Contract ID: 17LG-0045

Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon

Location of Contract:
Lupon, Davao Oriental

DETAILED ESTIMATES

Item No : B.4(1)
Description : Construction Survey and Staking
Quantity : 1.32 km
COST ANALYSIS
A. MATERIALS
Total Station @P 13,065.00 /set 4.00 set P 52,260.00
Sub-total,A P 52,260.00

B. EQUIPMENT/FUEL/OIL
NONE
C. LABOR
1 Engineer @P 650.00 /day for 2.00 days P 1,300.00
1 Foreman @P 566.08 /day for 2.00 days P 1,132.16
4 Laborers @P 316.72 /day for 2.00 days P 2,533.76
Sub-total C P 4,965.92

DIRECT COST : Php 57,225.92


OCM : Php 0.00
PROFIT : Php 0.00
TAXES : Php 2,861.30
TOTAL COST Php 60,087.22

UNIT COST P 45,520.62 /lot

Item No : B.8
Description : Traffic Management
Quantity : 9.00 Month

COST ANALYSIS

A. MATERIALS
Traffic Signages & Warnings, ect. @P 18,500.00 /set 4.00 set P 74,000.00
Sub-total,A P 74,000.00

B. EQUIPMENT/FUEL/OIL
NONE

Sub-total,B P 0.00

C. LABOR
1 Engineer @P 650.00 /day for 115.00 days P 74,750.00
1 Foreman @P 566.08 /day for 115.00 days P 65,099.20
4 Laborers @P 316.72 /day for 115.00 days P 145,691.20
Sub-total C P 285,540.40

DIRECT COST : Php 359,540.40


OCM : Php 0.00
PROFIT : Php 0.00
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon

Location of Contract:
Lupon, Davao Oriental

DETAILED ESTIMATES

TAXES : Php 17,977.02


TOTAL COST Php 377,517.42

UNIT COST P 41,946.38 /month

Item No : B.9
Description : MOBILIZATION & DEMOBILIZATION
Quantity : 1.00 L.S.

COST ANALYSIS

A. MATERIALS
NONE P
Sub-total,A P -

B. EQUIPMENT/FUEL/OIL

TRAILER FOR MAJOR & MINOR EQUIPMENTS 804,524.00

Sub-total,B P 804,524.00

C. LABOR
NONE P 0.00
Sub-total C P 0.00

DIRECT COST : Php 804,524.00


OCM : Php 0.00
PROFIT : Php 0.00
TAXES : Php 40,226.20
TOTAL COST Php 844,750.20

UNIT COST P 844,750.20 /l.s.

Item No : B.7
Description : Construction Safety and Health
Quantity : 9.00 Month

COST ANALYSIS

A. MATERIALS

Materials & equipments for safety 50,000.00


Sub-total,A P 50,000.00

B. EQUIPMENT/FUEL/OIL
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon

Location of Contract:
Lupon, Davao Oriental

DETAILED ESTIMATES

Sub-total,B P 0.00

C. LABOR
1 Engineer @P 650.00 /day for 115.00 days P 74,750.00
1 Foreman @P 566.08 /day for 115.00 days P 65,099.20
1 Laborers @P 316.72 /day for 115.00 days P 36,422.80
Sub-total C P 176,272.00

DIRECT COST : Php 226,272.00


OCM : Php 27,152.64
PROFIT : Php 18,101.76
TAXES : Php 32,583.17
TOTAL COST Php 304,109.57

UNIT COST P 33,789.95

Item No : B.5
Description : Project Billboard/Signboard
Quantity : 2.00 each

COST ANALYSIS

A. MATERIALS

Project Billboard/Signboard 9,420.00


Sub-total,A P 9,420.00

B. EQUIPMENT/FUEL/OIL

Sub-total,B P 0.00

C. LABOR
1 Engineer @P 650.00 /day for 1.00 days P 650.00
1 Foreman @P 566.08 /day for 1.00 days P 566.08
1 Laborers @P 316.72 /day for 1.00 days P 316.72
Sub-total C P 1,532.80

DIRECT COST : Php 10,952.80


OCM : Php 1,314.34
PROFIT : Php 876.22
TAXES : Php 657.17
TOTAL COST Php 13,800.53
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon

Location of Contract:
Lupon, Davao Oriental

DETAILED ESTIMATES

UNIT COST P 6,900.26

Item No : 100(3)a
Description : Individual Removal of Trees, (small)
Quantity : 26.000 each

COST ANALYSIS

A. MATERIALS
NONE P 0
Sub-total,A P 0

B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 2,156.00 /day for 7.00 days P 15,092.00
1 unit Boom truck @P 1,254.00 /day for 7.00 days P 8,778.00
Sub-total,B P 23,870.00

C. LABOR
1 Engineer @P 650.00 /day for 7.00 days P 4,550.00
1 Foreman @P 566.08 /day for 7.00 days P 3,962.56
2 Laborers @P 316.72 /day for 7.00 days P 4,434.08
Sub-total C P 12,946.64

DIRECT COST : Php 21,724.64


OCM : Php 2,606.96
PROFIT : Php 1,737.97
TAXES : Php 1,303.48
TOTAL COST Php 27,373.05

UNIT COST P 1,052.81

Item No : 101(1)a1
Description : Removal of Actual Structure and Obstruction (PCCP Unreinforced 0.15m thk)
Quantity : 193.040 sq.m.

COST ANALYSIS

A. MATERIALS
NONE P 0
Sub-total,A P 0

B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 1,251.00 /day for 25.00 days P 31,275.00
1 unit Boom truck @P 1,254.00 /day for 25.00 days P 31,350.00
Sub-total,B P 62,625.00
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon

Location of Contract:
Lupon, Davao Oriental

DETAILED ESTIMATES

C. LABOR
1 Engineer @P 1,254.00 /day for 25.00 days P 31,350.00
1 Foreman @P 750.00 /day for 25.00 days P 18,750.00
2 Laborers @P 650.00 /day for 25.00 days P 32,500.00
Sub-total C P 82,600.00

DIRECT COST : Php 113,950.00


OCM : Php 13,674.00
PROFIT : Php 9,116.00
TAXES : Php 6,837.00
TOTAL COST Php 143,577.00

UNIT COST P 743.77

Item No : 103(1)
Description : Structure Excavation
Quantity : 1,124.500 cu.m.

