Vivek Abhyankar

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

(Part I: Underground Metro Rail Projects)

Introduction to Enabling Works (Temporary


Structures) in Metro Rail Projects

Metro construction works are spread all over India. Apart from the design of permanent works there are several
enabling/temporary structures required during construction of permanent works. Often these temporary works are
not taught in school/colleges, and since temporary works are not paid for separately to the contractor, there is a
lot of cutting corners and negligence towards such temporary works. Er. Swaroop Maiti and Er. Vivek Abhyankar
discuss the various types of temporary works used in the underground metro construction projects and in elevated
metro projects, and also address queries by both budding and senior engineers.

Introduction utilities, limited working hours, safety safety, (1.6) CFD analysis, acoustic study
requirements etc. Metro projects are and other higher researches (as per the
Construction of metro rail projects is in
broadly classified as (a) elevated works (b) requirements in individual projects).
full speed across India’s urban areas.
underground works and (c) ramp portions Each of these disciplines have their own set
Delhi, Mumbai, Kolkata, Hyderabad,
which connect elevated stretch of metro to of requirements / expertise and complexities.
Ahmedabad, Surat, Kanpur, Nagpur,
an underground stretch. Each of these has In this paper, the authors have elaborated
Lucknow, Pune, Patna cities are leading
its own set of requirements and challenges mainly on Temporary Structures (also called
the construction of Metro rail connectivity.
and involve three main disciplines: enabling works). The paper is divided into
As compared to the railways, the Metro
Design, Construction, Operations and two parts: temporary works in underground
rail is faster and more flexible, and when
Maintenance. The design discipline has projects (including the ramp portions) and
compared to road traffic, it is hinderance
further sub-disciplines such as (1.1) temporary works in elevated metro projects.
free. Due to the advantages of metro rails
Architecture, (1.2) Structural design
in increasing urbanization, India has made Underground metro projects involve mainly
(1.2.a – design of permanent works, 1.2.b
significant investment in this sector during three types of structures: (a) bored tunnel
– design of temporary structures, 1.2.c –
the past ten years. tubes (b) station buildings (c) ancillary
geotechnical), (1.3) Mechanical – Electrical
The design and construction of metro works buildings and access underpass. The
– piping / plumbing (MEP), HVAC,
is highly challenging in city areas where temporary works required for these are
signaling, drainage, lighting, (1.4) building
there is a lot of congestion, underground listed below and described briefly.
information models (BIM), (1.5) Fire and

