Location of Contract:
Lupon, Davao Oriental
DETAILED ESTIMATES
Item No : B.4(1)
Description : Construction Survey and Staking
Quantity : 1.32 km
COST ANALYSIS
A. MATERIALS
Total Station @P 13,065.00 /set 4.00 set P 52,260.00
Sub-total,A P 52,260.00
B. EQUIPMENT/FUEL/OIL
NONE
C. LABOR
1 Engineer @P 650.00 /day for 2.00 days P 1,300.00
1 Foreman @P 566.08 /day for 2.00 days P 1,132.16
4 Laborers @P 316.72 /day for 2.00 days P 2,533.76
Sub-total C P 4,965.92
Item No : B.8
Description : Traffic Management
Quantity : 9.00 Month
COST ANALYSIS
A. MATERIALS
Traffic Signages & Warnings, ect. @P 18,500.00 /set 4.00 set P 74,000.00
Sub-total,A P 74,000.00
B. EQUIPMENT/FUEL/OIL
NONE
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 650.00 /day for 115.00 days P 74,750.00
1 Foreman @P 566.08 /day for 115.00 days P 65,099.20
4 Laborers @P 316.72 /day for 115.00 days P 145,691.20
Sub-total C P 285,540.40
Location of Contract:
Lupon, Davao Oriental
DETAILED ESTIMATES
Item No : B.9
Description : MOBILIZATION & DEMOBILIZATION
Quantity : 1.00 L.S.
COST ANALYSIS
A. MATERIALS
NONE P
Sub-total,A P -
B. EQUIPMENT/FUEL/OIL
Sub-total,B P 804,524.00
C. LABOR
NONE P 0.00
Sub-total C P 0.00
Item No : B.7
Description : Construction Safety and Health
Quantity : 9.00 Month
COST ANALYSIS
A. MATERIALS
B. EQUIPMENT/FUEL/OIL
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon
Location of Contract:
Lupon, Davao Oriental
DETAILED ESTIMATES
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 650.00 /day for 115.00 days P 74,750.00
1 Foreman @P 566.08 /day for 115.00 days P 65,099.20
1 Laborers @P 316.72 /day for 115.00 days P 36,422.80
Sub-total C P 176,272.00
Item No : B.5
Description : Project Billboard/Signboard
Quantity : 2.00 each
COST ANALYSIS
A. MATERIALS
B. EQUIPMENT/FUEL/OIL
Sub-total,B P 0.00
C. LABOR
1 Engineer @P 650.00 /day for 1.00 days P 650.00
1 Foreman @P 566.08 /day for 1.00 days P 566.08
1 Laborers @P 316.72 /day for 1.00 days P 316.72
Sub-total C P 1,532.80
Location of Contract:
Lupon, Davao Oriental
DETAILED ESTIMATES
Item No : 100(3)a
Description : Individual Removal of Trees, (small)
Quantity : 26.000 each
COST ANALYSIS
A. MATERIALS
NONE P 0
Sub-total,A P 0
B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 2,156.00 /day for 7.00 days P 15,092.00
1 unit Boom truck @P 1,254.00 /day for 7.00 days P 8,778.00
Sub-total,B P 23,870.00
C. LABOR
1 Engineer @P 650.00 /day for 7.00 days P 4,550.00
1 Foreman @P 566.08 /day for 7.00 days P 3,962.56
2 Laborers @P 316.72 /day for 7.00 days P 4,434.08
Sub-total C P 12,946.64
Item No : 101(1)a1
Description : Removal of Actual Structure and Obstruction (PCCP Unreinforced 0.15m thk)
Quantity : 193.040 sq.m.
COST ANALYSIS
A. MATERIALS
NONE P 0
Sub-total,A P 0
B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 1,251.00 /day for 25.00 days P 31,275.00
1 unit Boom truck @P 1,254.00 /day for 25.00 days P 31,350.00
Sub-total,B P 62,625.00
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon
Location of Contract:
Lupon, Davao Oriental
DETAILED ESTIMATES
C. LABOR
1 Engineer @P 1,254.00 /day for 25.00 days P 31,350.00
1 Foreman @P 750.00 /day for 25.00 days P 18,750.00
2 Laborers @P 650.00 /day for 25.00 days P 32,500.00
Sub-total C P 82,600.00
Item No : 103(1)
Description : Structure Excavation
Quantity : 1,124.500 cu.m.