COST ANALYSIS

A. MATERIALS
NONE P 0
Sub-total,A P 0

B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 2,156.00 /day for 125.00 days P 269,500.00
1 unit Boom truck @P 1,254.00 /day for 125.00 days P 156,750.00
Sub-total,B P 426,250.00

C. LABOR
1 Engineer @P 1,245.00 /day for 125.00 days P 155,625.00
1 Foreman @P 560.00 /day for 125.00 days P 70,000.00
2 Laborers @P 300.00 /day for 125.00 days P 75,000.00
Sub-total C P 300,625.00

DIRECT COST : Php 457,375.00


OCM : Php 54,885.00
PROFIT : Php 36,590.00
TAXES : Php 27,442.50
TOTAL COST Php 576,292.50

UNIT COST P 512.49

Item No : 103(3)
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon

Location of Contract:
Lupon, Davao Oriental

DETAILED ESTIMATES

Description : Foundation Fill


Quantity : 4.98 cu.m.

COST ANALYSIS

A. MATERIALS
NONE P 0
Sub-total,A P 0

B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 2,156.00 /day for 5.00 days P 10,780.00
1 unit truck @P 7,689.60 /day for 5.00 days P 38,448.00
Sub-total,B P 49,228.00

C. LABOR
1 Engineer @P 650.00 /day for 5.00 days P 3,250.00
1 Foreman @P 566.08 /day for 5.00 days P 2,830.40
2 Laborers @P 316.72 /day for 5.00 days P 3,167.20
Sub-total C P 9,247.60

DIRECT COST : Php 58,475.60


OCM : Php 5,262.80
PROFIT : Php 4,678.05
TAXES : Php 8,209.97
TOTAL COST Php 76,626.43

UNIT COST P 15,386.83

Item No : 103(6)a
Description : Pipe Culvert and Drain Excavation (Common Soil)
Quantity : 67.69 cu.m.

COST ANALYSIS

A. MATERIALS
NONE P 0
Sub-total,A P 0

B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 10,232.00 /day for 3.00 days P 30,696.00
1 unit Dumptruck @P 18,392.00 /day for 3.00 days P 55,176.00
Sub-total,B P 85,872.00

C. LABOR
1 Engineer @P 650.00 /day for 3.00 days P 1,950.00
1 Foreman @P 566.08 /day for 3.00 days P 1,698.24
2 Laborers @P 316.72 /day for 3.00 days P 1,900.32
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon

Location of Contract:
Lupon, Davao Oriental

DETAILED ESTIMATES

Sub-total C P 5,548.56

DIRECT COST : Php 91,420.56


OCM : Php 8,227.85
PROFIT : Php 7,313.64
TAXES : Php 24,835.45
TOTAL COST Php 131,797.50

UNIT COST P 1,947.07 /cu.m.

Item No : 104(1)a1
Description : Embankment from Roadway Excavation (Common Soil)
Quantity : 834.00 cu.m.

COST ANALYSIS

A. MATERIALS

NONE P 0
Sub-total,A P 0

B. EQUIPMENT/FUEL/OIL
3 unit Backhoe @P 11,987.00 /day for 9.00 days P 323,649.00
3 unit Dumptruck @P 15,687.00 /day for 9.00 days P 423,549.00
7 unit Boom Truck @P 8,520.00 /day for 9.00 days P 536,760.00
Sub-total,B P 1,283,958.00

C. LABOR
1 Engineer @P 1,250.00 /day for 9.00 days P 11,250.00
1 Foreman @P 987.00 /day for 9.00 days P 8,883.00
10 Laborers @P 350.00 /day for 9.00 days P 31,500.00
Sub-total C P 51,633.00

DIRECT COST : Php 1,335,591.00


OCM : Php 120,203.19
PROFIT : Php 106,847.28
TAXES : Php 187,516.98
TOTAL COST Php 1,750,158.45

UNIT COST P 2,098.51 /sq.m.

Item No : 104(1)b1
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon

Location of Contract:
Lupon, Davao Oriental

DETAILED ESTIMATES

Description : Embankment from Borrow (Common Soil)


Quantity : 5,364.00 cu.m.

COST ANALYSIS

A. MATERIALS

Filling Materials 1,000.00 /cu.m. P 5,364,000.00


Sub-total,A P 5,364,000.00

B. EQUIPMENT/FUEL/OIL
1 unit Grader @P 17,384.00 /day for 10.00 days P 173,840.00
1 unit Roller @P 12,056.00 /day for 10.00 days P 120,560.00
1 unit Water truck @P 8,520.00 /day for 10.00 days P 85,200.00
Sub-total,B P 379,600.00

C. LABOR
1 Engineer @P 765.00 /day for 10.00 days P 7,650.00
1 Foreman @P 650.00 /day for 10.00 days P 6,500.00
3 Laborers @P 566.08 /day for 10.00 days P 16,982.40
Sub-total C P 31,132.40

DIRECT COST : Php 5,774,732.40


OCM : Php 519,725.92
PROFIT : Php 461,978.59
TAXES : Php 810,772.43
TOTAL COST Php 7,567,209.34

UNIT COST P 1,410.74 /sq.m.

Item No : 105(1)a
Description : Subgrade Preparation (Common Material)
Quantity : 1,722.00 sq.m.

