Section E
• Commissioning Data
a. Measures Data
b. Measured Points
calibration certificate
GRAND HYATT MANILA Operation and Maintenance Manual of
SOUTH TOWER RESIDENCES Generator Set
In the event that abnormal vibration, oil or water leak or unusual noise are
observed when the engine is operating, load test should immediately be stopped and
corrections carried out before the other load test increments are continued.
MECHANICS: To be load tested are the 2 x 1250kVa Cummins power generating sets.
Testing proper will be done on the details below;
Load increments for EACH generator set are as follows:
GENERAL PROCEDURE:
1. Start-up the generator set. Check for any form of leak in water and oil
connections.
2. Operate the engine for 5 minutes at no load condition. Record all readings.
3. After 5 minutes has timed out, apply load to the engine about 30% of its rated
capacity by turning the knobs on the resistive load bank. Run the engine for 30
minutes. Record all readings as indicated on the load test report form.
4. After 2 hours has timed out, apply load to the engine about 50% of its rated
capacity by turning the knobs on the resistive load bank. Run the engine for 30
minutes. Record all readings as indicated on the load test report form.
5. After 2 hours has timed out, apply load to the engine about 75% of its rated
capacity by turning the knobs on the resistive load bank. Run the engine for 30
minutes. Record all readings as indicated on the load test report form.
GRAND HYATT MANILA Operation and Maintenance Manual of
SOUTH TOWER RESIDENCES Generator Set
6. After 2 hours has timed out, apply load to the engine about 100% of its rated
capacity by turning the knobs on the resistive load bank. Run the engine for 30
minutes. Record all readings as indicated on the load test report form.
7. After the full load (100%) test had been completed, remove the resistive load on
the generator set gradually until a no-load condition had been achieved. Allow the
engine to operate for about 3-5 minutes (no load) before shutting the engine off.
8. Re-check all engine and electrical parts for abnormal leaks. Perform necessary
corrections as required.
9. Disconnect all power and testing cables and re-check all mechanical and
electrical connections. Perform necessary corrections as required.
Note: After the resistive load bank test has been performed, the power
generating set has operated with load for at least two (2) hours.
Prepared by:
SAFETY: Before starting the machine, ensure that electrical power cables are secured and tightened on
all terminations, all moving parts on the fan belt area are guarded and working area is clean and free
from all debris and spillage.
In the event that abnormal vibration, oil or water leak or unusual noise are observed when the
engine is operating, test should immediately be stopped and corrections carried out before the test are
continued.
MECHANICS: To be tested are the transferring operation of 2 x 1250 kVa (1000kW) Cummins Diesel
power generating set. Testing proper will be done on the details below;
GENERAL PROCEDURE:
Prepared by: