0.4 to 1.0
Ohms
23 Regulation- 51 (i) Is the outdoor ( except pole type) sub-station efficiently protected by
fencing not less than 1.80 meteres in height ? Yes

(ii) Whether the mounting of a transformer on a single pole or H Pole is


done as per relevant Standard. NA

24 Regulation- 52 (For (i) Whether platform type construction is used for pole type substation,
Pole type sub- has sufficient space for a man to stand on the platform been provided ? NA
stations)
(ii) Has hand rail been provided and connected with earth ( if metalic
and if sub-station has not been erected on wooden supports and NA
wooden platform) ?

25 Regulation- 53 Has suitable provision been made for immdeiate and automatic or
manual discharge of every static condenser on disconnection of Yes
supply ?

As per Chapter-VII (Safety requirements of overhead lines and underground cables)


26 Over Head (OH) (i) What is the minimum size of the conductor of overhead lines used?
Lines State the type of conductors. (Regulation-57) NA

(ii) Whether clearances above ground of the lowest conductor of


overhead lines are as per Regulation-60 ? State clearance. NA

(iii) On the basis of maximum sag whether vertical clearance where the
lines of voltage exceeding 650V passes above or adjacent to any NA
building or part of a building as per Regulation-63 ? State clearance.
(iv) On the basis of maximum deflection due to wind pressure are
horizontal clearance between the nearest conductor and any part of NA
such building as per Regulation-61 ?

(v) Where conductors forming parts of system at different voltages are


erected on the same supports, whether adequate provisions has been
made as per Regulation-64 to guard against danger to lineman and
others from the lower voltage system being charged above its normal NA
working voltage by leakage from the contact with higher voltage system
?

(vi) Whether OH lines cross or are in proximity to each other whether


they have been suitably protected to guard against possibility of their
coming in contact with each other as per Regulation-71 ? NA

(vii) Has every guard wire been properly earthed as per Regulation-72
at each point at which its electrical continuity is broken ? NA

(viii) (a) Whether metal supports of overhead lines and metallic fittings
attached thereto are permanenetly earthed as per Requlation-74 ? NA

(b) Has each stay wire ( except in case where an insulator has been
placed in it at a height not less than 3 meteres from the ground ) been NA
earthed as per Regulation-74 ?

(ix) (a) Whether OH lines is suitably protected with a device for


rendering the line electrically harmless in case it breaks as per NA
Regulation-76 ?
(b) Whether anti climbing devices have been provided at each support
as per Regulation-75 ? No

Report No. 119/23-24 Page 5 of 19


S No Regulation No Requirements Report
(x) (a) Has the owner of overhead lines adopted efficient means for
diverting to earth any electrical surges due to lightining in every
overhead line which is so exposed as to be liable to injury from No
lightining as per Regultion-77 ?

(b) Whether earthing lead from the lightining arrestors been connected
to a separate earth electrode as per Regulation-77 ? No

(xi) Whether unsued overhead lines are being maintained in a safe


mechanical condition as per Regulation-78 ? NA

(xii) Whether statutory clearance from Authorities i.e. Forest


department/ Railways/ PTCC/ Defence(AHQ) /Civil Aviation have been NA
taken as per Indian Standard ? If yes, enclose copies of the same.

(xiii) Any other remarks.

8. Important Points observed which require attention:-


(i) In complince with Regulation-5, It shall be ensured that an Electrical Safety Officer is designated for ensuring observance of safety
measures specified under these regulations.

(ii) In compliance with Regulations-7&8, It shall be ascertained by GE to ensure safety measures for Operation & Maintenance of plants
and distribution lines system and they are operated by persons who hold degree / diploma in electrical / mechanical engineering.
Record for the maps,plans&sections of the system shall be maintained and submitted to the SEI as and when required.

(iii) In compliance with Regulation-10, Provision shall be ensured and a copy of maps shall be submitted to the SEI and a copy retained duly
certified by an appropriate authority.
(iv) In compliance with Regulation-11,12&13, It shall be ensured that the printed copies of the maps showing area of supply are always
maintained updated at GE office, and one copy is placed on display at the installation.

(v) In compliance with Regulation-77, During earth connections, it shall be ensured that the earthing lead for every lightning arrestor is
taken as directly as possible from the lightning arrestor without touching any other metal parts to a separate vertical ground electrode
or junction of the earthing subject to the avoidance of bends wherever practicable.

(vi) Sufficient Fire buckets with dry sand and Fire Extinguishers are to be provided & to be placed at a easily approachable place without
any obstructions.
(vii) Clearly visible identification at the front & rear of the HT panel is to be done.
(viii) Loose BE and NE strips to be tightened. Earth strips of BE & NE shall be routed seperately neatly and secured with clamps.