COST ANALYSIS
A. MATERIALS
NONE P 0
Sub-total,A P 0
B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 2,156.00 /day for 125.00 days P 269,500.00
1 unit Boom truck @P 1,254.00 /day for 125.00 days P 156,750.00
Sub-total,B P 426,250.00
C. LABOR
1 Engineer @P 1,245.00 /day for 125.00 days P 155,625.00
1 Foreman @P 560.00 /day for 125.00 days P 70,000.00
2 Laborers @P 300.00 /day for 125.00 days P 75,000.00
Sub-total C P 300,625.00
Item No : 103(3)
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon
Location of Contract:
Lupon, Davao Oriental
DETAILED ESTIMATES
COST ANALYSIS
A. MATERIALS
NONE P 0
Sub-total,A P 0
B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 2,156.00 /day for 5.00 days P 10,780.00
1 unit truck @P 7,689.60 /day for 5.00 days P 38,448.00
Sub-total,B P 49,228.00
C. LABOR
1 Engineer @P 650.00 /day for 5.00 days P 3,250.00
1 Foreman @P 566.08 /day for 5.00 days P 2,830.40
2 Laborers @P 316.72 /day for 5.00 days P 3,167.20
Sub-total C P 9,247.60
Item No : 103(6)a
Description : Pipe Culvert and Drain Excavation (Common Soil)
Quantity : 67.69 cu.m.
COST ANALYSIS
A. MATERIALS
NONE P 0
Sub-total,A P 0
B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 10,232.00 /day for 3.00 days P 30,696.00
1 unit Dumptruck @P 18,392.00 /day for 3.00 days P 55,176.00
Sub-total,B P 85,872.00
C. LABOR
1 Engineer @P 650.00 /day for 3.00 days P 1,950.00
1 Foreman @P 566.08 /day for 3.00 days P 1,698.24
2 Laborers @P 316.72 /day for 3.00 days P 1,900.32
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon
Location of Contract:
Lupon, Davao Oriental
DETAILED ESTIMATES
Sub-total C P 5,548.56
Item No : 104(1)a1
Description : Embankment from Roadway Excavation (Common Soil)
Quantity : 834.00 cu.m.
COST ANALYSIS
A. MATERIALS
NONE P 0
Sub-total,A P 0
B. EQUIPMENT/FUEL/OIL
3 unit Backhoe @P 11,987.00 /day for 9.00 days P 323,649.00
3 unit Dumptruck @P 15,687.00 /day for 9.00 days P 423,549.00
7 unit Boom Truck @P 8,520.00 /day for 9.00 days P 536,760.00
Sub-total,B P 1,283,958.00
C. LABOR
1 Engineer @P 1,250.00 /day for 9.00 days P 11,250.00
1 Foreman @P 987.00 /day for 9.00 days P 8,883.00
10 Laborers @P 350.00 /day for 9.00 days P 31,500.00
Sub-total C P 51,633.00
Item No : 104(1)b1
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon
Location of Contract:
Lupon, Davao Oriental
DETAILED ESTIMATES
COST ANALYSIS
A. MATERIALS
B. EQUIPMENT/FUEL/OIL
1 unit Grader @P 17,384.00 /day for 10.00 days P 173,840.00
1 unit Roller @P 12,056.00 /day for 10.00 days P 120,560.00
1 unit Water truck @P 8,520.00 /day for 10.00 days P 85,200.00
Sub-total,B P 379,600.00
C. LABOR
1 Engineer @P 765.00 /day for 10.00 days P 7,650.00
1 Foreman @P 650.00 /day for 10.00 days P 6,500.00
3 Laborers @P 566.08 /day for 10.00 days P 16,982.40
Sub-total C P 31,132.40
Item No : 105(1)a
Description : Subgrade Preparation (Common Material)
Quantity : 1,722.00 sq.m.
