Professional Documents
Culture Documents
Project-Management 20230607 0001
Project-Management 20230607 0001
b. calculate the expected time and variance for the other activities in the project.
$&["t]Tlsil}
^ z\2 /sY
/rs -
"':I i -(a/:1/8
u
project
b. The following table shows expected activity times and variances for the activities listed in the
descriPtion.
l5 o 1.78
B 7 B
C 5 10 15 10 2.78
D B I 16 10 1,78
OE 30 24 7.11
E 14
F 6 o 1B 10 40c
G 25 36 41 35 7.11
H
atr 40 45 40 278
10 t3 28 15 900
J 1 2 15 4 5.44
K 5 6 7 6 0,11
x)frcl$l$ru P$l$qT
The project team shoulcl notice that the greatest uncertainty lies in the time estimate for activity l,
followed by the estimates for activities E and G. These activities should be anaiyzed for the source of the
uncertainties, and actions should be taken to reduce the variance in the time estimates.
Because time estimates for activities involve uncertainty, project managers are interested in
rleterinining the probability of meeting project completion deadlines. To der,elop the probability
distributiori for project compietion time, we assume that the duration time of one activitl' docs
not depend. on t-trat-of urry oih". activity. This assumption enables us to estimate the mean and
varianie of the probabilitv distributi.on of the time duration of the entire proiect by summing the
duration times ind variances of the activities along the critical path. However, if one work crew is
assigned trn,o activities that can be done at the same time, the activity times wili be interdependent
andlhe assumption is not vaiid. In addition, if other paths in the network have small amounts
of slack, one oi them might becorne the critical path before the proiect is completed; we should
caiculate a probabitity distribution for those paths as well.
PROJECT MANAGEMENT CHAPTER 7 293
Because of the assumption that the activity duration times are independent random variables,
we can make use of the central limit theorem, which states that the sum of a group of indepen-
dent, i{enticaily distributed random variabies approaches a normal distribution as the number
of ranrlom variables increases. The meal of the normal distribution ls the surn of the expected
activity times on the path. In the case of the critical path, it is the eariiest expected finish time
for the projecl:
Similarly, because of the assumption of activity time independence, we use the sum of the
variances of the activities along the path as the variance of the time distribution for that path.
That is, for the critical path,
dr: )(Yariances of activities on the critical path)
To analyze probabilities of completing a project by a certain date using the normal distribu-
tion, we focus on the critical path and use the z-transformation formula:
T- Tz
UP
where
7: due date for the project
Given the value of z we use the Normal Distribution appendix to find the probabiiity that
the project will be completed by time f or sooner. An implicit assumption in this approach is
that no other path will 6ecome critical during the time span of the proiect. Example 7.5, part [a),
demonstrates this calculation for the St. John's Hospital proiect.
The procedure for assessing the probability of compieting any activity in a proiect by a spe-
cific date is similar to the one just discussed. However, instead of the critical path, we would use
the longest time patir of activities from the start node to the activity node in question.
A project's duration is a function of its critical path. However, paths that are close to the same
duration as the critical path may ultimately become the critical path over the life of the proiect.
In practice, at the start oi the project, managers typically do not know the activity times with
certainty and may netrer know which path was the critical path until the actual activity times are
knor,vn at the end of the proiect. Nonetheless, this uncertainty does not reduce the usefuiness of
identifying the probability of one path or another causing a project to exceed its target comple-
tion time; it heips to identify the activities that need close management attention. To assess the
chances of near-critical paths detaying the project completion, we can focus on the longest pattrs
in the project network, keeping in mind that both dulation and variance along the path must be
considered. Shorter paths witir high variances could have just as much a chance to delay the
project as longer paths with smaller variances. We can then estimate the probabiiity that a given
path will exceed the project target completion time. We demonstrate that approach using statisti-
cal analysis in Example 7.5, part (bi.
Alternatively, simulation can be used to estimate tire probabilities. The advantage of simula-
tion is that vou are not restricted to the use of the beta distribution for activity times. Also, activity
or path dependencies, such as decision points that couid invoive different groups of activities to
be undertaken, can be incorporated in a simulation model much more easily than with the sta-
tistical anaiysis approach. Fortunately, regardless of the approach used, it is rarely necessary to
evaLuate every path in the network. In iarge networks, many paths will have both short durations
and low variances, making them unlikely to affect the project duration.
