Dot 5 Pvt Ltd

Sanitary Pipe Fitings


Project Name : Bunglow

Materials Cost
S.L Items name QTY Unit Rate Total
1 4'' UPVC DOOR TREE 10 PCS 148.52 1,485.20
2 4'' UPVC LONG TRAP 20 PCS 189.60 3,792.00
3 4'' UPVC PLAIN TREE 8 PCS 116.92 935.36
4 4'' UPVC PLAN BOARD 25 PCS 82.95 2,073.75
5 4'' UPVC DOOR BAND 6 PCS 114.55 687.30
6 2'' UPVC BAND 14 PCS 19.75 276.50
7 2'' UPVC Y TEE 5 PCS 45.03 225.15
8 2'' UPVC 45G BAND 5 PCS 53.72 268.60
9 4'' UPVC CLAMP 30 PCS 60.83 1,824.90
10 2'' UPVC CLAMP 15 PCS 48.19 722.85
11 1'' CPVC PIPE SDR-11 (NPOLY) (1 pcs = 3mtr = 10ft) 33 PCS 653.20 21,555.60
12 3/4'' CPVC PIPE SDR-11 (NPOLY) (1 pcs = 3mtr = 10ft) 66 PCS 447.30 29,521.80
13 110MM (4'') UPVC PIPE WT-3.4mm (1 pcs = 6mtr = 20ft) 18 PCS 1,185.00 21,330.00
14 50MM (2'') UPVC PIPE WT-2.4mm (1 pcs = 3mtr = 10ft) 15 PCS 235.42 3,531.30
15 Solvent Cement (Npoly 500ml) 5 PCS 250.00 1,250.00
16 4'' UPVC DOOR TREE 10 PCS 148.52 1,485.20
17 4'' UPVC LONG TRAP 20 PCS 189.60 3,792.00
18 4'' UPVC PLAIN TREE 8 PCS 116.92 935.36
19 4'' UPVC PLAN BOARD 25 PCS 82.95 2,073.75
20 4'' UPVC DOOR BAND 6 PCS 114.55 687.30
21 2'' UPVC BAND 14 PCS 19.75 276.50
22 2'' UPVC Y TEE 5 PCS 45.03 225.15
23 2'' UPVC 45G BAND 5 PCS 53.72 268.60
24 4'' UPVC CLAMP 30 PCS 60.83 1,824.90
25 2'' UPVC CLAMP 15 PCS 48.19 722.85
26 1'' CPVC TEE (ASTRAL_SDR-11) 5 PCS 76.72 383.60
27 3/4'' CPVC TEE (ASTRAL_SDR-11) 75 PCS 48.72 3,654.00
28 2x1 CPVC TEE (ASTRAL_SDR-11) 6 PCS 465.92 2,795.52
29 2'' CPVC END CAP (ASTRAL_SDR-11) 2 PCS 137.20 274.40
30 1'' CPVC END CAP (ASTRAL_SDR-11) 10 PCS 25.20 252.00
31 3/4'' CPVC END CAP (ASTRAL_SDR-11) 12 PCS 16.80 201.60
32 1'' CPVC ELBOW (ASTRAL_SDR-11) 38 PCS 59.36 2,255.68
33 3/4'' CPVC ELBOW (ASTRAL_SDR-11) 150 PCS 36.40 5,460.00
34 1x3/4'' CPVC BOUSH (ASTRAL_SDR-11) 20 PCS 19.60 392.00
35 1'' CPVC BOLL BALVE (ASTRAL_SDR-11) 15 PCS 647.36 9,710.40
36 1'' CPVC SOCKET (ASTRAL_SDR-11) 33 PCS 38.64 1,275.12
37 3/4'' CPVC SOCKET (ASTRAL_SDR-11) 40 PCS 24.08 963.20
38 1/2'' CPVC PLAG (ASTRAL_SDR-11) 90 PCS 6.72 604.80
39 1x3/4'' CPVC TEE (ASTRAL_SDR-11) 5 PCS 98.00 490.00
40 3''/4''x1''/2'' CPVC FIMEL ELBOW (ASTRAL_SDR-11) 90 PCS 88.48 7,963.20
41 CPVC SOLVENT CEMENT (473ml) 8 PCS 1,486.24 11,889.92
42 CPVC SOLVENT CEMENT (237ml) 2 PCS 796.88 1,593.76
43 1'' CPVC TEE (ASTRAL_SDR-11) 20 PCS 76.72 1,534.40
44 3/4'' CPVC PLAIN TEE (ASTRAL_SDR-11) 80 PCS 48.72 3,897.60
45 3/4'' CPVC FEMALE TEE (ASTRAL_SDR-11) 45 PCS 158.48 7,131.60
46 1x3/4'' CPVC PLAIN TEE (ASTRAL_SDR-11) 80 PCS 98.00 7,840.00
47 3/4''x1/2'' CPVC FIMEL TEE (ASTRAL_SDR-11) 40 PCS 106.96 4,278.40
48 THREAT TAPE 5 PCS 13.44 67.20
49 1’’ CPVC ELBOW 90 DEGREE (ASTRAL_SDR-11) 70 PCS 58.30 4,081.00
50 1’’ CPVC TEE (ASTRAL_SDR-11) 20 PCS 75.35 1,507.00
51 1’’ CPVC SOCKET (ASTRAL_SDR-11) 20 PCS 37.95 759.00
52 1’’ CPVC CLIP CAP (ASTRAL_SDR-11) 50 PCS 24.75 1,237.50
53 2’’ KAWYAL CAP 5 PCS 29.00 145.00
54 CPVC ADHESIVE 473ml 4 PCS 2,654.00 10,616.00
55 4'' CPVC PIPE 20 PCS 1,190.00 23,800.00
56 4’’ BACK DOOR TEE 10 PCS 148.52 1,485.20
57 4’’x2’’ Y TEE 20 PCS 124.03 2,480.60
58 2’’ Y TEE 10 PCS 45.03 450.30
59 2’’ PLAIN BEND 45 DEGREE 10 PCS 53.72 537.20
60 4’’ OF SET 10 PCS 142.20 1,422.00
61 4’’ LOSE SOCKET 5 PCS 49.77 248.85
62 4’’ KAWYAL CAP (Vent Cowl) 10 PCS 31.60 316.00
Sub Total 225,765.97
carrying & Transport charge (Two time) 25,000.00
Total amount 250,765.97

Hot water return Line And Toilet fitting fixing Wages

Date items name QTY Unit Rate Total


1 Hot water return Line 1 Job 62500 62,500.00
2 Per toilet fitting fixing and accessory all complete work 10 pcs 14000 140,000.00
Total 202,500.00