1. PURPOSE
1.1 To describe the requirements for the auditing and inspection process of the Health,
Safety and Environmental Management System, including:
1.2 Inspections and Audits will identify and reduce safety and health hazards that could
contribute to occupational injury or illness and to ensure compliance with applicable
environmental regulations.
1.3 This procedure provides guidelines to conduct inspections to work site and Place
accommodation premises.
2. SCOPE
3. DEFINITION OF TERMS
Page 3 of 18
Doc #:PR-AUC-HSE-001 Originated by: ISS
Project :
CONTRACTOR :
4. RESPONSIBILITIES
4.2.1. Ensure that all incidents that occur in his area of responsibility are properly
investigated if requested, participate with the Investigation Team.
4.2.2. Coordinate with the investigation group regarding all the necessary data
needed for easy determination of the root causes of the incident.
4.2.3. Review the incident reports and implement any recommendation stipulated in
the report.
4.2.4. Closely monitor the implementation of the action to be taken, making sure that
his subordinates are following the HSE procedures.
4.3.1. Shall participate and conduct the Daily, Weekly and Monthly HSE Inspection.
4.3.2. Shall ensure that such inspections are carried out and hazards are identified &
attended to appropriately.
Page 4 of 18
Doc #:PR-AUC-HSE-001 Originated by: ISS
4.3.3. Shall log inspection findings of their Weekly, Monthly HSE Inspections in
CONTRACTOR HSE Actions Tracking Registry respectively for references /
follow-up of actions.
4.3.4. Shall ensure to carry out the immediate actions to complete/close-out of
recommendations.
5. PROCEDURE
Sanitary Regulation
Induction of personnel
Wearing of mandatory and task specific PPE
Worker compliance to site rules
Worker compliance to HSE Procedures
Adequate signage in place
Good housekeeping practices in place
Residential premises
5.1.1.3. The persons conducting the daily inspection shall ensure that non-
conformances are noted and corrective actions determined,
implemented, and closed out.
5.1.1.4. The persons conducting the daily inspection shall ensure that affected
are consulted with, prior to the implementation of those corrective
actions.
5.1.1.5. Results from the daily HSE inspection conducted shall be registered in
the HSE Logbook at the work site. Observations and
recommendations shall be discussed by CONTRACTOR and
Page 5 of 18
Doc #:PR-AUC-HSE-001 Originated by: ISS
Induction of personnel
Wearing of mandatory and task specific PPE
Worker compliance to site rules
Worker compliance to HSE Procedures
Adequate signage in place
Good housekeeping practices in place
Accommodation premises
5.2.2.1. The persons conducting the inspection shall ensure that non
conformances are noted and corrective actions determined,
implemented and closed out.
5.2.2.2. The persons conducting the inspections shall ensure that affected are
consulted with, prior to the implementation of those corrective actions.
5.2.2.4. Results from the weekly HSE inspection conducted shall be registered
in the CONTRACTOR HSE Actions Tracking System. Observations
and recommendations shall be discussed by the HSE Advisor,
CONTRACTOR HSE Manager, CONTRACTOR HSE Supervisor and
the Subcontractor HSE Manager to rectify the action items. A follow-
up and verification of the site inspection findings/observations by the
HSE Advisor.
Page 6 of 18
Doc #:PR-AUC-HSE-001 Originated by: ISS
Sanitary Regulation
HSE implementation
Mandatory and task specific PPE
Housekeeping
Electrical
Working at Height
Mobile equipment
Workers safety/traffic control
Transportation (of men and materials)
Traffic management / traffic safety
5.2.3.4. The PMT HSE Advisor may, during the course of the inspection/audit,
consult with CONTRACTOR HSE Manager regarding HSE issues
Identified or raised.
5.2.3.5. The CONTRACTOR HSE Management shall record HSE issues and
non-conformances on the inspection/audit walkthrough Form
(Attachment 3)
Page 7 of 18
Doc #:PR-AUC-HSE-001 Originated by: ISS
5.2.3.8. The status of corrective actions shall remain open on the tracking
system until the HSE Advisor verifies and close out through
consultation with the CONTRACTOR HSE Manager/Site
Manager/Supervisor and with follow up inspections.
