Tertiary air duct in 8 steps

KIH 620, 15.04.2011

Polysius
Step 1:
• install CC-duct
• install supports in preheater
tower

Page 1
This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on
the cement plant construction sector).
The document does not reflect the details/circumstances of specific projects.
Polysius
Step 2:
• install main duct in preheater
tower
• pre-assembly of main duct,
welding

Page 2
This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on
the cement plant construction sector).
The document does not reflect the details/circumstances of specific projects.
Polysius
Step 3:
• install support 1
• install main duct up to support 1
• pre-assembly of main duct, welding

Page 3
This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on
the cement plant construction sector).
The document does not reflect the details/circumstances of specific projects.
Polysius
Step 4:
• install support 2
• install main duct up to support 2
• pre-assembly of main duct, welding

Page 4
This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on
the cement plant construction sector).
The document does not reflect the details/circumstances of specific projects.
Polysius
Step 5:
• install support 3
• positioning of compensator on the
guide pipe
• pre-assembly of main duct, welding

Page 5
This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on
the cement plant construction sector).
The document does not reflect the details/circumstances of specific projects.
Polysius
Step 6:
• install main duct up to compensator

Page 6
This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on
the cement plant construction sector).
The document does not reflect the details/circumstances of specific projects.
Polysius
Step 7:
• install compensator

Page 7
This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on
the cement plant construction sector).
The document does not reflect the details/circumstances of specific projects.
Polysius
Step 8:
• install refractories

Page 8
This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on
the cement plant construction sector).
The document does not reflect the details/circumstances of specific projects.
Polysius