SAID RESTAURANT @ MIRDIFF CITYY CENTER, DUBAI MAY JUNE JULY AUGUST

SCHEDULE M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
S.no. Task Name Duration Start Finish 20 21 22 23 24 25 26 27 28 29 30 # 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 # 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
1 SAID DAL- 1923 CIVIL, FIT-OUT AND MEP 90 days Thu 23/05/24 Wed 21/08/24
20% ADVANCE PAYMENT 20th May 24 22nd May 24 20%
2 Mobilization and Safety Induction 1 day Thu 22/05/24 Fri 24/05/24
3 Mall NOC and Police Permission Application 1 day Fri 24/05/24 Sat 25/05/24
Preparation of Method Statements and Material data sheets and
4 5 days Sun 26/05/24 Fri 31/05/24
necessary documents for approvals
5 Preparation of sample mood boards for MEP and Joinery 7 days Fri 31/05/24 Fri 07/06/24
6 Submission of MEP & Joinery Material Samples for Approval by Client 1 day Fri 07/06/24 Sat 08/06/24

7 Submission of MEP & Joinery Material Samples for Approval by Client 1 day Sat 08/06/24 Sun 09/06/24
Demolition of Existing Ceiling, Walls and Floor finishes of dining area
8 14 days Sat 25/05/24 Sat 08/06/24
and Clearing the debris
9 Waterprofing the Existing Drainage Stubouts for Kitchen and Bar 6 days Sat 08/06/24 Mon 13/06/24
10 Ponding Test for the Drainage points in dining area 4 days Sun 09/06/24 Tue 12/06/24
11 Drainage Plumbing works and Gravity Test 2 days Tue 11/06/24 Thu 13/06/24
12 Gravity Test Inspection 1 day Fri 14/06/24 Fri 14/06/24
13 Levelling Protection screed 1 day Thu 13/06/24 Fri 14/06/24
14 Laying of Low Level Power and Electrical Conduits 4 days Mon 10/06/24 Fri 14/06/24
15 Laying of Screeding 2 days Fri 14/06/24 Sun 16/06/24
15% SECOND PAYMENT 17th June 24 19th June 24 15%
Electrical High Level Trunking and Cable tray works for Power, Data
16 3 days Sun 16/06/24 Sun 23/06/24
and CCTV
17 Cable work for Power includinng GI conduiting 3 days Sun 23/06/25 Wed 26/06/25
18 Cable works for Fire Alaram, Emergency and Exit Lights 3 days Wed 26/06/24 Sat 29/06/24
Duct Branches, supports, Hanging of main ducts, Flexing ducts,
19 3 days Wed 26/06/24 Sat 29/06/24
Plenum boxes and Smoke Extract Ducting.
20 FF Main Pipe for Pendant Sprinklers 2 days Sat 29/06/24 Tue 02/07/24
21 Testing of FF Main Piping 1 day Tue 02/07/24 Thu 04/07/24
22 Water supply PPR and pex Piping 2 days Thu 04/07/24 Fri 05/07/24
23 Testing of Water Supply Pipes 1 day Thu 04/07/24 Sat 06/07/24
24 Maintenace platforms for AC, Void Detectors and Valves. 3 days Sat 06/07/24 Sun 07/07/24
25 Flooring Works Tiling 7 days Thu 04/07/24 Sun 07/07/24
26 FOH Dining area Gypsum Ceiling suspension and levelling 5 days Sun 07/07/24 Fri 12/07/24
27 Pendant Pipe Dropping and Pressure Test 1 day Fri 12/07/24 Sat 13/07/24
BOH Storage and Washing area 60x60 Aluminum Ceiling Suspension
28 4 days Sat 13/07/24 Wed 17/07/24
and Levelling
BOH Kitchen Area Rectification of 60x60 Aluminum Ceiling
29 2 days Sat 13/07/24 Mon 15/07/24
Suspension and Leveling
30 FOH Highlevel MEP inspection for closure 1 day Fri 12/07/24 Sat 13/07/24
31 Gypsum Ceiling closure and Paint Finish 2 days Sat 13/07/24 Mon 15/07/24
32 Expose Ceiling area Paint Finish 2 days Mon 15/07/24 Wed 17/07/24
33 Gypsum Wall Finishes and Paint Finish 7 days Wed 15/07/24 Wed 22/07/24
10% THIRD PAYMENT 22nd July 24 24th July 24 10%
34 Installation of Wall shelves and joinery 5 days Wed 17/07/24 Mon 22/07/24
35 Fixing of Switches and Sockets 2 days Mon 22/07/24 Wed 24/07/24
36 Fixing of Light Fittings 1 day Wed 24/07/24 Thu 25/07/24
37 Fixing of Air Diffusers and Grills 3 days Wed 23/07/24 Sat 25/07/24
38 Fixing of CCTV and DATA Sockets 1 day Wed 24/07/24 Thu 25/07/24
39 Fixing of Smoke Detectors 1 day Thu 25/07/24 Fri 26/07/24
40 DB Installation and DB Dressing 2 days Fri 26/07/24 Sun 28/07/24
41 Megger Test, Live Test, Trip Test 1 day Sun 28/07/24 Mon 29/07/24
42 Air Balancing and Water Balancing 2 days Mon 29/07/24 Wed 31/07/24
43 Fire alarm testing and Programming 1 day Mon 29/07/24 Tue 30/07/24
44 FF Connection to Mall 1 day Mon 29/07/24 Tue 30/07/24
45 Metal Partitions, Glass works and Doors 5 days Tue 30/07/24 Sun 04/08/24
46 Inner Shopfron Wooden Partions and Glass Works 4 days Sun 04/08/24 Thu 08/08/24
10% FOURTH PAYMENT 8th Aug 24 10th Aug 24 10%
47 Capentry and other Furniture Installation 2 days Thu 08/08/24 Sat 10/08/24
48 Outdoor Furniture Installation 2 days Thu 08/08/24 Sat 10/08/24
49 Signage Installation 2 days Sat 10/08/24 Mon 12/08/24
50 Kitchen Equipment Intallation connections 3 days Fri 09/08/24 Mon 12/08/24
51 Gas Connection Completion by client 1 day Mon 12/08/24 Tue 13/08/24
52 AMC Contract for Safety Certificate 1 day Tue 13/08/24 Wed 14/08/24
Close out Documents and Green star Documents Submission
53 2 days Wed 14/08/24 Fri 16/08/24
Including Safety certificate approvals
54 Deep Cleaning 3 days Fri 16/08/24 Mon 19/08/24
55 Café Merchandise & VM Branding 2 days Mon 19/08/24 Wed 21/08/24
56 Final Mall Inspection for MEP 1 day Mon 19/08/24 Tue 20/08/24
57 Final Mall Inspection for Architectural and Joinery 1 day Tue 20/08/24 Wed 21/08/24
58 Store Opening 1 day Wed 21/08/24 Thu 22/08/24
10% FIFTH PAYMENT 23rd Aug 24 25th Aug 24 10%
10% SIXTH PAYMENT 23rd Sept 24 25th Sept 24 10%
10% SEVENTH PAYMENT 23rd Oct 24 25th Oct 24 10%
10% EIGHTH PAYMENT 23rd Nov 24 25th Nov 24 10%
5% AFTER THE DLP PERIOD 23rd Nov 25 25th Nov 25 5%