Big Ticket Projects

Project Cost Status


USD Million INR Cr
Physical Progress 32%
Integrated Hospitality & Sports Complex, 13.86 125.00 Financial Progress 23%
Shillong Stage of Work:
In Multipurpose Sports Hall
1. Ground Floor (5500sqm) Grade slab casting 100% completed
2. First Floor (1705sqm) Slabs and beams concrete casting 95% completed
3. Second Floor (4300sqm) Slab and beams 50% completed
In Serviceable Block
1. Foundation work in progress of completed 70%
2. Plinth Beam casting 40% completed
3. Ground floor grade slab 20% completed

Physical Progress 17%


Integrated Hospitality& Convention 6.08 56.20 Financial Progress 2.67%
Stage of Work
Centre, Tura 1. Foundation

Shillong Peak Ropeway Project 18.37


Physical Progress 69%
Tura Town Internal Road 5.66 51.10 Financial Progress 65%
Stage of Work:
1.

Physical Progress 90%


Jowai Nartiang Kdiap Khanduli Road 6.13 55.27 Financial Progress 88.89
Stage of Work:
Reconstruction of Guard Wall and installation of Traffic signage

Physical Progress 25%


Revamping of Orchid Lake Resort 17.83 Financial Progress 0.26
Stage of Work:
1. Mock Up rooms for VIP and VVIP suite about 78% completed

Physical Progress 15%


Kudengrim Kudengthymmai Road project 15.97 Financial Progress 0%
Stage of Work:
1. CD works in progress
2. Road Widening in progress