Professional Documents
Culture Documents
KTMB - Permanent Way Manual - Volume 2 of 2 - 2015
KTMB - Permanent Way Manual - Volume 2 of 2 - 2015
KTMB - Permanent Way Manual - Volume 2 of 2 - 2015
----KTitll
KERETAPI TANAH MELAYU BERHAD
PERMANENT WAY
MANUAL \
VOLUME 2/2
2015
~ICTIIII
Permanent Way Manual
Document Approval
VOLUME 2- PART IV
24 Welding of Rails
25 Welded Rails Laying and Maintenance
26 Realignment of Curves
IV 27 Rails Defects and their Rectification
34 Vegetation Control
\
\
VOLUME 2- PART V
PART CHAPTER DESCRIPTION
35 Duties of Regional Engineer
50 Schedule of Inspections
VOLUME 2
PART IV
TRACK MAINTENANCE
SYSTEMS
AND
METHODS
: I
Permanent Way Manual Part IV
W orks Planning Chapter 20
Chapter 20
Works Planning
Do cument History
Issue Date Descript ion
Authorised By:
Signature:
TABLE OF CONTENTS
Maintenance
Preventive Corrective
Maintenance Maintenance
~ondition based
Maintenance
Predetermined
Maintenance
I*Deferred~ ~*Immediate
*Scheduled
continuous or *Scheduled
on request
20.1.3 Preventive maintenance is the foundation of the entire maintenance strategy. If the
preventive maintenance program is effective, corrective maintenance need not be
required. Corrective maintenance are unplanned activities that incur higher costs and
disrupts daily operational schedule.
20.1.4 Preventive maintenance activities include partial or complete track component overhauls
at specified periods. In addition the track conditions are continuously monitored and rate
of deterioration analysed to enable correct scheduling for replacement or repair of worn
or deteriorating parts. The work can then be carried out in time before they cause system
failure.
20.2.1 Planning of maintenance activities involves the matching of the available resources with
the work load. Accurate forecasts of the work load are necessary for the preparation of a
workable plan.
20.2.2 For the identification of works, systematic inspection of track is essential. The output
obtained from the track recording car also helps to achieve the purpose.
20.2.3 The Work Plan fulfils the important task of projecting the track works to be carried out.
Besides it indicates the allocation of track materials and deployment of men and
machines, for carryir.g out these works.
20.3.1 Permanent Way works fall mainly in the following three categories:
a) Manual Method
b) Mechanised Method
3. Off-Track Maintenance works
20.3.2 The amount of work required to be carried out, in each of the above categories is closely
interrelated. Badly maintained and worn out track components would require track
geometry to be rectified more often. Similarly, poorly maintained track geometry or
poorly maintained off-track elements can lead to faster degeneration of track
components and lead to poor track stability and poor quality.
These factors are taken into account in formulating the works plan.
20.5.1 For the works required to be carried out in a calendar year Y, all item of works are listed
out by the end of year Y-1 for each of the Sectional Gangs. Material, men and machines
required for carrying out these works are then worked out. The resources available are
matched with the requirement. Ways and means are found to maintain the track at the
desired standard by mustering additional resources or by postponing certain non-
essential items of work.
20.5.2 For exercising proper control, annual plan is converted into monthly plans. In monthly
plans, the works required to be carried out in a particular month are listed out in detail.
From the monthly plan, the Permanent Way Inspector, bring out weekly schedules of
work. These schedules are handed over to the Ganger of the Sectional Gangs, for
carrying out the track works.
20.5.3 In order to carry out the works planning, the maintenance works required to be carried
out in a particular year are identified into pre-determined maintenance works (or
scheduled works) and condition-based maintenance works.
20.6.1 This refers to the works to be executed at specified intervals. The following are included
in the scheduled works:
TABLE T-20.1
20.6.2 The schedules for the above mentioned items would differ from section to section, and
are indicated above as a good practice guide. Further changes may also have to be
made from year to year, taking into account the actual need of such works.
20.6.3 For the surfacing of track, the mode of working is to be decided. This depends upon:
All scheduled maintenance shall be done by machines. Where machines are not
available and in emergency, manual maintenance with beater packing or portable hand
tampers may be resorted to.
20.7.1 Items required for the maintenance of track other than those listed in clause 20.6.1, are
termed as condition-based items it will cover the following·
. -P~~.sHJ>fi<'>i-1
1
Noo ji .Type_ ..
·· ·.·. •· • · . •· · · · · ·•. ·.·.· .. •·.·•·•• L
The quantum of work under these items can vary considerably from year to year.
20.7.2 The volume for such works as carried out in the previous years can provide an important
guideline for estimating the work for the ensuing year. The planning proforma, recorded
using standard computer software, can form a quick database that provide easy access
to data of work done in the previous years.
20.8.1 The process involved in maintenance works planning are in the following order:
20.8.2 In the following clauses, the method of works planning is explained in detail. The
proforma required to be filled, the scrutiny to be exercised at various levels and the field
level supervision required for proper implementation of the plan, have been brought out.
20.9 PROSPECTING
20.9.1 Prospecting involves determination of the amount of work to be executed in the following
year. An assessment of the corresponding requirement of materials, manpower, and
machines to maintain the track to the prescribed standards is then made. lt requires the
personal inspection of each kilometre of track by the PWI along with the Ganger (or
Patrolman). During these inspections, they make assessment of the following items:
1. The type of maintenance works that are needed in the following year based
on the track condition at various locations.
20.9.2.1 The PWI shall personally inspect the stretches of track in each Gang's length along with
the Ganger to assess the requirement of track materials. Any component that is not
expected to give a further service life of 18 months shall be planned for replacement. The
PWI shall arrange to mark all defective material in waterproof paint or colour as under:
20.9.2.2 The methodology to be followed for inspection of track is indicated in Annexure 20.1.
20.9.2.3 The requirement of materials shall be recorded in Form PTM 1 (as per Annexure 20.2)
and forwarded to the CPWI and the Regional Engineer. The CPWI shall verify the
correctness of the estimates conducting checks of at least 10% of the requirements. The
Regional Engineer shall conduct check at random.
20.9.3.1 The PWI shall also estimate the amount of work to be executed in the following year in
each gang's length and group them under predetermined (scheduled) and condition-
based categories as has been described earlier in Clause 20.6 and 20.7.
20.9.3.2 The assessment is recorded in Form PTM 2 (as per Annexure 20.3) - under relevant
sub-items of work. (As an illustration, the amount of work for a typical PWI's unit is
arrived at in this Annexure).
20.9.3.3 The information gathered by the PWI during his routine inspections throughout the year
and from the various inspection registers, shall also be reflected under relevant sub-
items of work in Annexure 20.3.
20.9.3.4 Where work load cannot be precisely estimated, the PWI shall take the amount of work
executed in the previous year as a guide in arriving at a realistic assessment. For this
purpose the form at Annexure 20.8 can be used.
20.9.4.1 The PWI shall record the man-days required for execution of each of the items of work
listed at Clause 20.5.2.1 & 20.5.3.1 in Form PTM 2 (Annexure 20.3).
In estimating the unit output of work by labour or by machines, the PWI shall be
guided by the actual output in the previous year.
20.9.4.2 Where machine tamping is planned, the PWI shall assess the manpower required for
pre-tamping and post-tamping work. He shall also estimate the machine-hours required
for such maintenance work by machines. He will need to coordinate with the Regional
Engineer to ascertain the expected productivity of the machine that will be deployed in
his area.
20.9.4.3 The man-days required for each item of work shall then be summarized as brought out
on page 3 of Annexure 20.3. The available man-days per Gang shall be worked out for
the whole year as on page 2 of Annexure 20.3.
20.9.4.4 As an illustration, the manpower requirement is worked out for a typical PWI section in
Annexure 20.3.
20.10 PROGRAMMING
20.10.1 Drawing up the Annual Maintenance Programme:
20.1 0.1.1 The Annual Maintenance Programme shall be carefully drawn up by the PWI to
allocate the jobs to the Gangs at the identified location during specific periods. Details
collected from the following reports shall be utilized for this purpose:
20.1 0.1.2 While preparing the Annual Maintenance Programme, the following aspects shall be
l<ept in view.
1. Existing gang strength
2. Working day in each month
3. Availability of:
• Temporary labour
• Tools and plant
• Line Possession
• Projects and Third Parties works
• Other resources
20.1 0.1.3 The PW I shall prepare work schedules for each Gang-length, allocating the work to be
executed during each month of the ensuing year. He shall also allocate the regular
annual maintenance works like turnout maintenance, patrolling and lubrication of rail
joints during the specified periods in the year. The month-wise work schedule for all the
12 months shall be prepared for each Gang-length in Form PTM 3 (Annexure 20.4) by
the PWI and submit to the CPWI for his approval.
20.10.1.4 The CPWI and the Regional Engineer shall modify the programme, if required, taking
into account the information given in Form PTM 2 (Annexure 20.3), and the availability
of resources in the entire Region as also the relative priorities amongst the needs of
different PWis. The amended programme shall be returned to the PWI.
20.10.1.5 The PWI shall then prepare the final approved Annual Maintenance Programme for the
ensuing year in quadruplicate and submit a copy each to the CPWI , the Regional
Engineer and the General Manager Perm anent Way Division . One copy of the schedule
for every month shall be supplied to the Ganger before the beginning of the month.
20.10.2 Maintenance Programme Diagram
The final approved programme for the following year is also reflected in a Maintenance
Programme Diagram (as per Annexure 20.5). The PW I shall prepare one diagram for
each Gang as indicated below:
1. Show physical features like stations, kilometre and quarter kilometre posts and track
structure and components at the bottom of the chart.
2. Show the location, direction and degree of curves at the bottom of the chart.
3. Indicate the total quantum of work to be done for the year in respect of Tamping
works, Surfacing, Weeding, Patroll ing etc., and the location at the top of the chart.
4. Indicate the work to be done in each day and its location as shown in the enclosed
diagram, adopting the following colour scheme.*
The Weekly Programme is designed to enable the PWI to plan, organise and control the
work for a period of one week. lt also helps the CPWI and the Regional Engineer to
monitor the utilisation of manpower.
(iii) Points noted during inspection by foot, trolley, locomotive, rear vehicle and
other inspections.
2. The PWI shall finalize the weekly programme and allocate the deployment of
manpower for each day against the specific work in Form R1 (As per Annexure
20.6).
lt spells out the different types of work to be carried out during each of the
working days of the week and allocates the men for each day for a specific
work.
Part 3: Work completed for the week:
lt indicates the man-hours spent for each task and the time spent on each
day for a specific work.
4. The PWI shall put a slash (thus: /) against each man allocated for the work. He
shall send the Weekly Programme for the following week to the Ganger on every
Friday.
On receipt of the weekly programme (clause 20.10.6), the Ganger shall visit and inspect
the work site. He shall arrange for appropriate tools and organise the men for execution
of the work. He shall also inform every man of the work assigned to him in the following
week.
20.11.1.2 Execution of the work
The Ganger shall ensure that, on each day, the work is carried out according to the
programme for the day. At the end of the day, he shall put a horizontal dash (thus: -)
against the name of each man who has done the allotted work. The appraisal by the
Ganger in Form R1 shall indicate the total quantum of work done and the location. At the
end of the working week, the Ganger shall send the Form R1 to the PWI.