(ix) Kirloskar 315 KVA Transformer :- Cable entry glands to be provided. Mircoscopic Oil leak is observed at welding in Tr tank. Tr main
body is to be earthed. Earth Strip at neutral Terminal is found rusted. These points shall be rectified.

(x) 300 KVA Transformer :- one of the body earth is provided with wire, it shall be replaced with strip earth. One of the NE strip is
touching Tr body, it shall be retified.
(xi) 100 KVA Tr :- Oil leak at Bushing shall be arrested. Over hang NE strip is to be clamped properly.
(xii) Indotech 315 KVA Transformer :- Oil leak at Bushing shall be arrested.
(xiii) LAs and Anticlimbing Devices shall be provided at all the Pole Structures. Stay assembly shall be grouted to earth in place of opposte
4Pole structure
(xiv) Regular cleaning of S/S Building housing VCBs shall be ensured. Stores kept in S/S bldg shall be shifted to suitable place.Regular
cleaning of the yard is to be ensured.

Date : (Signature of the Inspecting Officer)


Name : Saurabh, IDSE
Rank : CE(NF)
Report No. 119/23-24 Page 6 of 19
Disgnation : Senior Electrical Inspector
For ADG(P) Chennai

Report No. 119/23-24 Page 7 of 19


Form of Inspection Report as per Schedule-II
[ Refer Regulation-32 & 45 of CEA (Measures relating to Safety & Electric Supply) Regulations, 2023 ]

FORM-III
(Installations of voltage exceeding 650V)

Report No. : 120/23-24


Date of Inspection by Electrical
: 14 Mar 2024
Inspector
Date of Last Inspection : -
1. Consumer No. : -
2. Voltage and system of Supply:-
(i) Voltage : 11 KV
(ii) No of Phases : 3 PHASE
(iii) AC/DC : AC
3. Name of Consumer/Owner : GE DSSC
4. Address of Consumer/Owner : GE DSSC Wellington
5. Location of the premises : S/S No 5

6. Particulatrs of Inspection : Periodic Inspection

Make Ser No Capacity Voltage Location


(a) TRANSFORMERS :
(i) Esennar ET2-7421 of year 250 KVA 11KV/433V S/S No 5
2022
(ii) IndoTech IT-44700 of year 2010 100 KVA 11KV/433V S/S No 5

(iii) ITL 9124 of year 1986 100 KVA 11KV/433V S/S No 5


(b) HT BREAKERS: RMU

(i) Siemens (1-I/C and LQR02/19/03/7007 630 Amp 12 KV Sub Stn No 5


6-O/G)
(c) OTHER EQPTS:
(i)
(d) Total connected load kW : 270 kW

7. General conditions of the Installation:-


The Outdoor unmanned installation is observed in good functional state. Regulation wise points observed as
under with respect to the outdoor installation shall be rectified on priorty:-

S No Regulation No Requirements Report


As per Chapter-II
1 Regulation -3 Is the register of the designated persons properly made and kept up to
date duly attested ? No

A record having the names of persons designated to operate and carry out the work on the electrical
apparatus is to be maintained. And that the designated persons shall possess a certificate of
competency or electrical work permit and the same shall be ensured by GE.

2 Regulation -5 Whether Electrical Safety Officer as required under the Regulation is


designated ? No

Report No. 120/23-24 Page 8 of 19


S No Regulation No Requirements Report
As per Chapter-III (General Safety Requirement)
3 Regulation -14 (i) Is/are there any visible sign(s) of overloading in respect of any
apparatus ? No

(ii) Whether any unauthorised temporary installation exists ? No


(iii) Whether the motors and controlling equipment are being over
hauled periodically and record kept of the same in register ? Yes

(iv) Whether the transformer oil samples are being tested periodically
and results recorded in a register ? Yes,

Record in register is to be maintained.


(v) Whether suitable lightning arrestors have been provided near the
transformers for protection against lightning ? NA

(vi) Whether earth resistance is being measured periodically once a


year and results recorded in a register ? Yes,

Reading enetered in Register are not matching with readings tested at the installation. Earth
Resistance shall necessorily be measured in dry season. It is to be ensured that Earth Resistance
Register is regularily checked by AGE E/M and GE.
(vii) Any other defect or condition which may be source of danger. If Yes, Earth resistance
yes, please explain ? too high
(viii) Whether operation and maintenence date has been clarified,
catergoized and computerized for prompt and easy retrieval ? Yes,

computorization is to be done for easy retrieval.