72-69 3 ,-
tt I /
-
Vr r.as 3.45
294 PART 1 MANAGING PROCESSES
[1; . ']r .{ir: . ' ffh '*t-q$rl3 ffit; ;'"xilt"','}}#t;1E l' :'rr'
Uncertainty in activity times or costs can certainly create angst on the part of proiect managers,
horr.ever uircertailtl, in the project requirenents is at another 1evel. Such uncertainty arises in
product deveiopment projeits, such is software products, which have a number of function-
alities that ,rrrrt bn create-d. The project team must be agile in order to deal with unexpecteil
Scrunl changes in their assignecl activitles. Scrum is an agile project mana€ement framework that
fo".,sleu on allowing te-ams to respond rapidly, efficiently, and effectively to change' Traditional
An agile project management
framework that focuses on
project.rrurage-"rrl methods, *hi"h ou" have presented in thischapter, fix prolect lequire:nents
allowing teams to respond rapidly,
i.cope) in aJeffort to manage time and cost. the Cleveland Clinic project in Managerial Prac-
efficiently, and effectively to
il"" z.f is an example of a pioject suitable for the traditional approach. It is large and complex,
involves -u.ry *oik teams, hai requirements that are clearlv defined at the start, emphasizes the
chance.
seqrientia).ity of phur"r, and has a project manager who has overall responsibility. Scrum, how-
ever, fixes time and cost in an effort to manage requirements, which are the product's features.
The development of a software package is an exampie of a project well-suited for Scrrirn. It is
smali or *"dir* scale, involveiu r*uil team with muitiple skiils such as developer, designer,
and clatabase aclministrator, has a set of functional product requirements that are subject to
change throughout the project, has steps knortn in advance that do not have to be done in a
sequJntiai *Jnrr"., andillows the team to make decisions as to how to builri the product.
There are three roles in Scrum known as tire Scrum Team: The ScrumMaster, who iacilitates
team communication, removes obstacles to progress, and negotiates with those externai to the team;
the Produr;t Ortner, who has authoritv to make decisions about the product and prioritize its fea-
tures; a1c| the Development Team, which consists of a small multifunctional group of people rt'ho
are responsible for the delivery of the product. The Developmerrt'feam-estimates the time to accom-
plish t-he tasks, assigns owneiship oflasks, and has daily meetings called the Daily Scrum, which
iakes its name from rugby where teams form a circle and try to get the ball back into pia;r' The
Development Team is seli-organizing and chooses how it wili build the features of the pr-oduct.
TG project begins by formalizing a set of product features or product changes and putting
them in a Product Backlog in orcler of importance. The Development Team, in conjunction wlth
tlre Product Owner and ScrumMaster, selects a time box, called a sprint, tstally one to lour
weeks, and then selects product features from the Product Backlog it thinks it can complete r'r'ithin
the sprint. Daily scrums iron out problems and convey project status. At the end of the splint
the Team demoi the work it has completed to the Product Owner, selects new features from the
product Backlog along with those left unfinished from the iast sprint, and begins the next sprint.
bver the life oflhe pioject, features can be added or removed from the Product Backlog, which
emphasizes the need to have an agile approach to project management.
Choosing the best approach for a project must be done with care because each approach
comcs .n,ith iis shortcomlngs. With the traditional approach, it is hard to adapt quickly to shiit-
ing environments and requirements because problems at the operating leve I must be sen-t.r.ip
stieam to managers for resolution, making it difficult to overcome budgetary and tirneilnc
issues before they cause real harm. Ciient involvement is restricted to the early stages and an-v
changes later on causes backtracking and u.aste. A sudden change to requirements can bring
the whole proiect to a hait. Scrum, on the other hand, also has its drawbacks. The organization
must be committed to an agile management style, which may strip authority from some people'
PHOJECT MANAGEMENT CHAPTER ? 2#7
vir #E H
$"W.? $:aqtAp.$*";3ga*$
1
w:.^*.!:,-.*,,,: w@*@ww"******\*!****-*.*"******w,
3. Project costs:
Crashcostperperiod: ffi
CC-NC
NT-CT
&ssessE*g amd &ma$gr&:rg ffiisks
4. Activity time statistics
le : mearl of an activity's beta distribution
a*4m*b
6
02: ( 6 )
5. z-transformation formula
{rp
where
7: due date for the project
7s : ) (expected activity times on the critical pathl
: mean of normal distribution of critical path time
op : standard deviation of critical path time distribution
I
t
r, "".
