Professional Documents
Culture Documents
GRE 502 19 - Question
GRE 502 19 - Question
3. Consider a PERT network with the precedence relations specified in the table below.
Immediate
Activity Estimated duration (in days)
Predecessor
Optimistic Most likely Pessimistic
A - 2 5 14
B - 1 4 7
C A 3 3 3
D A, C 1 2 3
E B, D 1 2 21
F C, D 2 4 24
G D, E 1 3 5
(a) Draw the network and determine the earliest possible and latest allowable starting and
finishing times. [
1
8 ¿
2
(b) What is the minimum duration of the project? [2]
(c ) Calculate the probability of completing the project in 23 days. [
1
7 ¿
2
(d) What can be done if management considers this probability of 84% not high enough? [2]
4. (a) what is plant layout? Distinguish between product layout and process layout. [6]
(b) Three outlets A, B and C are supplied by three suppliers X, Y and Z. The table shows the
cost, in Naira, of transporting each unit, the number of units required at each outlet and the
number of units available at each supplier. [14]
A B C SUPPLY
X 9 11 10 40
Y 10 8 12 60
Z 12 7 8 50
DEMAND 50 40 30
(i) Use the north-west corner method to obtain an initial solution and estimate the
total shipment cost, and
(ii) state if the solution is degenerate or not, with reason.
6. (a) List and explain any three (3) the principles in the design of an efficient system of
materials Handling. [9]
(b) Bassey and Tony Saviour recently time-studied a janitorial task. From a sample of 75
observations, they computed an average cycle time of 15 minutes with a standard deviation of
2 minutes. Was their sample large enough that one can be 99% confident that the standard
time is within 5% of the true value? [7]
(c) what is Engineering management. [4]
7. (a) Why is forecasting important in organizations? [5]
(b) State five (5) objectives of Work Measurement [5]
(c) A friend needs N500 now, and will pay you back N570 in a year. Is that a good
investment when you can get 10% elsewhere? [10]