COST ANALYSIS
A. MATERIALS
NONE P 0
Sub-total,A P 0
B. EQUIPMENT/FUEL/OIL
1 unit Bakhoe @P 17,384.00 /day for 21.00 days P 365,064.00
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon
Location of Contract:
Lupon, Davao Oriental
DETAILED ESTIMATES
C. LABOR
1 Engineer @P 860.00 /day for 21.00 days P 18,060.00
1 Foreman @P 765.00 /day for 21.00 days P 16,065.00
10 Laborers @P 650.00 /day for 21.00 days P 136,500.00
Sub-total C P 170,625.00
Item No : 200(1)
Description : Aggregate Subbase Course
Quantity : 3,225.00 cu.m.
COST ANALYSIS
A. MATERIALS
B. EQUIPMENT/FUEL/OIL
1 unit Grader @P 16,920.00 /day for 20.00 days P 338,400.00
3 unit Dump truck @P 20,300.00 /day for 20.00 days P 1,218,000.00
1 unit Roller @P 12,056.00 /day for 20.00 days P 241,120.00
1 unit Water truck @P 8,520.00 /day for 20.00 days P 170,400.00
Sub-total,B P 1,967,920.00
C. LABOR
1 Engineer @P 860.00 /day for 20.00 days P 17,200.00
1 Foreman @P 456.00 /day for 20.00 days P 9,120.00
3 Laborers @P 350.00 /day for 20.00 days P 21,000.00
Sub-total C P 47,320.00
Location of Contract:
Lupon, Davao Oriental
DETAILED ESTIMATES
PCC Pavement
Item No : 311(1)b (Unreinforced),
Description : 200 mm thk
Quantity : 5,680.57 Sq.m.
COST ANALYSIS
A. MATERIALS
Portland cement @P 250.00 /bag 2,123.00 bags P 530,750.00
Reinforcing steel bars @P 310.00 /kg. 3,213.00 kgs. P 996,030.00
Curing compound @P 200.00 /lit. 321.00 lit. P 64,200.00
Asphalt sealant @P 75.00 /lit. 124.00 lit. P 9,300.00
Steel forms @P 60.00 /lm. 451.00 lm. P 27,060.00
Gravel @P 1,000.00 /cu.m. 15.00 cu.m. P 15,000.00
Sand @P 1,000.00 /cu.m. 2.00 cu.m. P 2,000.00
Tie Wire @P 56.00 /kg. 4.00 kgs. P 224.00
G.I Pipes @P 300.00 /lm. 43.00 lm. P 12,900.00
Grease tar @P 250.00 /lit. 65.00 lit. P 16,250.00
Sub-total,A P 1,673,714.00
B. EQUIPMENT/FUEL/OIL
2 unit Transit mixer @P 10,232.00 /day for 50.00 days P 1,023,200.00
2 unit Conc. Vibrator @P 1,191.04 /day for 50.00 days P 119,104.00
1 unit Batching plant @P 9,664.24 /day for 50.00 days P 483,212.00
1 unit Payloader @P 13,864.00 /day for 50.00 days P 693,200.00
1 unit Conc. Sceeder @P 4,360.00 /day for 50.00 days P 218,000.00
1 unit Water truck @P 2,400.00 /day for 50.00 days P 120,000.00
1 unit Conc. Saw @P 1,339.04 /day for 50.00 days P 66,952.00
1 unit Bar cutter @P 1,758.00 /day for 50.00 days P 87,900.00
Sub-total,B P 2,811,568.00
C. LABOR
1 Engineer @P 650.00 /day for 50.00 days P 32,500.00
1 Foreman @P 566.08 /day for 50.00 days P 28,304.00
8 Mason @P 410.64 /day for 50.00 days P 164,256.00
12 Laborers @P 316.72 /day for 50.00 days P 190,032.00
Sub-total C P 415,092.00
Location of Contract:
Lupon, Davao Oriental
DETAILED ESTIMATES
Item No : 500(1)b3
Description : Pipe Culverts, 910mm dia., Class IV
Quantity : 57.00 lm
COST ANALYSIS
A. MATERIALS
NONE P 0
Sub-total,A P 0
B. EQUIPMENT/FUEL/OIL
1 unit Dump truck @P 20,300.00 /day for 3.00 days P 60,900.00
1 unit Roller @P 12,056.00 /day for 3.00 days P 36,168.00
1 unit Water truck @P 8,520.00 /day for 3.00 days P 25,560.00
Sub-total,B P 122,628.00
C. LABOR
1 Engineer @P 860.00 /day for 3.00 days P 2,580.00
1 Foreman @P 456.00 /day for 3.00 days P 1,368.00
3 Laborers @P 350.00 /day for 3.00 days P 3,150.00
Sub-total C P 7,098.00
Item No : 506(1)
Description : Stone Masonry
Quantity : 42.00 cu.m.
