SIAL Project Closing of - Mr. Mohammed Saidul Islam Job No 500 - 558-16 - at Dhaka

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

SANMAR INTERIOR & ARCHITECTURE LTD

Project Closing Report

Implementation has successfully completed the “Mr. Mohammed Saidul Islam Job no 500 & 558-16”
with in the stipulated time.

Project Name: Mr. Mohammed Saidul Islam, Job no 500 & 558-16
Project location: Dhanmondi 14/A- Dhaka
Project type: Interior
Project start date: 25.08.16
Declared Handover Date: 01.01.17
Actual hand over date: 28.01.17

Project concern person Name Designation


Sales Rajib Khan Executive
Implementation Md. Takbir Ahmed Project Eng.

Project income statement:

Particular Taka Particular Taka


Project work order value 25,60,830.00 Project budget cost 19,35,255.00
Project final bill 22,41,260.48 Project Actual Cost 17,03,740.00

Note: Client approval not found for each and every additional work.

Sub -Contractor Evaluation Matrix:


Performance
Nature of Name of skill
work Contractor Finishing Handover Financial Material Remarks
Man
work Time Strength support
power
Carpenter Delay of
Jamal Khalashi A A B B N/A
Labour work material supply
Electric New J.K
A A A A N/A
Labour work Engineering
Lacquer work A.R Builders A A B A A
Ceiling Jahan
B B B B N/A
Labour works Enterprise
Kuddus
Paint work B B B B B
Enterprise
Loose
Haque
Furniture B B A B B
Furniture
Supply
Note : A = Very Good ( 05 POINT),B = Satisfactory (04 POINT),C = Need Improvement (03 POINT),D= Dissatisfied &
will be discontinued (02 POINT)
Observation from QC Team:
Carpentry work: Very good in solid wood work.
Electrical work: Good in his work management and quality.
Lacquer polishes work: Work quality is good.
Celling works: Not so good in his work management.
Paint work: Work quality is medium.
Loose Furniture supply: Work quality is medium and time management is good.

*For this project no books of record maintained.