RINI SETIANINGSIH 23/513365/PTK/15081 PERENCANAAN MONITORING PROYEK

PRECEDENCE CRASH TO NORMAL

0 10 5 5 20 8 8 30 15 15 40 21 21 50 31
A B C E H
Dur : 5 Dur : 3 Dur : 7 Dur : 6 Dur : 10
0 0 5 5 0 8 8 0 15 15 0 21 21 0 31
CRITICAL CRITICAL CRITICAL CRITICAL CRITICAL

8 32 13 15 42 20 21 52 29 31 60 33 33 70 36
D F I J K
Dur : 5 Dur : 5 Dur : 8 Dur : 2 Dur : 3
10 2 15 16 1 21 23 2 31 31 0 33 33 0 36
NOT CP NOT CP NOT CP CRITICAL CRITICAL

13 44 20
G
Dur : 7
16 3 23
NOT CP

Crash Slope Iterasi TCTO (Crash to Normal) Durasi Total


Activity CPM
Duratio ($) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Tersisa Aktifitas Cost
A 5 - 0 0 5 500
B 1 150 1 1 0 0 3 900
C 4 300 1 1 1 0 0 7 3.250
D 3 150 2 2 0 5 1.000
E 3 450 3 0 0 6 1.400
F 3 400 1 1 1 0 5 1.100
G 4 300 3 3 0 7 1.500
H 5 600 1 1 1 1 1 0 0 10 4.200
I 4 Matrix 2 2 2 0 8 800
J 1 200 1 0 0 2 1.100
K 2 200 1 0 0 3 1.300
Days 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 36 17.050
Cost ($) 25.550 25.400 25.200 25.000 24.700 24.400 24.100 23.700 23.300 22.700 22.100 21.500 20.700 20.100 17.050 17.050 17.050 17.050 17.050 17.050 36 Days - Cost
Selisih (150) (150) (200) (200) (300) (300) (300) (400) (400) (600) (600) (600) (800) (600) (3.050) - - - - - $17050

REKAPITULASI TCTO (CRASH TO NORMAL)


Iterasi Days Cost ($)
0 21 25.700
1 22 25.550
2 23 25.400
3 24 25.200
4 25 25.000
5 26 24.700
6 27 24.400
7 28 24.100
8 29 23.700
9 30 23.300
10 31 22.700
11 32 22.100
12 33 21.500
13 34 20.700
14 35 20.100
15 36 17.050