Comissionamento Terra 54HV
C J G T Pages 5
Applicable chargers T53/T23 X X X X Version 1.2
Date 15-06-2017
Assistance 2nd line support required? No
Required tools Two pole voltage tester (e.g. Duspol) with ability to switch a 200 mA testing current.
This document includes the SAT procedure instructions to be done on-site. For this procedure, you will need the
remote support from the ABB contact person from your country.
The SAT consists of five steps, you are responsible for steps II and IV:
Step I – ABB contact person does the preparation and schedules an SAT date
Step II – Commissioning engineer performs the first checks, powers on the charger and informs the ABB contact
person the rating of the external fuse and that the charger is powered on.
Step III – ABB contact person configures initial settings and informs commissioning engineer to do the functional tests.
Step IV – Commissioning engineer does functional tests, signs document and sends it to the ABB contact person.
Step V – ABB contact person configures OCPP settings and fills in the final administrative data.
List of components:
• Front door
A Power modules (PM)
B DC bus for the power modules
C HMI (charger PC and touchscreen)
D Utility group RCBO (HMI, CCB, CPIs and PM control)
E DC charging group RCD, CCS and CHAdeMO (if present)
F Main switch
• Right door
G CCS CPI (left) and CHAdeMO CPI (right, if present)
H 24V power supply for utility group
I CCB
J Charging cable
K Power module circuit breakers
L DC charging group AC contactor
M Overvoltage protection
• Left door
N AC charging CPI (if present)
O AC charging contactor (if present)
P AC charging Circuit Breaker (if present)
Q AC charging RCD (if present)
Administrative checks
1) Fill in the charger serial number. This is located on the external side of the cabinet’s right door, beneath the charging
cables and has the format TX3-XX1-XXXX-XXX, for example T53-IT1-0123-012.
2) Check the rating of the external fuse. Power routing can be set according to the external fuse.
80
External fuse rating: A
• During the visual inspection, the main switch [F] has to be OFF.
• Verify that there are NO voltages on the grid side [E], [M] and on the DC bus [B].
5) Check if the charger cables of the CCS [J], CHAdeMO and AC outlet (if present) are mounted properly.
✘
Use force by hand.
• Check if the boards listed below are firmly mounted and properly connected by (gently) pulling the cables/wires
9) [I] CCB ✘
11) All wires and cables have a good connection and are undamaged. Pay special attention to the door earthing, ✘
to the cables on the AC contactor [L] and power module circuit breakers [K].
• First check that all RCDs are switched off: [D], [E] and [Q]
• Check the wiring from the main switch to the circuit breakers.
• It is not safe to remove the isolation covers of the main switch to measure the grid voltages.
• Switch on the main switch [F] and measure the voltages on the lower side of the RCD [E]
13) Verify that the voltages between the phases and PE and between phases and neutral are all 230VAC (±10%).
✘
This test consists of 6 measurements.
14) Verify that the voltages between the 3 phases is 400VAC (±10%). This test consists of 3 measurements. ✘
15) The utility group RCBO [D] trips when making an earth leak.
16) The DC charging group RCD [E] trips when making an earth leak.
17) Switch the RCBO [D] and the RCD [E] back on. ✘
18) Switch on all power module circuit breakers [K] (T23 has only two CBs). ✘
20) The screen displays “Out of order” when the door is open. ✘
21) The screen displays the emergency message when the emergency button
is pressed, and the message disappears when the button is released. ✘
22) The AC charging RCD [Q] trips when making an earth leak.
• Contact the ABB contact person from your country to continue with Step III. Inform that the charger is powered on,
provide the charger serial number and the external fuse rating.
Step IV *Only proceed after the ABB contact person confirms that Step III is done.
Functional Tests
CCS outlet
24) Charge session successfully started and stopped (by pressing Stop)
26) Charge session successfully started and stopped (by pressing Stop)
28) Charge session successfully started and stopped (by pressing Stop)
__________________________________
Signature
NOTE: Please send this signed form to the ABB contact person of your country.