Professional Documents
Culture Documents
Lecture 5 Tender Procedure and Contract Documents
Lecture 5 Tender Procedure and Contract Documents
1
Lecture 5
2
Working Stages
• Client’s Brief
• Design
• Tendering
• Contract
• Construction
• Completion
• Maintenance Program
3
Tendering
4
Contract
5
Method of Tendering
• Competitive Tendering
– Open Tendering
– Selective Tendering
• Negotiated Tendering
– Two-stage Tendering
• Stage I – Comparison of price basis and design
proposal
• Stage II – Project design, BQ and agreeing final
price
6
Method of Tendering
• Serial Tendering
• Combination of selective and negotiated tendering
7
Tendering Process
• The basic purpose of tendering is to select an
appropriate contractor to construct the
designed structures at a reasonable price.
8
Tendering Process
• When tender documents are prepared, they
are sent to the tenderers with instruction on
tender or sometimes the tenderers are
required to collect the documents at the
specified office normally an
Architect’s/Engineer’s office.
9
Tendering Process
• The priced tenders will have to be submitted
back to the Client at the specified time, date
and venue.
10
Tendering Process
• The priced tenders will have to be submitted
back to the Client at the specified time, date
and venue.
11
Documents Used in the Tender
Process
1. Notes to Tenderers
2. Conditions of Tender
– General Conditions of Tender (GCT) and Special
Conditions of Tender (SCT)
3. Form of Tender
4. Schedule of Proportions for calculating the Price
Fluctuation Factor
5. Conditions of Contract
– General Condition of Contract (GCC) and Special
Condition of Contract (SCC)
12
Documents Used in the Tender
Process
6. Specifications
– General Specification (GS) and Particular Specification (PS)
7. Standard Method of Measurement (SMM)
8. Preambles
– General Preamble and Particular Preamble
9. Bills of Quantities
10.Drawings
11.Any relevant pre-contract correspondence with the
Contractor (e.g. tender addendum, circular letter to tenderers)
13
Documents Used in the Tender
Process
• Notes to Tenderers – information relating to conditions of
tender for example where and when to return tender, what
other documents that need to be submitted.
14
Documents Used in the Tender
Process
• Special Conditions of Tender – any alterations to a GCT
shall be effected by a SCT. Commonly used SCT clauses to
be included in the Conditions of Tender for works
contracts other than design and build contracts are
provided in ETWB TCW No. 26/2004.
15
Documents Used in the Tender
Process
• Special Conditions of Contract – Any amendments,
additions, deletions and amplifications to the GCC should
be effected by the inclusion of SCC clauses. However, SCC
clauses should only be included when there is a genuine
need to alter or supplement the GCC. Matters concerning
materials or workmanship standards or detailed
arrangement for the execution of Works should not in
general be stipulated in the form of SCC.
16
Documents Used in the Tender
Process
• Specification - Specification giving information regarding
the quality and workmanship for the works
17
Return of Tenders
• The tenderers are usually given 4 to 6 weeks for pricing of
the tender. When the priced tenders are returned, the
following steps will normally be taken by the Client's
consultants:-
18
Return of Tenders
– Check if there is any alternative proposals to the offer
whether technically or contractually
– Prepare a tender report to the Client listing out the
analysis on the prices and other relevant information.
– Once the Client's has selected a contractor, a letter of
intent will be issued to the Contractor and letters will
also be sent out to notify those unsuccessful tenderers
of the tender result.
– Prepare the contract documents for signing by the
Client and the Contractor. Once the contract is signed,
then the post-contract period shall commence and the
contractor shall begins his construction on site.
19
Tender Evaluation
• Methods
– Formula Approach
• When the contract is not of unusual complexity and there are
no minimum qualifications required.
• Only take into account the tender price and the tenderer’s
past performance
– Marking Scheme
• When there is unusual complexity, but no prequalification of
tenderers and no minimum qualification are required.
• Tender price and technical score percentage split
• Two-envelope approach; the technical submission and the
tender price document
20
Contract Document Composition
1. Articles of Agreement
2. Correspondence Forming Part of the Contract
3. Schedule of Proportions for calculating the Price Fluctuation Factor
4. Conditions of Contract
– General Condition of Contract (GCC); and
– Special Condition of Contract (SCC)
5. Specifications
– General Specification (GS); and
– Particular Specification (PS)
6. Standard Method of Measurement (SMM)
7. Preambles
– General Preamble;
– and Particular Preamble
8. Bills of Quantities
9. Drawings
21
References
• Building Contract Procedures in Hong Kong
Martyn J. Hills, Longman 1995
• Building Quantities Explained (3rd Edition)
Ivor H. Seeley, Macmillan 1985
• Hong Kong In China: Real Estate In The Economy
Prof. Anthony Walker, et al, Dept. Of Surveying, The University of Hong Kong 1995
• The Construction Industry: Aspect of its Economics and Management
George Ofori, Singapore University Press 1990
• Measurement In Contract Control
Martin Barnes,1977, Thomas Telford Ltd
• Hong Kong Standard Method of Measurement of Building Works (3rd Edition) 1979
• General Specification of Material and Workmanship for Hong Kong Housing Authority,
Housing Department, Hong Kong
• Building Economics (3rd Edition)
Ivor Seeley, Macmillan, 1983
22
End
23