Project Management
Project Management
https://t.me/dheeraj_sardana
1 1
A. 15 ,28to42 B. 15 ,30to45
1 1
C. ,28to42 D. ,30to45
12 12
Sol.
15. The flow net of activities of a project
is shown in the below figure. The
duration of the activities are written
along the arrows:
The critical path of the activities is
along
A. 1-2-4-5-7-8
B. 1-2-3-5-7-8
C. 1-2-3-6-7-8
D. 1-2-4-5-3-6-7-8
Codes:
(a) Both Assertion (A) and Reason (R) are individually
true and Reason (R) is the correct explanation of
Assertion (A).
(b) Both Assertion (A) and Reason (R) are individually
true but Reason (R) is NOT the correct explanation of
Assertion (A).
(c) Assertion (A) is true but Reason (R) is false.
(d) Assertion (A) is false but Reason (R) is true.
Sol.
16. Assertion (A): Crashing is done only for critical
activities.
Reason (R): Critical activities duration if reduced
reduces the total project duration. So more
resources are allotted to these critical activities.
Sol.
17. Assertion (A): Most conflict in a project occurs during
the execution phase.
Reason (R): Execution takes most of the resources &
is longest time consuming process.
Sol.
18. A schedule performance index SPI of 0.76 means:
A. you are over budget.
B. you are ahead of schedule.
C. you are only progressing at 76 percent of the
rate originally planned.
D. you are only progressing at 24 percent of the
rate originally planned.
Sol.
19. All the question of a contractor are assured
A. Kickoff meeting
B. bidder conference
C. project charter
D. issue log
Sol.
20. E.M.D. is
A. Depositing 2% of the contract value
B. Same as security deposit
C. Depositing 10% of the contract value
D. Depositing only 5% of the contract value
Sol.
21. The security deposit is
A. Refunded in the middle of the contract
B. Refunded after the maintenance period
C. Not refunded
D. Refunded as soon as the construction is over
Sol.