The Ganger shall obtain the approval of the PWI to carry out any urgent work which is
not programmed. He shall enter the type of work in the work column and show a
horizontal dash (thus: -} against each man to whom the work is entrusted-. Thus the
connotation of various symbols in Form R1 shall mean:
20.11.3 The PWI shall coordinate with the concerned authorities to ensure timely receipt of
materials, tools and plant, track machines, and additional man-power and to obtain Line
Possession, so that the progress of work is not hampered.
After every fortnight, the PWI shall update the progress in the Maintenance Programme
Diagram (Annexure 20.5}.
Actual work performed by the Gangs shall be recorded in the performance section of
Form PTM 3 (Annexure 20.4) which shall be kept up-to-date.
At the end of the month, the PWI shall return the Form to the Regional Engineer so as to
reach him before the 5th of the following month.
20.12 INSPECTION
20.12.1 The PWI shall check as frequently as possible whether the progress is according to the
plan and whether the quality of work executed by the Gangs is according to the
20.12.2 The Regional Engineer or his representative shall make spot checks periodically to
ensure that the quality and quantum of work executed are according to the requisite
standards and to the approved programme.
20.12.3 Officers from the Permanent Way Headquarters Office shall also carry out inspections to
the extent possible.
20.13 MONITORING
20.13.1 The recordings by the Track Recording Car EM 120 shall be fully utilised to evaluate the
quality of track work done. The track quality shall be assessed by the Track Quality Index
of each parameter (TQI) and the Overall Track Quality Index (TQI-0), as indicated in
Chapter 13.
20.13.2 The Regional Engineer shall maintain a Master Record of track maintenance works
carried out in his Region. He shall identify areas of weakness in maintenance procedures
and take action to rectify the shortcomings. He shall also compare the performance of
the various PWis under his charge, to identify and rectify operations showing abnormal
input in terms of time and manpower.
20.13.3 The Regional Engineer shall send extracts from the Master Record to the Permanent
Way Division Headquarters once in every three months, to enable the Headquarters
Office to monitor the progress of track works on the entire system.
20.13.4 The Regional Engineer shall also utilise profitably the data generated by the system
through various forms as below:
•
,Form > ·
1·••·. · · ·.·;_ .. /·"••us11For •· · · ._·.·~- ·.···•·· :·. i
PTM 1 • Orders for materials
• Fixing Stock Levels in Regional stores .
PTM 1 & PTM 2 • Annual Estimates
PTM3 • Master charts
Steps required to be taken for effective Works Planning can be summarized as under.
20.14.1 Action by PWI in the Year Y-1
7. Prepare the monthly work schedule for all 12 months in Form PTM 3 (Annexure
20.4) and submit to the CPWI;
S. Prepare the final approved programme in quadruplicate and send it to the CPWI,
Regional Engineer and Head of the Civil Engineering Department; and
10. Prepare the Maintenance Programme Diagram (Annexure 20.5).
5. Bring to the notice of CPWI & Regional Engineer, if there is a significant variation to
the original approved programme;
6. Send a copy of the revised monthly work schedule to the Ganger before the
beginning of the month;
7. Determine the works to be executed in each week for every gang;
8. Allocate the deployment of man power for each day in Form R1 (Annexure 20.6);
9. Send the weekly programme on every Friday to the Ganger (for the works to be
executed in the following week);
10. Collect the Form R1 from the Ganger at the end of the week, after the execution of
the work;
11. Check that the actual work in the field is carried out in accordance with the
approved programme;
12. Evaluate the output of work and man days spent in Form R2 (Annexure 20.7);
15, Record the actual work done for the month in Form PTM 3 (Annexure 20.4);
16. Send the Form PTM 3 to the Regional Engineer before 5th of the following month;
and
17. Check frequently whether progress is according to the plan and whether quality is
according to the prescribed technical standards.
7. Obtain the finalized programme for machines from Headquarters and advise PWis;
8. Plan for the Line Possession in the statement at Annexure 20.10;
9. Finalise the programme for Line Possession in consultation with the Operation
Division and advise the PWis;
10. Check that the work carried out in the field is in accordance with the approved
programme;
11. Give directions if the PWis suggest a deviation lo the approved programme due to
special circumstances;
12. Get the weekly report from PWis in Form R2 (Annexure 20. 7) to review the
progress and to monitor the utilisation of manpower;
13. Get the monthly report in Form PTM 3 (Annexure 20.4) from PWis on 5th of the
following months;
14. Check whether progress is according to the plan and quality is according to the
prescribed technical standards;
15. Keep a Master Record of track maintenance works and evaluate unit cost of each
maintenance operation;
17. Identify areas of weakness in maintenance procedures and take remedial action;
18. Compare the performance of various PWis and rectify operations involving
abnormal time and manpower;
19. Send extracts from the Master Record to the Headquarters; and
2(}. Utilise the data generated for effective management of the work.
LIST OF ANNEXURES
Annexure 20.8 Comparison of work load with that of the previous years
20.1 A detailed inspection of the track must be done every year for planning of
the works in the ensuing year. The work is to be done by the PWI along
with the ganger (or spiker) to determine the exact quantity of material
required and the quantum of track work to be executed.
If outer rails on curves show significant wear, lubrication of the gauge face
shall be done. (The adequacy of cant provided shall also be verified
(Please see Clause 12.6).
• Rust and dust shall be removed from corroded rails, using wire
brushes.
• Kinks at joints to be examined for wear on the fishing planes and for
tightness of fish bolts.
• Rail joints to be examined for wear on the fishing planes and for
tightness of fish bolts.
20.2.2 Sleepers shall be inspected for their condition and soundness particularly
at the rail seats. On wooden sleepers, spikes and rail screws shall be
examined for their firm grip. Wooden sleepers shall be checked for split
and decay.
20.2.3 Fastenings and fittings shall be examined to ensure that they are in good
order and appropriately tightened.
20.3 Methodology
1. Wooden Sleepers:
2. Fastenings
Rev. 0 Page 17 of 47
Permanent Way Manual Part IV
Works Planning Chapter 20
3. Sleeper rectification:
• Mark on the wooden sleepers with chalk the work to be done such as
plugging of holes, drilling of holes, shifting of the bearing plate etc.
• Mark with chalk the sleepers to be squared, re-spaced and those
requiring to be re-gauged.
4. Wear and Rail fastenings:
5. Rail:
6. Other works:
MATERIAL PROSPECTING
Class of Line
Inspection of Track
Requirement for
Whole Length
MATERIAL PROSPECTING
Class of Line
Replacement of Sleepers
Total
MATERIAL PROSPECTING
Class of Line
Class of Line
Necessary Works
'.9 0 ""'
*
I
I 0. E
"'
~ c
"' ""'
Km KM m
"0 u.
-~ :E"' "'
"
·~ ""'
·o
m
"'
Q)
a: E
m
"'
"
'6
"5 o.E
Q)
"'
<(
"'
;::
a: C"
m
0.
(f) <!J 0.
m
Q)
"'
0.
Q)
Q)
i" '6"
<(
u; a: ()
Total
ANNEXURE BOOK
ANNUAL CALENDAR PROGRAMME
FOR
TRACK MAINTENANCE WORKS
REGION
PWI
GANGS
YEAR
Checked by:
YARDSTICK
No. Activity Yardstick
1. Levelling and packing of joints 3 joints I man I day
2. Oiling and greasing 8 single joints I man I day
3. Over hauling of Turnouts 12 man days I turnout
4. Over hauling of level crossing 20 man days /level crossing
5. Clearing of side drains 50 m I man I day
6. Cutting of Grass and bushes 250 m route length/ man I day
manually
7. Cutting of grass & bushes with 500m I man I day
machine
8. Complete levelling/Partial levelling 5m I man I day
9. Attending to EM 120 defects list 15m I man I day
CALCULATION OF MANDAYS
51
Example of 1 Quarter
Activity Calculation Mandays
1. Patrol man 5 days in a week x 13 weeks 65
Total = 3 x 12 = 36 mandays
51
8. Complete Over hauling of 1 Quarter - Nil
Nil
Level crossing
TOTAL 225
In this example, in the first quarter, in Gang No.1 out of total 884 mandays, 225 mandays
are to be utilized by planned works as calculated and the balance 659 mandays shall be
utilized for other improvement works & inspection works or to be judiciously used in
adjacent gang lengths that require additional men.
Also, other track maintenance works are to be assessed from past records & the same
planned. The following are other track maintenance works that will be required:
v} Attention to tunnel
(Sample Calculation)
A. Cycles of Maintenance
COH Length
Location
B. Calculation of Man hours
Working Hours
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
Sunday
=
Working hours for a week ................... MH per man per week.
For a year of 52 weeks, working hours ............... = MH per man per year
Less:
Public Holiday ............................. days
Gang No. of men Man hrs. per man Total Man hrs. available
Gang 1 MH
Gang 2 MH
Gang 3 MH
SUMMARY
SI. Work Item FORECAST HOURS Details at
No. Page
Gang 1 Gang2 Gang 3
1. Training of Staff
2. Patrolling
3. C.O.H.
4. E.O.H.
5. Surfacing
7. Sidings
9. Site Cleanliness
14. Gate-Keeping
20. Miscellaneous
1. Total man-hours
1. Training at
School
2. Practical
training at site
3. Safety Lectures
Total
Assumption: For illustration training at school is taken as 6 days, Practical Training at site is taken as
8 days. Training on safety is taken as 3 days.
1. Periodical
Patrolling Of
Track
2. Occasional
patrolling at hot
weather
3. During rainy
weather
Total
Assumption: Periodical patrolling is assumed to last 24days, hot weather patrolling 12days and
patrolling during rainy weather 12days. The duration of each assumed as 4 hours.
2. Renewal of Rails
4. Creep adjustment
5. Sleepers Squaring
7. Regauging
8. Renewal of Sleepers
9. Grinding of Rails
12. Cessing
Total
Assumption: The output of each activity in man-hours per unit is assumed for an average worker and
illustrative
2. Lubrication of joint
(without disassembly)
3. Tightening of Fastening
Total
Ref No 5: Surfacing
S. llem of Work Units Quantity Calculation Forecast Hours
No. Gang Gang Gang Man-hour Gang Gang Gang
1 2 3 per unit 1 2 3
1. Complete levelling & lining
3. Joint levelling
4. Lining/Siewing alone
5. Alignment of Curve
Total
(A)
Total (A)
(B)
S. Item of Work Units Quantity (No.s)
Calculation Forecast Hours
No. Gang Gang Gang Man-hour Gang Gang Gang 1
·. 1 2 3 per unit 1 2
2 .. Checking safety
Measurements of Clearances
3. Lubrication
4. Tightening bolts
5. Minor Repairs
Total (B)
(A)
Total (A)
(B)
S. Item of Work Units QuantityCalculation Forecast Hours
No. Gang Gang Gang Man-hour Gang Gang Gang
1 2 3 per unit 1 2 3
1. Minor repairs
4.
5.
Total (B)
2. Sleepers
3. Fastenings
4. Ballast
5. Chippings
6. Cess Materials
7. Others
8.
9.
Total
3. Bridge
4. Culvert
5. Drains (m)
6.
Total
2.
Total
Total
2. Supplying materials
Total
2. Material replacement
(a) Fastening
(b)
(c)
Total
Total
2. FlagMan
Total
2. Transportation
3. Payment
4.