(ix) Whether residual life assessment and life extension programs are
being under taken for instalations or equipments of voltage exceeding
650V ? ( Applicable for installation or equipments more than 15 years Yes
old)
(x) Whether all required type and routine test at factory done for
equipments. Deficiency and discrepancies in above test report and NA, being periodic
results, if any, shall be reported. inspection

(xi) Are there deficiencies in construction with refernce to Indian


Standard requirements? Please specify. No

4 Regulation -15 Give report on the condition of service lines, cables, wires, apparatus
and such other fittings placed by the supplier/owner of the premises. If Satisfactory,
not satisfactory, give details.

5 Regulation -16 Whether suitable cut-outs/CBs provided by the supplier at the


consumers premises are within enclosed fire proof receptacle ? Yes

6 Regulation -17 (i) Whether switches are provided on live conductors ? Yes
(ii) Whether indication of a permanent nature is provided as per
regulation so as to distungish earthed conductor or earthed neutral Yes
conductor from the live conductor ?
(iii) Whether a direct line is provided on the neutral in the case of single
phase double pole iron clad switch/CBs instead of fuse ? Yes

7 Regulation -18 (i) Whether earthed terminal is provided by the supplier ? Yes
(ii) General visible condition of the earthing arrangement ? Satisfactory
8 Regulation -19 (i) Are live parts in building inaccessible ? Yes
(ii) Whether readily accesible switches have been provided for
rendering them dead ? Yes
9 Regulation -20 Whether " Danger Notices" in Hindi and the local language of the
district and of a design as per relevant Indian Standard are affixed Yes,
permanenetly in conspicuous position ?

Report No. 120/23-24 Page 9 of 19


S No Regulation No Requirements Report
10 Regulation -21 (i) Whether the practice of working on live lines and apparatus is
adoped? If so, have the safety measure been adopted as per No
Schedule-I ?
(ii) Whether insulating floor or mats confirming to IS-15652: 2006 have
been provided ? Yes

(iii) Whether identification of panel has been provided on the front and
the rear of the panel ? No

Clearly visible Identification at the front & rear of the panels is to be done.
11 Regulation -23 Whether flexible cables used for portable or transportable equipment
(For portable/ covered under the regulation are heavily insulated and adequately
transpoetable Yes
protected from mechanical injury ?
apparatus)

12 Regulation -24 State the condition of metalic coverings provided for various
conductors. (For cables protected by bituminous materials) NA

13 Regulation -26 Whether the circuits or apparatus intended for operating at different
(Distinction of circuits) voltage(s) are distinguishable by means of indication(s) of permanent Yes
nature ?
14 Regulation -28 Whether all circuits and apparatus are so arranged that there is no
(Accidental charging of danger of any part(s) becoming accidentally charged to any voltage
circuits)
Yes
beyond the limits of voltage for which it/they is/are intended ?

15 Regulation -29 (i) In the case of generating stations/enclosed sub-stations/switching


sub-stations, whether fire buckets filled with clean dry sand been
conspicuously marked and kept in convenient situations in addition to No
fire extinguisher suitable for dealing with electric fires ?

Fire buckets with dry sand s required to be kept and maintained.

(ii) Whether First Aid boxes or cupboards conspicuously marked and


properly equipped are provided and maintained at generating stations /
enclosed sub-stations / enclosed switching sub-stations / Electrical NA
Maintenance vehicles except in case of unattended installations ?

(iii) Is adequate staff trained in First Aid Treatment and fire fighting ? No,
Regular training in liason with Stn HQ is required to be imparted.
16 Regulation -30 (i) Whether instructions in English or Hindi and the local language of
the district and where Hindi is the local language, in English and Hindi,
for the resuscitation of persons suffering from electric shock have been NA,
affixed in a "conspicuous place" ?

(ii) Are the persons mentioned in this regulation able to apply


instructions for resuscitation of persons suffering electric shock ? No

Regular training in liason with Stn HQ is required to be imparted.

As per Chapter-IV (General conditions relating to supply and use of electricity)


17 Regulation - 36 Leakage on premises : State insulation resisitance between conductors
and earth in Mega Ohms >1000 M Ohms

18 Regulation - 37 (i) Whether a suitable linked switch or circuit breaker, or a emergency


tripping device is placed near the point of commencement of supply so
as to be readily accessible and capable of being easily operated to Yes
completely isolate the supply ?

Report No. 120/23-24 Page 10 of 19


S No Regulation No Requirements Report
(ii) Whether suitable linked switch or a circuit breaker to carry and
break the full load current is provided on the secondary side of a Yes
transformer ?
(iii) Whether every distinct circuit is protected against excess electricity
by means of suitable circuit breaker or cut outs ? Yes
(iv) Whether linked switch or circuit breaker or emergency tripping
device is provided near the motor or other apparatus at Voltage Yes
exceeding 650V but not exceeding 33KV for controlling supply to the
motor or apparatus ?
(v) Whether adequate precautions are taken to ensure that no live parts
are so exposed as to cause danger ? Yes

19 Regulation- 39 (i) Whethe clear space of 100cm is provided in front of the main switch
board ? Yes

(ii) Whether the space behind the switch board exceeds 75cm in width
or is less than 20cm ? >75cm

(iii) In case the clear space behind the switch boards exceeds 75 cm,
State whether a passage way from either end of the switch board to a Yes
height of 1.80 meters is provided ?
Passage/space is always required to be always kept cleared of obstructions.