2 NBM&CW APRIL 2024


A. Temporary works involved in i. Gantry arrangement for lowering of wall, depend on the type of soil strata
construction of diaphragm walls & stations: TBM, handling of precast Segment, (loose / medium / dense / stiff etc.) and
a. Guide walls & Stop Ends. removal of muck. the depth of proposed wall and weight of
j. Crane foundation for lowering of TBM in rigging equipment. Before commencing the
b. Rebar Cage Lifters.
Launching Shaft. excavation in soil, surveyor shall ensure
c. Shoring works (in bottom-up type correctness on the coordinates of guide
construction) – steel Walers, supporting C. Temporary works involved for Tunnel
walls. After installation of D’wall is over,
brackets, insert plates and struts (active Lining rings / pre-casting:
the guide wall can be broken / dismantled.
/ passive), temporary king posts / a. Casting yard & stacking yard sheds with For design of guide-walls the long-term
stanchions. EOT cranes. and serviceability checks (like crack-width,
d. Temporary steel decking to facilitate b. Segment casting molds with steam shrinkage, creep etc.) are not applicable
surface vehicles movements. curing facility. due to short life and temporary nature.
e. Box pushing technique for subways (if c. Segment tilting device. Stop Ends: (Fig.2) Longitudinal ends of
applicable). d. EOT Goliath cranes. two adjoining D’walls panels are connected
f. Plunge columns and barrettes (in top- using a grove shaped geometry, which also
e. Steel sheds for office / workshop / testing
down method) – this forms an integral supports the water bar; this grove / or even
labs.
part of the final structure. a projection is facilitated using steel beam
f. Concrete Batching and crushing plants.
placed on the extreme edges of primary
g. Temporary bridges for crossing utility
Each of the above items are briefly panels are called as stop ends. In case of
lines / mast supports etc.
explained below: diaphragm walls with greater depths, the
B. Temporary works involved for TBM:
Guide walls: (Fig.1) As the name stop ends are even provided with spice
a. Temporary thrust frames for Tunnel suggests, guide walls are temporary connection to optimize the lifting weight.
Boring Machine (TBM). concrete blocks / walls / structures The stripping time for stop ends matter
b. Steel cradle to support TBM shield. constructed on either side of the D’wall, a lot, which ranges from 8hrs to 10hrs;
longitudinally, to predefine the footprints otherwise, the steel plates of stop ends may
c. Temporary rails and walkway inside
of the proposed diaphragm walls with get firmly stuck to the hardened concrete.
tunnel lining to support the muck carrying
some construction tolerance (Thickness of Bottom ends of each stop end unit may
wagons.
D-wall +50mm say 50mm) to facilitate the be tapered / chamfered. The width of stop
d. Eye seal & temporary slurry piles at
digging rig to enter the soil inside. Rarely end is kept 5mm lesser than the width of
head wall.
do contractors construct guide walls using wall to facilitate easy removal (i.e. say if
e. Intervention Shaft for the TBM. steel plate units; such walls are reusable the thickness / width of wall is 600mm then
f. Muck bin, muck removing carts / chariot, but their sturdiness has to be ensured with the width of the stop end is kept 595mm or
muck bucket tilting device. proper design and detailing. The distance so). Steel stop ends are reusable; however
g. Temporary Ring support during cutting between two opposite face guide-wall now a days sacrificial precast concrete stop
of Segment for Cross – Passage units is maintained (equal to thickness ends are also used in a few projects.
construction. of proposed wall + tolerance, say 50mm (L) freshly fabricated stop end units, (M)
or so) using temporary wooden props workers placing water stopper and applying
h. NATM / lining in cross passages
or tailormade steel frames. Thickness, lubricant / de-bonding agent to exposed
between two tunnel tube lines (upward
depth and reinforcement in the guide- surfaces, (R) chamfered bottom edge of
and downward lines).

(left) placing rebar and formwork, (middle) poring concrete, (right) completed guide wall
Figure 1: Guide wall construction

NBM&CW APRIL 2024 3


(left) freshly fabricated stop end units (middle) workers placing water stopper and applying lubricant / de-bonding agent to exposed surfaces
(right) chamfered bottom edge of stop end

(left & middle) Precast concrete sacrificial stop end (right) Typical spliced connection in stop ends.
Figure 2: Stop Ends for Diaphragm walls

stop end (Left & Middle) Precast concrete engineer. For long length cage the bars For struts having longer length intermediate
sacrificial stop end (Right) Typical spliced are connected using laps / couplers. The steel column support may be given using
connection in stop ends. final assembled cage is inspected by the kingpost to avoid sagging under self-
clients (GEC) and after certification lifted weight and to maintain the effectiveness
using cranes as shown in the photo of of this struts. In some cases, the struts are
right hand. To avoid the localized bending applied with a pre-compression using jacks
buckling of individual rebars a steel lifter / or wedges – these are called active struts
spreader beam / strong-back, is given at (else if preload is not applied then called as
the top of the cage to which the wire ropes passive struts). Struts may be formed from
are connected at bottom and at top to the - rolled joists / built-up truss / or simply steel
crane hook. Capacity of each lifter beam liner pipes.
shall be properly designed and detailed; In certain open excavations to facilitate
also to be marked with paint on respective equipment movements the open struts
lifter beam/s. may cause hindrance and hence are not
Shoring works (in bottom-up type permitted; in such case prestressed soil
construction), steel walers, supporting anchors are used at certain spacing to hold
brackets, insert plates and struts (active / the waler beams in position.
passive), temporary king posts / stanchions In certain cases, the opposite side walls is
(Fig. 3): Steel shoring is required to keep located far away (which would lead too long
the D’wall / soldier pile wall in proper length of a strut); in such cases inclined
position against the lateral soil load at struts inside excavated pit are given (shown
Rebar Cage Lifters: The steel rebar
the back of the wall. Accidental loads and ahead in the photo). At walls bending
cages are fabricated in the yard by the
additional stresses due to temperature 90degree inward, the diagonal struts are
seasoned iron workers under guidance of
changes shall be carefully considered preferable. To increase the effectiveness of
experienced foremen / supervisor / shift
while designing and detailing the struts. struts and to shorten its effective length in

4 NBM&CW APRIL 2024


(left) waler – strut junction, (middle) typical section of trench, (right) junction sketch

(left) diagonal struts at corners, (middle) circular struts, (right) inclined struts
Figure 3: Guide wall construction

compression buckling check, short inclined hardening of it, the excavation is done
‘splay’ members are often provided. Hollow below slab; to support the load of this
circular pipe sections / liners perform better slab during construction rolled steel
in large compression and shorter lengths, sections called plunge columns are driven
than RSJ or built-up sections. Several in advance. At the bottom end of these
software programs are available to plan steel columns a firm concrete plug / shoe
and design the strutting and waling system. called ‘barrette’ is also driven in advance.
Temporary Steel Decking: When Proper connection between Plunge column
underground construction goes on for any and Barrette / Bored pile considering
metro line, the surface operations (mainly construction tolerance need to be checked.
the traffic movements) should go on Box pushing for subway: Often in urban Vertical eccentricity of plunge column in
without any disturbance; traffic diversion areas, open trench cutting is not possible. both directions also need to be checked.
could be only a temporary solution. To In such cases to enable the public entry Shear connector with Slab and Plunge
enable the vehicle movement over trench towards the metro station, underground column need to be checked.
area, steel decking is a good option. Such subways are constructed using box TBM thrust frames and Steel cradle: For
steel decking is nothing but a small span pushing method. the initial few meters of length of boring in
temporary steel bridge spanning over Plunge columns and barrettes: In soil, the Tunnel Boring Machine requires
two opposite side diaphragm walls or top down method of construction, after external support with thrust of 10000kN to
temporary beams (as seen on the RHS installation of D’wall the ground slab 14000kN depending on geological condition
photo). is constructed before and then after (thrust frame and back to generate forward

NBM&CW APRIL 2024 5


Figure 4: Typical steel Plunged columns

(left & middle) thrust, (right) cradle sledge support

TBM cradle lifting / shifting using hydraulic jacks


Figure 5: TBM Thrust frame and cradle

marching force) and a cradle frame at base


to facilitate leveling and avoid rolling of the
circular shield. Once the TBM machine
moves for about 60m length inside the
soil mass then the friction between soil
and concrete rings is adequate to sustain
/ facilitate forward push to TBM and then
the thrust frames are removed.
Tunnel Eye/Soft Eye: At the starting
location of penetration of TBM through (left & middle) installation of tunnel eye ring, (right) TBD cutter head penetrates though soft eye.
D’wall and at the end point of receiving the Figure 6: Tunnel eye / soft eye
TBM, a steel frame called Tunnel Eye is
installed. Normally, GFRP bar is used for MS U-clamps of each bar. Eye seal is used Temporary Rails & Walkway: Mucking
Tunnel Eye location considering 150mm when the water table is above the TBM. If carts are used to remove the muck
all-round tolerance. All GFRP bars are tied the water table is below the TBM, Tunnel generated by TBM shield. These carts run
with reinforcement by using 8mm dia four Eye seal may not be required. horizontally from the TBM inside tunnel to