Total
Total
Assumption :The tamping machine is assumed to have an output of 800 sleepers per hour.
Total
1"--"'
Programme for January 20 ...... .
2. Patrolling
3. C.O.H.
4. E.O.H
5. Surfacing
7. Sidings
9. Site Cleanliness
10. Derailments/Accidents
11. Sickness/Absenteeism
12. Renewals/Special
works
13. Level Crossing works
14. Gate-keeping
15 Track Protection
Note: Where it is not possible to identify the quantum of work, the previous year's actuals as indicated
in Annexure 20.7 can be adopted.
~
KONCI %KEMAJUAN
CJ KERJA TIDAK DIRANCANG
(hila m)
M.IWAl SUtNAII
~
'
c:::J C.O.ll
(hijau)
~
~
~
CJ PEPARlTAN
~
~
~ (ungu)
~
~
~
~
c:::J E-~O.H 24
jcoklat) Ifs CJ POTONG RUMPUT
'22 (sengkang ungu)
fii
tfo
c:::J PERATAAN PENUH '"i9
~ CJ m
I
{merah) MENEBAS HUTAN
~
"16
'E
c:::J PERATAAN SEPARUH
(selljfkang merohl
'14
~
fE
ru~
I
c:::J PERATAAN SAMBUNG
{kunlng)
Fg
7 ~
c:::J POIN & CROSSING
~
'6
rt
l"t IZJ RANCANGAN I
c:::J
{seng:kang bitam)
MEMINYAKAPITREl
(biru)
7
ti:
1-1"
i- '»
~
r;.
ISI TELAH DILAKSANAKAN
If+
tfo
tt
tU.
ffs
,_ j-~ 1~11
~ CUCf BAlAST
1ft MAKLUMAT
ITs '>•MSATI\l'l
~ LANOASAN
tTI
~ TOKARREL t"20
tfg
it.
t:':
; /FITTINq
f¥· ~
~·
~
~
TUKAR KAYU LANOASAN
...¥
~
13
@
KmETAPI TANAHMELAYU BERHAD
q
s: OISTRJCT
~
CD
PWI WEEKLYREPORT(RI) WEEK NO:
ci
z
CJi
NAME OF WORKM AN
z
0
F=
<
z
0
[ii
Q
M T w T F s s M T w T F s s M T w T F s s M T w T F s s M T w T F s s
REMARKS
)>
I
i
:::s
I :::s
Cl)
2
><
s::::
~
Cl)
3
N
0
4
5
a,
I
.,
Cl)
6 :E ~
~~:::s
Cl)
Cl)
7
25: 0
;:o
(!)
:::.
8
.,
"<: .... Cl)
'A;:s
(/J ..
0 9 ~
0
cc
J2:E
t1> AI
..,
10
AI s' <
s· s:
11 3 <OAI
12 3 :::s
-
Cl)
s::::
13 ~
"11
14 0..,
3
;:o
....
TOTAL& WORKING PLACE
{ACTUAL)
"'0
fl) (")
CO ~
(!)
~
(,.,)
- - I -c.,
AI
-
0
......
r:-
PUBUC HOUOA Y CA NOT PRESENT 111 TRAINING BK Prepared by PWI on 20
-AI
~::l
N-
o<
YEARLY LEAVE CT SICK s UNRECORDED LEAVE CIR Received by Ganger on 20
Permanent Way Manual Part IV
I CTIIII Works Planning Chapter 20
2 Pet rolling
iii)
7 Loop I S idings
9 S ite Cleanliness
10 Dcraibnents I A cc id ents
11 Sickness I A bsentee ism / Acciden ts
12 Re newals I Sp ecia l W orks
14 Gate-keeping
I S Track Protectio n
16 Tile Lost
19 Ballas t Cleaning
20 Miscellaneous
TOTAL
i. Rails :
ii. Sleepe rs :
Annexure 20.8- Comparison of Work Load with that of the previous Years
2. Patrolling
3. C.O.H.
4. E.O.H
5. Surfacing
6. Switches &
Crossings
7. Sidings
8. Loading &
Unloading
9. , Site Cleanliness
10. Derailments/Accide
nts .
11. Sickness/Absenteei
sm
12. Renewals/Special
works
14. · Gate-keeping
15 Track Protection
16. Time lost
17. Other Track
Maintenance Works
Section Jurisdiction Km to Km
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Complete Over-
1. Hauling
2. Surfacing
Realignment of
3.
Curves
Renewals/Spec
4.
ial Works I
Ballast
5.
Cleaning
6. Miscellaneous
Section Jurisdiction Km to Km
"-I""'""
Km Engineer
.
day in of Days in kmph in days
hours
2 3 4 5 6 7 8 9 10 11 12 13
1. Jan.
2. Feb.
3. Mar.
4. Apr.
5. May
6. Jun.
7. Jul.
8. Aug.
9. Sep.
10. Oct.
11. Nov.
12. Dec.
Chapter 21
Track Maintenance System
Document History
Issue Date Prepared By
Authorised By:
~r '
Signature:
Date: MOHD RAMLI MOHO NOH 2 I MAY 201~
General • •
- w,.u
Ktretapt Tilnah Melayu Berhad
.,
Kuilla Lump~Jr
TABLE OF CONTENTS
21.1 GENERAL
21.1.1 As brought out in Chapter 20, the works required to maintain the track to the prescribed
standards can be divided mainly into two categories. These are:
21.1.2 There are certain other scheduled works which are carried out at specified intervals.
21.3 ACTIVITIES
21.3.1 General
The following activities need to be carried out on a periodic basis as shown in Chapter
20, Table T-20.1.
• Examination of the track including checking of all components and analysis of track
deterioration and defects
• Replacement of worn out components and
• Attention to track geometry, levels, track cross sectional profile and other track
defects
21.3.2 Maintenance input
The periodicity and input of maintenance work will depend upon the rate of deterioration
of track components and track geometry. This will vary from section to section. However
periodical works and track inspections shall be performed in accordance to the stipulated
period defined in Chapters 20, 47 and 50.
Complete track renewal will be prescribed by the General Manager Permanent Way,
taking into account the above mentioned aspects and all other relevant factors.
21.3.3 Sequence of Operations
1. Inspection of Track
This involves:
i. Checking of measurements;
ii. Checking condition of components, including ballast, sub-ballast etc.; and
iii. Examination of drainage and vegetation condition.
2. Track Components maintenance
In this operation, all components are attended to and track assembly is brought to as
perfect a condition as possible. Worn out and defective track materials are
renewed, missing components are replaced, and loose fastenings are tightened. Re-
gauging of track is done where required. Preventive maintenance of track materials
is also carried out to get longer lease of life.
3. Track Geometry Maintenance
• With use of Tamping Machine
• Manual Lining and levelling(including rectification of alignment in curves)
21.4 METHODOLOGY
21.4.1 Inspection of Track
There are two types of inspection (a) for defects identification and rectification (b) for
annual planning purpose. Defects identification are part of the schedule patrolling and
inspection as defined in Chapters 50.
21.4.2 Inspection for planning
1. The process starts one year in advance, when the inspection of track and planning of
works for the ensuing year is made. Since inspection for planning is done a year in
advance, the inspection is confined to update the data already logged. This will take
into account changes that have occurred during the intervening period.
2. The inspection shall identify:
Track surfacing and lining defect rectification is done by packing of the track either
manually or by on-track machines to bring the track to correct line and level. Depending
on the extent of work, the packing or tamping work can be through continuous or spot
tamping.
Modern On-track tamping machines carry out lifting, levelling, aligning and tamping of
track, all automatically and simultaneously. The working of the machines is described in
Chapter 22.
Tamping Machine can be utilised for continuous through tamping, isolated tamping for
picking up slacks and low joints.
21.4.5 Lining
Lining refers to the rectification of alignment. The procedure adopted for the lining of the
track manually is described in Chapter 39. This method is only suitable for timber sleeper
tracks whereas rectification of alignment for concrete sleeper track shall be by the use of
On-track tamping machines.
• The rails are at their correct relative level (Tangent track are level and curves
provided with the required cant).
• No sleeper has a void at the sleeper seat.
2. Method of levelling:
• Where the work is done manually for timber sleeper areas, the operations
involved in complete levelling are described at Annexure 21.1. Simultaneous
lining and levelling operation with on-track machines is employed for high speed
and concrete sleeper lines. 11 is described in Chapter 22.
• The operations involved in partial levelling are described at Annexure 21.2.
• The operations involved in joint levelling are described at Annexure 21.3. This
method is only for use in timber sleeper tracks.
For spot levelling, manual packing with the use of portable hand tamper is described
in Annexure 21.1.
Beater packing shall NOT be used for concrete sleeper tracks and is only
allowed for timber sleeper track.
Hand Held Tampers are to be used in groups of four men. The ballast shall be cleared
from the side of the sleepers and the portable tampers are operated initially from a
near vertical position. They are then worked down at an inclined angle to the
horizontal allowing the ballast to be squeezed under the sleepers. The ballast shall be
forced right under the sleepers but it must be ensured that the machines are not held
too inclined such that the track gets lifted or too long such that the ballast stones gets
broken up.
21.4.7 Periodicity Of Scheduled Works
21.4.8 The periodicity for execution of scheduled works is summarised in Chapter 20, Table T-
20.1
LIST OF ANNEXURES
Annexure 21.1 Manual packing by beaters
Annexure 21.2 Partial Levelling
Annexure 21.3 Joint Levelling
i. Opening up of ballast
ii. Examination of rails, sleepers and fastenings
iii. Squaring of sleepers
iv. Slewing of track to correct alignment
v. Gauging
vi. Packing of sleepers
vii. Repacking of joint sleepers
viii. Boxing of ballast section and tidying
These operations are described below:
1. Ballast in the cribs shall be opened out from the end of the sleepers to 350mm
inside rail seats for a depth of 50mm below the packing surface, without disturbing
the cores under the sleepers. At this time, the rails, sleepers and fastenings shall
also be examined for defects. Squaring of sleepers, where necessary, shall be
carried out after the ballast have been opened up.
2. The ballast shall be drawn by shovels. The portion of ballast on the outside of
the rail shall be drawn outwards and the portion between the rails shall be drawn
towards the centre. Care however, shall be taken to see that the ridge, which forms
between the rails, does not project more than 50mm above rail level.
3. One rail (the base rail) shall be sighted by the Ganger along the lower edge of
the head of the rail and any dip or low joint lifted correctly. (Lifting may be done
either by crowbars or by jacks). The adjacent sleepers shall then be packed and the
top checked. After two rail lengths have been thus attended to, the rail on the other
side shall be brought to the correct level, checking cross level at every rail joint and
at every fourth sleeper. The next two rail lengths shall then be taken up and the
process continued.
4. No joint or dip shall be lifted higher than the correct level in the expectation that it will
settle to the correct level.
5. Having aligned the track and adjusted the 'top', PL shall be distributed in batches of
two for packing all sleepers in a systematic manner, commencing from one end.
Four men shall deal with every sleeper successively, two at each rail seat. The
ballast under the sleeper shall be packed by the· men standing back-to-back and
working their beaters diagonally under the rail seat at the same time to ensure firm
packing.