As per Chapter-VI (Safety provisions for electrical installations & apparatus of voltage exceeding 650V)
20 Regulation- 46 (i) Whether all conductors and apparatus including live parts thereof are
inaccesible ? Yes
(ii) Whether all windings of motors or other appparatus are suitably
protected ? Yes
(iii) Whether the separation wall or fire wall between apparatuses or
consumer premises, in a substation or a switching station with
apparatus having more than 2000 litres of oil are installed, have been NA
provided as required under the regulation?

(iv) Where 9,000 litres or more oils used in any one oil tank, has
provisions been made for draining away or removal of oil which may NA
leak or escape from such tank(s) ?
(v) Whether suitable firefighting system as per the regulation has been
provided ? No

(vi) Whether trenches inside sub-station containing cable are filled with
non-inflammable material or completely covered with non-inflammable NA
slabs ?
(vii) Are conductors and apparatus so arranged that they may be made
dead in sections for carrying out work thereon ? Yes

21 Regulation- 47 Whether protections and inter-locks have been provided ? Give details
of the protection scheme & their settings. Yes

22 Regulation- 50 (i) Have all non-current carrying metal parts associated with the
(Connection with installation been effectively earthed with the earthng system or mat by Yes
earth for apparatus of two seperate & district connections ?
>650V)
(ii) Is the earth wire free from any mechanical damage ? Yes
(iii) Has the neutral point at the transformer and generator been
earthed by two separate and distinct connections with earth ? Yes

(iv) Have the metal casings or metallic coverings containing or


protecting and electric supply line or apparatus been properly earthed
and so joined and connected across all junction boxes as to make good Yes
mechanical and electrical connection throughout their whole length ?

Report No. 120/23-24 Page 11 of 19


S No Regulation No Requirements Report
(v) Whether earthings has been properly executed and has been Yes,
tested? If yes, give value of earth resistance. 0.8 to 12.0
Ohms
23 Regulation- 51 (i) Is the outdoor ( except pole type) sub-station efficiently protected by
fencing not less than 1.80 meteres in height ? Yes

(ii) Whether the mounting of a transformer on a single pole or H Pole is


done as per relevant Standard. NA

24 Regulation- 52 (For (i) Whether platform type construction is used for pole type substation,
Pole type sub- has sufficient space for a man to stand on the platform been provided ? NA
stations)

(ii) Has hand rail been provided and connected with earth ( if metalic
and if sub-station has not been erected on wooden supports and NA
wooden platform) ?

25 Regulation- 53 Has suitable provision been made for immdeiate and automatic or
manual discharge of every static condenser on disconnection of Yes
supply ?

As per Chapter-VII (Safety requirements of overhead lines and underground cables)


26 Over Head (OH) (i) What is the minimum size of the conductor of overhead lines used?
Lines State the type of conductors. (Regulation-57) NA

(ii) Whether clearances above ground of the lowest conductor of


overhead lines are as per Regulation-60 ? State clearance. NA

(iii) On the basis of maximum sag whether vertical clearance where the
lines of voltage exceeding 650V passes above or adjacent to any NA
building or part of a building as per Regulation-63 ? State clearance.
(iv) On the basis of maximum deflection due to wind pressure are
horizontal clearance between the nearest conductor and any part of NA
such building as per Regulation-61 ?

(v) Where conductors forming parts of system at different voltages are


erected on the same supports, whether adequate provisions has been
made as per Regulation-64 to guard against danger to lineman and
others from the lower voltage system being charged above its normal NA
working voltage by leakage from the contact with higher voltage system
?

(vi) Whether OH lines cross or are in proximity to each other whether


they have been suitably protected to guard against possibility of their
coming in contact with each other as per Regulation-71 ? NA

(vii) Has every guard wire been properly earthed as per Regulation-72
at each point at which its electrical continuity is broken ? NA

(viii) (a) Whether metal supports of overhead lines and metallic fittings
attached thereto are permanenetly earthed as per Requlation-74 ? NA

(b) Has each stay wire ( except in case where an insulator has been
placed in it at a height not less than 3 meteres from the ground ) been NA
earthed as per Regulation-74 ?