COST ANALYSIS

A. MATERIALS

NONE P 0
Sub-total,A P 0

B. EQUIPMENT/FUEL/OIL
1 unit Bakhoe @P 17,384.00 /day for 21.00 days P 365,064.00
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon

Location of Contract:
Lupon, Davao Oriental

DETAILED ESTIMATES

1 unit Dumptruck @P 12,056.00 /day for 21.00 days P 253,176.00


1 unit Boom Truck @P 8,520.00 /day for 21.00 days P 178,920.00
Sub-total,B P 797,160.00

C. LABOR
1 Engineer @P 860.00 /day for 21.00 days P 18,060.00
1 Foreman @P 765.00 /day for 21.00 days P 16,065.00
10 Laborers @P 650.00 /day for 21.00 days P 136,500.00
Sub-total C P 170,625.00

DIRECT COST : Php 967,785.00


OCM : Php 87,100.65
PROFIT : Php 77,422.80
TAXES : Php 135,877.01
TOTAL COST Php 1,268,185.46

UNIT COST P 736.46 /sq.m.

Item No : 200(1)
Description : Aggregate Subbase Course
Quantity : 3,225.00 cu.m.

COST ANALYSIS

A. MATERIALS

Aggregate Subbase Course P 34,521.00


Sub-total,A P 34,521.00

B. EQUIPMENT/FUEL/OIL
1 unit Grader @P 16,920.00 /day for 20.00 days P 338,400.00
3 unit Dump truck @P 20,300.00 /day for 20.00 days P 1,218,000.00
1 unit Roller @P 12,056.00 /day for 20.00 days P 241,120.00
1 unit Water truck @P 8,520.00 /day for 20.00 days P 170,400.00
Sub-total,B P 1,967,920.00

C. LABOR
1 Engineer @P 860.00 /day for 20.00 days P 17,200.00
1 Foreman @P 456.00 /day for 20.00 days P 9,120.00
3 Laborers @P 350.00 /day for 20.00 days P 21,000.00
Sub-total C P 47,320.00

DIRECT COST : Php 2,015,240.00


OCM : Php 181,371.60
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon

Location of Contract:
Lupon, Davao Oriental

DETAILED ESTIMATES

PROFIT : Php 161,219.20


TAXES : Php 282,939.70
TOTAL COST Php 2,640,770.50

UNIT COST P 818.84 /sq.m.

PCC Pavement
Item No : 311(1)b (Unreinforced),
Description : 200 mm thk
Quantity : 5,680.57 Sq.m.

COST ANALYSIS

A. MATERIALS
Portland cement @P 250.00 /bag 2,123.00 bags P 530,750.00
Reinforcing steel bars @P 310.00 /kg. 3,213.00 kgs. P 996,030.00
Curing compound @P 200.00 /lit. 321.00 lit. P 64,200.00
Asphalt sealant @P 75.00 /lit. 124.00 lit. P 9,300.00
Steel forms @P 60.00 /lm. 451.00 lm. P 27,060.00
Gravel @P 1,000.00 /cu.m. 15.00 cu.m. P 15,000.00
Sand @P 1,000.00 /cu.m. 2.00 cu.m. P 2,000.00
Tie Wire @P 56.00 /kg. 4.00 kgs. P 224.00
G.I Pipes @P 300.00 /lm. 43.00 lm. P 12,900.00
Grease tar @P 250.00 /lit. 65.00 lit. P 16,250.00
Sub-total,A P 1,673,714.00

B. EQUIPMENT/FUEL/OIL
2 unit Transit mixer @P 10,232.00 /day for 50.00 days P 1,023,200.00
2 unit Conc. Vibrator @P 1,191.04 /day for 50.00 days P 119,104.00
1 unit Batching plant @P 9,664.24 /day for 50.00 days P 483,212.00
1 unit Payloader @P 13,864.00 /day for 50.00 days P 693,200.00
1 unit Conc. Sceeder @P 4,360.00 /day for 50.00 days P 218,000.00
1 unit Water truck @P 2,400.00 /day for 50.00 days P 120,000.00
1 unit Conc. Saw @P 1,339.04 /day for 50.00 days P 66,952.00
1 unit Bar cutter @P 1,758.00 /day for 50.00 days P 87,900.00
Sub-total,B P 2,811,568.00

C. LABOR
1 Engineer @P 650.00 /day for 50.00 days P 32,500.00
1 Foreman @P 566.08 /day for 50.00 days P 28,304.00
8 Mason @P 410.64 /day for 50.00 days P 164,256.00
12 Laborers @P 316.72 /day for 50.00 days P 190,032.00
Sub-total C P 415,092.00

DIRECT COST : Php 5,118,374.00


OCM : Php 614,204.88
PROFIT : Php 409,469.92
TAXES : Php 307,102.44
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon

Location of Contract:
Lupon, Davao Oriental

DETAILED ESTIMATES

TOTAL COST Php 6,449,151.24

UNIT COST P 1,135.30 /sq.m.

Item No : 500(1)b3
Description : Pipe Culverts, 910mm dia., Class IV
Quantity : 57.00 lm

COST ANALYSIS

A. MATERIALS

NONE P 0
Sub-total,A P 0

B. EQUIPMENT/FUEL/OIL
1 unit Dump truck @P 20,300.00 /day for 3.00 days P 60,900.00
1 unit Roller @P 12,056.00 /day for 3.00 days P 36,168.00
1 unit Water truck @P 8,520.00 /day for 3.00 days P 25,560.00
Sub-total,B P 122,628.00

C. LABOR
1 Engineer @P 860.00 /day for 3.00 days P 2,580.00
1 Foreman @P 456.00 /day for 3.00 days P 1,368.00
3 Laborers @P 350.00 /day for 3.00 days P 3,150.00
Sub-total C P 7,098.00

DIRECT COST : Php 129,726.00


OCM : Php 11,675.34
PROFIT : Php 10,378.08
TAXES : Php 18,213.53
TOTAL COST Php 169,992.95

UNIT COST P 2,982.33 /sq.m.

Item No : 506(1)
Description : Stone Masonry
Quantity : 42.00 cu.m.