5.3.1. AUC shall conduct Health, Safety and Environment Management System audits
on a half-yearly basis.
5.3.2. CONTRACTOR shall submit documents related to the following but not limited to
the HSE who is performing the Audit.
Project HSE Management Plans
Policies
Procedures
Work practices
5.3.3. HSE Audit findings (observations and recommendations) in the form of signed
report shall be sent to the CONTRACTOR Management for implementation of
audit recommendations.
Page 8 of 18
Doc #:PR-AUC-HSE-001 Originated by: ISS
5.4.4. The audits and possible corrective actions would be carried out in accordance
with the documented procedures of the CONTRACTOR Corporate Internal
HSE Audit Procedure.
5.4.5. The deviations noted and the comments given by the members in the
inspection team shall be recorded on the NCR (Non-Conformance Report) and
inspection reports. The results of inspection should be communicated in a
written way of the Project Site Manager to the personnel responsible for the
area concerned, Subcontractor Manager & Subcontractor HSE Manager.
5.4.6. Follow up actions shall be made to ensure the findings/deviations noted by the
inspection members are fully rectified. All CAR (Corrective Action Request)
issued shall be recorded and updated in the CAR Log by the HSE Department.
If the response is acceptable, CAR shall be closed out.
5.5.2. The Unscheduled HSE Audit shall be carried out by HSE Advisors.
5.5.5. CONTRACTOR HSE shall prepare specific checklist for conducting Audit.
Page 9 of 18
Doc #:PR-AUC-HSE-001 Originated by: ISS
5.5.6. CONTRACTOR HSE shall log all the findings and track recommendations on
the same system utilized for the HSE Audit. (Attachment 6)
5.5.7. The tracking system shall be filed in the CONTRACTOR HSE file of the Project.
5.6.1. Audits shall be carried out in an open and constructive way and with the
involvement of relevant personnel at all levels.
Toolbox meetings
Subcontractor meetings
HSE committees (where applicable)
HSE notice boards (where appropriate)
5.8. Close-Out
5.8.1. The status of corrective actions shall remain open on the register until the
CONTRACTOR HSE Manager confirms close out through site inspections and
consultation with the HSE Advisor.
5.8.2. Closure Certificate (Attachment 4) for Monthly Inspection, Half Yearly Audit and
Unscheduled Inspection/Audit shall be issued to CONTRACTOR Manager
through PMT Manager by HSE Manager as verified and confirmed by PMT
HSE Advisor assigned in the project, confirming all corrective action and
recommendation items has been closed out.
Page 10 of 18
Doc #:PR-AUC-HSE-001 Originated by: ISS
5.9. Protocol
5.9.3. All HSE Monthly Inspections shall be undertaken in a proactive, open and
transparent manner.
5.10.1. CONTRACTOR HSE Manager shall maintain soft and hard copies of audits for
the duration of the project.
5.10.2. CONTRACTOR HSE Manager shall develop and maintain an HSE Actions
Tracking System containing details from Weekly HSE Inspection (Attachment
4), Monthly HSE Inspection (Attachment 5), and HSE Audit (Attachment 6),
Unscheduled Inspection/Audit (Attachment 6) findings.
5.10.3. The HSE Actions Tracking System shall be filed in the HSE file for the Project
Page 11 of 18
Doc #:PR-AUC-HSE-001 Originated by: ISS
6. ATTACHMENTS
Page 12 of 18
Doc #:PR-AUC-HSE-001 Originated by: ISS
Page 13 of 18
Doc #:PR-AUC-HSE-001 Originated by: ISS
Page 14 of 18
Doc #:PR-AUC-HSE-001 Originated by: ISS
Page 15 of 18
Doc #:PR-AUC-HSE-001 Originated by: ISS
Page 16 of 18
Doc #:PR-AUC-HSE-001 Originated by: ISS
Page 17 of 18
Doc #:PR-AUC-HSE-001 Originated by: ISS
Page 18 of 18