IQ PW V03 Gedeon Richter - IQ - PW
IQ PW V03 Gedeon Richter - IQ - PW
120501-IQ-PW
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Reviewed by
Approved by
Approved by
Checked by
Reviewed by
Approved by
Approved by
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 1 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Contents
1 Document Control 3
1.1 Revision History 3
1.2 Guidelines 3
1.3 List of used documentation 3
2 Purpose / Scope 4
3 Equipment / System Description 5
4 Installation Qualification (IQ) Execution 6
4.1 Requirements 6
4.2 Installation Qualification (IQ) Procedure 6
4.3 Working with documents 6
4.4 Completion of qualification / Approval of the documentation 6
5 Installation Qualification (IQ) Participants 7
6 List of Measuring Instruments Used in IQ 8
7 Installation Qualification Control Sheets 9
7.1 IQ-1. Documentation 9
7.2 IQ-2. System Technical Characteristics 13
7.3 IQ-3. Instrumentation 18
7.4 IQ-4. Utilities 31
7.5 IQ-5. System Compliance to GMP Requirements 33
7.6 IQ-6. Control System 39
7.7 IQ-7. Calibration 41
8 Annexes 44
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 2 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
1 Document Control
1.2 Guidelines
1. EC GMP Guide, Volume 4 - Guidelines for good manufacturing practices for medicinal products for human
and veterinary use, incl. all Annexes (February 2010).
2. GOST R 52249-2009 Good Manufacturing Practice for Medicinal Products, incl. all Annexes.
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 3 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
2 Purpose / Scope
The aim of production facilities and processes qualification and validation in pharmaceutical plants is to establish and
provide documented evidence that:
the facilities, equipment and processes have been designed in accordance with the requirements of cGMP.
the facilities and equipment have been built and installed in compliance with their specifications.
the facilities and equipment operate in accordance with their specifications to repeatedly and reliably
manufacture products of the predetermined quality.
During Installation Qualification (IQ) an inventory is made for the equipment delivered and installed at the customer’s
site, in particular the following points are checked:
check, if types/serial numbers (e.g. information on factory plate) and labeling of equipment comply to the
specification,
check, if all parts of the equipment are delivered from the supplier without damage, their type complies to
specification and all parts of the equipment are installed correctly,
check correct connection to all necessary utilities and energy supply lines;
check the unambiguous identification (labeling etc.) of all separate parts of the equipment (valves, sensors,
control devices, etc.),
During IQ the equipment does not need to be turned on, therefore IQ is possible to perform also in the absence of
supply of utilities and energy.
Installation Qualification refers to units and components of the system which are capable do influence directly or
indirectly on quality and safety of the product which is defined by GMP guidelines and already performed GMP Risk
Analysis. All other units and components of the system will not be tested in the course of current IQ tests.
The Protocol includes general description of Installation Qualification (IQ) steps, list of participants, checklists for
separate IQ tests and fields for recording the test results, list of deviations and Installation Qualification Summary
which represents successful implementation of Installation Qualification. The cover page includes a table of approval
of Installation Qualification Protocol (the upper table) and a table of approval of Installation Qualification Report (the
lower table).
Copies of documentary evidence (certificates, etc.) are attached to the Protocol or reference is given to their storage
place.
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 4 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 5 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
4.1 Requirements
Before execution of Installation Qualification (IQ) the following requirements should be fulfilled:
Design Qualification (DQ) has been successfully performed by checking system specifications against URS
and requirements identified during Risk Analysis (RA).
Installation Qualification Protocol is checked and approved by authorized participants, table of approval of
Installation Qualification Protocol (the upper fields with signatures) on the cover page is filled in.
All the documents listed in 1.3 are present.
At least two of participants taking part in Installation Qualification are present.
During Installation Qualification equipment is checked step by step in accordance with the procedure described in the
corresponding control sheets. The results of each test and comments are filled in the corresponding control sheet.
If any deviation is detected it should be described exhaustively but briefly in the field for comments on the control
sheet. These deviations are also recorded in the separate List of Deviations that is attached to this Protocol as Annex
1.
The data inserted into any control sheet or any field should be confirmed with the signature and date. The data should
be filled in using ball pen of blue or purple color.
