ES-1019659182-0010 New International Airport Rwanda - WTCC10 PANEL TEST REPORT - R0
ES-1019659182-0010 New International Airport Rwanda - WTCC10 PANEL TEST REPORT - R0
Client
Subcontractor Schneider
Inspection / Test Inspection Agency
Reference Documents Verification Verification Verification
Control Type: Check to Carry Out Name, Date, and Signature Name, Date, and Signature Name, Date, and Signature
4. Dielectric stiffness
Doc. Reference 1 EACSP-MNF-000000-PRC-ECIPE00-ES-R00 Point 2.6.4.
Type of Control Test
IVFabricación According to Appendix 3 100%
5. Electrical Insulation
Doc. Reference 1 EACSP-MNF-000000-PRC-ECIPE00-ES-R00 Point 2.6.5.
Type of Control Test
IVFabricación According to Appendix 3 100%
Observations
Internal
#
Inspection Points Program
Manufacturing of Electrical and Electronic Equipment
RCT I (Traceability Record I)
Project NEW RWANDA INTERNATIONAL AIRPORT SST Reference AIRPORT
Project PEP ES-1019659182-0010 Serial No. ES1019659182-0010_30
Equipment WATCH TOWER CONTROL PANEL 10
Order ETF Y1826277_ED_WTCC1 Order PPD NOT APPLY
# Internal
Inspection Points Program
Manufacturing of Electrical and Electronic Equipment
DEF/MEF of the ETF (Deviations/Modifications to the Manufacturing Technical Specifications)
Project NEW RWANDA INTERNATIONAL AIRPORT SST Reference AIRPORT
Project PEP ES-1019659182-0010 Serial No. ES1019659182-0010_30
Equipment WATCH TOWER CONTROL PANEL 10
Order ETF Y1826277_ED_WTCC1 Order PPD NOT APPLY
Appendix
Explanatory
Incident No. Details/s or Sheet(s)
Subject Solution Adopted
Red Mine
Page/s
YES/NO
ETF
Internal
#
Inspection Points Program
Manufacturing of Electrical and Electronic Equipment
DEF/MEF of the ETF (Deviations/Modifications to the Manufacturing Technical Specifications)
Project NEW RWANDA INTERNATIONAL AIRPORT SST Reference AIRPORT
Project PEP ES-1019659182-0010 Serial No. ES1019659182-0010_30
Equipment WATCH TOWER CONTROL PANEL 10
#Internal
Inspection Points Program
Manufacturing of Electrical and Electronic Equipment
DEF/MEF of the ETF (Deviations/Modifications to the Manufacturing Technical Specifications)
Project NEW RWANDA INTERNATIONAL AIRPORT SST Reference AIRPORT
Project PEP ES-1019659182-0010 Serial No. ES1019659182-0010_30
Equipment WATCH TOWER CONTROL PANEL 10
#Internal
Inspection Points Program
Manufacturing of Electrical and Electronic Equipment
DEF/MEF of the ETF (Deviations/Modifications to the Manufacturing Technical Specifications)
Project NEW RWANDA INTERNATIONAL AIRPORT SST Reference AIRPORT
Project PEP ES-1019659182-0010 Serial No. ES1019659182-0010_30
Equipment WATCH TOWER CONTROL PANEL 10
#Internal
Inspection Points Program
Manufacturing of Electrical and Electronic Equipment
PID (Availability Inspection Points of the PPD)
100%
100%
3. Verification of Communications
100%
100%
100%
Observations
Internal
#
Workshop Checklist
Manufacturing of Electrical and Electronic Equipment
CLT (Program of Verification Points)
Verification of cable entry: Position and placement of transfer plates, removable or non-
4 removable, no. of orifices, type of stuffing box, cable guide, etc...
Verification of Doors and closing mechanisms: opening and closing lever, type of lock, plan
6 holder
7 Verification of the direction and degree of openness for Doors and frame
Verification of identification and traceability, colour, finish, and position according to ETF,
8 logos and other adhesives defined in the ETF
9 Verification of Plates and/or mounting panels: arrangement of ducts, DIN rails, chassis, etc.
Verification of the item Assembly: Complete equipment according to ETF, all equipment well-
10 attached or firm (no loose pieces)
14 Verification of cabling inside ducts: there are not cables inside reserved ducts.
15 Verification of the placement of the Luminaire, door switches according to the ETF
22 Verification of Grounding for the chassis or mechanical parts of electrical equipment (F.A.)
Verification of the Numbering of terminal blocks including those with special identification
24 such as the PE (all according to the ET).
Verification of Corrugated Tubes: When opening and closing they do not rub against the
25 metal parts, the length is correct without forcing cables, etc.
Internal
#
Workshop Checklist
Manufacturing of Electrical and Electronic Equipment
CLT (Program of Verification Points)
Internal
#
Workshop Checklist
Manufacturing of Electrical and Electronic Equipment
CLT (Program of Verification Points)
Verification of supply cables for main equipment (cable size and colour, correct connection to
27 equipment according to ETF, etc...)
Verification of photographic report (photos with door closed of all the sizes, photo of serial no.
28 top-down photos of cabinet devices etc...)
Verification that there are enough cables, no tension nor paths that damage the cabling
29
(especially when there is F.O.)
30 Verification that there are no points or conductive parts exposed to the air
Verification of the possibility of access and re-cabling of devices with a difficult mechanical
32
position in the cabinet.
Verification of cabinets with Rack 19" of attachment for equipment with a large depth, tie, or
33
attachment on the back without the possibility of vibration or breakage during transport.
34 Verification that there are not three or more cables on any device electrical connection
36 Verification of the place of fuses in the case of block terminals with fuse or fuse holder N.A.
Verification of power strip bridge according to ETF and/or special terminal blocks such as
37
disconnect, fuse holder, with diode etc.
Verification of the moveable parts in the cabinet (removable trays, articulated arms,
41
corrugated tubes, doors, etc...)
42 Verification of Quality Documentation (in RCT correct Project Name, PEP, etc...)
44
45
Internal
#
Workshop Checklist
Manufacturing of Electrical and Electronic Equipment
CLT (Program of Verification Points)
Internal
#
Workshop Checklist
Manufacturing of Electrical and Electronic Equipment
CLT (Program of Verification Points)
47
48
63
64
65
Internal
#
Workshop Checklist
Manufacturing of Electrical and Electronic Equipment
CLT (Program of Verification Points)
Name, Date, and Signature Name, Date, and Signature Name, Date, and Signature
Internal
#
Workshop Checklist
Manufacturing of Electrical and Electronic Equipment
CLT (Program of Verification Points)
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
Internal
#
Workshop Checklist
Manufacturing of Electrical and Electronic Equipment
CLT (Program of Verification Points)
Internal
#