COST ANALYSIS

A. MATERIALS
boulders @P 1,200.00 /cu.m. 30.00 cu.m. P 36,000.00
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon

Location of Contract:
Lupon, Davao Oriental

DETAILED ESTIMATES

Sub-total,A P 36,000.00

B. EQUIPMENT/FUEL/OIL
2 unit Grader @P 17,880.00 /day for 3.00 days P 107,280.00
2 unit Roller @P 12,056.00 /day for 3.00 days P 72,336.00
1 unit Water truck @P 8,520.00 /day for 3.00 days P 25,560.00
Sub-total,B P 205,176.00

C. LABOR
1 Engineer @P 650.00 /day for 3.00 days P 1,950.00
1 Foreman @P 566.08 /day for 3.00 days P 1,698.24
2 Laborers @P 316.72 /day for 3.00 days P 1,900.32
Sub-total C P 5,548.56

DIRECT COST : Php 246,724.56


OCM : Php 22,205.21
PROFIT : Php 19,737.96
TAXES : Php 34,640.13
TOTAL COST Php 323,307.86

UNIT COST P 7,697.81 /cu.m.

Item No : 605(3)
Description : Guide or Informatory Signs, (600mm x 750mm)
Quantity : 1.00 each

COST ANALYSIS

A. MATERIALS
Guide or Informatory @P 1,200.00 /cu.m. 1.00 cu.m. P 1,200.00
Sub-total,A P 1,200.00

B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 2,456.00 /day for 1.00 days P 2,456.00
Sub-total,B P 2,456.00

C. LABOR
1 Engineer @P 650.00 /day for 1.00 days P 650.00
1 Foreman @P 500.00 /day for 1.00 days P 500.00
2 Laborers @P 300.00 /day for 1.00 days P 600.00
Sub-total C P 1,750.00

DIRECT COST : Php 5,406.00


OCM : Php 486.54
PROFIT : Php 432.48
TAXES : Php 759.00
TOTAL COST Php 7,084.02

UNIT COST P 7,084.02 /cu.m.


Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon

Location of Contract:
Lupon, Davao Oriental

DETAILED ESTIMATES

Item No : 624(1)a1
Description : Single Arm Post with Street Light
Quantity : 2.00 each

COST ANALYSIS

A. MATERIALS
Single Arm Post with St@P 1,200.00 /cu.m. 1.00 cu.m. P 1,200.00
Sub-total,A P 1,200.00

B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 2,456.00 /day for 1.00 days P 2,456.00
Sub-total,B P 2,456.00

C. LABOR
1 Engineer @P 650.00 /day for 1.00 days P 650.00
1 Foreman @P 500.00 /day for 1.00 days P 500.00
2 Laborers @P 300.00 /day for 1.00 days P 600.00
Sub-total C P 1,750.00

DIRECT COST : Php 5,406.00


OCM : Php 486.54
PROFIT : Php 432.48
TAXES : Php 759.00
TOTAL COST Php 7,084.02

UNIT COST P 3,542.01 /cu.m.

Item No : 803(1)a
Description : Structure Excavation
Quantity : 3.16 cu.m.

COST ANALYSIS

A. MATERIALS
Structure Excavation @P 1,200.00 /cu.m. 1.00 cu.m. P 1,200.00
Sub-total,A P 1,200.00

B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 2,456.00 /day for 1.00 days P 2,456.00
Sub-total,B P 2,456.00

C. LABOR
1 Engineer @P 650.00 /day for 1.00 days P 650.00
1 Foreman @P 500.00 /day for 1.00 days P 500.00
2 Laborers @P 300.00 /day for 1.00 days P 600.00
Sub-total C P 1,750.00
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon

Location of Contract:
Lupon, Davao Oriental

DETAILED ESTIMATES

DIRECT COST : Php 5,406.00


OCM : Php 486.54
PROFIT : Php 432.48
TAXES : Php 759.00
TOTAL COST Php 7,084.02

UNIT COST P 2,241.78 /cu.m.

Item No : 900(1)
Description : Reinforced Concrete
Quantity : 2.99 cu.m.

COST ANALYSIS

A. MATERIALS
Portland cement @P 250.00 /bag 23.00 bags P 5,750.00
Reinforcing steel bars @P 310.00 /kg. 4.00 kgs. P 1,240.00
Curing compound @P 200.00 /lit. 5.00 lit. P 1,000.00
Grease tar @P 250.00 /lit. 23.00 lit. P 5,750.00
Sub-total,A P 13,740.00

B. EQUIPMENT/FUEL/OIL
1 unit Transit mixer @P 10,232.00 /day for 2.00 days P 20,464.00
2 unit Conc. Vibrator @P 1,191.04 /day for 2.00 days P 4,764.16
1 unit Conc. Saw @P 1,339.04 /day for 2.00 days P 2,678.08
1 unit Bar cutter @P 1,758.00 /day for 2.00 days P 3,516.00
Sub-total,B P 2,012.00

C. LABOR
1 Engineer @P 650.00 /day for 2.00 days P 1,300.00
1 Foreman @P 566.08 /day for 2.00 days P 1,132.16
8 Mason @P 410.64 /day for 2.00 days P 6,570.24
12 Laborers @P 316.72 /day for 2.00 days P 7,601.28
Sub-total C P 2,154.00

DIRECT COST : Php 17,906.00


OCM : Php 2,148.72
PROFIT : Php 1,432.48
TAXES : Php 1,074.36
TOTAL COST Php 22,561.56

UNIT COST P 7,545.67 /sq.m.

Item No : 902(1)a1
Description : Reinforcing Steel (Deformed)
Quantity : 125.00 kgs
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon

Location of Contract:
Lupon, Davao Oriental

DETAILED ESTIMATES

COST ANALYSIS

A. MATERIALS
Reinforcing Steel (Defo @P 1,200.00 /cu.m. 1.00 cu.m. P 1,200.00
Sub-total,A P 1,200.00

B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 2,456.00 /day for 2.00 days P 4,912.00
Sub-total,B P 4,912.00

C. LABOR
1 Engineer @P 650.00 /day for 2.00 days P 1,300.00
1 Foreman @P 500.00 /day for 2.00 days P 1,000.00
2 Laborers @P 300.00 /day for 2.00 days P 1,200.00
Sub-total C P 3,500.00

DIRECT COST : Php 9,612.00


OCM : Php 865.08
PROFIT : Php 768.96
TAXES : Php 1,349.52
TOTAL COST Php 12,595.56

UNIT COST P 100.76 /cu.m.