COST ANALYSIS
A. MATERIALS
boulders @P 1,200.00 /cu.m. 30.00 cu.m. P 36,000.00
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon
Location of Contract:
Lupon, Davao Oriental
DETAILED ESTIMATES
Sub-total,A P 36,000.00
B. EQUIPMENT/FUEL/OIL
2 unit Grader @P 17,880.00 /day for 3.00 days P 107,280.00
2 unit Roller @P 12,056.00 /day for 3.00 days P 72,336.00
1 unit Water truck @P 8,520.00 /day for 3.00 days P 25,560.00
Sub-total,B P 205,176.00
C. LABOR
1 Engineer @P 650.00 /day for 3.00 days P 1,950.00
1 Foreman @P 566.08 /day for 3.00 days P 1,698.24
2 Laborers @P 316.72 /day for 3.00 days P 1,900.32
Sub-total C P 5,548.56
Item No : 605(3)
Description : Guide or Informatory Signs, (600mm x 750mm)
Quantity : 1.00 each
COST ANALYSIS
A. MATERIALS
Guide or Informatory @P 1,200.00 /cu.m. 1.00 cu.m. P 1,200.00
Sub-total,A P 1,200.00
B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 2,456.00 /day for 1.00 days P 2,456.00
Sub-total,B P 2,456.00
C. LABOR
1 Engineer @P 650.00 /day for 1.00 days P 650.00
1 Foreman @P 500.00 /day for 1.00 days P 500.00
2 Laborers @P 300.00 /day for 1.00 days P 600.00
Sub-total C P 1,750.00
Location of Contract:
Lupon, Davao Oriental
DETAILED ESTIMATES
Item No : 624(1)a1
Description : Single Arm Post with Street Light
Quantity : 2.00 each
COST ANALYSIS
A. MATERIALS
Single Arm Post with St@P 1,200.00 /cu.m. 1.00 cu.m. P 1,200.00
Sub-total,A P 1,200.00
B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 2,456.00 /day for 1.00 days P 2,456.00
Sub-total,B P 2,456.00
C. LABOR
1 Engineer @P 650.00 /day for 1.00 days P 650.00
1 Foreman @P 500.00 /day for 1.00 days P 500.00
2 Laborers @P 300.00 /day for 1.00 days P 600.00
Sub-total C P 1,750.00
Item No : 803(1)a
Description : Structure Excavation
Quantity : 3.16 cu.m.
COST ANALYSIS
A. MATERIALS
Structure Excavation @P 1,200.00 /cu.m. 1.00 cu.m. P 1,200.00
Sub-total,A P 1,200.00
B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 2,456.00 /day for 1.00 days P 2,456.00
Sub-total,B P 2,456.00
C. LABOR
1 Engineer @P 650.00 /day for 1.00 days P 650.00
1 Foreman @P 500.00 /day for 1.00 days P 500.00
2 Laborers @P 300.00 /day for 1.00 days P 600.00
Sub-total C P 1,750.00
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon
Location of Contract:
Lupon, Davao Oriental
DETAILED ESTIMATES
Item No : 900(1)
Description : Reinforced Concrete
Quantity : 2.99 cu.m.
