Procurement Plan
I. General
1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated
in Appendix 1 to the Guidelines for Procurement:
5. Summary of the Procurement Packages planned during the first 18 months after project
effectiveness (including those that are subject to retroactive financing and advanced
procurement)
1 2 3 4 5 6 7
Ref. Description Estimated Packages Domestic Review Comments
No. Cost Preference by Bank
US$ (yes/no) (Prior /
million Post)
Public Disclosure Authorized
2. Short list comprising entirely of national consultants: Short list of consultants for services,
estimated to cost less than US$500,000 equivalent per contract, may comprise entirely of national
consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines.
1 2 3 4 5 6
WORKS
Bid Evaluation
Activity Reference No. / Draft Bidding
Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and
Description Component Review Type Method Document / Signed Contract Contract Completion
No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for
Justification
Award
Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual
Component C: Supporting
Request for Single Stage - One
XL14 / Upgrading office IDA / 57040 Sustainable Coffee Prior Open - National 65,000.00 0.00 Canceled 2016-12-01 2017-01-26 2017-05-25
Quotations Envelope
Production and Rejuvenation
Component C: Supporting
Request for Single Stage - One
XL-14 / Upgrading office IDA / 57040 Sustainable Coffee Post Open - National 65,000.00 62,547.42 Completed 2016-12-01 2017-01-26 2017-05-26
Quotations Envelope
Production and Rejuvenation
Component C: Supporting
XL16 / Upgrading of Request for Single Stage - One
IDA / 57040 Sustainable Coffee Post Open - National 100,000.00 69,030.33 Completed 2018-07-02 2018-08-16 2018-11-14
nursey Quotations Envelope
Production and Rejuvenation
XLKT02 / Investment
support infrastructure for Component C: Supporting
Request for Single Stage - One
SCP village Quyet Thang IDA / 57040 Sustainable Coffee Post Open - National 190,355.00 178,720.11 Signed 2018-08-12 2018-10-07 2019-04-05
Quotations Envelope
CT, Ha Mon commune, Production and Rejuvenation
DakHa district
XLKT03 / Investment
support infrastructure for Component C: Supporting
Request for Single Stage - One
SCP village 7 CT, Ngoc IDA / 57040 Sustainable Coffee Post Open - National 198,560.00 186,431.68 Signed 2018-08-13 2018-10-08 2019-04-06
Quotations Envelope
Wang commune, DakHa Production and Rejuvenation
district
Component C: Supporting
XL15 / Upgrading of first Request for Single Stage - One
IDA / 57040 Sustainable Coffee Post Open - National 20,000.00 0.00 Canceled 2018-06-01 2018-08-01 2018-10-30
line seed nursey Quotations Envelope
Production and Rejuvenation
XLKT05 / Investment in
infrastructure for Dat Den
Component C: Supporting Pending
Fresh and organic coffee Single Stage - One
IDA / 57040 Sustainable Coffee Post Request for Bids Open - National 337,031.00 0.00 Implementati 2019-12-18 2019-12-23 2020-01-22 2020-02-05 2020-02-19 2020-08-17
production CT in Village 7, Envelope
Production and Rejuvenation on
Ngoc Wang commune, Dak
Ha district
GOODS
Bid Evaluation
Activity Reference No. / Draft Bidding
Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and
Description Component Review Type Method Document / Signed Contract Contract Completion
No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for
Justification
Award
Page 1
Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual
Component C: Supporting
Request for Single Stage - One
HH37 / Office equipment IDA / 57040 Sustainable Coffee Post Open - National 61,000.00 58,867.18 Completed 2016-09-01 2016-10-16 2017-02-16
Quotations Envelope
Production and Rejuvenation
Component C: Supporting
HH38 / Equipment for Request for Single Stage - One
IDA / 57040 Sustainable Coffee Post Open - National 24,000.00 23,082.20 Completed 2016-10-07 2016-11-21 2017-03-21
laboratories Quotations Envelope
Production and Rejuvenation
CONSULTING FIRMS
Activity Reference No. / Combined Evaluation
Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of
Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion
No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal
Negotiated Contract
Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual
INDIVIDUAL CONSULTANTS
Activity Reference No. / Invitation to
Loan / Credit Market Contract Type Estimated Actual Draft Negotiated
Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion
No. Approach Amount (US$) Amount (US$) Contract
Consultant
Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual