Professional Documents
Culture Documents
Visit Report 62022716 - 20.0237 - Ankara - 20240419 MVC
Visit Report 62022716 - 20.0237 - Ankara - 20240419 MVC
Page 1 of 15
Visit Report
Page 2 of 15
Visit Report
Due to the broken parts that need to be replaced, the issue with the “foamy glycol” couldn’t
be resolved.
Due to the broken magnetic valve, what most probably caused the aftercooler to get
damaged, the client wants to see warranty over this, due to the fact that the CO2 Recovery
Plant is just not running 2 years.
- Running hours of the CO2 Compressor: 7154 hours.
- Data of hand-over (according to Process Data Setpoint-list): 29 April 2022.
Project build and handed over by: Tanakorn Kiawkaew.
Shaft seal is leaking at the NH3 Compressor from project 20.0237 with 8256 running hours.
Advise to:
- Check alignment when compressor unit is still “hot”.
- Replace shaft seal.
- Align compressor block again with certificate.
- Advise to get SABROE / Johnson Controls on-site a.s.a.p.
Several points are repainted, please be aware that type plates must always be visible.
NH3 level in the CO2 Condenser from NH3 cooling unit 3 seems a bit low.
This needs to be double checked by the client.
When needed, they need to add some NH3, or exchange the Level Transmitter.
There’s a small NH3 leak at the cooling unit from project 04.0931 at a coupling from
V0820.1025 when they open V0820.1026, this needs to be solved / repaired by the brewery
due to safety issues / NH3 leakages.
Running hours:
CO2 Compressor 1: 7150 running hours.
CO2 Compressor 1, head cooling pump: 8282 running hours.
CO2 Compressor 1, cooling pump: 7150 running hours.
CO2 Compressor 2: 11124 running hours.
CO2 Compressor 2: head cooling pump: 11621 running hours.
CO2 Compressor 3: 80501 running hours.
CO2 Liquid Pump 1: 2061 running hours.
CO2 Liquid Pump 2: 18539 running hours.
NH3 Compressor 1: 8256 running hours.
NH3 Compressor 2: 11256 running hours.
NH3 Compressor 3: 27752 running hours.
Page 3 of 15
Visit Report
Performed operations
Page 4 of 15
Visit Report
Wednesday 17-4-2024:
- Had a short meeting with the client, and talked about the issue they had, and agreed
on a plan what to check.
- Tested CO2 Compressor units 1 and 2, to be 100% sure that there’s no leakage.
➔ Drained all glycol from CO2 Compressor 2, and started the pressure test with
water on the complete compressor unit.
Pressure test was OK.
➔ Drained all glycol from CO2 Compressor 1, and started the pressure test with
water on the complete compressor unit.
Pressure test was Not OK, because of a pressure drop of 0,2 bar.
Agreed to build the cooler out, the next day, to find the leakage.
- According to the client, they had a leak in the past on the aftercooler from CO2
Compressor 3 (NEA 2TZS25), and had 2 pipes leaking, and closed the pipes and
ordered a new aftercooler.
- According to the client, they’ve already tried to clean the oil cooler on the NH3
compressor, with CIP (Caustic solution).
➔ Agreed that they’re going to connect a steam line on it, and let it flow reversed,
compared of the normal glycol flow.
➔ Steam was 113 degrees Celsius (maximum temperature measured).
Flushed the oil cooler for approx. 3 hours, from which the last hour the
temperature wouldn’t rise anymore on the outlet.
- Pulled from both stages a valve, so see the inside.
From a discharge valve 1st stage, a corner is broken of the valve cage, advise to
replace it.
Also all the nuts where not on torque, according to the client, this comes because
they inspect the valves regularly and they didn’t know the correct torque.
Thursday 18-4-2024:
- Build out the aftercooler from CO2 Compressor 1 (from project 20.0237).
➔ Found ice inside the piping (gas side) of the aftercooler, what means that there’s
something wrong with the glycol circuit.
➔ After checking the magnetic valve V0650.0803 it was found faulty.
So this means that there was a constant flow over the aftercooler, with glycol of -
4 degrees Celsius.
➔ Pressure test on the aftercooler from CO2 Compressor 1 (from project 20.0237)
Result was that 1 of the cooling pipes was leaking a little bit, so we’ve closed this
pipe on both sides, and build it back into the compressor unit.
- Tested CO2 Compressor unit 3, to be 100% sure that there’s no leakage.
➔ Drained all glycol from CO2 Compressor 3, and started the pressure test with
water on the complete compressor unit.
Pressure test was Not OK, because of a pressure drop of 0,6 bar.
Customer already ordered a new cooler, so they don’t want to repair this cooler
again.
- The Temperature Transmitter (TT1030.0405) of the CO2 inlet at the HRS (project
06.7235) was broken due to bending, replaced it sensor and the measuring pipe for a
new one.
- Did a pressure test on the HRS (from project 06.7235), and the result was not OK.
Advise to exchange the HRS a.s.a.p.
- CO2 Compressors 2 & 3 are running to warm after the aftercooler and too cold on
the cylinder block.
Page 5 of 15
Visit Report
Friday 19-4-2024:
- Adjusted the NH3 compressor, so that we run on 5 bar discharge instead of 4,4 bar.
However the discharge temperature would then get higher, what then would reduce
the capacity by the SABROE software.
