DAILY CONSTRUCTION REPORT

Contract No.: JO/HC157/FE22 Date of Report (for Previous 24 hours) : 21 May 24, (Tue)
Contract Name: NEW CORE HOUSE FACILITIES BUILDING Sub-Project:
Construction Supervisor: GOWTHAM LAKSMANAN Project Engineer: RASHED AL-MULLA

EVENTS YESTERDAY
Morning Tailgate Safety Meeting Topic: Hand Tools and Power Tools
Activities:
1. Continue manual excavation for plumbing pipeline including plumbing works - In Progress
2. Continue transportation of temporary facilities materials (temporary fence materials) - In Progress
3. Continue Mobilization of portacabin offices - In Progress (4nos- Completed)
4. Start installation of kirby sheet fence - In progress
5. Mobilization and installation of toilet container - Completed
6. Electrical DB box foundation excavation and concrete pouring - Completed
EVENTS PLANNED TODAY
Morning Tailgate Safety Meeting Topic: Housekeeping
Activities:
1. Continue transportation of portacabin office and toilet portacabin.
2. Continue kirby sheet installation around the temporary perimter fence.
3. Continue plumbing works
4. Excavation for septic tank location and electrical cable trench
4. False Ceiling works and electrical works for temporary office
Offsite activities: Continue preparation works for temporary facilities requirements.
Resources Employed:
Sub- Sub-
Manpower Number Contractor Equipment Number Contractor
Contractor Contractor
1.Contractors Representative 1 1 1.Excavator
2.Project Manager 1 1 2.Backhoe Loader (JCB) 1 1
3.HSE Coordinatior 1 1 3.Telehandler (Forklift)
4.QA/QC Manager 1 1 4.Skid Loader (Bobcat)
5.QC Inspector 1 1 5.Wheel Loader
6.HSE Supervisor 6.Dump Truck (18 cu.m)
7.Civil Engineer 1 1 7.Dump Trailer (32 cu.m)
8.HVAC/Mech Engineer 8.Water Tanker
9.Electrical Engineer 9.Roller Compactor-10 Ton
10.Planning Engineer 1 1 10.Hand Steel Roller Compactor
11.Steel Structure Site Engineer 11.Jumping Compactor
12.Mandoop 1 1 12.Plate Compactor
13.Document Controller 1 1 13.Air Compressor
14.Land Surveyor 1 1 14.Concrete Vibrator
15.Civil Supervisor 1 1 15.Mechanical Concrete Floater
16.Electrical Engineer/Supervisor 16.Concrete/Asphalt Cutter
17.HVAC/Mechanical Supervisor 17.Portable Concrete Mixer
18.Carpenter 1 1 18.Welding Machine
19.Mason 19.Drilling Machine
20.Steel Fixer 20.Impact Wrenches
21.Painter 21.Torque Wrenches
22.Plumber 1 1 22.Mobile Crane 1 1
23.Electrician 23.Manlift - 22m
24.Rigger 24.Flat Bed Trailer 1 1
25.Flagman 25.Lowbed Trailer
26.Driver 1 1 26.Vacuum Tanker
27.Equipment Operator 2 2 27.Diesel Tanker
28.Fabricator-Structure 28.Big Bus- 52 Seater
29.Fitter-Structure 29.Coaster 1 1
30.Welder 1 1 30.Pick-up/Jeep
31.HVAC Technician 31.Tower Light
32.HVAC Labor 2 2 32.Portable Generator 1 1
33.Electrical Technician 33.Big Generator
34.Scaffolder 2 2 34. Survey Equipment
35.General Labor/Helper 2 2 35. Boom truck 1 1

TOTAL: 23 23 6 6

Remarks:

SAFETY INCIDENTS Description: Vehicle Injury Prop Damg Near Miss Paper Work Safety Meet

- N/A

Morning Report Signed by Construction Supervisor


PROGRESS PHOTOS

FENCE WORKS ‐ IN PROGRESS

PORTACABIN INSTALLATION ‐ IN PROGRESS