LOCATION MAP SITE DEVELOPMENT PLAN


NOT TO SCALE NOT TO SCALE

VICINITY MAP
NOT TO SCALE PERSPECTIVE VIEW
NOT TO SCALE

REPUBLIC OF THE PHILIPPINES


San Antonio-LingalingSan
ESAntonio-Lingaling ES

CAGAYAN VALLEY REGION PREPARED BY: REVIEWED & CHECKED BY: APPROVED BY: CONCURRED BY: PROJECT TITLE: SHEET CONTENT:
KALAHI-CIDSS, DSWD
San Antonio-Lingaling ES
LOCATION MAP
MUNICIPALITY OF STO. NIÑO
CONSTRUCTION OF 1 UNIT SOLAR DRYER VICINITY MAP
PROVINCE OF CAGAYAN SITE DEVELOPMENT PLAN SHEET
APOL JOY SOMEJO ENGR. ZOILO P. PIÑERA LORILYN G. BATTAD WITH PALAY SHED
NOT TO SCALE

ACT-TECHNICAL FACILITATOR MUNICIPAL ENGINEER BSPMC CHAIRPERSON PERSPECTIVE VIEW


OFFICE OF THE BRGY SUB-PROJECT
MANAGEMENT COMMITTEE DATE: DATE: DATE: DATE: LOCATION: BRGY. MAPITAC, STO. NIÑO, CAGAYAN
1 8
MAPITAC, STO. NIÑO
10.80

EXISTING 100mm THK CONCRETE SLAB


CLASS B MIXTURE
13.30

10.80 mts 13.30 mts

EXISTING 100mm THK PERSPECTIVE


NOT TO SCALE
CONCRETE SLAB CLASS
"B" MIXTURE

SOLAR DRYER PLAN


NOT TO SCALE

REPUBLIC OF THE PHILIPPINES


PREPARED BY: REVIEWED & CHECKED BY: APPROVED BY: CONCURRED BY: PROJECT TITLE: SHEET CONTENT:
CAGAYAN VALLEY REGION
KALAHI-CIDSS, DSWD
IMPROVEMENT OF POST HARRVEST
MUNICIPALITY OF KAYAPA PERSPECTIVE
PROVINCE OF NUEVA, VIZCAYA
FACILITIES AT CENTRO LATBANG SHEET
MARCO A. MARAMAG ENGR. CRISPIN D. NISPEROS JR. RICHMOND A. JUAN SOLAR DRYER PLAN
ACT-TECHNICAL FACILITATOR MUNICIPAL ENGINEER BDC-TWG CHAIRPERSON PROJECT DEVELOPMENT OFFICER IV
OFFICE OF THE BRGY SUB-PROJECT
MANAGEMENT COMMITTEE DATE: DATE: DATE: DATE: LOCATION: CENTRO LATBANG, BRGY. LATBANG KAYAPA
2 6
A B A B

5.00 5.00
F1-C1 F1-C1
1 1

100MM THK SLAB ON


2.50

2.50

FTB
GRADE W/ 10MMØ
PALAY SHED REBARS @ 0.40

FTB
O.C.B.W.

F1-C1 F1-C1

2 2

FLOOR PLAN FOUNDATION PLAN


NOT TO SCALE NOT TO SCALE

REPUBLIC OF THE PHILIPPINES


PREPARED BY: REVIEWED & CHECKED BY: APPROVED BY: CONCURRED BY: PROJECT TITLE: SHEET CONTENT:
CAGAYAN VALLEY REGION
KALAHI-CIDSS, DSWD
IMPROVEMENT OF POST HARRVEST
MUNICIPALITY OF KAYAPA
FACILITIES AT CENTRO LATBANG PALAY SHED SHEET
PROVINCE OF NUEVA, VIZCAYA
MARCO A. MARAMAG ENGR. CRISPIN D. NISPEROS JR. RICHMOND A. JUAN PLANFOUNDATION PLAN
ACT-TECHNICAL FACILITATOR MUNICIPAL ENGINEER BDC-TWG CHAIRPERSON PROJECT DEVELOPMENT OFFICER IV
OFFICE OF THE BRGY SUB-PROJECT
MANAGEMENT COMMITTEE DATE: DATE: DATE: DATE: LOCATION: CENTRO LATBANG, BRGY. LATBANG KAYAPA
3 6
1 2 A B

