COMPLIANCE QUESTION BANK

Emergency
QB30 Planning

No Question Y/N State where this is documented (Detailed location


reference required or evidence attached to the form)
Other comments
ADR.OPS.B.005(a)
1 Is the aerodrome emergency plan
Yes
commensurate with the type and level
No
of aircraft operations at the aerodrome?
ADR.OPS.B.005(a)
Is the aerodrome emergency plan
2 commensurate with other activities Yes
conducted at the aerodrome? No
ADR.OPS.B.005(b)
Does the aerodrome emergency plan
provide for the coordination of
Yes
3 appropriate organisations in response to
emergencies that may occur at the No
aerodrome or in its surroundings?
ADR.OPS.B.005(c)
Does the aerodrome emergency plan
contain procedures for periodic testing Yes
4
of the adequacy of the emergency plan No
and for reviewing the results?
Aerodrome Emergency Planning - General
AMC1 ADR.OPS.B.005(b); (a)
Where an aerodrome is close to
water/swampy areas and a significant Yes
proportion of approach or departures No
takes place over these areas, does the
5 emergency plan include:
• the ready availability of specialist
rescue services for these areas?
• coordination of specialist rescue
services for these areas?

[QB30 Emergency Planning: Ver 1/2017]


COMPLIANCE QUESTION BANK

Emergency
QB30 Planning

AMC1 ADR.OPS.B.005(b); (b)

Has an assessment of the areas within


6 1000m of each runway threshold been Yes
carried out? No
AMC1 ADR.OPS.B.005(b); (b)

Has the (1000m) assessment identified Yes


7 options available for intervention? No

Emergency Planning Document


AMC2 ADR.OPS.B.005(b);(a)

Does the EPD contain details of the Yes


8
types of emergencies planned for? No
AMC2 ADR.OPS.B.005(b);(b)

Does the EPD include details of the


9 agencies involved in the emergency
plan?
AMC2 ADR.OPS.B.005(b);(b)

Does the EPD include details of local


10 area emergency planning arrangements Yes
and forums? No
AMC2 ADR.OPS.B.005(b);(c)
Does the EPD include details of the role
11 and responsibility of each of the Yes
agencies included in the plan? No

[QB30 Emergency Planning: Ver 1/2017]


COMPLIANCE QUESTION BANK

Emergency
QB30 Planning

AMC2 ADR.OPS.B.005(b);(c)
Does the EPD include details of the role
12 and responsibility of the emergency Yes
operations centre? No
AMC2 ADR.OPS.B.005(b);(c)
Does the EPD include details of the role
13 and responsibility of the command post Yes
for each type of emergency? No
AMC2 ADR.OPS.B.005(b);(d)
Does the EPD include information
(names and telephone numbers) of Yes
14
people or offices to be contacted for a No
particular emergency?
AMC2 ADR.OPS.B.005(b);(e)

Does the EPD include a grid map of the


15 aerodrome and its immediate
surroundings?
Emergency Exercise – Section Relevant to Aerodromes following AMC1 ADR.OPS.B.005(c)
AMC1 ADR.OPS.B.005(c);(a)

Is the aerodrome emergency plan tested


16 with a full scale exercise at intervals not Yes
exceeding 2 years?
No
AMC1 ADR.OPS.B.005(c);(b)

Is the emergency plan tested by carrying


17 out a partial emergency exercise in the
Yes
intervening year?
No
AMC1 ADR.OPS.B.005(c);(b)
Is the partial exercise designed to test
deficiencies identified during the full- Yes
18
scale exercise to ensure they have been No
corrected?

[QB30 Emergency Planning: Ver 1/2017]


COMPLIANCE QUESTION BANK

Emergency
QB30 Planning

AMC1 ADR.OPS.B.005(c)
Following the full-scale and partial
exercises, is the aerodrome emergency Yes
19
plan reviewed so as to correct any No
deficiencies identified?
AMC1 ADR.OPS.B.005(c)

Following an actual emergency, is the


20 aerodrome emergency plan reviewed so Yes
as to correct any deficiencies identified? No
Emergency Exercise – Section Relevant to Aerodromes following UK AltMoC1 ADR.OPS.B.005(c)
UK-AltMoc 1 ADR.OPS.B.005(c);(1)

Is the aerodrome emergency plan tested


21 by carrying out a series of modular Yes
tests? No
UK-AltMoc 1 ADR.OPS.B.005(c);(1)

Does the series of modular tests


22 conclude with a full-scale test at Yes
intervals not exceeding 4 years? No
UK-AltMoc 1 ADR.OPS.B.005(c);(2)

Following the full-scale exercise, is the


23 aerodrome emergency plan reviewed so Yes
as to correct any deficiencies identified? No
UK-AltMoc 1 ADR.OPS.B.005(c);(2)

Following an actual emergency, is the


24 aerodrome emergency plan reviewed so Yes
as to correct any deficiencies identified? No
Removal of Disabled Aircraft
AMC3 ADR.OR.E.005(a) Part D (6.11)
Have the contact details of the
aerodrome coordinator for the removal Yes
25
of disabled aircraft been reported to the No
AIS?

[QB30 Emergency Planning: Ver 1/2017]


COMPLIANCE QUESTION BANK

Emergency
QB30 Planning

AMC3 ADR.OR.E.005(a) Part D (6.11)


Has information about the capability to
remove disabled aircraft (expressed in Yes
26
terms of the largest aircraft type) been No
reported to AIS?
AMC3 ADR.OR.E.005(a) Part E (21)

Have details of the plans for the removal


27 of disabled aircraft been included in the Yes
aerodrome manual? No