Professional Documents
Culture Documents
Vivek Abhyankar
Vivek Abhyankar
Vivek Abhyankar
Metro construction works are spread all over India. Apart from the design of permanent works there are several
enabling/temporary structures required during construction of permanent works. Often these temporary works are
not taught in school/colleges, and since temporary works are not paid for separately to the contractor, there is a
lot of cutting corners and negligence towards such temporary works. Er. Swaroop Maiti and Er. Vivek Abhyankar
discuss the various types of temporary works used in the underground metro construction projects and in elevated
metro projects, and also address queries by both budding and senior engineers.
Introduction utilities, limited working hours, safety safety, (1.6) CFD analysis, acoustic study
requirements etc. Metro projects are and other higher researches (as per the
Construction of metro rail projects is in
broadly classified as (a) elevated works (b) requirements in individual projects).
full speed across India’s urban areas.
underground works and (c) ramp portions Each of these disciplines have their own set
Delhi, Mumbai, Kolkata, Hyderabad,
which connect elevated stretch of metro to of requirements / expertise and complexities.
Ahmedabad, Surat, Kanpur, Nagpur,
an underground stretch. Each of these has In this paper, the authors have elaborated
Lucknow, Pune, Patna cities are leading
its own set of requirements and challenges mainly on Temporary Structures (also called
the construction of Metro rail connectivity.
and involve three main disciplines: enabling works). The paper is divided into
As compared to the railways, the Metro
Design, Construction, Operations and two parts: temporary works in underground
rail is faster and more flexible, and when
Maintenance. The design discipline has projects (including the ramp portions) and
compared to road traffic, it is hinderance
further sub-disciplines such as (1.1) temporary works in elevated metro projects.
free. Due to the advantages of metro rails
Architecture, (1.2) Structural design
in increasing urbanization, India has made Underground metro projects involve mainly
(1.2.a – design of permanent works, 1.2.b
significant investment in this sector during three types of structures: (a) bored tunnel
– design of temporary structures, 1.2.c –
the past ten years. tubes (b) station buildings (c) ancillary
geotechnical), (1.3) Mechanical – Electrical
The design and construction of metro works buildings and access underpass. The
– piping / plumbing (MEP), HVAC,
is highly challenging in city areas where temporary works required for these are
signaling, drainage, lighting, (1.4) building
there is a lot of congestion, underground listed below and described briefly.
information models (BIM), (1.5) Fire and
(left) placing rebar and formwork, (middle) poring concrete, (right) completed guide wall
Figure 1: Guide wall construction
(left & middle) Precast concrete sacrificial stop end (right) Typical spliced connection in stop ends.
Figure 2: Stop Ends for Diaphragm walls
stop end (Left & Middle) Precast concrete engineer. For long length cage the bars For struts having longer length intermediate
sacrificial stop end (Right) Typical spliced are connected using laps / couplers. The steel column support may be given using
connection in stop ends. final assembled cage is inspected by the kingpost to avoid sagging under self-
clients (GEC) and after certification lifted weight and to maintain the effectiveness
using cranes as shown in the photo of of this struts. In some cases, the struts are
right hand. To avoid the localized bending applied with a pre-compression using jacks
buckling of individual rebars a steel lifter / or wedges – these are called active struts
spreader beam / strong-back, is given at (else if preload is not applied then called as
the top of the cage to which the wire ropes passive struts). Struts may be formed from
are connected at bottom and at top to the - rolled joists / built-up truss / or simply steel
crane hook. Capacity of each lifter beam liner pipes.
shall be properly designed and detailed; In certain open excavations to facilitate
also to be marked with paint on respective equipment movements the open struts
lifter beam/s. may cause hindrance and hence are not
Shoring works (in bottom-up type permitted; in such case prestressed soil
construction), steel walers, supporting anchors are used at certain spacing to hold
brackets, insert plates and struts (active / the waler beams in position.
passive), temporary king posts / stanchions In certain cases, the opposite side walls is
(Fig. 3): Steel shoring is required to keep located far away (which would lead too long
the D’wall / soldier pile wall in proper length of a strut); in such cases inclined
position against the lateral soil load at struts inside excavated pit are given (shown
Rebar Cage Lifters: The steel rebar
the back of the wall. Accidental loads and ahead in the photo). At walls bending
cages are fabricated in the yard by the
additional stresses due to temperature 90degree inward, the diagonal struts are
seasoned iron workers under guidance of
changes shall be carefully considered preferable. To increase the effectiveness of
experienced foremen / supervisor / shift
while designing and detailing the struts. struts and to shorten its effective length in
(left) diagonal struts at corners, (middle) circular struts, (right) inclined struts
Figure 3: Guide wall construction
compression buckling check, short inclined hardening of it, the excavation is done
‘splay’ members are often provided. Hollow below slab; to support the load of this
circular pipe sections / liners perform better slab during construction rolled steel
in large compression and shorter lengths, sections called plunge columns are driven
than RSJ or built-up sections. Several in advance. At the bottom end of these
software programs are available to plan steel columns a firm concrete plug / shoe
and design the strutting and waling system. called ‘barrette’ is also driven in advance.
Temporary Steel Decking: When Proper connection between Plunge column
underground construction goes on for any and Barrette / Bored pile considering
metro line, the surface operations (mainly construction tolerance need to be checked.
the traffic movements) should go on Box pushing for subway: Often in urban Vertical eccentricity of plunge column in
without any disturbance; traffic diversion areas, open trench cutting is not possible. both directions also need to be checked.
could be only a temporary solution. To In such cases to enable the public entry Shear connector with Slab and Plunge
enable the vehicle movement over trench towards the metro station, underground column need to be checked.
area, steel decking is a good option. Such subways are constructed using box TBM thrust frames and Steel cradle: For
steel decking is nothing but a small span pushing method. the initial few meters of length of boring in
temporary steel bridge spanning over Plunge columns and barrettes: In soil, the Tunnel Boring Machine requires
two opposite side diaphragm walls or top down method of construction, after external support with thrust of 10000kN to
temporary beams (as seen on the RHS installation of D’wall the ground slab 14000kN depending on geological condition
photo). is constructed before and then after (thrust frame and back to generate forward