Item No : 903(1)
Description : Forms and Falseworks
Quantity : 1.00 l.s.

COST ANALYSIS

A. MATERIALS
Forms and Falseworks @P 1,200.00 /cu.m. 1.00 cu.m. P 1,200.00
Sub-total,A P 1,200.00

B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 325.00 /day for 2.00 days P 650.00
Sub-total,B P 650.00

C. LABOR
1 Engineer @P 650.00 /day for 2.00 days P 1,300.00
1 Foreman @P 500.00 /day for 2.00 days P 1,000.00
2 Laborers @P 300.00 /day for 2.00 days P 1,200.00
Sub-total C P 3,500.00

DIRECT COST : Php 5,350.00


OCM : Php 481.50
PROFIT : Php 428.00
TAXES : Php 751.14
TOTAL COST Php 7,010.64
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon

Location of Contract:
Lupon, Davao Oriental

DETAILED ESTIMATES

UNIT COST P 7,010.64 /cu.m.

Item No : 1047(2)a
Description : Structural Steel
Quantity : 1,350.00 kgs

COST ANALYSIS

A. MATERIALS
Structural Steel @P 1,200.00 /cu.m. 320.00 cu.m. P 384,000.00
Sub-total,A P 384,000.00

B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 325.00 /day for 54.00 days P 17,550.00
Sub-total,B P 17,550.00

C. LABOR
1 Engineer @P 650.00 /day for 54.00 days P 35,100.00
1 Foreman @P 500.00 /day for 54.00 days P 27,000.00
2 Laborers @P 300.00 /day for 54.00 days P 32,400.00
Sub-total C P 94,500.00

DIRECT COST : Php 496,050.00


OCM : Php 44,644.50
PROFIT : Php 39,684.00
TAXES : Php 69,645.42
TOTAL COST Php 650,023.92

UNIT COST P 481.50 /cu.m.

Item No : 1013(1)
Description : Corrugated Metal Roofing
Quantity : 18.00 sq.m.

COST ANALYSIS

A. MATERIALS
Corrugated Metal Roofi @P 1,200.00 /cu.m. 15.00 cu.m. P 18,000.00
Sub-total,A P 18,000.00

B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 325.00 /day for 54.00 days P 17,550.00
Sub-total,B P 17,550.00

C. LABOR
1 Engineer @P 650.00 /day for 54.00 days P 35,100.00
1 Foreman @P 500.00 /day for 54.00 days P 27,000.00
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon

Location of Contract:
Lupon, Davao Oriental

DETAILED ESTIMATES

2 Laborers @P 300.00 /day for 54.00 days P 32,400.00


Sub-total C P 94,500.00

DIRECT COST : Php 130,050.00


OCM : Php 11,704.50
PROFIT : Php 10,404.00
TAXES : Php 18,259.02
TOTAL COST Php 170,417.52

UNIT COST P 9,467.64 /cu.m.

Item No : 404(1)a
Description : Reinforcing Steel, Grade 40
Quantity : 25,735.29 kgs

COST ANALYSIS

A. MATERIALS
Reinforcing Steel, Grade@P 1,200.00 /cu.m. 1,501.00 cu.m. P 1,801,200.00
Sub-total,A P 1,801,200.00

B. EQUIPMENT/FUEL/OIL
1 unit Bar cutter @P 2,541.00 /day for 50.00 days P 127,050.00
Sub-total,B P 127,050.00

C. LABOR
1 Engineer @P 650.00 /day for 50.00 days P 32,500.00
1 Foreman @P 500.00 /day for 50.00 days P 25,000.00
2 Laborers @P 300.00 /day for 50.00 days P 30,000.00
Sub-total C P 87,500.00

DIRECT COST : Php 2,015,750.00


OCM : Php 181,417.50
PROFIT : Php 161,260.00
TAXES : Php 283,011.30
TOTAL COST Php 2,641,438.80

UNIT COST P 102.64 /cu.m.

Item No : 405(1)a1
Description : Structural Concrete, Class A
Quantity : 980.10 cu.m.

COST ANALYSIS

A. MATERIALS
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon

Location of Contract:
Lupon, Davao Oriental

DETAILED ESTIMATES

Portland cement @P 250.00 /bag 568.00 bags P 142,000.00


Reinforcing steel bars @P 310.00 /kg. 45.00 kgs. P 13,950.00
Curing compound @P 200.00 /lit. 46.00 lit. P 9,200.00
Asphalt sealant @P 75.00 /lit. 124.00 lit. P 9,300.00
Steel forms @P 60.00 /lm. 451.00 lm. P 27,060.00
Gravel @P 1,000.00 /cu.m. 15.00 cu.m. P 15,000.00
Sand @P 1,000.00 /cu.m. 2.00 cu.m. P 2,000.00
Tie Wire @P 56.00 /kg. 4.00 kgs. P 224.00
G.I Pipes @P 300.00 /lm. 43.00 lm. P 12,900.00
Grease tar @P 250.00 /lit. 65.00 lit. P 16,250.00
Sub-total,A P 247,884.00

B. EQUIPMENT/FUEL/OIL
2 unit Transit mixer @P 10,232.00 /day for 10.00 days P 204,640.00
2 unit Conc. Vibrator @P 1,191.04 /day for 10.00 days P 23,820.80
1 unit Batching plant @P 9,664.24 /day for 10.00 days P 96,642.40
1 unit Payloader @P 13,864.00 /day for 10.00 days P 138,640.00
1 unit Conc. Sceeder @P 4,360.00 /day for 10.00 days P 43,600.00
1 unit Water truck @P 2,400.00 /day for 10.00 days P 24,000.00
1 unit Conc. Saw @P 1,339.04 /day for 10.00 days P 13,390.40
1 unit Bar cutter @P 1,758.00 /day for 10.00 days P 17,580.00
Sub-total,B P 562,313.60

C. LABOR
1 Engineer @P 650.00 /day for 10.00 days P 6,500.00
1 Foreman @P 566.08 /day for 10.00 days P 5,660.80
8 Mason @P 410.64 /day for 10.00 days P 32,851.20
12 Laborers @P 316.72 /day for 10.00 days P 38,006.40
Sub-total C P 83,018.40

DIRECT COST : Php 936,816.00


OCM : Php 112,417.92
PROFIT : Php 74,945.28
TAXES : Php 56,208.96
TOTAL COST Php 1,180,388.16

UNIT COST P 1,204.35 /sq.m.