"%fa:
uFE^"!
i -"" .- -T T-ft*
a(t^{11 --1. "
(pw"f&tr\..",,'tt} "-**.- ,,
&
, ': '(;{J- }. B s...H l$.,"".^ . ..4 fl$"
/,d
An aclvertising project manager developed the network diagram shown in Figure 7.10- for a new
advertising In addition, the manager gathered the time information for each activitv,
as shown in"u*puig..
the accompanying table.
A 1 4 7
B 2 6 7
o 6 B
C 3
D 6 13 14 A
E 3 6 12 A,C
F 6 B 16 B
\r 1 5 6 E,F
Start
$0r[,Tl0N
a. The expected time and vatiance for each activity are calculated as
follows:
a-f 4m-lb
.e Fi*uffiH 7.1S 6
I'iotv'/or( Diagiaffi ior tno
Arlvril si,ng Pro;eci Activity Expected Time (wks)
A 40 100
D
D
trE 0.69
CE 0.25
C
D 12.0 1.78
E 6,5 2.25
F 9.0 2.78
G 4.5 0.69
h. We need to calculate the earliest start, latest start, earliest finish, and latest finish times
for each actirrity. Starting with activities A and B, we proceed lrom the beginning of the
network and move to the end, calculating the earliest start and finish tirnes:
Activity
A 0 0+4.0:4.0
D
0
n r Rtr - trtr
C
EE 5,5+3.5:9.0
D 4,0 4.0+12,0:16.0
E 9.0 9,0+6,5:15.5
F 66 5.5+9,0:14.5
G I5.5 15.5+4,5:2C.0
\
Based on expected times, the earliest finish for the project is week 20, when activity G has been
compieted. Using that as a target date, we can work backward through the network, calculating
the latest start and finish times (shown graphically in Figure 7.11):
G 15.5 20.0
F 6.5 15.5
E 90 15,3
D 8.0 200
C 5.5 9.0
B 00 5.5
A 4,0 8.0
4 FIS{-'RE 7.T1
Network Diagi'am with Ail
D
Time Estimates Needed to
Compute Slack
A E
4.4 b.5
L
Start
3.5
B G
6E 4.5
9.0
l,Ve now calculate the activity slacks and determine which actirrities are on the critical path:
A 00 40 4.0 BO 4.0 No
5.5
trE 90 9.0 0.0 Yes
C
a
I 90 9.0 15 5 t5.5 0.0 Yes
F 55 65 14.5 15 5 1.0 No
tJ t5.3 Itr tr
20,0 20.0 0.0 Yes
302 PART 1 MANAGING PROCESSES
are
expected times and variances'
The paths, and' their totai
(wks)
Total Variance {;i)
Total ExPected Time
1.00+1.78:2'78
4 + 12:16
A-U
1.oo + 2.25 + 0.69
: 394
A-E-G
4+6,5+4.5:15 3.88
+ 45: 0,69 + 0.25+2,25+0.69
+ 3,5 + 6,5 2A
B-C-E-G 5.5
0.69 + 2.78 + 0.59
: 4.16
B-F-G
5,5+9+4.5:19
path B-F-G is
a total expected time
of 20 weeks' However'
is B-C-E-G' with
The critical Path
varrance'
^;.weeks and has a large
19
the z-value:
W" first calculate
T- Te 23-ZA : l.3L
Ap
- v 3.88
ol
fu'i.' e-n-c ii
close to that
UsinetheNormalDjstributionapp-endix.we[indtlrattheprobabililvofcompletingthe
Lhe
A 2 ApParel.
A
4
B
lime (daYs) lmmediate Predecessor(s)
ActivitY ActivitY
A
C 5
A 7
B
D 2 A
B
2
B
1 A
E
C
4
B,C
F 8 B,C
D
4
D D,E
G
J D
E
4
F
5
H I
F
F
4 E
G
5
7
G H,I
J
"/
Exppcrso ACTUAL
Expecreo AcTIVITy ExpEcrEo CotvrpLrloN Expecrpo % AcruN-% Cosr ro
\crrvlty cosr DuR"ATroN Srlnr Dlre DATE Covpr-ers CorrrpLrtr, Ders
Calculate the Schedule Variance. Schedule Perlormance lndex, and Cost Performance Index for
rhe project.