COST ANALYSIS
A. MATERIALS
Portland cement @P 250.00 /bag 23.00 bags P 5,750.00
Reinforcing steel bars @P 310.00 /kg. 4.00 kgs. P 1,240.00
Curing compound @P 200.00 /lit. 5.00 lit. P 1,000.00
Grease tar @P 250.00 /lit. 23.00 lit. P 5,750.00
Sub-total,A P 13,740.00
B. EQUIPMENT/FUEL/OIL
1 unit Transit mixer @P 10,232.00 /day for 2.00 days P 20,464.00
2 unit Conc. Vibrator @P 1,191.04 /day for 2.00 days P 4,764.16
1 unit Conc. Saw @P 1,339.04 /day for 2.00 days P 2,678.08
1 unit Bar cutter @P 1,758.00 /day for 2.00 days P 3,516.00
Sub-total,B P 2,012.00
C. LABOR
1 Engineer @P 650.00 /day for 2.00 days P 1,300.00
1 Foreman @P 566.08 /day for 2.00 days P 1,132.16
8 Mason @P 410.64 /day for 2.00 days P 6,570.24
12 Laborers @P 316.72 /day for 2.00 days P 7,601.28
Sub-total C P 2,154.00
Item No : 902(1)a1
Description : Reinforcing Steel (Deformed)
Quantity : 125.00 kgs
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon
Location of Contract:
Lupon, Davao Oriental
DETAILED ESTIMATES
COST ANALYSIS
A. MATERIALS
Reinforcing Steel (Defo @P 1,200.00 /cu.m. 1.00 cu.m. P 1,200.00
Sub-total,A P 1,200.00
B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 2,456.00 /day for 2.00 days P 4,912.00
Sub-total,B P 4,912.00
C. LABOR
1 Engineer @P 650.00 /day for 2.00 days P 1,300.00
1 Foreman @P 500.00 /day for 2.00 days P 1,000.00
2 Laborers @P 300.00 /day for 2.00 days P 1,200.00
Sub-total C P 3,500.00
Item No : 903(1)
Description : Forms and Falseworks
Quantity : 1.00 l.s.
COST ANALYSIS
A. MATERIALS
Forms and Falseworks @P 1,200.00 /cu.m. 1.00 cu.m. P 1,200.00
Sub-total,A P 1,200.00
B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 325.00 /day for 2.00 days P 650.00
Sub-total,B P 650.00
C. LABOR
1 Engineer @P 650.00 /day for 2.00 days P 1,300.00
1 Foreman @P 500.00 /day for 2.00 days P 1,000.00
2 Laborers @P 300.00 /day for 2.00 days P 1,200.00
Sub-total C P 3,500.00
Location of Contract:
Lupon, Davao Oriental
DETAILED ESTIMATES
Item No : 1047(2)a
Description : Structural Steel
Quantity : 1,350.00 kgs
COST ANALYSIS
A. MATERIALS
Structural Steel @P 1,200.00 /cu.m. 320.00 cu.m. P 384,000.00
Sub-total,A P 384,000.00
B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 325.00 /day for 54.00 days P 17,550.00
Sub-total,B P 17,550.00
C. LABOR
1 Engineer @P 650.00 /day for 54.00 days P 35,100.00
1 Foreman @P 500.00 /day for 54.00 days P 27,000.00
2 Laborers @P 300.00 /day for 54.00 days P 32,400.00
Sub-total C P 94,500.00
Item No : 1013(1)
Description : Corrugated Metal Roofing
Quantity : 18.00 sq.m.
COST ANALYSIS
A. MATERIALS
Corrugated Metal Roofi @P 1,200.00 /cu.m. 15.00 cu.m. P 18,000.00
Sub-total,A P 18,000.00
B. EQUIPMENT/FUEL/OIL
1 unit Backhoe @P 325.00 /day for 54.00 days P 17,550.00
Sub-total,B P 17,550.00
C. LABOR
1 Engineer @P 650.00 /day for 54.00 days P 35,100.00
1 Foreman @P 500.00 /day for 54.00 days P 27,000.00
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon
Location of Contract:
Lupon, Davao Oriental
DETAILED ESTIMATES
Item No : 404(1)a
Description : Reinforcing Steel, Grade 40
Quantity : 25,735.29 kgs
COST ANALYSIS
A. MATERIALS
Reinforcing Steel, Grade@P 1,200.00 /cu.m. 1,501.00 cu.m. P 1,801,200.00
Sub-total,A P 1,801,200.00
B. EQUIPMENT/FUEL/OIL
1 unit Bar cutter @P 2,541.00 /day for 50.00 days P 127,050.00
Sub-total,B P 127,050.00
C. LABOR
1 Engineer @P 650.00 /day for 50.00 days P 32,500.00
1 Foreman @P 500.00 /day for 50.00 days P 25,000.00
2 Laborers @P 300.00 /day for 50.00 days P 30,000.00
Sub-total C P 87,500.00
Item No : 405(1)a1
Description : Structural Concrete, Class A
Quantity : 980.10 cu.m.
COST ANALYSIS
A. MATERIALS
Contract ID: 17LG-0045
Contract Name: Concreting of Road at National Highway Junction, Barangay Cocornon
Location of Contract:
Lupon, Davao Oriental
DETAILED ESTIMATES
B. EQUIPMENT/FUEL/OIL
2 unit Transit mixer @P 10,232.00 /day for 10.00 days P 204,640.00
2 unit Conc. Vibrator @P 1,191.04 /day for 10.00 days P 23,820.80
1 unit Batching plant @P 9,664.24 /day for 10.00 days P 96,642.40
1 unit Payloader @P 13,864.00 /day for 10.00 days P 138,640.00
1 unit Conc. Sceeder @P 4,360.00 /day for 10.00 days P 43,600.00
1 unit Water truck @P 2,400.00 /day for 10.00 days P 24,000.00
1 unit Conc. Saw @P 1,339.04 /day for 10.00 days P 13,390.40
1 unit Bar cutter @P 1,758.00 /day for 10.00 days P 17,580.00
Sub-total,B P 562,313.60
C. LABOR
1 Engineer @P 650.00 /day for 10.00 days P 6,500.00
1 Foreman @P 566.08 /day for 10.00 days P 5,660.80
8 Mason @P 410.64 /day for 10.00 days P 32,851.20
12 Laborers @P 316.72 /day for 10.00 days P 38,006.40
Sub-total C P 83,018.40
Item No : 508(1)
Description : Hand-Laid Rock Embankment
Quantity : 4,757.00 cu.m.
COST ANALYSIS
A. MATERIALS
Location of Contract:
Lupon, Davao Oriental
DETAILED ESTIMATES
B. EQUIPMENT/FUEL/OIL
1 unit Truck @P 8,520.00 /day for 3.00 days P 25,560.00
Sub-total,B P 25,560.00
C. LABOR
1 Engineer @P 655.00 /day for 3.00 days P 1,965.00
1 Foreman @P 432.00 /day for 3.00 days P 1,296.00
2 Skilled @P 650.00 /day for 3.00 days P 3,900.00
2 Laborers @P 160.00 /day for 3.00 days P 960.00
Sub-total C P 8,121.00
Submitted By:
EARL L. NAVARRO
Proprietor/General Manager
PYRAMID CONSOLIDATED BUILDERS & GEN. MDSE.
March 14, 2017
CONTRACT ID : 17LG-0045
Contract : Concreting of Road at National Highway Junction, Barangay Cocornon
Name
BILL OF QUANTITIES
Pay Item
No. Description Quantity Unit Unit Price Amount
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
Page 1 of 21
DPWH-INFR-17-2016
CONTRACT ID : 17LG-0045
Contract : Concreting of Road at National Highway Junction, Barangay Cocornon
Name
Removal of Actual Structure
and Obstruction (PCCP
Location Lupon,0.15m
Unreinforced Davaothk)
Oriental
: #VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
Page 1 of 22
DPWH-INFR-17-2016
CONTRACT ID : 17LG-0045
Contract : Concreting of Road at National Highway Junction, Barangay Cocornon
Name
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
Page 1 of 23
DPWH-INFR-17-2016
CONTRACT ID : 17LG-0045
Contract : Concreting of Road at National Highway Junction, Barangay Cocornon
Name
Structure Excavation
Location Lupon, Davao Oriental
: #VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
Page 1 of 24
DPWH-INFR-17-2016
CONTRACT ID : 17LG-0045
Contract : Concreting of Road at National Highway Junction, Barangay Cocornon
Name
:
PART F. BRIDGE CONSTRUCTION (BOX CULVERT)
508(1) Hand-Laid Rock 4,757.00 cu.m. In words: In words:
Embankment
#VALUE! #VALUE!
In words: In Figure:
TOTAL Php 29,106,054.06
#VALUE!
Submitted by :
EARL L. NAVARRO Date : March 14, 2017
Proprietor/General Manager
PYRAMID CONSOLIDATED BUILDERS AND GENERAL MERCHANDISE
Page 1 of 25
DPWH-INFR-17-2016
Department of Public Works and Highways (DPWH)
CONTRACT ID : 17LG-0045
Concreting of Road at National Highway Junction, Barangay Cocornon
NAME :
Lupon, Davao Oriental
LOCATION :
SUBMITTED BY:
EARL L. NAVARRO
Proprietor/General Manager
PYRAMID CONSOLIDATED BUILDERS & GEN. MDSE.