Item No : 508(1)
Description : Hand-Laid Rock Embankment
Quantity : 4,757.00 cu.m.
COST ANALYSIS
A. MATERIALS

Hand-Laid Rock Emban @P 523.00 20.00 P 10,460.00


Portland Cement @P 5,423.00 15.00 P 81,345.00
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon

Location of Contract:
Lupon, Davao Oriental

DETAILED ESTIMATES

Sand and Gravel @P 320.00 2.00 P 1,522,240.00


Sub-total,A P 1,522,240.00

B. EQUIPMENT/FUEL/OIL
1 unit Truck @P 8,520.00 /day for 3.00 days P 25,560.00
Sub-total,B P 25,560.00

C. LABOR
1 Engineer @P 655.00 /day for 3.00 days P 1,965.00
1 Foreman @P 432.00 /day for 3.00 days P 1,296.00
2 Skilled @P 650.00 /day for 3.00 days P 3,900.00
2 Laborers @P 160.00 /day for 3.00 days P 960.00
Sub-total C P 8,121.00

DIRECT COST : Php 1,555,921.00


OCM : Php 140,032.89
PROFIT : Php 124,473.68
TAXES : Php 218,453.21
TOTAL COST Php 2,038,880.78

UNIT COST P 428.61

TOTAL COST: 29,106,054.06

Submitted By:

EARL L. NAVARRO
Proprietor/General Manager
PYRAMID CONSOLIDATED BUILDERS & GEN. MDSE.
March 14, 2017
CONTRACT ID : 17LG-0045
Contract : Concreting of Road at National Highway Junction, Barangay Cocornon
Name

Location Lupon, Davao Oriental

BILL OF QUANTITIES
Pay Item
No. Description Quantity Unit Unit Price Amount

PART B. OTHER GENERAL REQUIREMENT


B.4(1) Construction Survey and 1.32 km In words: In words:
Staking

#VALUE! #VALUE!

In Figure: Php 45,520.62 In Figure: Php 60,087.22


B.5 Project Billboard/Signboard 1.00 each In words: In words:

#VALUE! #VALUE!

In Figure: Php 6,900.26 In Figure: Php 6,900.26


B.7 Occupational Safety & 3.83 mos. In words: In words:
Health Program

#VALUE! #VALUE!

In Figure: Php 33,789.95 In Figure: Php 129,415.52


B.8 Traffic Management 4.67 mos. In words: In words:

#VALUE! #VALUE!

In Figure: Php 41,946.38 In Figure: Php 195,889.59


B.9 MOBILIZATION & 1.00 L.S. In words: In words:
DEMOBILIZATION

#VALUE! #VALUE!

In Figure: Php 844,750.20 In Figure: Php 844,750.20


PART C. EARTHWORKS
100(3)a Individual Removal of Trees, 26.00 each In words: In words:
(small)

#VALUE! #VALUE!

In Figure: Php 1,052.81 In Figure: Php 27,373.05


101(1)a1 Removal of Actual Structure 193.04 sq.m. In words: In words:
and Obstruction (PCCP
Unreinforced 0.15m thk)
#VALUE! #VALUE!

Page 1 of 21
DPWH-INFR-17-2016
CONTRACT ID : 17LG-0045
Contract : Concreting of Road at National Highway Junction, Barangay Cocornon
Name
Removal of Actual Structure
and Obstruction (PCCP
Location Lupon,0.15m
Unreinforced Davaothk)
Oriental

: #VALUE! #VALUE!

In Figure: Php 743.77 In Figure: Php 143,577.00


103(1) Structure Excavation 1,124.50 cu.m. In words: In words:

#VALUE! #VALUE!

In Figure: Php 512.49 In Figure: Php 576,292.50


103(3) Foundation Fill 4.98 cu.m. In words: In words:

#VALUE! #VALUE!

In Figure: Php 15,386.83 In Figure: Php 76,626.43


103(6)a Pipe Culvert and Drain 67.69 cu.m. In words: In words:
Excavation (Common Soil)

#VALUE! #VALUE!

In Figure: Php 1,947.07 In Figure: Php 131,797.50


104(1)a1 Embankment from Roadway 834.00 cu.m. In words: In words:
Excavation (Common Soil)

#VALUE! #VALUE!

In Figure: Php 2,098.51 In Figure: Php 1,750,158.45


104(1)b1 Embankment from Borrow 5,364.00 cu.m. In words: In words:
(Common Soil)

#VALUE! #VALUE!

In Figure: Php 1,410.74 In Figure: Php 7,567,209.34


105(1)a Subgrade Preparation 1,722.00 sq.m. In words: In words:
(Common Material)

#VALUE! #VALUE!

In Figure: Php 736.46 In Figure: Php 1,268,185.46


PART D. BASE AND SUBBASE COURSE
200(1) Aggregate Subbase Course 3,225.00 cu.m. In words: In words:

Page 1 of 22
DPWH-INFR-17-2016
CONTRACT ID : 17LG-0045
Contract : Concreting of Road at National Highway Junction, Barangay Cocornon
Name

Location Lupon, Davao Oriental


Aggregate
: Subbase Course

#VALUE! #VALUE!

In Figure: Php 818.84 In Figure: Php 2,640,770.50


PART E. SURFACE COURSES
311(1)b PCC Pavement 5,680.57 Sq.m. In words: In words:
(Unreinforced),
200 mm thk

#VALUE! #VALUE!

