BAH054 Project Handover Sequence

Complete Late

APC Construction -
Required Completion APC Snag List APC Desngging Complete &
Walkdown Area Date Complete Signed Off
Data Hall 5-Aug-18 10-Aug-18 19-Aug-18
Days to Complete 2 3 1
Electrical Room 5-Aug-18 10-Aug-18 19-Aug-18
Days to Complete 2 3 1
AHU Room 4-Aug-18 11-Aug-18 19-Aug-18
Days to Complete 2 3 1
Office - Grd Flr 5-Aug-18 10-Aug-18 19-Aug-18
Days to Complete 2 3 1
Mezzanine Flr (incl Stairs) 19-Aug-18 21-Aug-18 24-Aug-18
Days to Complete 2 3 1
Corridor/Ancillary Plant Areas (Grd Flr) 19-Aug-18 21-Aug-18 24-Aug-18
Days to Complete 2 3 1
External Bldgs (Guardhouse, 19-Aug-18 21-Aug-18 24-Aug-18
Sprinkler, Generator Compound)
Days to Complete 2 3 1
External Areas (Fencing) 6-Aug-18 11-Aug-18 19-Aug-18
Days to Complete 2 3 1
Roof Level 06/-08/18 15-Aug-18 24-Aug-18
Days to Complete 2 3 1
External Envelope 19-Aug-18 21-Aug-18 24-Aug-18
Days to Complete 2 3 1
ver Sequence
Issue Date: 2-Aug-18

AWS Snag AWL Desnagging


Offer Area to AWs List Complete & Ready for Handover
for Client Snagging Required Final Walkdown Area to AWS
25-Aug-18 27-Aug-18 30-Aug-18 2-Sep-18
2 3 3
25-Aug-18 27-Aug-18 30-Aug-18 2-Sep-18
2 3 3
25-Aug-18 27-Aug-18 30-Aug-18 2-Sep-18 Air Bal - 06/08/18
2 3 3
25-Aug-18 27-Aug-18 30-Aug-18 2-Sep-18
2 3 3
25-Aug-18 27-Aug-18 30-Aug-18 2-Sep-18
2 3 3
25-Aug-18 27-Aug-18 30-Aug-18 2-Sep-18
2 3 3
25-Aug-18 27-Aug-18 30-Aug-18 2-Sep-18
2 3 3
25-Aug-18 27-Aug-18 30-Aug-18 2-Sep-18
2 3 3
25-Aug-18 27-Aug-18 30-Aug-18 2-Sep-18
2 3 3
25-Aug-18 27-Aug-18 30-Aug-18 2-Sep-18
2 3 3