APEX OF ROOF

0.90

0.80
TOP OF ROOF BEAM

3.00

FLOOR FINISH LINE


0.2

NGL

LEFT ELEVATION FRONT ELEVATION


NOT TO SCALE NOT TO SCALE

2 1 B A

APEX OF ROOF
0.90

0.80

TOP OF ROOF BEAM


3.00

FLOOR FINISH LINE


0.2

NGL
RIGHT ELEVATION REAR ELEVATION
NOT TO SCALE NOT TO SCALE

REPUBLIC OF THE PHILIPPINES


PREPARED BY: REVIEWED & CHECKED BY: APPROVED BY: CONCURRED BY: PROJECT TITLE: SHEET CONTENT:
CAGAYAN VALLEY REGION
KALAHI-CIDSS, DSWD
IMPROVEMENT OF POST HARRVEST
MUNICIPALITY OF KAYAPA
PROVINCE OF NUEVA, VIZCAYA
FACILITIES AT CENTRO LATBANG ELEVATIONS SHEET
MARCO A. MARAMAG ENGR. CRISPIN D. NISPEROS JR. RICHMOND A. JUAN
ACT-TECHNICAL FACILITATOR MUNICIPAL ENGINEER BDC-TWG CHAIRPERSON PROJECT DEVELOPMENT OFFICER IV
OFFICE OF THE BRGY SUB-PROJECT
MANAGEMENT COMMITTEE DATE: DATE: DATE: DATE: LOCATION: CENTRO LATBANG, BRGY. LATBANG KAYAPA
4 6
800
200

100
6-12mm Ø RSB
ON BOTH WAYS

D
800
1500
300
800

6-12mm Ø RSB,
10mm Ø ties

200
800

FOOTING DETAILS
NOT TO SCALE

200 200
2-12mmØ
Ø10mm: 2 @ 50; 2-12mmØ
300

Ø10mm: 2 @ 50;

300
10 @ 75; REST @ 2-12mmØ 10 @ 75; REST @
2-16mmØ 120mm O.C. 2-16mmØ 120mm O.C.

BEAM DETAILS
NOT TO SCALE COLUMN DETAILS
NOT TO SCALE

REPUBLIC OF THE PHILIPPINES


PREPARED BY: REVIEWED & CHECKED BY: APPROVED BY: CONCURRED BY: PROJECT TITLE: SHEET CONTENT:
CAGAYAN VALLEY REGION
KALAHI-CIDSS, DSWD
IMPROVEMENT OF POST HARRVEST
MUNICIPALITY OF KAYAPA FOOTING DETAILS, COLUMN
FACILITIES AT CENTRO LATBANG SHEET
PROVINCE OF NUEVA, VIZCAYA
MARCO A. MARAMAG ENGR. CRISPIN D. NISPEROS JR. RICHMOND A. JUAN DETAILS, TYPICAL BEAM
ACT-TECHNICAL FACILITATOR MUNICIPAL ENGINEER BDC-TWG CHAIRPERSON PROJECT DEVELOPMENT OFFICER IV
DETAILS
OFFICE OF THE BRGY SUB-PROJECT
MANAGEMENT COMMITTEE DATE: DATE: DATE: DATE: LOCATION: CENTRO LATBANG, BRGY. LATBANG KAYAPA
5 8
A B
6.60
A B
5.00