6. it is important that PL should thoroughly 'break' the cores with the "pick" ends of
their beaters and then use the "blunt" ends, as otherwise, uniform packing will not be
achieved and elasticity of the track-bed will be affected. After packing the rail seat,
the packing shall be continued outwards to the end of the sleeper and inwards for
350mm. Beaters shall not be lifted above chest level, the strokes being kept as
nearly horizontal as possible.
• forcing under the sleeper any large stone, which may cause uneven bearing.
• striking the edges of the sleepers. (All men shall aim to work the beater from the
same height (chest level) so that the sleepers are uniformly packed. Higher or
lower lifting of the beaters results in uneven compactness).
8. Packing under the rail seat of the wooden sleeper causes the ballast to work towards
the centre. Before final dressing is done, it shall be ensured that no sleeper is
'centre-bound' by working the pick ends over the central ridge.
9. Care shall be taken while packing to ensure that the work does not result in adjoining
sleepers being lifted off their bed, thus creating artificial voids under them.
10. Before boxing the track, the packing under every rail seat shall be checked by the
anger by tapping with a wooden mallet or canne-a-boule. A hollow sound indicates
defective packing, which shall be re-done again.
11. As soon as packing is completed, slight distortions, if any, in alignment and top shall
be corrected, sleepers disturbed for this purpose being finally repacked.
12. The joint and 'shoulder' sleepers shall be repacked and the cross-levels at joints
checked (before boxing of ballast is done).
13. Boxing of ballast section and tidying up of the work site.
1. Partial levelling shall be done where the alignment is kinky or top level is uneven
and the track has to be restored to normal condition quickly. In the field, partial
levelling is also commonly called as 'picking up of slacks' or 'casual packing'. Partial
levelling would also entails partial lining for correction of horizontal a·lignment.
• inspections and
• results of track recording runs by the EM-120 car.
2. Procedure for Partial Levelling:
At first, sighting is done, the defects assessed and marks made on sleepers. The
marked sleepers shall then be attended to using beaters or portable hand tampers,
care being taken to see that the packing of adjacent sleepers does not get
disturbed.
The procedure for partial levelling using beaters or portable hand tampers is the
same as indicated in Annexure 21.1.
The sequence shall be as follows:
Note:
1. In continuous levelling, provide a general lift of 1Omm for the first round of
packing and 5mm for subsequent rounds.
Joint levelling can be done either by beaters or by portable hand tampers. Joint levelling
means picking up of joints ensuring the rail are in line vertically and laterally and packing
them to ensure a better ride quality and minimise damages to the joints.
Chapter 22
On-Track Machines for Track
Maintenance Works
Document History
Authorised By:
Signature:
~r'
MOHD RAMLI MOHD NOH 2 8 MAY 2015
Date: General Manat~er Permanent Wav
Keretap• Tanah Melayu Berhaa
Kuala Lumpur
TABLE OF CONTENTS
22.1 GENERAL
22.1.1 The superiority of mechanised track maintenance over manual maintenance is well
known. This is mainly on account of the following factors:
..... .
SQUEEZE FORCE SQUEEZE FORCE
...
...
.. TAMPING REACTION
FORCE
DIRECTIONAL VIBRATION
The tamping process beg ins with the insertion of the tamping tines into the ballast in
between the sleeper crib. Upon penetration of the ballast bed from above, the ballast are
compacted under the sleeper with a squeezing movement. All the tamping tines work with
the same pressure and frequency of vibration. This directional, linear vibration combined
with the non-synchronous tine movement thus produces a homogeneously compacted
ballast bed.
22.2.3 The following types of On-track machines are presently in use in KTMB:
22.2.3.1 Tampers (Plain line)
These machines lift, level and align plain line track. Technical features of these machines
are given in Annexure 22.8.
22.2.3.2 Tampers (Turnouts)
These machines do similar work on turnouts. They can also tamp the approach track near
switches and crossings at a slower rate compared to the plain line tampers. Technical
features of these machines are given in Annexure 22.9.
22.3.1.2 In compensating (smoothening) method, track is measured at 4 points and the two
versines are compared to control the lining. The existing errors are reduced in this
method and the curve is smoothened.
22.3.1.3 In the precision method, track is measured at three points and lined according to specific
theoretical versines. If track is to be lined with respect to fixed points, this method is
adopted.
22.3.1.4 Further details of the Lining system are given at Annexure 22.1.
22.3.2.1 The leveling system in the machines can provide levelling either by smoothening method
or absolute profile method.
22.3.2.2 In the smoothening method a pre-selected general lift is decided. During tamping, the
track gets the desired lift along with the reduction in irregularities in longitudinal level.
22.3.2.3 In the absolute profile method, longitudinal level is pre-marked and absolute longitudinal
level is obtained.
22.3.2.4 Further details of Levelling system are given at Annexure 22.2.
These machines are used for complete screening of ballast. The muck in the ballast is
removed and clean ballast is put back on the track. Technical features of these machine
are given in Chapter 25, Annexure 25.1.
As the name suggests, these machines are used for the interchange of sleepers in track.
These machines can be used for loading, unloading and transportation of railway
materials. They can also be used as locomotives for pulling a few wagon's for
departmental use. Technical features of these machines are given in Annexure 22.10.
They consolidate the ballast and increase the lateral and longitudinal resistance of the
track.
22.4.6 Dynamic Track Stabilisers (DTS)
They produce fast, accurate and controlled settlement of the track and give the desired
degree of compaction to the ballast bed. Refer to Annexure 22.11
A minimum depth of 150mm of clean ballast below the sleepers is necessary for the
proper functioning of track tampers. Adequate ballast should be available in the
shoulders and cribs. For this purpose, cleaning of ballast and provision of additional
ballast at deficient places shall be done well in advance.
22.5.2 Formation
An unyielding formation with uniform strength characteristics is considered desirable for
the success of mechanical tamping.
22.5.3 Line Block
On-track machines require Line Possessions for their working. lt is desirable to obtain as
long a Line Possession as possible, so that the net time available for working on the line
is reasonable, for economical and productive performance of work. Time allowance for
working the machines shall be provided in the train operation Time Table. For this
purpose, the Regional Engineer shall arrange a programme for working the machines in
consultation with the Operation Department and forward it to the Headquarters office.
22.5.4 Rules forworking machines
The working of on-track machines in Block Sections shall be governed by the provisions
of the Appendix 9 to the General Manual of the current KTMB Rules and Regulation
Book.
22.6.1.15 Clearing of ballast on sleepers to make them visible to the machine operator.
22.6.1.17 Ensuring good drainage of water from track and cleaning of drains.
22.6.1.18 Estimating the rail temperature during working hours and deciding the possible duration
for execution of work. (Refer to Chapter 25, clause 25.5 & 25.8).
Note:
Tamping of welded rail track shall be done when the rail temperature is below Id + 5"C. If
the temperature after tamping rises above Id + 20"C during consolidation period, a speed
restriction of 30 km/hr shall be imposed with the use of crib and shoulder compactors.
Otherwise a speed restriction of 20 kmph shall be imposed till the passage of 20,000
gross tonnes of traffic. (Annexure 22.6 gives a sample guide for estimating train
tonnage/day)
Other than consolidation by rail traffic, ballast consolidation is achievable with the use of
Dynamic Track Stabiliser (DTS). In this case, the imposition of a speed restriction is not
necessary, provided the track geometry requirements are met.
Marking, for the guidance of the Machine Operator:
If the absolute profile method of longitudinal levelling is adopted, the lift required on
sleepers shall be indicated on every fifth sleeper of the reference-rail. Similarly if the
precision method of lining (3-point system) is adopted, the quantum of slews shall be
indicated on the reference rail at 10 meter intervals.
Note:
Normally one insertion up to 20mm lift and two insertions for lifts above 20mm will be
sufficient. One additional insertion may be required for joint sleepers.
22.6.1.21 Indicating the location of the run off ramp.
Note:
A run-off ramp of 2mm per sleeper shall be given before closing the day's work, as a
temporary measure. Permanent ramp shall be flatter than 1mm per sleeper.
If D is the date programmed for machine working all preparatory work shall be completed
as indicated in Table T-22.1 below.
Table T-22.1
·..•.....•....•.•...·
...•....···········•··
Unloading of ballast
• ~~~Ill ot.~ork .
.....·.·.·······••··
·Tiuget Date for <:PW~Ietiq~ .of'Nqrk
D-14days
Recording of versines D- 7 days
Working out slews D- 3 days
Indication of levels and slews D- 2 days
All other works as indicated at clause 22.06.1 D- 30 days
22.6.4 PWI shall give the certificate for track preparation for tamping machines in Form JM-5
(copy at Annexure 22.3) for plain track and Form JM-6 (copy at Annexure 22.4) for
switches and crossings.
22.6.5 PWI shall also provide the information as indicated in Clauses 22.6.1.19 to 22.6.1.23 to
the machine operator.
The tamping (squeezing) pressure shall be adjusted according to the type of sleeper, as
per the recommendations of the manufacturer.
22.7.3 Insertions
Care shall be taken to ensure that tamping tools are inserted centrally between the
sleepers into the ballast to avoid any damage to sleepers, the number of insertions being
in accordance with Clause 22.6.1.21.
The shoulders shall be compacted along with tamping, where provision for shoulder
compaction is available on the machine.
22.7.5 '.. Obstructions
At obstructions such as signal rods, cables, pipes and check rails of Level Crossing, the
Operator shall exercise special care to avoid damage.
22.8.1 Fastenings
As some of the fastenings might get loose, all such fastenings shall be examined
immediately after tamping and tightened where required. Broken fastening shall be
replaced.
Gauge and Vertical Clearances shall be checked and adjusted, wherever necessary, after
tamping.
22.8.3 Quality Assurances
A check of the work done by tamping machine shall be carried out by the PWI of the
section. At places where the track geometry is not found within acceptable limits, the
work shall be repeated. A check list for quality assurance is given in Annexure 22.5 for
guidance.
22.8.4 Ballast
Ballast shall be re-profiled neatly and consolidation of ballast between the sleepers shall
be done. Ballast regulator/shoulder and crib compactor/Dynamic track stabiliser, shall be
used, where available. If ballast is found to be deficient after tamping, additional ballast
shall be provided without delay.
22.9.2.1 Where more than one machine is used in the same Block Section, the movement of the
machines is coordinated to ensure safety in operation.
22.9.2.2 A system of "Look out" is enforced to ensure safety of workmen especially where
adjacent lines are open to traffic (See Chapter 52, Clause 52.4.2).
22.9.3.1 That the machine is fully equipped and the brakes are in order before commencement.
22.9.3.2 Ensure that the maximum speed does not exceed what is specified (generally 70 km/hr in
train formation, 70 km/hr when running under its own power, 40 km/hr over high speed
turnouts and 25 km/hr over conventional turno.uts) and that the machine does not infringe
the adjoining tracks.
22.9.3.3 Follow the safely precaution as indicated in Chapter 47, Clause 47.4.4 while operating
the machines.
22.9.3.4 Ensure that all locking devices are properly secured, brakes are "on" and the switches are
put to "off' while stabling the machines. Wedges or sprags shall be used under the
wheels on track laid on gradient for additional protection.
22.11.1 Only trained and experienced persons are deputed to operate the machines.
22.11.2 Calibration of machines is checked as per procedure and intervals specified by the
Permanent Way Depot engineer, local authorised agents or manufacturers.
