12/12/2023 5 0 5 0 0 0 0 10 0 12 12
Only repair works were achieved. There was no provision for
helpers and grinders for tie-in works. Sellyfak team deviated
18/12/2023 0 0 0 0 0 0 0 0 0 12 12
from plans agreed with Molecularpro as regards continuing
tie-in works today.
Excavator operator downtool for 5 hours. Deviation from
agreed workplan by Sellyfak team about ensuring all
19/12/2023 0 3 0 0 0 0 0 0 3 12 9
equipment and machinery are ready for next day work
prevented optimization of specialists productivity.
Lay and weld joints at the skipped area of the paper recycling
company completed. Deviation from agreed workplan by
20/12/2023 4 1 4 0 0 0 0 8 1 12 11 Sellyfak team about ensuring all equipment and machinery
are sufficient and ready for next day work prevented
optimization of specialists productivity.
Deviation from agreed workplan by Sellyfak team about
ensuring all equipment and machinery are sufficient and
21/12/2023 0 0 0 4 0 0 0 0 4 12 8
ready for next day work prevented optimization of specialists
productivity.
Faulty excavator and lack of stop-gap contigency plan
prevented the 2 spread from achieving good result. Only 2
joints were completed by the team. Team commenced wotrk
22/12/2023 0 0 1 1 0 0 0 1 1 12 11 at 8:00am till 12:30pm. The only excavator servicing the team
developed fault at 1:00pm (cut track chain) while relocating
to another work location and could not be replaced till team
demobilised from site at 4:30pm.
1 excavator was provided for each spread to work. Spread B
23/12/2023 0 4 0 2 0 0 0 0 6 12 6 commenced work at 1:00pm. Difficult work terrain slow down
pace of work for both spreads.
1 excavator was provided for each spread to work. Working
24/12/2023 0 2 0 4 0 0 0 0 6 12 6 around difficult terrain slow down pace of work for both
spreads.
Weekly Total 4 10 5 11 0 0 0 9 21 84 63
Joints Report for Week 9 on the SLDZ Phase 3, Ijebu - Ode
Excavator operators did not resume back on site early until
12:00pm. The first set of operators that resumed on site have
0 0 0 0 0 0 0 0 0 12 12 their excavators at locations that are not ready for tie-in.
Arrangement was made for welding works to continue
26/12/2023 tomorrow Wednesday, 27/12/2023.
Punctured tyre of selfloader truck while going to worksite
makes it unavailable for use. Self loader truck tyre to be fixed
0 2 0 2 0 0 0 0 4 12 8 against tomorrow work. Lack of stop-gap contigency plan by
Sellyfak project team in case of equipment or machinery
27/12/2023 failure prevent the optimization of specialists productivity.
Self-loader truck yet to be fixed. Preparation of work location
for tie-in welding delayed the team from commencing work
0 1 0 0 0 0 0 0 1 12 11
until 12:00pm. Faulty developed by excavator servicing the
28/12/2023 specialists prevented the completion of more than 1 joint.
Only one spread worked on site today while the second
0 0 0 2 0 0 0 0 2 6 4 spread was demobilised because only 2 tie-in joints are ready
29/12/2023 to be worked.
Team worked within a restricted work area. Only 2 joints were
0 0 0 2 0 0 0 0 2 6 4 completed due to the difficulty encountered at the work
30/12/2023 environment.
Weekly Total 0 3 0 6 0 0 0 0 9 48 39
Weekly Total 0 18 0 18 0 2 0 0 38 54 16
Joints Report for Week 12 on the SLDZ Phase 3, Ijebu - Ode
All the 3 spreads arrived on site early and commenced work
immediately. Spread A worked at HDD tie-in point which
poses some challenges, spread B worked at a good location
and achieved 3 joints while Spread C worked on the internal
15/1/2024 0 2 0 3 10 0 10 0 5 12 7 piping.
Spread A worked at a good work location and achieved 3
joints. Spread B experienced delay due to ditch prepartion at
tie-in point and eventually completed 2 tie-in joints. Spread C
could only complete 1 tie-in joint due to difficult acces to
16/1/2024 0 3 0 2 0 1 0 0 6 12 6 terrain of work and excavator down time.
Unavailability of excavator at the location of work prevented
spread A from achieving any joint. Faulty power generator
prevented Spread B from accomplishing much work. Faulty
excavator and difficult work terrain delayed Spread C from
17/1/2024 0 0 0 1 0 2 0 0 3 12 9 starting work early.
Spread A worked at a good work location and achieved 3
joints. Spread B experienced delay due to ditch prepartion at
tie-in point and eventually completed 2 tie-in joints. Spread C
could only complete 1 tie-in joint due to difficult access to
18/1/2024 0 2 0 3 0 1 0 0 6 12 6 work area, also the tie-in ditch was not properly prepared.
Spread A and Spread C commemnced work early but worked
at a very difficult terrain, which require lots of due diligence
to achieve good result. Spread C could not achieve any joint
19/1/2024 0 2 0 0 0 2 0 0 4 12 8 due to faulty excavator.
Spread A could only achieve 1 joint due to difficult work area
which require due diligence to be properly prepared. Spread B
could only achive 1 joint because of faulty excavator,
excavator to be ready tomorrow. Spread C achieved 1 joint
due to the work terrain which require that road be cut for the
20/1/2024 0 1 0 1 0 1 0 0 3 12 9 joint to be ready.
Weekly Total 0 10 0 10 10 7 10 0 27 36 22
Total To
Date 4 51 5 53 10 9 10 9 113 270 157