6 NBM&CW APRIL 2024


at open plot. For critical case of intervention
at below building area, face pressure is to
be maintained.
Muck removing carts / chariot, muck
carrying conveyors. muck lifting / tilting
device, muck storage bin: The daily
TBM operation generates loads of soil
muck, which is continuously collected from
the TBM cutter using a screw conveyor
and handed over to muck removing
Figure 7: Steel sleepers below temporary rails and walk-way inside tunnel tube under construction
carts or chariots with the help of short
belt conveyors. Muck carts are usually
battery-operated wagons that run from
TBM assembly towards the station / shaft
area where the EOT unloads them into
dedicated muck storage bins. Later, the
trailers excavate the muck and dispose it
off site to designated remote locations (Fig
9 shows the whole process).
Casting yard & stacking yard sheds with
(left) Circular shaft with secant piles, (middle) rectangular shaft with diaphragm walls,
(right) TBD cutter head penetrates though soft eye. EOT cranes, segment casting molds with
Figure 8: TBM accessing shafts steam curing facility: As shown in the
photos below, the tunnel ring segments are
cast using inverted curved steel formwork
the nearest vertical shaft / station, where these shafts are of temporary nature
and subsequently cured using steam curing
the muck is lifted vertically to ground. To and sometimes preplanned permanent
chamber. Then the hardened segments are
run these motorized carts, temporary rails structures. This intervention shaft is
lifted from mould using vacuum pads and
are required (as shown ahead). During the required to replace the parts of TBM,
tilted upside down with a mechanical tilting
tunneling operations. Crossover is required otherwise cutter head intervention can be
device. All tilted segments in a single ring
for crossing the muck car at certain done from inside of TBM with atmospheric
are clubbed together and then stacked in
intervals, but the first crossover shall be pressure and location of intervention will be
after 100m from the launching shaft.
Temporary slurry piles at head wall:
Slurry wall or Pile of PCC concrete Grade
M10, M15 or M20 are normally used if
water table is high and GFRP bars are not
used. If water table is low, GFRP bars are
used at head wall and if there is no building
around the influence zone of head wall,
then slurry wall / pile may be avoided.
Intervention Shaft for TBM: Generally,
the TBM assembly is lowered / retrieved
from a designated area of UG station
(called launching shaft). In some projects,
the TBM is to be lowered / retrieved / or
accessed (for repair and maintenance
purpose) in between two UG stations.
In such cases, a dedicated vertical
intervention shaft (either in rectangular or
circular shaped in plan) is bored / driven /
sunk using either diaphragm walls / secant
piles or well sinking method. Sometimes Figure 9: Muck carrying carts and storage bins