22.11.6 Development of adequate repair facilities in the field as in the base workshop.
22.11.7 Overhaul of each machine after prescribed interval.
22.11.8 Training of staff associated with the machines (the Operators, the Maintainer and
Permanent Way staff) in proper operation and maintenance of the machines and in the
techniques and principles of working of the machines (Chapter 54).
LIST OF FIGURES
Figure 22.1 -Operation of Tamping Workhead (source: Plasser & Theurer)
LIST OF ANNEXURES
Annexure 22.1 Details of the lining system.
Annexure 22.2 Details of the levelling system.
Annexure 22.3 Certificate for track preparation for plain track {Form JM - 5).
Annexure 22.4 Certificate for track preparation for switches and crossings
(Form JM - 6).
Annexure 22.5 Check list for Quality Assurance.
Annexure 22.6 Example Calculation of Traffic Load/day
1 = THEORETICAL ALIGNMENT
2 = BEFORE LINING
3 = AFTER LINING
n= F. = INITIAL ALIGNMENT DEFECT
F, = RESIDUAL ALIGNMENT DEFECT
n = ERROR REDUCTION RATIO
i = VERS!NE RA110
COMPENSATING METHOD
ANNEXURE 22.1 Fig. 1
Then {AC 1) x (C 1 D)
= 2RH 1- H12
= 2RH 1 approximately since H 1 is small
AC1 x C1D
= ---'-'-'---"'------
H,
2R
AB1 x 8 10
Similarly, H2 =
2R
H1 AC1 x C1D
:. Versine ratio i = -- =
H2 AB1 x 8 10
Thus i is independent of the radius of the curve.
In this method the versine H at point B is measured and this represents the measuring
base. The track which may not be in proper alignment is stewed in such a way that at
point C, the versine H is in the correct ratio to H (i.e.) till H=HXi
Trolleys at A, B, C and D are pneumatically pressed against the rail selected for line
measurement, usually the high rail of a curve. The wire chord stretched between A
and D represents the 'Reference Line' and the transmitting potentiometer (Transducer)
which are fixed to the measuring trolley B and lining trolley C are connected to this wire
by means of Forks and the wire drives.
The measured ordinate at B is multiplied through the electronic circuit by the specified
ratio and compared with ordinate at C. Then electronic signal is emitted which activates
the hydraulic control of the lining mechanism to effect necessary correction.
When working on transition portion of curve, necessary adjustment can be applied by
digital control on the front trolley. When the front tower of the tamping machine enters the
curve, the rear tightening bogie is still on straight. Therefore, it experiences error because
of the curvature and certain adjustments have to be applied at the front bogie to
compensate the error due to curvature. Similar adjustments are also required when the
tamping machine leaves the curve at other end.
3. Precision Method
WQRK!NG Q!BfCIR!ON
A B
Iv. =HI
+ f·l 1 =
2 =
1HEORETICAL ALIGNMENT
BEFORE LINING
3 = AFTER LINING
Fo 4 = ACTUAL. POSITION OF 1HE LINING CHORD
IF. =--
n
5 =
Fo =
F, =
1HEORETICAL POSITION OF 1HE LINING CHORD
INITIAL ALIGNMENT DEFECT
RESIDUAL ALIGNMENT DEFECT
n = ERROR REDUCTION RA 110
BD
In= BC
PRECISION METHOD
ANNEXURE 22.1 Fig. 2
BKxKD
Versine h =
2R
The lining mechanism is operated in such a way that point C is shifted to the correct position to obtain
ideal versine h.
In three point lining method, only Versine is measured by lining transducer and same is
compared with theoretical Versine, which is fed by Versine potentiometer from front
cabin.
The same principle is applicable for lifting. Thus this technique is also called the precision
lining and levelling method.
1.1 The level of each rail is sensed separately with the help of rollers at the following three
points:
1.2 The reference line for longitudinal levelling is a steel chord stretched over each rail from
the rear reference point to the front one.
1.3 The equipment rolling over the tamping area carried sensors, which scan the height of the
reference chords, with respect to each rail. The signals from the sensing device get
amplified and act on a servo system, which controls the lifting cylinders.
1.4 The longitudinal levels are corrected by the tampers on the principle of proportional
levelling.
2. Method of levelling
• Smoothening method
• Absolute Profile Method
3. Smoothening Method
In this method, a pre-selected general lift is decided. The total lift of the track is the sum
of
Annexure 22.3 (Sheet 1) -Form JM-5 Certificate for Track Preparation for
Tamping Machine
Region ......................................................... .
Location Km ..................... .to ...................... .
NameofPWI ............................................... .
Section .......................................................... .
:;N~·· I .· · •··. Item ofw~~l< •.·.i···•i...... i:.; i M~r~ (o[lick) the Date of •• Remarks ·.
..............I··· ..···. . ...•
-
•••••••••••••••••••••••••••
j
Note:
1. All preparations shall be completed one month before the machine working.
2. Ballast to be unloaded two weeks in advance.
PWI
Date ........................... .
Annexure 22.3 (Sheet 2) -Form JMS A & B for use in Electrified Lines
From: ~s:A]
Regional Engineer Date value taken ......... I ............ 1.... ....... .
To
Between
I station I station Ene I
GM Electrification
Tamping lining machine is programmed to work at following location on (date) ........ 1......... 120 ......
Listed below irregularities observed and require confirmation for OIH Staggering values column 12,13 & 14.
Please make the necessary clarification before (date) I 120
Location Mast No Actual value Track Freeze Value Difference OIH Equipment
1 2 3 4 5 6 7 8 9 10 11 12 13 14
No R. Remarks
Off R. Cant
Off R. Off Set Level Cant Values Values Height
Set Level Set Level Theo.
Km Cant 13- 6) 14-7) 18- 5) Left Riaht
5 ----····-----
I For;1,JM 58 I
From To
PWI Machine Regional Engineer
No I I
Date Worked
Copy
Between Mechanize Engineer PWD HQ
UP/ON/Single L__ _ _ _ _ _L__ _ ____J
Location mentioned below has been worked and given below for your information
and for the necessary record
Prepared by : Verified by :
Date: Date:
Annexure 22.4 - Form JM-6 - Certificate for Track Preparation For Tamping
By Turnout Tamper
Region .............................................................. .
Section .............................................................. .
Name of Station ........... : ..................................... .
Identification No. of Turnout .............................. .
Kilometer ........................................................... .
Name ofPWI ...................................................... .
damaged sleepers
8. Adjustment of gauge.
1
1. Crosslevel Every 5 h sleeper &
joint
3. Alignment On10mbase&at10
m interval (20 m chord
in curves)
Packing raillength
6. Shoulder To be checked in
consolida- lengths.
tion.
7. Run off
ramp at the
end of the-
day
action taken
1. Tightening of fastenings
2. Replacement of missing or
broken fastenings
3. Profiling of ballast
1. AT the start of every day's work all track parameters and quality of packing in the first
three rail lengths must be checked thoroughly after tamping and machine setting
corrected accordingly.
2. All defects noticed after tamping operation must be attended to by machines
immediately. If not, appropriate speed restriction shall be imposed. The machine shall
not leave the PWI's section without attending to the defects.
PWI
Date ....................... .
Basis of calculation:
ii. Number of EMU services per hour = 8 (assumed every 7.5mins for busy
section, use lesser figure if the frequency is less)
v. Freight trains/day= 6
20x 8 =160
EMU - 6x4x15
15 (@ 7 .5 minutes 160x360=57600
6 car sets =360
interval)
ETS These 10 services
trains- 6 15 360 4 4x 360= 1440 are to be
car accommodated
Intercity within the 160 EMU
500 6 6x 500=3000 services /day
lrains
Runs between
2400 hrs to
Freight
1200 5 1200 X 5 =6000 04 00 hrs
trains
.Accounts for only
10% of traffic
Total 68040
1
(tonnes)
'
i
·.·· ..
.· ... ·.• ·.·· . . .··.
.· · pertram . ·· .· ·.·......•.·.··.·. •••• . . .. · . .··. ·.
Rapid commuter
312 10 3120
EMU
Intercity passenger 500 6 3000
Freight trains 1200 4 4800
Total 10,920
Width 3080 mm
Height 3200 mm
2. CENTRE PLOUGH
The centre plough is hydraulically adjusted in height which allows its precise adaptation
to sleeper position. In this way the sweeping unit fixed to the end of the machine is
allowed a higher output which in turn increases the output of the machine. The centre
plough is composed of a number of rigidly fixed guiding sheets and a number of mobile
guiders.
The mobile guiding sheets allow the ballast to flow:
3. SHOULDER PLOUGHS
Two hydraulically adjustable shoulder plough are fixed between the axles of the machine
to obtain any disired profile. The extension or retraction of the ploughs is hydraulically
powered and gives flexibility to adjust to the width of the embankment. The angle of the
lateral ploughs may be adjusted from 0 to 45 degree through any slant of the ballast
profile.
In case of obstacles, the shoulder ploughs may be retracted, still keeping the same angle
so that no ballast is heaped up. Measured from track centre, the shoulder plougs have a
range upto 2500 mm and can work at a level 1,250 mm below rail top.
4. SWEEPER UNIT
The sweeper is mounted in a welded steel plate housing. The rotating brush consists of
a nurnber of rubber hoses. lt brings excess ballast via deflectors to either side of the
machine. The sweeper is hydraulically driven via a double chain.
Gauge 1000 mm
Width 2800 mm
Height 3300 mm
Weight, (approx) 34 t
2. Frame
Rigid frame riding on two free steering axles in front and rear.
A work unit frame is arranged between the axles. The frame is joined to the main
machine frame by a longitudinal roller guide in the front and supports itself on the track
by an axle in the rear.
3. Engine:
Two independent tamping units are attached to the work unit frame between the front
and rear axles by means of vertical guiding columns. The work unit frame is joined to the
main machine frame by a roller guide for longitudinal movement and is supported on the
track at the rear end by one axle. During work, the machine moves continuously and the
work unit frame is driven hydrostatically and by a hydraulic cylinder in a cyclic motion.
The work sequence is controlled, either fully automatic or by the operator using pedals.
The units carry a total of 16 tamping tools (8 per unit) arranged in pairs with which one
sleeper may be tamped at a time.
5. Tamping system:
During tamping, a resistance is built up in front of each pair of tools. Once the resistance
reaches the pre-selected pressure, the corresponding tool pair stops automatically. The
other tools continue working until they too encounter the same resistance in the ballast.
The lifting and lowering of the tamping units is achieved by means of hydraulic cylinders
which are controlled proportionally. The tamping depth is set, as required, on a digital
selector.
7. Tamping Tools.
The tamping tools (drop-forged of special steel) are arranged in opposing pairs on each
side of the sleeper. Each sleeper is tamped by 2 such pairs, on both sides of each rail.
The corresponding pairs penetrate the sleeper crib at the same time.
The spade-like edge permits easy penetration of the ballast. Worn tamping tools may be
re-surfaced economically by welding.
The machine is equipped with roller lifting and lining units which are attached to the work
unit frame in front of the tamping units and supported each by a vertical guide column.
As the lifting and lining installations are combined, both operations are achieved in one
passage.
The lifting and lining operation is started automatically by lowering the tamping units.
Lifting lasts until the levelling equipment interrupts the control circuit of the automatic
lifting action. The track is held in a raised position by the clamp until completion of the
tamping operation.
