19.05.2024 DPR
19.05.2024 DPR
19.05.2024 DPR
Chainage Yesterday This This Cut & Cover Main Total Work Up to Total Project Balance
Sr.No. Location Remark
From To Work Done Month Month Length Tunnel Done Date Tunnel Length
1 LHS TUNNEL MORBE END 75680 73929.6 Length
3.4 Progress
75.7 Target
140 135 Length
1615.4 Length
1750.4 Length Length
3442.1 4160 717.9
2 RHS TUNNEL MORBE END 75680 73988.3 3.3 66.6 140 130 1561.7 1691.7
3 LHS TUNNEL BHOJ END 71520 73106.1 0.0 74.1 150 180 1406 1586
2820.9 4160 1339.1
4 RHS TUNNEL BHOJ END 71520 72754.8 0.0 74.8 150 5 1229.8 1234.8
Total 6.7 291.2 580 450 5813.0 6263.0 6263.0 8320 2057.0