This AGREEMENT made and executed on this of MAY 10, 2024 at Cebu City,
Philippines, by and between:
-and-
CES PHILIPPINES INC., a business establishment organized under Philippine laws with
office address at NO. 63 GENERAL LUNA STR, BRGY USUSAN, TAGUIG CITY.
represented in this act by its General Industries Representative, ALEXANDRIA DE SERRA
hereinafter called the SUB-CONTRACTOR;
WITNESSETH:
WHEREAS, the CONTRACTOR has entered into a contract with New City
Builders INC., hereinafter called the GENERAL CONTRACTOR of Megaworld Corp.,
hereinafter called the OWNER in connection with the
construction/development/improvement of BELMONT HOTEL, hereinafter called the
PROJECT;
1. GENERAL.
1.1 The SUB-CONTRACTOR shall carry out the CONTRACT WORKS in
strict compliance with the CONTRACT DOCUMENTS such as drawings,
specification, and approved cost proposal.
1.4 The SUB-CONTRACTOR shall ensure that all his personnel shall be in
uniform using the prescribed T-shirts and helmets. All uniform, helmets
or other paraphernalia provided by CONTRACTOR shall be chargeable
to the SUB- CONTRACTOR
1.5 The SUB-CONTRACTOR shall maintain a record duly signed and certified
by the Project Manager, showing all materials, tools, equipment and other
items belonging to the SUB-CONTRACTOR brought into the site. The
SUB-CONTRACTOR shall adopt the necessary measures to ensure the
security and safety of its property or materials inside the premises of the
PROJECT;
1.6 The CONTRACTOR shall not be liable to any loss or damage caused by
the use, mishandling or storage of such material, tool and equipment
belonging to the SUB-CONTRACTOR.
1.7 The CONTRACTOR shall provide electricity and water free of charge.
However unreasonable consumption based on industry practice shall be
charged to the SUBCONTRACTOR accordingly.
3. CONTRACT PERIOD.
3.1 The CONTRACT WORKS shall commence this 15th day of May 2024 and shall be
completed within a maximum period of 4 Months on or before 15 th day of August
2024.
3.3 The SUBCONTRACTOR shall not assign or sublet this contract any portion
covered by this contract without the written consent the CONTRACTOR. However,
this consent to assign or subcontract does not relieve the SUB-CONTRACTOR of
any liability or obligation under the contract.
7.1 For any changes that may vary the form, quantity and quality of any item of the
CONTRACT WORKS, the CONTRACTOR (not representative) shall issue a
WRITTEN SITE INSTRUCTION which authorizes additions and/or deductions
from the original scope covered by the CONTRACTOR WORKS. In such
eventuality, an approved VARIATION ORDER shall be issued by the
CONTRACTOR and the CONTRACT COST shall be adjusted accordingly.
7.2 No approved variation order, no work implementation or additional work policy
shall be implemented.
8. OTHER CONDITIONS
8.2 Any dispute which arises out of the CONTRACT between the CONTRACTOR
and SUBCONTRACTOR, whether the dispute arises from any action/s of those
employed by the CONTRACTOR, shall possible, be settled amicable by the
PARTIES thereto.
8.3 Cases or disputes in relation to this CONTRACT shall be filed with the appropriate
courts(s) of Cebu City.
CONTRACTOR:
By:
____________________________
MA. ALMA N. PAESTE
CEO
____________________________
CTC No./Date/Place Issue
SUBCONTRACTOR:
CES PHILIPPINES
No. 63 General Luna Str, Brgy Ususan, Taguig City
By:
____________________________
ALEXANDRIA DE SERRA
General Industries Representative
___________________________
CTC No /Date/Place Issue