In Figure: Php 1,135.30 In Figure: Php 6,449,151.24


PART G DRAINAGE & SLOPE PROTECTION STRUCTURE
500(1)b3 Pipe Culverts, 910mm dia., 57.00 lm In words: In words:
Class IV

#VALUE! #VALUE!

In Figure: Php 2,982.33 In Figure: Php 169,992.95


506(1) Stone Masonry 42.00 cu.m. In words: In words:

#VALUE! #VALUE!

In Figure: Php 7,697.81 In Figure: Php 323,307.86


PART H MISCELLANEOUS STRUCTURES
605(3) Guide or Informatory Signs, 1.00 each In words: In words:
(600mm x 750mm)

#VALUE! #VALUE!

In Figure: Php 7,084.02 In Figure: Php 7,084.02


624(1)a1 Single Arm Post with Street 2.00 each In words: In words:
Light

#VALUE! #VALUE!

In Figure: Php 3,542.01 In Figure: Php 7,084.02


PART I WAITING SHED - 1 UNIT
803(1)a Structure Excavation 3.16 cu.m. In words: In words:

#VALUE! #VALUE!

Page 1 of 23
DPWH-INFR-17-2016
CONTRACT ID : 17LG-0045
Contract : Concreting of Road at National Highway Junction, Barangay Cocornon
Name
Structure Excavation
Location Lupon, Davao Oriental

: #VALUE! #VALUE!

In Figure: Php 2,241.78 In Figure: Php 7,084.02


900(1) Reinforced Concrete 2.99 cu.m. In words: In words:

#VALUE! #VALUE!

In Figure: Php 7,545.67 In Figure: Php 22,561.56


902(1)a1 Reinforcing Steel 125.00 kgs In words: In words:
(Deformed)

#VALUE! #VALUE!

In Figure: Php 100.76 In Figure: Php 12,595.56


903(1) Forms and Falseworks 1.00 l.s. In words: In words:

#VALUE! #VALUE!

In Figure: Php 7,010.64 In Figure: Php 7,010.64


1047(2)a Structural Steel 1,350.00 kgs In words: In words:

#VALUE! #VALUE!

In Figure: Php 481.50 In Figure: Php 650,023.92


1013(1) Corrugated Metal Roofing 18.00 sq.m. In words: In words:

#VALUE! #VALUE!

In Figure: Php 9,467.64 In Figure: Php 170,417.52


CONSTRUCTION OF CONCRETE REVETMENT 400 LM.
PART F. BRIDGE CONSTRUCTION (BOX CULVERT)
404(1)a Reinforcing Steel, Grade 40 25,735.29 kgs In words: In words:

#VALUE! #VALUE!

In Figure: Php 102.64 In Figure: Php 2,641,438.80


405(1)a1 Structural Concrete, Class A 980.10 cu.m. In words: In words:

#VALUE! #VALUE!

In Figure: Php 1,204.35 In Figure: Php 1,180,388.16

Page 1 of 24
DPWH-INFR-17-2016
CONTRACT ID : 17LG-0045
Contract : Concreting of Road at National Highway Junction, Barangay Cocornon
Name

Location Lupon, Davao Oriental

:
PART F. BRIDGE CONSTRUCTION (BOX CULVERT)
508(1) Hand-Laid Rock 4,757.00 cu.m. In words: In words:
Embankment

#VALUE! #VALUE!

In Figure: Php 428.61 In Figure: Php 2,038,880.78

In words: In Figure:
TOTAL Php 29,106,054.06
#VALUE!

Submitted by :
EARL L. NAVARRO Date : March 14, 2017
Proprietor/General Manager
PYRAMID CONSOLIDATED BUILDERS AND GENERAL MERCHANDISE

Page 1 of 25
DPWH-INFR-17-2016
Department of Public Works and Highways (DPWH)

CONTRACT ID : 17LG-0045
Concreting of Road at National Highway Junction, Barangay Cocornon

NAME :
Lupon, Davao Oriental
LOCATION :

CASH FLOW BY QUARTER AND PAYMENT SCHEDULE


PARTICULAR % 1ST QUARTER 2ND QUARTER 3RD QUARTER 4TH QUARTER
WT.
ACCOMPLISHMENT 100% 25.00% 25.00% 25.00% 25.00%
CASH FLOW PHP 7,276,513.52 PHP 7,276,513.52 PHP 7,276,513.52 PHP 7,276,513.52
CUMULATIVE ACCOMPLISHMENT 100% 25.00% 50.00% 75.00% 100.00%
CUMULATIVE CASH FLOW PHP 7,276,513.52 PHP 14,553,027.03 PHP 21,829,540.55 PHP 29,106,054.06

SUBMITTED BY:

EARL L. NAVARRO
Proprietor/General Manager
PYRAMID CONSOLIDATED BUILDERS & GEN. MDSE.
March 14, 2017

DPWH-INFR-19-2016 Page 1 of 26
Department of Public Works and Highways

CONTRACT ID : 17LG-0045

Concreting of Road at National Highway Junction, Barangay Cocornon

NAME :

Lupon, Davao Oriental


LOCATION :
-----------------------------------------------------------------------------------------------------------------------------------------------------

Date: BID FORM


To: BAC CHAIRMAN
DPWH, REGION XI
OFFICE OF THE REGIONAL DIRECTOR

We, the undersigned, declare that:


(a) we have examined and have no reservation to the bidding documents, including Supplemental/Bid Bulletins, for the
above stated Contract:

Concreting of Road at National Highway Junction, Barangay Cocornon

Lupon, Davao Oriental

(b)
we offer to execute the Works for this Contract in accordance with the Bidding Documents, including the Bid
Data Sheet, General and Special Conditions of the Contrac, Specifications and Drawings therein;
we present our Bid to execute the Works, consisting of our Technical Proposal (Annex "A") and our Financial Proposal
(c) (Annex "B");
(d) our Technical Proposal includes the following required documents;