The control of the lining process also is fully automatic. Lining errors are detected by
one chord system and electronically transmitted to the control. Lining is automatically
switched off, once the correct value is reached.
After the work cycle is finished, the work unit frame advances to the next sleeper to be
tamped.
9. Levelling Unit
The system (rolling over the tamped area) carries a measured value received on both
sides scanning the height of the steel chord.
Lowering the tamping units initiates levelling operation. The measuring installation over
the tamped area determines the necessary amperage for lifting. This amperage is
amplified and acts on a servo system, which controls the lifting cylinders.
As the levelling and lifting unit works during the entire tamping process, the track level is
automatically checked the whole time. The raising of the tamping units interrupts the
levelling process. Cross level is also controlled by the two steel chords. The "front tower"
carries an electronic precision pendulum which automatically controls the cross level of
the two chords. In this way, cross level is always set to the desired value.
10. Working methods
When working according to the compensation method all errors in longitudinal level
are reduced. Cross level faults are completely corrected.
The total lift of the track is made up of:
The basic lift is pre-selected by adjusting the height of the appropriate reference
line.
2. Precision method
The lifting values of the reference rail are established by levelling before the start of
work and marked on every 5th. or 1oth. sleeper. During work the corresponding left
or right hand reference line is set according to the marked values, while the other is
automatically raised to the correct crosslevel. The lift itself is controlled as
described above. With this method, an absolutely correct londigtudinal level is
achieved.
a) The cross level of the sleeper under tamping is checked by another electronic
pendulum. A large panel and a digital presetting for the required superelevation
allow very precise readings.
b) For the control of the cross level of the corrected track, the machine is equipped
with a digital display and an electronic pendulum.
12. Lining measuring system
The one chord measuring system is a compensation system, by which faults are
detected and reduced by the lining unit. it also allows lining to previously established
fixed points.
Width 2800mm
Wheelbase 8000 mm
Gauge 1000mm
2. ENGINE
Water cooled GM-Diesel engine.
Output: approx. 167 KW (227 HP)
The engine and accessories are fixed to the frame by means of metal-rubber springs.
3. DRIVE
During travelling on its own power, the drive is provided from a hydraulic motor via axle
gear on the rear axle.
During work, the drive is provided by the same hydraulic motor over a special control
circuit.
Max, driving speed self-propelled: up to 60 km/h in both directions, infinitely variable.
4. OTHER FEATURES
Other features of the machine are similar to standard plain line tamping machines,
except the tamping unit which is described below:
1. Tamping Unit:
One tamping unit is mounted on two vertical guide columns immediately in front of the
rear axle.
The work unit frame is guided on two lateral columns which in turn are fastened to the
main frame. By a hydraulic motor and a chain-drive the tamping unit can be moved
laterally.
2. Tamping system:
Same as in plain line tamping machine except the working of the tamping tools as
indicated below.
3. Tamping tools:
Each tamping unit has four forged tamping tools; their conic shafts are secured by
screws and springs to the swing arms. Four swing levers carry a joint on their lower
end. This joint allows the individual tilting of each tamping tool parallel to the sleeper. In
this manner the tools may be adjusted up to an angle of 15" towards the inside and 85"
towards the outside from their normal vertical position. This allows also tamping of
switch areas including such inaccessible parts as diamond crossing, wing rails, check
rails, etc.
The tilting of the tamping tools is hydraulically controlled from the operator's seat.
The TG 80-4 is a heavy duty permanent way car with high traction force for all round use.
1. TECHNICAL DATA
Length 17740 mm
Width 2500 mm
Height 3420 mm
2. MACHINE DESIGN
The chassis has two 2-axle bogies. All axles are powered hydrodynamically.
At one end, there is the enclosed driver's and operator's cabin and at the other end a
crane or excavator. The vehicle has a spacious loading platform.
Various types of crane and excavator are available.
Depending upon operating conditions, they can be fitted with load hook, double shell
grab, electromagnet, shrub cutter or earth borer.
The TG 80-4 is fitted with buffers and draw gear at both ends.
3. APPLICATION
The following tasks can be carried out by the TG 80-4.
• On and Off-loading of rails, equipment, sleepers, ballast, waste and other materials
onto the loading platform or onto a hauled wagon.
• Material transportation over any distance.
• Use as a traction vehicle, as a work locomotive.
• All tasks which can be carried out by crane or excavator or with other special
• Equipment installed on the vehicle.
2. The use of DTS helps the track to achieve consolidation and regaining the resistance to
lateral displacement. This helps in relaxing the speed restrictions expeditiously and the
track maintenance cycle can be extended.
3. Dynamic track stabilizers shall be deployed behind the tamping machine and be used
after the tamping machines have finished tamping the track.
4. The machine should be used in maximum settlement mode when carrying out track
renewal or rehabilitation works or when carrying out ballast cleaning. For normal track
maintenance, it should be used in controlled settlement mode. The horizontal and
vertical force and frequency of vibration shall be adjusted so as to carry out effective
stabilization on various types of track structures.
5. The machine are equipped with a frequency modulation measuring unit for optimum
regulation of frequency. There are display units to indicate amplitude of vibration to
enable monitoring of vibration frequency and degree of settlement on both rails.
6. Precautions
The following extra precautions are necessary in the operation of this machine:
i) Complete and tight fittings to hold rails with sleepers are essential.
ii) Adequate pre-depositing of ballast for achieving the required profile is necessary.
iii) The vertical pre-load is to be selected if the levelling system is used, in such a
way that the determined maximum settlement is not exceeded. Lateral vibrations
shall be created without any vertical impact to avoid damages on the rail surface
by excess friction and force by the rollers.
iv) The selection of frequency (depending on track condition), working speed &
vertical pre-load should be judicious according to the needs and with/without
"Levelling" system in "ON" condition. The frequency is properly set when the
machine appears to be in smooth behaviour i.e. the vibrations are transmitted to
the track and not back to the machine.
v) When stabilising on bridges, with ballasted deck the frequency selected must not
be within the natural frequency of the bridges so as to avoid resonance
conditions. The natural frequency of girder bridges with a span of over 10 m lies
below 30 Hz. The frequency of 40-45 Hz is selected when stabilizing the bridges.
vi) While working the machine in stretches adjacent to walls, trench walls, retaining
walls, platform etc., no restrictions for the working of the machines are normally
necessary. However when these structures are defective, extra care is
necessary in the proximity of 20 m on either side, to avoid likely damages to the
structure.
' c.. • •
_M_·._sJlecr· -~ -_ei_nse_·_. •·.•.· •·.··. :·· . . •M~cr_
No_._._. • _.•. ·. • ·.·•· .·• . •
·• .•· •
ine
.No. ·.·
.··•. ·••·· .·. ·. ·.· • ..
I_ ·-.. • .. ·· •··. . •
Typ~o.f. ~~~h.· in§ \
·..• : •· • , , • "-'•· -:,·
•••••.••• ···• ; '• •
· .• •: •:
i ·P· --·_._·r.·.ozyc·"lu.)r._'erjmo,te)ni_..t···.··
i.. ·;..•.;••;.
1 07-16 G 2204 Levelling, lining and tamping machine 1982
2 07-16 GS 2305 LevellinQ, lininQ and tamping machine 1983
3 07-16 GS 2306 Levelling, lining and tamping machine 1983
4 07-16 GS 2307 Levelling, lining and tamping machine 1983
5 07-16 GS 2308 Levellin!l, linin!l and tamping machine 1983
6 PBR202 1203 Ballast Regulating & Profiling Machine 1982
7 PBR202 1204 Ballast ReQulatinQ & ProfilinQ Machine 1982
8 PBR202 1205 Ballast Regulating & Profiling Machine 1982
9 PBR202 1206 Ballast ReQulatinQ & ProfilinQ Machine 1982
10 PBR202 1207 Ballast Regulating & Profiling Machine 1982
11 TG80-4 4101 Multi-purpose Machine 1983
12 TG80-4 4102 Multi-purpose Machine 1983
13 TG80-4 4103 Multi-purpose Machine 1983
14 PBR400R 1409 Ballast Re!lulatin!l & Profilin!l Machine 1992
15 PBR400R 1410 Ballast Regulating & Profiling Machine 1992
16 PBR400R 1411 Ballast Re!lulatin!l & Profiling Machine 1992
17 PBR400R 1412 Ballast Regulating & Profiling Machine 1992
18 TG80-4 4204 Multi-purpose Machine 1992
19 TG80-4 4205 Multi-purpose Machine 1992
20 TG80-4 4206 Multi-purpose Machine 1992
21 RM74 3202 Ballast Cleaning Machine 1992
22 DGS62N 7101 Dynamic Track Stabiliser 1993
23 Plassermatic 2510 Three-Rail Synchronous Lifting Turnout 1993
levelling, lining and tamping machine.
Unimat
08-75 GS
24 SSP 203 1513 Ballast Re!lulating and profiling machine 1995
25 09-16 CAT 2409 Continuous action levelling, lining and 1993
tamping machine.
26 09-16 CAT 2411 Continuous action levelling, lining and 1993
tampin!l machine.
27 09-16 CAT 2412 Continuous action levelling, lining and 1995
tamping machine.
Unimat 08-12 GS
~
c
(!)
E
a_
'5
o-
Q)
ro"'c
p.. 2g.
...---<
s
<;:$
"'c
2c
[] 0
0
c
3
~ 0
.>::.
OD
........ fiJ
<J)
(/) c
Q) :c
0
Q "'
::;:
Tamping Machine
-"'
c
E
a..
·s
uQ)
(ij
V c:
0
a
...--; :p
0.
0
<h
·roc
~
V
c 0
0
c:
;;:
0 0
.c
OD
.. ',.--4
(/)
"'
Q)
.I;
V
""
0
0 "'
::2
Tamping Machine
I;J6Md§riii@!I:Ja TG80-4
1-:
"'
E
a
·:;
0"
Q)
1\i
c
0
li
0
.E
"'
1-:
8
~
E
Ol
c
·~
Cl
Multi-Purpose Machine
-
c:
ID
E
·s0.
o-
ID
(ij
<!) c:
.....-< ~
0; <>-
s
cd
0
"'
c
·a;
c0
:X: (.)
<!)
c
cbf) ~
.c
• ..-<
V)
"'
ID
.£
<!) .c
u
Q <n
::2:
Ballast Cleaner
-cQ):
E
Cl.
·:;
er
Q)
())
roc:
......-! 0
:g_
0...
sro 0
.Ul
c:
.§
c:
~ 0
u
())
c:
q 5
0
bJ) .c
(})
........ Q)
V) c:
()) :c
0
ro
Q :;;;:
Ballast Regulator
- - ·- · - ~~I· '
,
t
Multi-Purpose Machine
1
I
~
c
"'E
a.
'5
0"
ro"'c
,.......
Q)
.Q
0.. 15.
0
8
(';$
"'
c
2c:
t3 0
0
c
:;:
q 0
OJ) .<:
.,....; "'c
V)
Q) "' :c
Q ""'
:2
Chapter 23
Creep Control and Other
Track Works
Document History
Authorised By:
t- •
Signature:
Date: General Manager Permanent Way 2 8 MAY 201
I
Kuala Lumpur
TABLE OF CONTENTS
23.3 MAINTENANCE OF RAIL JOINTS ..... ..... ....... .. .................. ........................... ..................... 6
23.1 GENERAL
23.1.1 In addition to the maintenance of track components and track geometry, there are many
other ancillary works relating to track which have to be undertaken for the efficient upkeep
of permanent way. This chapter deals with the methods adopted in carrying out these
works.