2"x4" X 1.5mm C-PURLINS


SPACED @0.60m 5.00

RB-1
1 1 C1 C1

TRUSS 01

TRUSS 01

TRUSS 01
4.10
2.50

2.50

RB-1

RB-1
2 2 C1 RB-1 C1

ROOF BEAM PLAN


ROOF FRAMING PLAN NOT TO SCALE

NOT TO SCALE

0.60
PRE-PAINTED RIB TYPE ROOFING SHEETS
2"x4" 1.5mm C-PURLINS SPACED @0.60m
2"x2"x41" ANGLE BAR
ROOF BEAM

0.625
4.10

TRUSS-1 DETAIL
NOT TO SCALE

REPUBLIC OF THE PHILIPPINES


PREPARED BY: REVIEWED & CHECKED BY: APPROVED BY: CONCURRED BY: PROJECT TITLE: SHEET CONTENT:
CAGAYAN VALLEY REGION
KALAHI-CIDSS, DSWD
IMPROVEMENT OF POST HARRVEST
MUNICIPALITY OF KAYAPA
FACILITIES AT CENTRO LATBANG ROOF FRAMING PLAN, ROOF SHEET
PROVINCE OF NUEVA, VIZCAYA
MARCO A. MARAMAG ENGR. CRISPIN D. NISPEROS JR. RICHMOND A. JUAN BEAM PLAN, TRUSS-1 DETAIL
ACT-TECHNICAL FACILITATOR MUNICIPAL ENGINEER BDC-TWG CHAIRPERSON PROJECT DEVELOPMENT OFFICER IV
OFFICE OF THE BRGY SUB-PROJECT
MANAGEMENT COMMITTEE DATE: DATE: DATE: DATE: LOCATION: CENTRO LATBANG, BRGY. LATBANG KAYAPA
6 6
2440mm.

1220mm.

STANDARD PROJECT BILLBOARDS


SCALE NTS

3-50 x 50 Lowland Lumber


2440mm.

1220mm.
1220mm.

2 - 50 x 75 Lowland Lumber

DISPLAY AREA DISPLAY AREA


(1-1220mm X 2440mm X 6.25mm (1-1220mm X 2440mm X 6.25mm
MARINE PLYWOOD) MARINE PLYWOOD)

1000mm.
3 - 50 X 75 LOWLAND LUMBER
1000mm.

NGL NGL
500mm.

500mm.
1000mm.
FRONT SIDE
BILLBOARD FRAME
SCALE NTS

REPUBLIC OF THE PHILIPPINES


PREPARED BY: REVIEWED & CHECKED BY: APPROVED BY: CONCURRED BY: PROJECT TITLE: SHEET CONTENT:
CAGAYAN VALLEY REGION
KALAHI-CIDSS, DSWD
IMPROVEMENT OF POST HARRVEST
MUNICIPALITY OF KAYAPA
FACILITIES AT CENTRO LATBANG SHEET
PROVINCE OF NUEVA, VIZCAYA
MARCO A. MARAMAG ENGR. CRISPIN D. NISPEROS JR. RICHMOND A. JUAN PROJECT BILLBOARD
ACT-TECHNICAL FACILITATOR MUNICIPAL ENGINEER BDC-TWG CHAIRPERSON PROJECT DEVELOPMENT OFFICER IV
OFFICE OF THE BRGY SUB-PROJECT
MANAGEMENT COMMITTEE DATE: DATE: DATE: DATE: LOCATION: CENTRO LATBANG, BRGY. LATBANG KAYAPA
7 8
800

100 100
600

100
450X600MM BRASS MARKER

4" THK CHB WALL; 10MM DIA

450
VERTICAL BARS @ 0.40M O.C.

1200
100MM THK CHB WALL;
PAINTED PLASTER FINISH

NGL

FRONT ELEVATION SECTION DETAILS


A SCALE NTS B SCALE NTS

PROJECT MARKER
SCALE NTS

REPUBLIC OF THE PHILIPPINES


PREPARED BY: REVIEWED & CHECKED BY: APPROVED BY: CONCURRED BY: PROJECT TITLE: SHEET CONTENT:
CAGAYAN VALLEY REGION
KALAHI-CIDSS, DSWD
IMPROVEMENT OF POST HARRVEST
MUNICIPALITY OF KAYAPA
FACILITIES AT CENTRO LATBANG SHEET
PROVINCE OF NUEVA, VIZCAYA
MARCO A. MARAMAG ENGR. CRISPIN D. NISPEROS JR. RICHMOND A. JUAN PROJECT MARKER
ACT-TECHNICAL FACILITATOR MUNICIPAL ENGINEER BDC-TWG CHAIRPERSON PROJECT DEVELOPMENT OFFICER IV
OFFICE OF THE BRGY SUB-PROJECT
MANAGEMENT COMMITTEE DATE: DATE: DATE: DATE: LOCATION: CENTRO LATBANG, BRGY. LATBANG KAYAPA
8 8

You might also like