(1) Bid Security in the required form, amount and validity period, using Form DPWH-INFR-09,10 or 11, as applicable
(Annex ";A-1")
(2) Organizatiuonal Chart for the Contract, using Form DPWH-INFR-13 (Annex "A-3")

(3) Contractor's Certification on Key Personnel for the Contract, with the Key Personnel's Affidavits of Commitment to
Work on the Contract, using Form DPWH-INFR-14 (Annex "A-4")
(4) List of Contractor's Major Equipment Pledged for the Contract, using Form DPWH-INFR-15 (Annex "A-5")

(5)
Omnibus Sworn Statement required under RA 9184-IRR Sec. 25.2b)iv), using Form DPWH-INFR-15(Annex "A-6")
(e) our Finanacial Proposal includes the following required documents:

DPWH-INFR-09-2016 Page 1 of 27
(1) This Bid Form (Annex "B-1")
(2) Bid Prices in the Bill of Quantities Form, using Forms DPWH-INFR-16 and 17 (Annex "B-2")
(3) Detailed estimates (Annex "B-3")
(4) Cash Flow by quarter, using Form DPWH-INFR-18 (Annex "B-4");
the total price of our Bid for this Contract based on the unit proces in the said Bill of Quantities, excluding any
(f) discounts offered in item(g) below, is:
#VALUE!

Php29,106,054.06

(g) the discounts we offer and the methodology for their application for this Contract are:

None

(h) our Bid shall be valid for a period of 120 Calendar Days after the date fixed for the opening of bids in accordance with
the Bidding Documents, and it shall remain binding upon us and may be accepted by you at any time before the
expiration of that period;

(i) if our Bid is accepted and we receive from you a Notice of Award, we commit, within ten (10) calendar days, after our
receipt of the said Notice, (1) to submit to you the rquired Performance Security and other documents prescribed in
the Bidding Documents, and (2) to sign the Contract Agreement;

we understand that, if the contract is awarded to us, this Bid, together with your writeen acceptance thereof through
(j) your Notice of Award, shall constitute a binding contract between us, until a formal Contract Agreement os prepared
and executed;

(k)
we understand that you are not bound to accept the Lowest Calculated Bid or any other Bid that you may receive; and

(l) we acknowledge that failure to sign each page of this Form of Bid and the accomplished Bill of Quantites shall be a
ground for the rejection of our Bid.

Name : EARL L. NAVARRO


In the capacity of : President/General Manager

Signed :
Duly authorized to sign the Bid for & In Behalf of : PYRAMID CONSOLIDATED BUILDERS & GEN. MDSE.
Date : March 14, 2017

DPWH-INFR-09-2016 Page 1 of 28
DPWH-INFR-09-2016 Page 1 of 29
CONTRACT ID : 17LG-0045
Contract : Concreting of Road at National Highway Junction, Barangay Cocornon
Name

Location Lupon, Davao Oriental

SUMMARY OF BID PRICES


Pay Item
No. Description Total

PART B. OTHER GENERAL REQUIREMENT


B.4(1) Construction Survey and Staking Php 60,087.22
B.5 Project Billboard/Signboard Php 6,900.26
B.7 Occupational Safety & Health Program Php 129,415.52
B.8 Traffic Management Php 195,889.59
B.9 MOBILIZATION & DEMOBILIZATION Php 844,750.20
PART C. EARTHWORKS
100(3)a Individual Removal of Trees, (small) Php 27,373.05
101(1)a1 Removal of Actual Structure and Obstruction (PCCP Unreinforced Php 143,577.00
0.15m thk)
103(1) Structure Excavation Php 576,292.50
103(3) Foundation Fill Php 76,626.43
103(6)a Pipe Culvert and Drain Excavation (Common Soil) Php 131,797.50
104(1)a1 Embankment from Roadway Excavation (Common Soil) Php 1,750,158.45
104(1)b1 Embankment from Borrow (Common Soil) Php 7,567,209.34
105(1)a Subgrade Preparation (Common Material) Php 1,268,185.46
PART D. BASE AND SUBBASE COURSE
200(1) Aggregate Subbase Course Php 76,626.43
PART E. SURFACE COURSES
311(1)b PCC Pavement Php 6,449,151.24
(Unreinforced),
PART G DRAINAGE & SLOPE PROTECTION STRUCTURE
500(1)b3 Pipe Culverts, 910mm dia., Class IV Php 169,992.95
506(1) Stone Masonry Php 323,307.86
PART H MISCELLANEOUS STRUCTURES
605(3) Guide or Informatory Signs, (600mm x 750mm) Php 7,084.02
624(1)a1 Single Arm Post with Street Light Php 8,971.00
PART I WAITING SHED - 1 UNIT
803(1)a Structure Excavation Php 6,897.00
900(1) Reinforced Concrete Php 22,561.56
902(1)a1 Reinforcing Steel (Deformed) Php 12,595.56
903(1) Forms and Falseworks Php 7,010.64
1047(2)a Structural Steel Php 650,023.92
1013(1) Corrugated Metal Roofing Php 170,417.52
CONSTRUCTION OF CONCRETE REVETMENT 400 LM.
PART F. BRIDGE CONSTRUCTION (BOX CULVERT)
404(1)a Reinforcing Steel, Grade 40 Php 2,641,438.80
405(1)a1 Structural Concrete, Class A Php 1,180,388.16

Page 1 of 30
DPWH-INFR-17-2016
CONTRACT ID : 17LG-0045
Contract : Concreting of Road at National Highway Junction, Barangay Cocornon
Name

Location Lupon, Davao Oriental

:
PART F. BRIDGE CONSTRUCTION (BOX CULVERT)
508(1) Hand-Laid Rock Embankment Php 2,038,880.78
Total Php 29,106,054.06

Submitted by :
EARL L. NAVARRO
Proprietor/General Manager
PYRAMID CONSOLIDATED BUILDERS AND GENERAL MERCHANDISE
March 14, 2017

Page 1 of 31
DPWH-INFR-17-2016