23.2.1.1 The longitudinal movement of rails in the track under the influence of traffic is termed
creep. Creep can be a severe phenomenon associated with the jointed track with poor
track fastenings. On LWR/CWR track with good track fastenings, laid on concrete
sleepers, although the extent of rail creep is minimal, the rail creep needs to be monitored
closely to ensure track stability.
23.2.1.2 On lines with uni-directional traffic, creep is generally in the direction of traffic. On single
lines with traffic in both directions, creep may occur in either direction, particularly in the
direction of dominant traffic, steep down gradient and approaches to stop signals.
23.2.1.3 Rail-creep noticed may be due to movement of rail with respect to sleepers or due to
movement of both rails and sleepers on the ballast bed. In the latter case, the crib-ballast
too moves with sleepers and no cleavage between sleeper and ballast may be seen.
23.2.1.4 Extent of creep of both rails may not be always equal.
23.2.2 Adverse Effect of creep
Creep of rail will produce additional compression on one end of the rail and
corresponding additional tension on the other end. Net creep out (additional tension) of a
section of track may result in pull-apart of rails/fish-plated joints/welds. Net creep into
(additional compression) increases the potential for track buckling.
23.2.3 Limit of creep
Creep of each rail is measured with respect to fixed points (i.e. creep posts) erected firmly
on the cess. These creep posts are short rail posts planted on cess on either side,
square to the track, and are longitudinally spaced at interval of half kilometre. Their top
levels match with the top of running-rails. A string is stretched across the track, holding
its ends at the fixed points marked on the creep posts. In jointed track, the creep posts
are erected opposite to a rail-joint, so that the movement of this joint from the fixed point
can be measured from time to time. In LWR/CWR track, a paint mark (or a punch mark)
is made on the non-gauge face (on the field side) of the rail-head, to serve as reference
for the rail-creep with respect to the fixed point. Reference Figure 23.2 and 23.2 (a) &
23.2 (b) , as could be seen, the km and half km posts, which are erected as track
signage, are used as creep posts.
23.2.4.3.1 When net creep exceeds a limit of 50mm into or out of a 500 m section, the PWI shall
destress the track. He shall also reset the reference marks on the rail exactly opposite to
the creep posts and resume recording creep accordingly.
The following examples illustrate the working out of Net Creep on tangent track
between creep posts located at 500m interval.
Example 1·
Creep measured at CP x -10mm Net creep= -25-(-10) = -15mm
Example 2·
Creep measured at CP x -10mm Net creep= +55-(-10) = +65mm
Note: The direction of creep is measured as(+) if it is in increasing kilometre and (-)if in
decreasing kilometre. Net creep if (+ve), implies tension in the rail and if (-ve),
compression in the rail.
23.2.4.4 In the case of curved track, the alignment may get affected due to excessive
compression/tension in LWR/CVVR. In the case of turnouts in welded track, the switch
anchors (provided at the heel of switch rail} transmit the thermal forces along the main
welded rail-string of the turnout. Any sign of distortion of switch anchor may indicate
presence of incipient rail-creep and the possibility of failure of switch anchor with
consequential effect on signalling system. PWI shall bear these facts in mind, in the case
of LWR/CWR track, irrespective of the stipulation in the previous clause.
(Note: Switch anchor is also sometimes called anti creep device, switch trap or creep
anchor)
• Rails not secured properly to sleepers (Insufficient toe loads of rail fastenings, loose
fittings and worn rail seats).
• Inadequate resistance by ballast to movement of sleepers (insufficient ballast,
loose/uneven packing, damaged or unevenly spaced sleepers, yielding formation,
lack of drainage).
• High tractive and braking forces that occur near stop signals located on gradients
where trains may be required to stop/start.
• Inadequately maintained rail joints with improper expansion gaps.
• Rails too light for loads carried.
23.2.5.2 The PWI shall examine all these factors and identify the likely causes for creep so as to
eliminate these.
23.2.6 Remedial Action
23.2.6.1 The primary requirement to eliminate or reduce creep is that the rails shall be held firmly
to the sleepers which shall, in turn, generate adequate resistance from the ballast. To this
end, rail sleeper fastenings shall be tight, sleepers well packed and ballast in cribs and
shoulders adequately compacted.
2_3.2.6.2 Where creep of rail with respect to sleeper is prevalent, creep anchors of the type
approved by the General Manager Permanent Way Department, shall be used as
specified below:
• The pattern of fixing the anchors shall be decided by the CPWI depending on the
direction of creep.
• The number of anchors per rail shall be decided by the CPWI depending on the
severity of creep.
• No anchors shall be provided against joint sleepers.
• Both rail-seals of a sleeper shall be anchored on the same side.
• Where creep occurs in both directions, back-up anchorage {anchors on opposite
sides ot and butting with the sleepers} shall be provided.
23.2.7 Adjustment of creep
This is done by pulling back of rails in fish-plated track and destressing of welded track in
LWR/CWR track.
23.3.2 The PWI shall observe the following procedures to ensure adequate maintenance of rail
joints.
• Tighten fish bolts to the prescribed torque while lubricating the fishing surfaces
periodically using the stipulated lubricants, so that the rail ends are allowed to move
optimally at the joints.
• Use standard spanners only. Preferably use torque spanners.
• Pack joint and shoulder sleepers firmly.
• Use shims to take up wear of fishing planes.
• Lubricate the fishing surfaces to prevent/reduce wear.
• Examine the rail ends thoroughly during lubrication of fishplates.
• Change any rail found with a crack in the web, head or foot.
• Use rail straightener to straighten hogged rail ends.
23.4.2 During wet weather, the blowing joints' sleepers deteriorate as pumping sleepers when
the dust in the voids of ballast forms slurry. Such sleepers manifest a type of failure in
which undulations develop in the track surface, soon after rainfall or wet conditions.
23.4.3 As a temporary measure, lift the track and lower the slurry level by letting it to flow out
from the region of sleeper ends.
23.4.4 The following remedial measures shall be undertaken individually or collectively:
1. Removal of the ballast below the joint and shoulder sleepers, screening the ballast
and replenishing with fresh ballast.
2. Tightening all fastenings, lubrication of the joint and adjustment of expansion gaps.
3. Packing of joint sleepers and shoulder sleepers.
High compressive forces in rails without adequate lateral track resistance lead to the
buckling of track. Such conditions are created:
i} When expansion gaps in rails are inadequate due to
• Excessive creep
• Non-lubrication of joints.
• inadequacy of ballast or
• a low degree of compaction after works such as after cleaning of ballast or
lifting/slewing of track are undertaken.
23.5.2 Action on buckling of track
1. If buckling of track appears imminent as indicated by hollow sleepers or kinks (refer
to Clause 25.11.2) or if the buckling does occur, the track shall be protected
immediately according to the Rule 2 of part 1 Section B of the General Manual in
the current KTMB Rules and Regulation Book by the Patrolman or Ganger who
observes it first. The track shall be slewed under the supervision of the PWI to a
reverse curve as flat as possible if the buckle is on a straight section. (If possible,
buckets of water may be poured on the rail to cool them). On curves, track shall be
slewed outwards. Clearances to signals, line-side structures and to adjacent lines
shall be checked carefully. Traffic can be permitted to pass at a reduced speed of 15
km/hr over the affected portions, provided clearances are adequate and there is no
structural damage to track components. When temperature drops, joint gaps shall be
adjusted and the track restored to proper alignment.
2. Action to be taken on buckling in a LWR/CWR Track is dealt with in Clause 25.11 of
Chapter 25.
23.5.3 Additional Inspection after buckling
On receipt of information of a track buckle, the PWI shall proceed to the site by the
quickest means and make sure about the protection and speedy restoration of traffic. He
shall inspect the affected and adjacent portions of track to arrive at the likely causes
which led to the buckle.
23.5.4 Reporting
lt shall be ensured that factors which contributed to buckling are eliminated quickly. A full
report shall be made to the General Manager Permanent Way Department, through the
Regional Engineer on every occurrence of buckling.
A proforma. for reporting on buckling of track is given at Annexure 23.2.
Formation shall be maintained to the profile shown in Figure 10.2 and 10.3. If the width·
is less than specified, proposal for widening shall be framed by the PWI/CPWI, for
consideration and further action by the Regional Engineer.
23.6.2 Cess
The cess is that part of the formation top not covered by ballast. In the newly constructed
double track, sub-ballast is extended on both sides to form the cess. The cess should be
maintained at the proper level in reference to the rail, so that it allows drainage of water
flowing out of the ballast. At the same time, the cess should be at convenient level for the
trackmen to attend the track. If required, the cess shall be made up by using porous
material such as quarry dust, after obtaining the approval of the Regional Engineer. In
cuttings, the cess is not to be made up under normal circumstances. Spoil arising in
cuttings shall be taken out of the cutting. Grass and weeds must not be allowed to grow
on the cess surface to ensure proper drainage. Grass edges on cess shall be trimmed to
prevent the cess developing into a water course.
23.7.1.1 Every care shall be taken to ensure that water drains quickly away from the ballast and
formation.
23.7.1.2 The PWI shall pay special attention to drainage. During periods of heavy rainfall, he shall
check for inadequacies of drainage and report to the CPWI those cases where drainage
is not effective. All drains shall be watched for tendencies to scour or silt and timely
preventive action or repair shall be undertaken.
23.7.1.3 PWI shall ensure that, in the two-month period before the onset of heavy rains, all drains
in his jurisdiction are cleaned/repaired and made ready to function effectively during the
heavy rains.
23.7.2 Catch water drains at the edge of cuttings
lt shall be ensured that there is no percolation of water from catch water drains into the
sides of the cutting. There should be a proper outfall from these drains, leading water
away from the embankment at the end of the cutting. PWI should go up and inspect the
catch water drains periodically. He should examine whether any rain water flows into
catch water drain from outside the railway land, which is undesirable. If there are
problems with catch water drains, it may be examined whether provision of cascade
drains at their tail-ends is feasible and beneficial. Water from catch water drains should
not be short-circuited to fall into the side drains adjoining the track. The Regional
Engineer's approval shall be obtained for such improvements.
In the case of side drains, at locations where these drains go underground, such as Level
Crossing, etc., these shall be specially checked for the flow of water and kept clear. The
outfall shall be maintained as indicated for catch water drains.
23.7.4.1 Where slopes of banks and cuttings are made up of easily erodible material, water
flowing over the slopes can cause damage. Remedial measures include:
23.7.4.2 All such cases shall be reported by the PWI to the Regional Engineer who shall decide on
the most suitable remedial measure.
Drainage in station yards shall receive special attention from the PWI. He shall ensure
that all drains and catch pits in station yards are cleaned at least once in a year.
Water shall not be allowed to flow along the toe of an embankment, or to collect on one
side of it (unless the railway bank is designed to retain water). Any seepage or piping
through the embankment is hazardous and shall be watched for. In such situations,
provision of culverts and of pitching along the toe are indicated. Such works shall be
executed after approval by the General Manager Permanent Way Department.
23.7.7 Drainage along berms and terraces
Where berms or terraces are provided, they shall have a cross-slope as given to the
formation top to enable water on the berm surface to flow down its slope.