Therefor on request of the client, I’ve put the discharge pressure back on 4,4 bar.
- Measured temperatures on the oil cooler from the NH3 compressor unit.
➔ Oil inlet: 79,2 degrees Celsius.
➔ Oil outlet: 59,8 degrees Celsius.
➔ Glycol inlet: -0,3 degrees Celsius.
➔ Glycol outlet: 7,6 degrees Celsius.
➔ Oil after 3-way valve / inlet NH3 compressor: 63,4 degrees Celsius.
- Measured also the NH3 gas.
➔ Inlet: 2,1 degrees Celsius.
➔ Outlet: 92,7 degrees Celsius.
This temperature is slowly climbing when it runs for a longer period of time.
When the complete compressor unit is cold, it’s OK, but after a while you see the
temperature climbing and reaching 100 degrees Celsius as well…
- No pressure difference / pressure drop over oil filter.
- On the shaft seal is an “oil leak collector” placed, who was completely full.
This is then approx. 500cc of oil that came out at the shaft, with 8256 running hours.
- Did a vibration test, with an “SKF DMVP50 Vibration Pen” (Serial number: 8967)
Measured on several spots on the NH3 compressor unit, and all seem to within the
specifications.
Vibrations were checked on the main frame, electric motor and the NH3 screw
compressor block.
- Checked capacity slide of NH3 compressor.
Seems to be working correctly.
➔ -2% when standing OFF.
➔ When starting up, it goes to -27%, before it starts to climb up.
➔ When on full capacity, it shows 100%.
- Checked power consumption at 100% capacity / 60 Hz.
Fase 1: 52,46 A. Fase 2: 51,11 A. Fase 3: 51,31 A.
Page 6 of 15
Visit Report
Pressure tests :
Compressor Unit 1: (from project 20.0237)
- NEA 2V1 – 370/180
- Serial number: 909001008
Construction year: 2021
- Tested complete unit on 17-04-2024.
Start pressure: 4,8 Bar @ 15:44
Stop pressure: 4,6 Bar @ 16:30
Result: NOT OK
- Tested after cooler (when build out of unit) on 18-04-2024.
Start pressure: 15,4 Bar @ 11:58
Stop pressure: approx. 13,4 @ 13:15
Result: NOT OK
➔ Repaired the leakage by closing the leaking pipe on both sides.
So after this it was OK again.
However the advice to exchange the cooler.
Compressor Unit 2: (from project 04.0931)
- NEA 2V2 – 335/170
- Serial number compressor: 502336
Serial number unit: 900712
Construction year: 2005
- Tested complete unit on 17-04-2024.
Start pressure: 4,4 Bar @ 11:20
Stop pressure: 4,4 Bar @ 12:41
Result: OK
Compressor Unit 3: (from project 10.5563)
- NEA 2TZS25 – 250/120
- Serial number: 507583
Construction year: 2011
- Tested complete unit on 18-04-2024.
Start pressure: 5,4 Bar @ 15:20
Stop pressure: 4,8 Bar @ 15:50
Result: NOT OK
➔ Client ordered a new cooler already, and when it arrives they’ll exchange the
cooler.
HRS unit: (from project 06.7235)
- Vahterus
- Serial number:
- Tested heat exchanger on 18-04-2024.
Start pressure: 23 Bar @ 11:55
Stop pressure: 16,5 Bar @ 13:21
Result: NOT OK
➔ New HRS heat exchanger needs to be offered, and then build-in by the client.
Page 7 of 15
Visit Report
Pictures
Page 8 of 15
Visit Report
Page 9 of 15
Visit Report
Page 10 of 15
Visit Report
Renunciation
Customer has been made aware of following critical issues and or equipment and hereby
acknowledges that Pentair will not be accountable for any breakdown, malfunction or
warranty claims for mentioned issues and or equipment including claims for other parts of
the plant that are a result of and find their origin in the mentioned issues and or equipment,
should the customer continue to operate the plant, without rectifying mentioned issues or
replacing the mentioned equipment by original parts first
• ……
• ……
• ……..
……………………………………………………………………………………………………………
Page 11 of 15
Visit Report
Action List
Actions for Customer Actions for Pentair
Arrange a new measuring cell for the OGM Arrange new seal and NH3 engineer to
probes who’re having a bad Amplitude. replace seal and align NH3 compressor unit.
(<6000) when the Phase is above 60.
Buy all offered parts. Offer all needed parts.
Check warranty agreement according to Check warranty agreement according to
contract. contract.
Page 12 of 15
Visit Report
Page 13 of 15
Visit Report
Timesheet
Project number 04.0931 & 04.3294 & 06.7235 & 10.5563 &
20.0237
Job number / Service Order 62022716
Visited by Mark van Cranenbroek
Date visit from/until 17 till 19-4-2024
Date of report 19-4-2024
System type 04.0931 – CO2 Recovery System
04.3294 – Gas washer & Overpressure safety
06.7235 – HRS
10.5563 – CO2 Compressor & ACF/Dryer
20.0237 – CO2 Recovery System
Signature :
……………………………………………………………………………………………………………
Page 14 of 15
Visit Report
www.haffmans.nl www.union.dk
Spare Parts & Service Engineers offers : Spare Parts & Service Engineers offers :
Spareparts@pentair.com Union_Service@pentair.com
Phone : +31 773232 320 → Option 4 Phone : +45 7620 7700
Page 15 of 15