NBM&CW APRIL 2024 7


Apart from these temporary structures,
concrete batching plants / aggregate
crushing plants / chilling plants etc. are
also provided in the vicinity area. The
foundations of these temporary structures
have to be properly designed to sustain
permanent and variable loads (like wind
load); however, being temporary in nature,
up to 30% overstress can be permitted in
(Left) Preparing segment ring casting formwork and place Rebar (right) pour concrete these structures (however many clients /
proof checkers / GECs insist for a design
that is same for permanent structure, which
leads to wastage of national resources.
One must keep in mind that permanent
structures are designed to sustain for a life
of 100 years whereas temporary structures
are supposed to stay till maximum 5 years,
so some relaxation in terms of stresses
should be permitted as per authors
(Left) steam curing (right) vacuum lifting of fresh segment personal opinion).
References
1) Analysis of stability of rock column
between cut & cover Metro Station and
NATM Tunnels: et. al. International
Journal of Engineering Research and
Applications, www.ijera.com , ISSN:
2248-9622, Vol. 13, Issue 7, July 2023,
pp 214-224
2) Analysis of stability of rock column
(left) mechanical tilting of ring (right) stacking segment rings in open yard with Goliath crane between cut & cover Metro Station and
NATM Tunnel : ITA-AITES World Tunnel
Congress 2024, Shenzhen, China, 19-25
April 2024
3) Challenges of TBM Tunnelling in DMRC
Project, Phase – III, CC-04, Page
No – 96 : INDIAN ASSOCIATION OF
STRUCTURAL ENGINEERS
4) Chapter.18 contributed by Er. vivek
abhyankar in the book Design of Steel
(left) Mock-up ring assembly in yard (right) lowering ring segments inside trench Structures – by Dr. N. Subramanian
Figure 10: Various Processes on Precast segment rings published by Oxform IBH Publishers.
5) ‘Temporary works paves way to
a stacking yard using EOT cranes. Later workshops, concrete testing laboratory are permanent profit’ – paper by Er. Raja
as and when site tunneling team requires required to be set up. Sometimes, these Rajan, published in Ing. IABSE (Vol. 46,
rings the full set of segments is sent to site sheds are made up of brick walls and steel No.1 March 2016).
and lowered in the shaft area suing crane roofing trusses covered with corrugated 6) ‘Analysis of cracks in metro segment
/ EOT at site. sheets and sometimes directly made using FEM, rectification methods
Steel sheds for office / workshop from portable cabins. All the staff cabins, proposed and associated cost saving,
/ testing labs, Concrete Batching conference rooms, printers / plotters, points to ponder for young designers” –
and crushing plants: At the casting pantry and toilet etc. (all of temporary paper by Er. Vivek Abhyankar published
yard temporary steel sheds for offices, nature for three-to-four-year duration) are in Indian Concrete Journal (vol. 92, no. 3
provided. March 2018).

8 NBM&CW APRIL 2024


7) ‘Various hurdles in Design and Construction of Metro-Rail ** Er. Vivek G. Abhyankar – Founder
Projects in India’ – paper by Er. Vivek Abhyankar and Er. Raviteja of SGAWings Civil Engg Consultants
Kilaparthi, and Er Rafik Basha - published in B& SE, Vol. 47, No. and Advisor (OPC) Pvt. Ltd.; Fellow
2 June 2017. of Institute of Engg (India), Fellow
And various internet websites for the source of information & images. of IaSTRUCE, Licensed Structural
Engineer (MCGM) and Life member
Note: part-II of the article will discuss temporary works in
of various other professional
elevated metro projects and will be published in the next issue
Institutes (IRC, ISSE, IIBE, ACI, ICI,
of NBM&CW.
ACCE, ISRMTT, INSDAG, ASCE,
About the authors :- NICEE, SEFI). Gold medalist from
*Er. Swarup Maiti – has more than University of Mumbai in PG-Structures degree. Possess
19 years of experience in the field of over 25 years of rich experience in planning and design,
planning, design, execution and technical detailing of various civil engineering structures (roads
coordination of various metro projects like / metros / buildings / temporary works etc.). Apart from
Kolkata Metro UG projects (India’s first professional works author was also a visiting faculty for
metro rail project below River), Delhi Metro, Structural Engineering at VJTI, SPCE and has acquired
Kanpur and Surat metro. Apart from Indian vast experience in technical training for site engineers.
projects he has also participated in a few He has written more than 30 technical papers on practical
international metro projects. He holds a aspects of engineering and contributed 3 chapters in top
post graduate degree in Project Management from NICMAR and rated books and guided more than ten M.Tech, AMIE thesis.
post graduate degree in Tunnel Engineering from MIT peace Contributed to various professional initiatives in corporate
University. He has worked with eminent companies like L&T, sector like E-Learning, Knowledge management, Engineers’
AFCONS, CEC and HCC. Currently he is leading the technical Day, standardization of construction inventory etc. (contact
/ design team with Gulermak India (contact :- smaiti@gulermak. :- abhy_vivek@hotmail.com)
com.tr)

NBM&CW APRIL 2024 9

You might also like