Use of eraser or correction fluid is forbidden. Any corrections are made by striking the old record out and creating a
new record next to the old one. At the same time deleted record should remain readable. Each correction should be
accompanied by the signature of the person who did the correction and the date.
Any changes in formulation of acceptance criteria or instructions how to perform testing are not acceptable since the
moment the Protocol was approved for execution.
When all tests are completed Installation Qualification Summary is filled in where the success of Installation
Qualification is evaluated. . Operational Qualification Summary is attached to this protocol as Annex 2.
Installation Qualification is considered as successful if all acceptance criteria in all control sheet are met, or all
detected deviations are eliminated (or declared to be inessential, which should be substantiated by quality assurance
commission).
Final settlement of any nonstandard situations or deviations related to Installation Qualification, and also approval of
the IQ Protocol and IQ Report should be performed by the Leader of Validation Team of the enterprise, whose
functions could be done by different participating top managers, typically Quality Assurance Department Manager.
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 6 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
2.
3.
4.
5.
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 7 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 8 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Acceptance criteria:
Presence of all documentation listed in the table below.
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 9 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:................................................................................. Signature:........................................................................
Date:......................................................................................... Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 10 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:................................................................................. Signature:........................................................................
Date:......................................................................................... Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 11 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:................................................................................. Signature:........................................................................
Date:......................................................................................... Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 12 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Method:
Equipment inventory according to the table below.
Acceptance criteria:
Conformity of all characteristics of equipment to those listed in the table below:
- Type of equipment
- Identification data
- Main technical characteristics
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 13 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:................................................................................. Signature:........................................................................
Date:......................................................................................... Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 14 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:................................................................................. Signature:........................................................................
Date:......................................................................................... Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 15 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:................................................................................. Signature:........................................................................
Date:......................................................................................... Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 16 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:................................................................................. Signature:........................................................................
Date:......................................................................................... Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 17 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Method:
Inventory of actually installed equipment according to P&ID and component list.
The check is performed for Purified Water (PW) generation, storage and distribution system.
Acceptance criteria:
AC1: Installation is done according to P&ID.
AC2: Type of the component conforms to the specification (component list).
AC3: Proper quality of installation and absence of any visible damage.
AC4: Presence, correctness and readability of component’s labeling - labeling is in easy accessible place, resistant
towards working environment, all the components have unique identifiers.
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 18 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 19 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
3.2.8
PI-2758 Manometer
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 20 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
3.3.8
CV-2753 Check valve
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 21 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 22 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
3.5.8 Conductivity
AE-2710
sensor
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 23 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
3.6.8 Diaphragm
V1.212
pneumatic valve
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 24 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 25 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 26 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 27 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
3.10.7 Manual
SP-2704 Diaphragm
sample valve
3.10.8 Diaphragm
XV-2708
pneumatic valve
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 28 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
3.11.7
TY2751 3-way valve
3.11.8
HV-2752 Ball Valve
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 29 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
3.12.7
HV-2758 Ball Valve
3.12.8
XV-2771 Ball Valve
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 30 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Method:
Check of presence and connection of each line of supply of technological media and power supply listed in the table
below according to P&ID and specifications.
Acceptance criteria:
All connections according to P&ID and specifications are present.
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 31 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 32 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Acceptance criteria:
Described in test points in the table below.
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 33 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 34 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 35 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 36 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 37 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 38 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Method:
Check for compliance with the specification of labeling and accompanying documents for hardware.
Inventory of hardware and software documentation, installed software version control.
Acceptance criteria:
Listed in the table below.
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 39 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 40 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Acceptance criteria:
Listed in the table below.
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 41 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 42 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
Signature:.................................................................................
Signature:........................................................................
Date:.........................................................................................
Date:................................................................................
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 43 of 44
GEDEON RICHTER RUS
Quality Assurance System
Installation Qualification (IQ)
Purified Water (PW)
Generation, Storage and Distribution system
Project No.: 120501 Date: 05.12.2013 Version: V03
8 Annexes
No. Description Pages Version Date
1. List of Deviations
Prepared by: ah
Checked by: al 120501-IQ-PW-V03_GEDEON-RICHTER_RUS_IQ_PW_05122013 Page 44 of 44