Professional Documents
Culture Documents
Final Procurent For Highbury Fields Cafe
Final Procurent For Highbury Fields Cafe
2. Recommendation
2.1. To approve the procurement strategy for the Highbury Fields Café Building as
outlined in this report.
4. Background
4.1. Nature of the service
4.1.1. Highbury Fields is the borough’s largest greenspace, attracting an average of
2,000 visitors each day to the play area alone. It is also home to various sports
facilities including four netball courts and 11 tennis courts.
1
4.1.2. This scheme seeks to improve the north-east corner of the Fields by demolishing
the existing café kiosk, bandstand building, derelict former park-keeper’s bungalow
and removing various ancillary buildings. The cumulative footprint will be used to
create a new high-quality building that provides a café, public toilets and park-
keeper facilities. The café will comprise indoor and outdoor seating with a kitchen
to accommodate both food preparation and cooking facilities, a servery, store and
catering office. Public toilet provision will include four universal public toilets, one
wheelchair-accessible and one Changing Place (CP) toilet. The site of the park-
keeper’s bungalow and former bandstand building will require basic re-
landscaping to return these areas to open space.
The running costs for the café will be the responsibility of the café operator as will
the café fit-out and any maintenance costs associated with the café operations.
The Parks Department will be responsible for maintaining the fabric of the building,
the park keeper’s demise and the public toilets and and running costs will covered
by existing budgets.
4.1.3. Planning permission was granted in July 2023. The design team has begun
working on the technical documentation required for RIBA Stage 4 which details
how to manufacture and construct the building. This stage is expected to take
approximately 16 weeks to complete, and a Full Plan application will be submitted
to Building Control towards the end of this period.
4.2.2. A cost estimate for the contractor to undertake the demolition, construction and
limited landscaping works issued in July 2023 was £1,180,000. The remaining
project budget is assigned to cover design and project management fees, statutory
fees, surveys and contingencies.
4.2.3. The estimated construction period for the delivery of the contract is 32 weeks.
4.3. Timetable
4.3.1. The indicative key dates for the delivery of the project are:
2
August 2023 Approval to procure granted
4.3.2. Planning permission for this project was secured in July 2023. The council has
three years from this date to commence work.
4.3.3. The Parks Department have engaged extensively with the community and other
stakeholders in the course of preparing the proposals for the works to the park:
A physical letter drop to 15,100 households with the Highbury ward
A display of exhibition boards of the proposals at Islington’s Central Library
between 7 February 2022 and 11 March 2022
Two online engagement events held on 28 February 2022 and Wednesday 2
March 2022
A mailing list of 214 contacts, comprised of residents, park users and local
businesses
Other stakeholders engaged on the proposals:
Staff working in/near to Highbury Fields
Local schools
Sports groups, including local tennis groups
Voluntary and Community Sector (VCS) organisations
3
4.4.2. In-sourcing: The council does not have the relevant expertise, qualified staff or
equipment within the organisation to carry out the specialist construction work
needed to deliver this project.
4.4.4. Competitive tender using the restricted procedure: Procuring this contract using a
two-stage restricted procedure with a selection questionnaire will allow access to
more contractors to submit a tender for this opportunity than a framework
agreement. There is known interest from the market in this forthcoming
opportunity, including amongst local contractors and market research carried out
to date suggests that there is likely to be competition among suppliers.
This option also enables the council to have more control over the suitability
criteria used to assess contractors for this project through the use of the selection
questionnaire. The main disadvantage of this option is that it will require more time
to complete but this has been accounted for in the project timetable. This is the
preferred option given the above reasons.
4.4.5. Collaboration with other boroughs is not deemed appropriate for this scheme given
that the project is site-specific. For this reason there are no benefits to exploring
collaboration with other authorities and organisations.
4.4.6. Following appraisal of the above options the preferred and recommended
procurement route for this contract is a tender process using the two-stage
restricted procedure.
4
4.5. Key Considerations
4.5.1. Social Value: tenderers’ approach to Social Value will be assessed as part of the
contract via a specific Social Value question within the method statement
questions, weighted at 20%. In order to meet the minimum quality requirements,
the contractor’s proposed approach to Social Value will need to include:
4.5.2. Economic considerations: such as how they will contribute to developing skills and
tackling unemployment amongst people including excluded communities and
working with local and sub-regional supply chain/consultants.
Given the proximity of the site to a number of local schools, it is proposed that a
bespoke educational shadowing opportunity will be created for local pupils who
have an interest in the built environment as a potential career choice. The council
will work in partnership with the appointed contractor to co-design the learning
experience. Taking the contractor’s staff resources into account we anticipate that
this would require a maximum time commitment of between 12 and 14 hours in
total. A project proposal for this element is appended to the report.