$s)trution
Start-up is I 00 percent conlpletc and we are beyond the expected completion date. so budgeted
:ost is $ 100,000 for this acrivirV.
Step 2: Calculate the Budgered Cosr of the Work Performed (BCWPI ro dare:
Start-up is I00 percent complere. so budgeted cost is $100.000.
Construction is actually only 90 percent complete, so budgeted cost fbr this much of the activity is
(-325.000 x 0.9) :
$292,500.
Step 3: Actual Cost (AC) of the project ro date is $105,000 + $280,000 + $2,500 : $387,500.
Step 4: Calculate perlbrmance measures:
fhe project looks good since it is both ahead ofschedule and below the budgeted cost.
,A
Excel:
1
B 4 A Ch5_Solv*d
C a
A Problems
D 7 A
E 6 B
F 2 C,D
G l trtr
H I D
I
I 4 G,H
:
l
154 OpgRartorus nxo Suppl-v CHqrr.r MaNlaeeMeNr
b. Show the early start, early finish, late start, and late finish times.
c. Show the critical path.
d. What would happen if activity F was revised to take tbur days instead of two?
I
1
0l
Critical path:
A_B_E_G_I
22 (critical path)
1.1.19'l
A-L-F-G-I 17
A-D-F-G-I 21
A-D-H-I 21
S&wED FR*BI-ER/g 3
project has been defined to contain the following activities, along with their time estimates for
,A 1 4 tl,t7.
B 2 6 A
C 3 4 t) D
D 6 12 14 A
E 3 6 12 D
6 I 16 B,C
(: I 1 5 6 trtr
a. Calculate the expected time and the variance fbr each activity.
h. Draw the critical path diagranr.
c. Show the early start, early flnish times, and late start, late finish times.
PRolecrs chapter 5 155
{1.
a*4nt*b /h-a
ACTIViTY
ExPgcrro Tttvlr _'- Acrrvnv VARIANCE
\ 6
A 4.00 1
tr trn 0.6944
,2
+ tt o.25oo
,1 .7778
D 1133
650 2:2500
: 9.00 2.7778
G 4.50 o.6944
b.
B(5.s)
0 4 9.50 28.5
33
15.33 19"50
0
1l
4 15.33
c. Shown on diagram.
d. Shown on diagram.
A.B-F-G 23
A.D.C-F-G 33 critical path
A-D.E-G 26.33
34-33 1
,-D-Tu --
'- -=0.3922
2'5495
1lz"r*- -=
up that value in Appendix E and we see,that there is about a 65 percent chance of completing
project by that date.
H
1-f,
Pno.tecrs chapter 5
$otutioul
a*4m*b b-
ACTIVITY
EXPECTED TIME _'- ActtvlTv VAHANCE
6
A 4.00 1
B 550 0.6944
C 4.17 0.2500
D I I JJ 1.7178
F 6.50 225AO
F 9.OO 2.7178
G 4.50 o.6944
b.
B(5.5)
0 4 28.5
33
15.33 19.50
0
-) -)
4 15.33 t
A.B-F-G 23 ,,:,
D:Jz 34-33 1
7_
y't +
- 2.5495
- =0.3922
,,r>oi, t .7778 + 0.25 + 2.77'78 + O.6e44
up that value in Appendix E and we see that there is about a 65 percent chance of completing
project by that date.
f
structures:
A. Pure project
B. Functional
C. Matrix Project
4.Whatisthetermforagroupofprojectactivitiesthalareassignedtoasingle
organizational unit?
5.
to
30
have
to bring in
the prol'ect.
and Cost
1S the going?
cost is the
6.
and
to be onlY
ves
To
CPM:
A 1
B A 4
c A ?
D D
E C,D 5
F D 2
G F 2
H E,G 3
A
D
/\ :I
C A 4
D A 4
E B 6
F C,D ,6
G D,F ,2
H D 3
I E,G,H 3
you traui the option of shoitening any or all oi g. C. D. and C each one week.
,TlrMEs (DAYS)
Acrwmy ,: :, :IMMEDIATE:PREDECESSoRS Q nt b
"
A 1 3 5
B 1 2 3
C A 1 2 3
D A 2 a 4
E B 3 4 11
F C,D 3 4 5
G D,E 1 4 6
H F,G 2 4 5
160 OprRartoNs lNo Supprv CHatit Mnlacrurrur
a.
h. What is the critical Path?
c. What is the expected project compietion time?
