Ref.

to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.

13.8 2706 & Providing weep holes in Brick masonry/Plain/ Reinforced


2200 concrete abutment, wing wall/ return wall with 100 mm
dia AC pipe, extending through the full width of the
structure with slope of 1V :20H towards drawing foce.
Complete as per drawing and Technical

Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per cent ) metre 31.50 253.00 7969.50 M-056

Average length of weep hole is taken as one metre for the


purpose of estimating.
MS clamp each. 30.00 13.00 390.00 M-123
collar for AC pipe (average) taking 10% of above pipe each. 10.00 25.30 253.00 M-056/10
rate
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.05 3431.00 171.55 Item 12.6
(A)
b) Labour
Mate day 0.03 530.00 15.90 L-12
Mason day 0.50 585.00 292.50 L-11
Mazdoor day 0.25 490.00 122.50 L-13
c) Overhead charges @ 4.615% on (a+b) 425.27
d) Contractor's profit @ 10% on (a+b+c) 964.02
Cost for 30 m = a+b+c+d 10604.24
Rate per m (a+b+c+d)/30 353.47
say 353
Note 1. In case of stone masonry, the size of the weep hole shall be
150 mm x 80 mm or circular with 150 mm diameter.
2. For structure in stone masonry, the weep holes shall be
deemed to be included in the item of stone masonry work and
shall not be paid separately.