4.5.3. Social considerations: such as supporting the local community to make more use
of the park and additional open space being created by the project, for example
resourcing and organising a community planting day around the park area. The
commissioning of the contract to operate the cafe will provide additional future
opportunities. These will be outlined in the future procurement exercise on the use
of the cafe.
4.5.4. Environmental considerations: such as, supporting local activities that seek to
reduce the council’s and the community's negative environmental impact.
As set out in more detail in the environmental implications below the project will
have a number of environmental benefits including new energy efficient and
sustainable buildings, increase in the open space within the park and opportunities
to increase biodiversity on the site as part of the project and after its delivery.
A minimum of 10% of the total value of materials used in the construction will be
derived from recycled and re-used content in the products and materials selected.
Potential contractors will be encouraged to reuse and recycle as much of the
waste material from the existing buildings as possible. The building itself has been
designed to last as long as possible, to be flexible and versatile so its use can
change easily over time and it will also be straightforward to deconstruct at the end
of its life.
5
4.5.5. London Living Wage will apply and will be a condition of the contract.
4.5.6. In order to ensure best value, work with local supply chains will be monitored and
evaluated. Findings on best practice will be applied to future projects.
4.5.7. Similarly, processes and procedures relating to waste and recycling will be
monitored throughout the duration of the contract and any useful learning shared
with other project teams going forward.
4.6. Evaluation
This tender will be conducted in two stages, known as the Restricted Procedure as the
tender is ‘restricted’ to a limited number of organisations. The first stage assesses
Selection Criteria through a Selection Questionnaire (SQ) which establishes whether an
organisation meets the financial requirements, is competent and capable and has the
necessary resources to carry out the contract. The SQ is backwards looking and
explores how the organisation has performed to date, its financial standing, information
about their history and experience.
4.6.1. The award criteria will be weighted 40% cost and 60% quality (of which 20% will
be allocated to social value). The quality criteria will cover the following areas:
6
Total 100%
Works could be delayed This could lead to Work will take place
due to ecological increased project costs between mid-March –
limitations including due to programme April or September – late
roosting bats or nesting delays. October, outside of
birds. roosting season. Any tree
works will avoid the bird
nesting season between
September and February
7
An ecologist has been
appointed and will carry
out an updated site
walkover this summer to
ensure that the works
programme can go ahead
next year.
8
4.7.2. The business opportunities associated with this procurement are that it aims to
appoint a contractor that can deliver the works and ensure value for money as well
as Social Value for the council; local residents and local businesses. This
procurement provides a good opportunity for local contractors to submit tenders to
deliver this project. Social Value targets and aspirations will be requested as part
of the tender return submissions.
4.8. The Employment Relations Act 1999 (Blacklist) Regulations 2010 explicitly prohibit
the compilation, use, sale or supply of blacklists containing details of trade union
members and their activities. Following a motion to full Council on 26 March 2013,
all tenderers will be required to complete an anti-blacklisting declaration. Where
an organisation is unable to declare that they have never blacklisted, they will be
required to evidence that they have 'self-cleansed'. The Council will not award a
contract to organisations found guilty of blacklisting unless they have
demonstrated 'self-cleansing' and taken adequate measures to remedy past
actions and prevent re-occurrences.
9
4. Options appraisal for tender A two-stage restricted procedure is the preferred
procedure including consideration of option for this procurement. Collaboration
collaboration opportunities opportunities are not considered viable due to the
nature of the project.
5. Consideration of: London Living Wage will apply for this project and will
be a condition to the contract.
Social benefit clauses;
London Living Wage; All tenderers will be required to set out their
Best value; aspirations regarding social value and how they
TUPE, pensions and other intend to measure it as part of their submissions.
staffing implications
See paragraph 4.5
6. Award criteria The contract award will be based on 40% cost and
60% quality.
7. Any business risks associated Risks associated with failure of the procurement and
with entering the contract the disruption works are likely to cause exist but
mitigation is in place to reduce these risks.
5. Implications
5.1. Financial Implications
5.1.1. The three-year budget for Highbury Fields Café as of 22/23 was £1.518m. In
22/23, expenditure of £0.120m was incurred, which was funded via S106. The
remaining budget from 23/24 to 24/25 is £1.398m.
10
o The approved budget for 23/24 is £0.847m, funded by £0.237m S106 and
£0.610m borrowing.
o The approved budget for 24/25 is £0.551m, funded by borrowing.
5.1.2. The cost estimate for the contractor to undertake the demolition, construction and
limited landscaping works issued in July 2023 is £1,180,000. The remaining
project budget is assigned to cover design and project management fees, statutory
fees, surveys and contingencies.
5.1.3. The estimated construction period for the delivery of the contract is 32 weeks.
5.1.4. This is assuming all expenditure relates to capital works. There is no revenue
budget allocated to this project.
5.2.1. This report seeks pre-tender approval for the procurement strategy to procure a principal
contractor to deliver building improvements to the north-east corner of Highbury Fields.
5.2.2. The council has power to enter into the proposed contract under section 1 of the
Local Government (Contracts) Act 1997
5.2.3. The Local Government Act 1999, requires the council to make arrangements to
achieve Best Value in the exercise of its functions when considering a service
provision, which includes services detailed in the body of the report.
5.2.4. The estimated total value of the thirty-two (32) week contract is £1,180,000. Under
the Public Contract Regulations 2015 (PCR), relevant contracts over the relevant
threshold must comply with the regulations. This contract is under the PCR
threshold for works (£5,336,937). Whilst the contract is sub-threshold and is not
caught by the procurement regime of the PCR, the retained EU law principles of
equality of treatment, proportionality, non-discrimination and transparency must be
followed.
5.2.5. The procurement must comply with the council’s Procurement Rules. Procurement
Rule, 1.7A.2 band (iv) requires a formal tender process with a minimum of five (5)
written competitive tenders. It is stated in the body of the report that the restricted
procedure will be used.
5.2.6. Procurement Rule 24.2 states that all contracts over £24,999 will need formal
conditions prepared or agreed by the Legal Services Team. All contracts with a
11
value above £500,000 will need to be sealed by Legal Services.
5.2.7. Under Procurement Rule 18.1.1 Corporate Directors have the power to procure and
award the contracts using capital spend of up to £5,000,000.
5.2.8. The decision maker can approve the recommendations provided they are satisfied
with the contents of the report and the recommendations represents best value for
the council.
5.3.2. Existing buildings will be demolished and replaced with a thermally and energy
efficient café building. The demolition of the bungalow will also result in previously
unusable green space being returned to public use.
5.3.3. The café building will be single-storey, low impact and lightweight and will be built
on steel screw pile foundations and a timber superstructure using UK grown
Brimstone Ash. Steel will only be used for connection brackets and fixings. The
building is intended to be carbon responsible and has excluded concrete and
gypsum based products where possible so that it will be able to be fully recycled at
the end of building life.
5.3.4. There will be no gas supplies serving the building. A low temperature hot water
(LTHW) system will heat the building via an air source heat pump (ASHP) and it
will be ventilated via Mechanical Ventilation with Heat Recovery (MVHR). The
café, office, kitchen and bathroom will be heated via an underfloor heating system
and the external accessible toilet/baby change room and wildlife shelter toilet will
be provided with a ceiling mounted fan-assisted heater controlled via PIR system.
5.3.6. The proposal will deliver significant ecological enhancements as there will be a
Biodiversity Net Gain (BNG) increase of 45.76% in habitat units, such as
grassland and woodland and 100% increase in linear units, such as hedgerows
and the creation of a pond.
12
opportunity, and foster good relations, between those who share a relevant
protected characteristic and those who do not share it (section 149 Equality Act
2010). The council has a duty to have due regard to the need to remove or
minimise disadvantages, take steps to meet needs, in particular steps to take
account of disabled persons' disabilities, and encourage people to participate in
public life. The council must have due regard to the need to tackle prejudice and
promote understanding.
5.4.2. An Equalities Impact Assessment was completed on 9 June 2023. The main
findings are that there are no foreseeable negative impacts on users of the park as
a result of the scheme. Short-term negative impacts, such as disruption to
residents and park users, will be mitigated against with a Construction
Management Plan and Construction Logistics Plan signed off prior to work starting
on site. Local residents will be advised of the project programme in advance by
email, letter, signage in the park and via the council’s website and will be
encouraged to contact the Parks department should any issue arise. Ultimately,
the project is set to have a positive impact on park users and a positive impact on
those with protected characterists and people from disadvantaged groups. The full
Equalities Impact Assessment is appended.
13
7. Record of the decision
7.1. I have today decided to take the decision set out in section 2 of this report for the
reasons set out above.
Approved by:
Appendices:
Legal Implications Author: Mark Ferguson, Senior Commercial and Procurement Lawyer
Tel: 0207 527 3099
Email: Mark.Ferguson@islington.gov.uk
14