(ix) (a) Whether OH lines is suitably protected with a device for


rendering the line electrically harmless in case it breaks as per NA
Regulation-76 ?
(b) Whether anti climbing devices have been provided at each support
as per Regulation-75 ? NA

Report No. 120/23-24 Page 12 of 19


S No Regulation No Requirements Report
(x) (a) Has the owner of overhead lines adopted efficient means for
diverting to earth any electrical surges due to lightining in every
overhead line which is so exposed as to be liable to injury from NA
lightining as per Regultion-77 ?

(b) Whether earthing lead from the lightining arrestors been connected
to a separate earth electrode as per Regulation-77 ? NA

(xi) Whether unsued overhead lines are being maintained in a safe


mechanical condition as per Regulation-78 ? NA

(xii) Whether statutory clearance from Authorities i.e. Forest


department/ Railways/ PTCC/ Defence(AHQ) /Civil Aviation have been NA
taken as per Indian Standard ? If yes, enclose copies of the same.

(xiii) Any other remarks.

8. Important Points observed which require attention:-


(i) In complince with Regulation-5, It shall be ensured that an Electrical Safety Officer is designated for ensuring observance of safety
measures specified under these regulations.

(ii) In compliance with Regulations-7&8, It shall be ascertained by GE to ensure safety measures for Operation & Maintenance of plants
and distribution lines system and they are operated by persons who hold degree / diploma in electrical / mechanical engineering.
Record for the maps,plans&sections of the system shall be maintained and submitted to the SEI as and when required.

(iii) In compliance with Regulation-10, Provision shall be ensured and a copy of maps shall be submitted to the SEI and a copy retained duly
certified by an appropriate authority.
(iv) In compliance with Regulation-11,12&13, It shall be ensured that the printed copies of the maps showing area of supply are always
maintained updated at GE office, and one copy is placed on display at the installation.

(v) In compliance with Regulation-77, During earth connections, it shall be ensured that the earthing lead for every lightning arrestor is
taken as directly as possible from the lightning arrestor without touching any other metal parts to a separate vertical ground electrode
or junction of the earthing subject to the avoidance of bends wherever practicable.

(vi) Fire buckets with dry sand are to be provided & to be placed at a easily approachable place without any obstructions.

(vii) Clearly visible identification at the front & rear of the HT panel is to be done.
(viii) Loose BE and NE strips to be tightened. Earth strips of BE & NE shall be routed seperately neatly and secured with clamps. Not more
than 2 Earth strip shall be connected to Neutral terminal of Tr so as to avoid any NE strip touching body, if required grid of earth can
be made at ground level.

(ix) NE strips touching 250 KVA Tr body observed & it shall be rectified
(x) Earth Pit identification shall be provided.
(xi) 100 KVA Tr :- Oil leak at Bushing shall be arrested.
(xii) Regular grss cutting & cleaning of the yard is to be ensured.
(xiii) Immediate efforts shall be made to bring down very high earth resistances.

Date : (Signature of the Inspecting Officer)


Name : Saurabh, IDSE
Rank : CE(NF)
Disgnation : Senior Electrical Inspector
For ADG(P) Chennai

Report No. 120/23-24 Page 13 of 19


Form of Inspection Report as per Schedule-II
[ Refer Regulation-32 & 45 of CEA (Measures relating to Safety & Electric Supply) Regulations, 2023 ]

FORM-III
(Installations of voltage exceeding 650V)

Report No. : 121/23-24


Date of Inspection by Electrical
: 14 Mar 2024
Inspector
Date of Last Inspection : -
1. Consumer No. : -
2. Voltage and system of Supply:-
(i) Voltage : 11 KV
(ii) No of Phases : 3 PHASE
(iii) AC/DC : AC
3. Name of Consumer/Owner : GE DSSC
4. Address of Consumer/Owner : GE DSSC Wellington
5. Location of the premises : Gorkha Camp S/S

6. Particulatrs of Inspection : Pre-commissioning & Periodic Inspection

Make Ser No Capacity Voltage Location


(a) TRANSFORMERS : (Periodic inspection)
(i) IndoTech IT-22168 of year 1995 200 KVA 11KV/433V Gorkha Camp S/S

(b) HT BREAKERS: RMU(Pre-commissioning inspection)

(i) ABB IVYN040123000086 630 Amp 12 KV Gorkha Camp S/S

(c) OTHER EQPTS:


(i) One 2-Pole Structure with GoD 11 KV Gorkha Camp S/S

(d) Total connected load kW : 150 kW

7. General conditions of the Installation:-


The Outdoor unmanned installation is observed in good functional state. Regulation wise points observed as
under with respect to the outdoor installation shall be rectified on priorty:-

S No Regulation No Requirements Report


As per Chapter-II
1 Regulation -3 Is the register of the designated persons properly made and kept up to
date duly attested ? No

A record having the names of persons designated to operate and carry out the work on the electrical
apparatus is to be maintained. And that the designated persons shall possess a certificate of
competency or electrical work permit and the same shall be ensured by GE.

2 Regulation -5 Whether Electrical Safety Officer as required under the Regulation is


designated ? No

Report No. 121/23-24 Page 14 of 19


S No Regulation No Requirements Report
As per Chapter-III (General Safety Requirement)
3 Regulation -14 (i) Is/are there any visible sign(s) of overloading in respect of any
apparatus ? No

(ii) Whether any unauthorised temporary installation exists ? No


(iii) Whether the motors and controlling equipment are being over
hauled periodically and record kept of the same in register ? Yes

(iv) Whether the transformer oil samples are being tested periodically
and results recorded in a register ? Yes,

Record in register is to be maintained.


(v) Whether suitable lightning arrestors have been provided near the
transformers for protection against lightning ? No

(vi) Whether earth resistance is being measured periodically once a


year and results recorded in a register ? Yes,

Reading enetered in Register are not matching with readings tested at the installation. Earth
Resistance shall necessorily be measured in dry season. It is to be ensured that Earth Resistance
Register is regularily checked by AGE E/M and GE.
(vii) Any other defect or condition which may be source of danger. If
yes, please explain ? No

(viii) Whether operation and maintenence date has been clarified,


catergoized and computerized for prompt and easy retrieval ? Yes,

computorization is to be done for easy retrieval.


(ix) Whether residual life assessment and life extension programs are
being under taken for instalations or equipments of voltage exceeding
650V ? ( Applicable for installation or equipments more than 15 years Yes
old)
(x) Whether all required type and routine test at factory done for
equipments. Deficiency and discrepancies in above test report and Yes
results, if any, shall be reported.
(xi) Are there deficiencies in construction with refernce to Indian
Standard requirements? Please specify. No

4 Regulation -15 Give report on the condition of service lines, cables, wires, apparatus
and such other fittings placed by the supplier/owner of the premises. If Satisfactory,
not satisfactory, give details.

5 Regulation -16 Whether suitable cut-outs/CBs provided by the supplier at the


consumers premises are within enclosed fire proof receptacle ? Yes

6 Regulation -17 (i) Whether switches are provided on live conductors ? Yes
(ii) Whether indication of a permanent nature is provided as per
regulation so as to distungish earthed conductor or earthed neutral Yes
conductor from the live conductor ?
(iii) Whether a direct line is provided on the neutral in the case of single
phase double pole iron clad switch/CBs instead of fuse ? Yes

7 Regulation -18 (i) Whether earthed terminal is provided by the supplier ? Yes
(ii) General visible condition of the earthing arrangement ? Satisfactory
8 Regulation -19 (i) Are live parts in building inaccessible ? Yes
(ii) Whether readily accesible switches have been provided for
rendering them dead ? Yes
9 Regulation -20 Whether " Danger Notices" in Hindi and the local language of the
district and of a design as per relevant Indian Standard are affixed Yes,
permanenetly in conspicuous position ?

Report No. 121/23-24 Page 15 of 19


S No Regulation No Requirements Report
10 Regulation -21 (i) Whether the practice of working on live lines and apparatus is
adoped? If so, have the safety measure been adopted as per No
Schedule-I ?
(ii) Whether insulating floor or mats confirming to IS-15652: 2006 have
been provided ? No

(iii) Whether identification of panel has been provided on the front and
the rear of the panel ? No

Clearly visible Identification at the front & rear of the panels is to be done.
11 Regulation -23 Whether flexible cables used for portable or transportable equipment
(For portable/ covered under the regulation are heavily insulated and adequately
transpoetable Yes
protected from mechanical injury ?
apparatus)

12 Regulation -24 State the condition of metalic coverings provided for various
conductors. (For cables protected by bituminous materials) NA

13 Regulation -26 Whether the circuits or apparatus intended for operating at different
(Distinction of circuits) voltage(s) are distinguishable by means of indication(s) of permanent Yes
nature ?
14 Regulation -28 Whether all circuits and apparatus are so arranged that there is no
(Accidental charging of danger of any part(s) becoming accidentally charged to any voltage
circuits)
Yes
beyond the limits of voltage for which it/they is/are intended ?

15 Regulation -29 (i) In the case of generating stations/enclosed sub-stations/switching


sub-stations, whether fire buckets filled with clean dry sand been
conspicuously marked and kept in convenient situations in addition to No
fire extinguisher suitable for dealing with electric fires ?

Fire buckets with dry sand s required to be kept and maintained .