March 14, 2017
DPWH-INFR-19-2016 Page 1 of 26
Department of Public Works and Highways
CONTRACT ID : 17LG-0045
NAME :
(b)
we offer to execute the Works for this Contract in accordance with the Bidding Documents, including the Bid
Data Sheet, General and Special Conditions of the Contrac, Specifications and Drawings therein;
we present our Bid to execute the Works, consisting of our Technical Proposal (Annex "A") and our Financial Proposal
(c) (Annex "B");
(d) our Technical Proposal includes the following required documents;
(1) Bid Security in the required form, amount and validity period, using Form DPWH-INFR-09,10 or 11, as applicable
(Annex ";A-1")
(2) Organizatiuonal Chart for the Contract, using Form DPWH-INFR-13 (Annex "A-3")
(3) Contractor's Certification on Key Personnel for the Contract, with the Key Personnel's Affidavits of Commitment to
Work on the Contract, using Form DPWH-INFR-14 (Annex "A-4")
(4) List of Contractor's Major Equipment Pledged for the Contract, using Form DPWH-INFR-15 (Annex "A-5")
(5)
Omnibus Sworn Statement required under RA 9184-IRR Sec. 25.2b)iv), using Form DPWH-INFR-15(Annex "A-6")
(e) our Finanacial Proposal includes the following required documents:
DPWH-INFR-09-2016 Page 1 of 27
(1) This Bid Form (Annex "B-1")
(2) Bid Prices in the Bill of Quantities Form, using Forms DPWH-INFR-16 and 17 (Annex "B-2")
(3) Detailed estimates (Annex "B-3")
(4) Cash Flow by quarter, using Form DPWH-INFR-18 (Annex "B-4");
the total price of our Bid for this Contract based on the unit proces in the said Bill of Quantities, excluding any
(f) discounts offered in item(g) below, is:
#VALUE!
Php29,106,054.06
(g) the discounts we offer and the methodology for their application for this Contract are:
None
(h) our Bid shall be valid for a period of 120 Calendar Days after the date fixed for the opening of bids in accordance with
the Bidding Documents, and it shall remain binding upon us and may be accepted by you at any time before the
expiration of that period;
(i) if our Bid is accepted and we receive from you a Notice of Award, we commit, within ten (10) calendar days, after our
receipt of the said Notice, (1) to submit to you the rquired Performance Security and other documents prescribed in
the Bidding Documents, and (2) to sign the Contract Agreement;
we understand that, if the contract is awarded to us, this Bid, together with your writeen acceptance thereof through
(j) your Notice of Award, shall constitute a binding contract between us, until a formal Contract Agreement os prepared
and executed;
(k)
we understand that you are not bound to accept the Lowest Calculated Bid or any other Bid that you may receive; and
(l) we acknowledge that failure to sign each page of this Form of Bid and the accomplished Bill of Quantites shall be a
ground for the rejection of our Bid.
Signed :
Duly authorized to sign the Bid for & In Behalf of : PYRAMID CONSOLIDATED BUILDERS & GEN. MDSE.
Date : March 14, 2017
DPWH-INFR-09-2016 Page 1 of 28
DPWH-INFR-09-2016 Page 1 of 29
CONTRACT ID : 17LG-0045
Contract : Concreting of Road at National Highway Junction, Barangay Cocornon
Name
Page 1 of 30
DPWH-INFR-17-2016
CONTRACT ID : 17LG-0045
Contract : Concreting of Road at National Highway Junction, Barangay Cocornon
Name
:
PART F. BRIDGE CONSTRUCTION (BOX CULVERT)
508(1) Hand-Laid Rock Embankment Php 2,038,880.78
Total Php 29,106,054.06
Submitted by :
EARL L. NAVARRO
Proprietor/General Manager
PYRAMID CONSOLIDATED BUILDERS AND GENERAL MERCHANDISE
March 14, 2017
Page 1 of 31
DPWH-INFR-17-2016