J Wtu, is ttre probabiliiy ot'completing this project within 16 dllt?--
in X weeks or
ff . if-,"." i, an 82 iercent chance the proiect below can be completed
less. What is X?
Mosr Mosr Mosr
AcrrvlrY Orruursuc LIKELY Prssrulsrtc
2, 5 11
A
3 -) 3
B
J 5
C 1
n 6 8 10
,* 4 10
E
2 3 4
1
2 ; 1 2 3
) 1 4 5 12
4 1 3 4 11
2 J 5
5 I
3 2 3
6 1
1 4 1 B 9
5,6 2 4 6
8
9 8 2 4 12
10 l a 4 5
9, 10 5 7 8
11
any,'would:you choose?
r' e. reduced;:which"action,,if
What is the probabilitv that the projecr will take more than 30
days to
following activities;
ti. a cotritruction pro3ect is broken downinto the 10
4
1
2
2 1
4
3 1
3
4 1
2, 3 5
5
o 6
1 4 2
5 3
B
6, 7 5
9
o 9 1
10
126 PART I IiI-iICDUCTioN Io oPERATIoNS N/ANAGEIVIENT
Problenrs rr*e $6'means the problem may be solved with POM for Windows and/or Excel Olr,4.
" 3.: The work breakdown structure (WBS) for building a A Buy the land None 40
house (levels i and 2) is shown below: Get the constru ction iA 30
ission
re C Excavate B 10
Erect bulld!ne c 100
Electrical work D 10
13.03.01 kfast A 2
13.03.0, Coffee
A 4
lc A 4
Problern 3.3 rel io Proieit ffiuli l..1;,...' r,11;,.
D D
6
K 4
I
None 18
A
B A 8 A 60
I 1 .2
a B 6
1.,,.,-..,..--
A 9 6.0
D D
t.-* *". *."---*-.-
4.5 B,C
C,D 5 E
E
1.7 D
F
E 4
F
4.0 E,F
G
D 10
a) Draw the project network using AON
G
H E
l' ..,,,,.1 b) IdentifY the critical Path'
wir^irl the expected project comPletion time?
)
I
G,H "i
i) il;; Gantt chart lor the Project'
s%f.
tabie are
' 3'1o The activities described by the follou"ing
3.7 l)ralv the AON project network using the following
given lor the Howard Corporation in
Kansas:
information:
o
A.
4 :
1
A a A
l:.. ''"1
lSt-: 35: a
L A
6
5 D
C
B 9
E
9
D
C 4
F
3
E EF 6
G
F C,E D
G,H 3
D 7 t
1or.I.C. Howard's
H F 3
I a) Draw t1.re appropriate AON PERT diagram
'1
5
management team'
G,H
I
b) Find the critical Path'
ffi'&f
G 1 Wflu, is the project completion time?
J
"t the followillg
, ,3,1t Draw the AON project network using
project? Which activities
How long would it take to complete this information:
are included on the critical Path?
chain
. ' 3.8 Rogel Ginde is developing a program in supply
Ginde has. listed a num-
mana-gen-rent ce]'tif:ication tbr managers' 4
belbre a training program A
fr"t.iu.tirlti.s that must be completed
immediate pre- 3
ol this nature could be conducted' The activities' B A
table:
decessors, and times appear in the accompanying C : A 6
B 2
r B 3
2
A 5
E
:F C, D
B
,1
iG E,F
C
durations
B 10 a) Draw an AON diagram olthe project' including activity
D iir chroto-
A,D 3i ti p.nr" ii,. criticalpath, listing ali criticai activities
E
logical order.
F C 6, c) W]rat is the project duration
(in weeks)?
associated with any and all non-
G E,F B
O il;; ; the sla;k (in weeks)
critical paths through the project?
l tS pAmr r nlTRCDUCitoN To optRATtoNS rvtANAGEtvrENT
B: 1 F 6
ACNVITY C 3 Lr 10
A E D 2 H l
F B
C A G C,E
t --..
1. Additionul problent 3.16 is available in f""fiVL,,,"tl:t #g:ermt!oi"rs
D A D,F
H
b.,4efia&*r'ney1t. It involves 21 activities in building the Rover'
5 auto.
''':'''':r;PffiWtl" t"g1,ffiffi:'
--, "".3.1v Ross Hopkins, president ol Hopkins Hospitality, has
developed the tasks, drirations" and predecessor relationships in
4 the lollowing table lbr building nerv motels. Draw the AON net-
work and answer the questions that tbllow.