(ii) Whether First Aid boxes or cupboards conspicuously marked and
properly equipped are provided and maintained at generating stations /
enclosed sub-stations / enclosed switching sub-stations / Electrical NA
Maintenance vehicles except in case of unattended installations ?

(iii) Is adequate staff trained in First Aid Treatment and fire fighting ? No,
Regular training in liason with Stn HQ is required to be imparted.
16 Regulation -30 (i) Whether instructions in English or Hindi and the local language of
the district and where Hindi is the local language, in English and Hindi,
for the resuscitation of persons suffering from electric shock have been NA,
affixed in a "conspicuous place" ?

(ii) Are the persons mentioned in this regulation able to apply


instructions for resuscitation of persons suffering electric shock ? No

Regular training in liason with Stn HQ is required to be imparted.

As per Chapter-IV (General conditions relating to supply and use of electricity)


17 Regulation - 36 Leakage on premises : State insulation resisitance between conductors
and earth in Mega Ohms >1000 M Ohms

18 Regulation - 37 (i) Whether a suitable linked switch or circuit breaker, or a emergency


tripping device is placed near the point of commencement of supply so
as to be readily accessible and capable of being easily operated to Yes
completely isolate the supply ?

Report No. 121/23-24 Page 16 of 19


S No Regulation No Requirements Report
(ii) Whether suitable linked switch or a circuit breaker to carry and
break the full load current is provided on the secondary side of a Yes
transformer ?
(iii) Whether every distinct circuit is protected against excess electricity
by means of suitable circuit breaker or cut outs ? Yes
(iv) Whether linked switch or circuit breaker or emergency tripping
device is provided near the motor or other apparatus at Voltage Yes
exceeding 650V but not exceeding 33KV for controlling supply to the
motor or apparatus ?
(v) Whether adequate precautions are taken to ensure that no live parts
are so exposed as to cause danger ? Yes

19 Regulation- 39 (i) Whethe clear space of 100cm is provided in front of the main switch
board ? Yes

(ii) Whether the space behind the switch board exceeds 75cm in width
or is less than 20cm ? >75cm

(iii) In case the clear space behind the switch boards exceeds 75 cm,
State whether a passage way from either end of the switch board to a Yes
height of 1.80 meters is provided ?
Passage/space is always required to be always kept cleared of obstructions.

As per Chapter-VI (Safety provisions for electrical installations & apparatus of voltage exceeding 650V)
20 Regulation- 46 (i) Whether all conductors and apparatus including live parts thereof are
inaccesible ? Yes
(ii) Whether all windings of motors or other appparatus are suitably
protected ? Yes
(iii) Whether the separation wall or fire wall between apparatuses or
consumer premises, in a substation or a switching station with
apparatus having more than 2000 litres of oil are installed, have been NA
provided as required under the regulation?

(iv) Where 9,000 litres or more oils used in any one oil tank, has
provisions been made for draining away or removal of oil which may NA
leak or escape from such tank(s) ?
(v) Whether suitable firefighting system as per the regulation has been
provided ? No

(vi) Whether trenches inside sub-station containing cable are filled with
non-inflammable material or completely covered with non-inflammable NA
slabs ?
(vii) Are conductors and apparatus so arranged that they may be made
dead in sections for carrying out work thereon ? Yes

21 Regulation- 47 Whether protections and inter-locks have been provided ? Give details
of the protection scheme & their settings. Yes

22 Regulation- 50 (i) Have all non-current carrying metal parts associated with the
(Connection with installation been effectively earthed with the earthng system or mat by Yes
earth for apparatus of two seperate & district connections ?
>650V)
(ii) Is the earth wire free from any mechanical damage ? Yes
(iii) Has the neutral point at the transformer and generator been
earthed by two separate and distinct connections with earth ? Yes

(iv) Have the metal casings or metallic coverings containing or


protecting and electric supply line or apparatus been properly earthed
and so joined and connected across all junction boxes as to make good Yes
mechanical and electrical connection throughout their whole length ?

Report No. 121/23-24 Page 17 of 19


S No Regulation No Requirements Report
(v) Whether earthings has been properly executed and has been Yes,
tested? If yes, give value of earth resistance. 0.3 to 7.0
Ohms
23 Regulation- 51 (i) Is the outdoor ( except pole type) sub-station efficiently protected by
fencing not less than 1.80 meteres in height ? Yes

(ii) Whether the mounting of a transformer on a single pole or H Pole is


done as per relevant Standard. NA

24 Regulation- 52 (For (i) Whether platform type construction is used for pole type substation,
Pole type sub- has sufficient space for a man to stand on the platform been provided ? NA
stations)

(ii) Has hand rail been provided and connected with earth ( if metalic
and if sub-station has not been erected on wooden supports and NA
wooden platform) ?

