AHU TFA Check List & Air Balancing Sheet
AHU TFA Check List & Air Balancing Sheet
AHU TFA Check List & Air Balancing Sheet
Project name:
AHU/TFA Tag Name:
Sl No. Check Points
1 AHU Floor plans, schematic & Technical Data sheet approved from Daikin
2 AHU Control Kit installed as per installation manual
3 AHU Control Kit Wiring's continuity checked
4 Capacity setting adapter of AHU Control kit connected properly
5 Control Kit F1 & F2 terminal are looped with ODU's.
6 AHU Starter's panel Auxillary contactor integrate with Control box C1 & C2 Terminal
7 AHU Starter's panel Auxillary contactor integrate with limit switch & marine light
8 AHU's control box covered for weather protection
9 VFD's frequency set corrosponding to desired Airflow
10 If VAVs in system, Are they calibrated
11 Liquid, Gas & Return Air thermistor installed as per installation manual.
12 Ductwork intact and properly sealed.
13 Ductwork leak tested.
14 Access doors installed and properly secured.
15 Ductwork installed according to the drawings and specification.
16 Ductwork free from debris.
17 Dampers, including fire and smoke dampers, installed and accessible.
18 Terminal boxes, reheat coils, electrical reheat, etc. installed, functional and accessible.
19 All other air distribution devices such as diffusers, etc., installed and functional.
20 Return air has an unobstructed path from each conditioned space back to the unit.
21 Filters clean and correctly installed.
22 Filter frame properly installed and sealed.
23 Coils cleaned and properly installed.
24 Drive components properly installed.
25 Pulleys properly aligned and tight on their shafts.
26 Belts adjusted for the correct tension.
27 Fan dampers functional.
28 Flexible connections installed properly.
29 Fan bearings lubricated
30 Fan Rotation checked
ATION CHECK LIST
Date:
Yes No Remarks
AHU/TFA AIR BALANCING AT SUPPLY AIR COLLAR / RETURN A
S.No. Location Item CFM Collar Design Airflow Reading
Unit Capacity:
Air Quantity at Return Air Filter:
Average Reading
X Filter Area
Actual Air Quantity at Filter
Date / Time :
Quantity
Quantity
Quantity
X Filter Area
AIR HANDLING EQUIPMENT AIR BALANCING REPORT
PROJECT: - CAPACITY: -
Date
Location :
AHU/TFA Tag Number
Fan RPM
Voltage
R R
Y Y
Motor Current in Amps
B B