C ,A 1
E
D B
E B 2
F C,E
A
G D 2
BA LOl4
H F,G 3
C A I 12 16
D 'A 4 6 10
a) Dr.LB' the network to represent tl-ris situation
b) lVhicir aciivities are on the critical path? E i1 3
c) lViat rs the length of the critical path? &#
E,C
F 6 8 20
G E,C 2 3 4
H F 2 2 2
.Atldirional problem 3.14 is uvaihble ilt f'"fii11..a1* *,p*ratemts
i'ii:tl,t,inltit:tt\\lr!|" It involves finding tl-re activities lor a college I F 6 6 6
dcgree.
, ',t'' r
4 6 ', 12
:K tt 2 2 :3
probrems s.1s-3.16 rerate to 0etermining the Project Schedule
a) What is the expected (estirnated) time lbr activity C?
b) What is the variance fbr activity C?
c) Based on the calculation of estimated times, what is the critical
" S.ts Dave Fletcher (see Problem 3.l2) was able to deter- path?
rnine Lhe activity times Ibr constructing iris laser scanning machine. d) What is the estimated time ol the critical path?
Fl"^tcirer v,,culd like to detelmine ES, EF, LS, LF, and siack lor e) What is the activity variance along the critical path?
*ach activitl,. T'he total project completion time and the critical f) What is the probability of completion of the project belore
path siror"rld also bc determined. Here are the activity times: week36?W
L-
T29
CHAPT:R 3 PROJECT MANAGEMENT
1_:ti
.s.tSArenovationofthegiftshop^a.t0rlalrdoAmrvay
the following estinales.of
Center has six activities (* A.utt)]por
a. nx. arrdb, calcutrate tUe expecteO
tiae and the standard devia-
tion for each activitY: h(
11 IJ 19 <
A
a1 41
B 27
18 18 18
C
e
q
8 13 19
D
16 19 22
li ;t,;,'til" t*ptttta to*frttion time"of tlre"critical ratlil
time of the other path in the
F
10 14 A,E
6
;;o;;;il;;,ia are shown in rhe following table'
2 4 A,E "*n" in 53 days?
G
is the probability of being done
1
.i ffi;41
;;;;abilitv of cornpletion?
F
H 3 6 9
b) What date results t" ;i;i'
12 G
10 11
20 C
14 16
8 10 H, I
K 2
.l "O"i..t-t. gS, Ef', r-S, LF, an<l slack for each activity' 5 8
will finish DA
;*' w;;i il. pioOarrilitv iflut r<ttte Carpet and Trim
tt.,. f rol..t in +O duYt or less?
B# E B,C 1 9
3
predecessors tbr D 2
.'" 3,2O The estirnated times and irnmediate
:
F
B
:
4 , 10 tb
M K
I 2
?
A.
g 10 11
6
o N L, IVI
b r5 11
} S$ pART 1 INTRODUCTION TO OPERATICNS IVIANAGEIV]ENT
N
\
. ,'.'3.24
Four Scluares Productions, a firm hired to coordinate a) Find the expected completion time tbr this project.
thc rslease of the movie Pirares o.f the Caribbean: Deatl Men Tell b) What variance value would be ttsed to lind probabilities of lin-
No Ttt!cs (starring Johnny Depp), identified 16 activities to be ishing by a certain time? $k'
completed Lreiore the release of the film.
- . ,9.25 Janice Eliasson must complete the activities in tl-re
lollowing table to finish her consulting project.
A 2
B 3 3.5 4
C 10 12 13 A 7 2
;
D 4 1
B 3 A
2 4 5
)
C I A
r A 6 7 8
D 4 1 B,C
G B 2 4 5 5
H a 5 1.1 9 E 5 1 B,C
C 9.9 10 12 F 8 2 E
I
4 5
J 2
G 8 D,F ]
K D 2 4 6
L E 2 4 6
H 6;2 G
\4 F,G,H 5 6 6.5
a) Draw the appropriate PERT diagram.
N J,K,L b) Find tire critical patir and project completion time.
r') l, N,4 5 c) Find the probability that the project will take more than
? N i 49 tirne periods to complete. ffiff
H 2 1
'1
3,000 5,000 2,000
A 2 8
B 9
C A 4 1 10
D B 2 5 14
C
) 3 3