25 Regulation- 53 Has suitable provision been made for immdeiate and automatic or
manual discharge of every static condenser on disconnection of Yes
supply ?

As per Chapter-VII (Safety requirements of overhead lines and underground cables)


26 Over Head (OH) (i) What is the minimum size of the conductor of overhead lines used?
Lines State the type of conductors. (Regulation-57) NA

(ii) Whether clearances above ground of the lowest conductor of


overhead lines are as per Regulation-60 ? State clearance. NA

(iii) On the basis of maximum sag whether vertical clearance where the
lines of voltage exceeding 650V passes above or adjacent to any NA
building or part of a building as per Regulation-63 ? State clearance.
(iv) On the basis of maximum deflection due to wind pressure are
horizontal clearance between the nearest conductor and any part of NA
such building as per Regulation-61 ?

(v) Where conductors forming parts of system at different voltages are


erected on the same supports, whether adequate provisions has been
made as per Regulation-64 to guard against danger to lineman and
others from the lower voltage system being charged above its normal NA
working voltage by leakage from the contact with higher voltage system
?

(vi) Whether OH lines cross or are in proximity to each other whether


they have been suitably protected to guard against possibility of their
coming in contact with each other as per Regulation-71 ? NA

(vii) Has every guard wire been properly earthed as per Regulation-72
at each point at which its electrical continuity is broken ? NA

(viii) (a) Whether metal supports of overhead lines and metallic fittings
attached thereto are permanenetly earthed as per Requlation-74 ? NA

(b) Has each stay wire ( except in case where an insulator has been
placed in it at a height not less than 3 meteres from the ground ) been NA
earthed as per Regulation-74 ?

(ix) (a) Whether OH lines is suitably protected with a device for


rendering the line electrically harmless in case it breaks as per NA
Regulation-76 ?
(b) Whether anti climbing devices have been provided at each support
as per Regulation-75 ? No

Report No. 121/23-24 Page 18 of 19


S No Regulation No Requirements Report
(x) (a) Has the owner of overhead lines adopted efficient means for
diverting to earth any electrical surges due to lightining in every
overhead line which is so exposed as to be liable to injury from No
lightining as per Regultion-77 ?

(b) Whether earthing lead from the lightining arrestors been connected
to a separate earth electrode as per Regulation-77 ? No

(xi) Whether unsued overhead lines are being maintained in a safe


mechanical condition as per Regulation-78 ? NA

(xii) Whether statutory clearance from Authorities i.e. Forest


department/ Railways/ PTCC/ Defence(AHQ) /Civil Aviation have been NA
taken as per Indian Standard ? If yes, enclose copies of the same.

(xiii) Any other remarks.

8. Important Points observed which require attention:-


(i) In complince with Regulation-5, It shall be ensured that an Electrical Safety Officer is designated for ensuring observance of safety
measures specified under these regulations.

(ii) In compliance with Regulations-7&8, It shall be ascertained by GE to ensure safety measures for Operation & Maintenance of plants
and distribution lines system and they are operated by persons who hold degree / diploma in electrical / mechanical engineering.
Record for the maps,plans&sections of the system shall be maintained and submitted to the SEI as and when required.

(iii) In compliance with Regulation-10, Provision shall be ensured and a copy of maps shall be submitted to the SEI and a copy retained duly
certified by an appropriate authority.
(iv) In compliance with Regulation-11,12&13, It shall be ensured that the printed copies of the maps showing area of supply are always
maintained updated at GE office, and one copy is placed on display at the installation.

(v) In compliance with Regulation-77, During earth connections, it shall be ensured that the earthing lead for every lightning arrestor is
taken as directly as possible from the lightning arrestor without touching any other metal parts to a separate vertical ground electrode
or junction of the earthing subject to the avoidance of bends wherever practicable.

(vi) Fire buckets with dry sand are to be provided & to be placed at a easily approachable place without any obstructions.

(vii) Clearly visible identification at the front & rear of the HT panel is to be done.
(viii) Loose BE and NE strips to be tightened. Earth strips of BE & NE shall be routed seperately neatly and secured with clamps.

(ix) As S/S exists in MD Accn area, Certain places in fencing have apossibility of kid's entry to the yard. Such eccess shall be blocked on
priority.
(x) Immediate efforts shall be made to bring down Higher earth resistances.
(xi) Las and Anti-Climbing Devices shall be provided on 2-Pole Structure. Sufficient no of Danger Notice Plates shall be provided.

(xii) Regular grass cutting & cleaning of the yard is to be ensured.

Date : (Signature of the Inspecting Officer)


Name : Saurabh, IDSE
Rank : CE(NF)
Disgnation : Senior Electrical Inspector
For ADG(P) Chennai

Report No. 121/23-24 Page 19 of 19