23.7.8.1 These shall be inspected before and during the rainy weather and kept clear. Each outlet
shall be cleared to its proper outfall, even if such outfall is beyond the railway land limits.
23.9.1.2 The following points require special attention during construction and maintenance of
cribs.
1. Sleeper cribs shall be laid as indicated in Figure 23.1. Single crib has all layers laid
with sleepers, whereas Double crib has alternate layers laid with sleepers and rails.
With heavier wheel loads of 20 tonnes, double crib height shall be limited to 6 layers
(260mm height only) and single crib be limited to 4 layers only.
2. Single cribs shall not be used on soft ground. A combination of single cribs with
double cribs as indicated in Table T-23.1 below shall be adopted for various heights.
(The table is based on use of BOibs rail with timber sleepers)
TableT -23.1
1.02 4 48 12 4 34 82
1.27 6 64 18 4 34 98
1.52 8 80 24 4 34 114
1.78 10 96 30 4 34 130
2.03 12 112 36 4 34 146
2.29 14 128 42 4 34 162
23.9.3 Reports from Train Crew and Traffic Staff regarding track defects:
23.9.3.1 The Driver who experiences or notices undesirable conditions of track (such as, rough
running, visual buckling tendency, water flowing across the track or heading on the track,
etc.) will stop his train at the next station and advise the Station Manager as per
paragraph 7 Section C of General Manual of the current KTMB Rules and
Regulation Book indicating the defect noticed, like rough riding, floods, fallen trees and
slips. The Driver shall also use his mobile phone and inform CTC. The Station
Manager/CTC operator will advise all concerned. Trains shall be allowed into the
Section only after the site has been inspected and cleared by the PWI.
23.9.3.3 A detailed report shall be submitted by the PWI in each case to the CPWI and the
Regional Engineer. The CPWI shall also inspect the site and initiate further remedial
measures, if required, making a report to the Regional Engineer.
LIST OF FIGURES
Figure 23.1 (Sheet 1) Standard Sleeper Cribs.
Figure 23.1 (Sheet 2) Standard Sleeper Cribs(side View)
Figure 23.2 Arrangement of Creep Post (Conventional)
Figure 23.2 (a) Arrangement for measurement of creep using km and half km
posts in CWR track (Plan)
Figure 23.2 (b) Arrangement for measurement of creep using km and half km
posts in CWR track (Section and Detail)
LIST OF ANNEXURES
Annexure 23.1 Standard expansion gap chart
Annexure 23.2 Proforma for report on Buckling of Track.
~
~
.,.,
tB"
c
Cil .. . ' ··-·'4 ••••
,.,
N
~
~~.:·<··;.·:
~_ ....... ...
~-.
_..,._~·~.:..:. __ _
~
(/)
~
::l"
ro Temporary.
~ girder span. ;?,;..____ ·s. No. P:Osts:(S!ee·per or R'o-U) ""Cl
N
~ o-u
4.J!l.J.ai!!:...~C-\sleep:!'!:!L ~ ~~
ll!L.IW-.-.--Sieeper·wall 0
:::l "'
~
0
Ill "' 3
i 0 '"
- :::l
= = /
:::l
:;o 0. Ill "'
Ill
~ a 3~LCI~~C-=-.t sleep:!(L :::l
Q.
"
-
o:E
0 (/)
16"
2~ jcij!r_ ~<t=_ ~- SleGg,e!!_
I ~,~ ~r, ~~~
/,7--~ -·--~~t-~··.·
j
:_:-. I1 -~---'-Rciker~(sleeper: to.eult)· - s:'"
~'<
~
~
1.$-i!'~S£-=-.'\..steep!f'i_
-, -~ -·1 - ............,,
~
:;I '"
0 4.J!l. La-X!LI1_C-=-~ rails __. Ill "
" <:::
:0.
0"
(j) 3~ !a.l!!:_Q,C-=-.1?. sleep:!(L Note :-
"' '"
~-
CiJ
0:
ro
2~}~Q.~~ rails~-
.- _ (i). u~e ·:Oiity. new St8epers ·Jor ~
st lo I // I . . crib . .& on Sf!dn
< ·--·,:- ~~· "L"" _, .,. .1 . . ',.;;... r··•J· ....· .(11} Sp. a..c.in•g.of en.d ·.leepera
..
! ,
_ .........,;:/.!.. "'....<...::;:L __ ,_____
... • __
750
.. - 1 ----------
750
··: ':..1 "":~:. :.•- ....
,.-..,....;_..-
1 J
on t11.e. temp. spon.:-&:: .th,e
sle~Per_on ·the ,tfO_Ck :sh-all
not exceed -300' mm
.. - ------ _. ___ . _- -
..-. - - - - - - - - , __ > (ill) ln·c_reose,.- takers to,· suit
~J------·19]5
1 1
m'!' mal~!!!::'l,l!!.99.!~g_._.___._.' 225 ..I height of crib
I~
, Abbrgdgtlon
5C : Single Crib
~ DC : Double Crtb ,.
(")
~
(,.)
8,
~
-'" '"
"tl ,
~
N-
w<
;:!.
"'
Permanent Way Manual Par! IV
Creep Control and Other Track Works Chapter 23
Fig. 23.2
r----------vARIES---------- 1
I
UNE
DETAIL 'A'
i~ rr
~~~
1
lii
0
n.
I
I
~g
"'"'
.._
~
"'
0
::!
"'
:l
oc
Figure 23.3(a)- Arrangement for measurement of creep using km and half km posts in CWR track
(Plan)
~
OJ iil
"'"'w
:§:
~
"'"3
:ooo (MIN) I
i
"-420()---,. I
i
.3000 (t,iiN
~~
(/)~
'" SEtYrroN -TANGENT TRACk "0
()"0
(1) (1)
>l-3
"0 "'
~
a· g: "0 3'"
::0
CD
"~
'" 0
:::l- I.I~~
c - - -I I
.··.
-T~~~~~~rW~~J8TA.L
.. ··.···· .··
ON NON GAUGE FACE -
-"
'" "'
"o:!E
a. "
-
"'
0
Q.(l
oiil
(1) (1)
OF EACfl RAIL HOO
5' "'
(1) '<
m-o
:::C
WrTH ~ ;;:
~en :;!Ill
:;·
"'3
DETAIL 'A' '" "
Cl t:
"'"
.DETAIL '8' ;<-
Q.
:::; 1 en
'"
:;; ARRANGEMENT FOR MEASUREMENT OF' CREEP
-~
3 USING KM OR HALF KM POSTS IN CWR TRACK CSECI!ON AND DETAIL)
"0
Fig. 23.2 (b) ~
~
:;·
"'
,..._
Cl ALL DIMENSIONS iN MILLIMETRES
~
(")
~
Ill
(0 :::;
CD
"'
~
"'
8,
~
-
::0
iil
R-
~"0
"' "':::1.
~
~<
"'
Permanent Way Manual Par! IV
Creep Control and Other Track Works Chapter 23
20 - 21 5
22 - 27 4
28 - 35 3
36 - 43 2
44 - 51 1
52 - 60 0
1. General information:
1. Region .................................... .
2. Section ......................................
3. Between station ........................ .
4. Kilometerage ............................ .
5. Gang No .................................. .
6. Straight or curve ....................... .
7. Degree of curvature (or Radius) ................... .
8. Gradient and Gradient direction ................................. .
9. Laying or Restressing temperature for LWR/CWR ............................ .
2. Track structure
1. Rail.. .......................................... .
2. LWR/CWR or fishplated jointed track ....................... .
3. Type of sleepers ......................... .
4. Sleeper density.......................... .
5. Fastenings ................................. .
6. Ballast depth........................... (indicate clean ballast depth)
1. Effectiveness of fastenings
2. Extent of creep
3. Amount of expansion gap and rail temperature
4. Lubrication of rail joint
5. Adequacy of ballast
6. Consolidation of ballast
4. Track Maintenance Works recently under taken with date
5. Details of Buckling:
1. Extent of buckling
2. Condition of Sleepers
3. Condition of fastenings
4. Other adverse effects
7. Temporary restoration:
1. Method adopted
2. Speed restriction imposed
3. When speed restriction was relaxed
4. Confirmation regarding non-infringement with any line side structure
8. Cause of Buckling:
Date .......................... .
PWI
Chapter 24
Welding of Rails
Document History
Authorised By:
Signature:
Date: MOHD RAMLI MOHD NOH
General M
2 8 MAY 2015
KereaJpl Tanah Melayu !erhad
Kuala Lumpur
TABLE OF CONTENTS
24.1 GENERAL
24 .1.1 A rail joint is the weakest link in a track structure. Due to the impact of the moving loads
on the joint, the packing of the sleepers under the joint gets disturbed, thereby requiring
frequent attention. Other adverse effects of rail joints include:
SKV is the short form of German Phrase ".§chwei(l,verfahren m it !Surz ~orwarmung" . This
when translated into English reads as "Short Pre-Heating (SPH) process. In this process
prefabricated dry moulds are used and the time of preheating is shortened to mere 10
minutes. The minimum time required for different rail sizes are as follows:-
Short pre-heating have been mostly done by Air-petrol fuel mixture. Oxy-LPG or
Compressed Air-petrol fuel mixture have been developed as these techniques take less
time for pre-heating the rail ends to desired temperature resulting in saving of line
possession time with improved quality of joint.
The rest of the Thermit process involves preparation of crucibles kept ready by putting
Thermit portions and ignite it with special igniters. A violent exothermic reaction takes
place and the Thermit mixture turns into a molten bath. Thereafter the automatic tap
releases the molten metal into the mould. After cooling, the extra weld metal surrounding
the parent rail is removed by shearing to match the rail profile.
b) Long preheat
The long preheat process means that to produce a satisfactory weld the preheat must
supply the majority of the heat, between 950°C - 1ooooc evenly over the rail ends as
required.
AT welding of different hardness rails is possible with the condition that portion used
should be suitable for the higher hardness rail. However, older rails and rails lighter than
80 lbs are not recommended for thermit welding as the steel composition is not
appropriate.
24.3.3 Moulds
Moulds are required for pouring molten metal into the rail ends for welding. These are
prefabricated and ready to use as per profile of the rail.
The moulds are made of a Sodium Silicate and sand mixture with various other materials
used to give heat resistance etc. and is C02 dried. When C02 is blown through the mould
the Sodium Silicate hardens. After removal from the pattern the mould is oven dried to
remove moisture. Although the moulds should have adequate reinforcement to avoid
crushing, care must be taken during transportation and welding works as they are fragile
and liable to breakage. Standard prefabricated moulds are manufactured to ensure
adequate permeability for the escape of mould gases.
Before mounting on the rail ends to be welded, each pair of rnoulds shall be examined for
defects, dampness, cracks, blocked vents etc. and defective moulds shall be discarded.
The Alumino-Thermic Powder Mixture used for the welding of the rail shall be compatible
with the chemical composition of the grade of rails to be welded. The Alumina-Thermic
welding powder (portion) shall be tested for weight, moisture content and chemical
composition in accordance with the instructions issued by the Permanent Way Division.
The stipulations laid down by the suppliers about the shelf life of the portion, shall be
strictly followed for main running lines. Shelf life shall be as per manufacturer's
recommendation but shall not be less than 2 years. Where portion material is out of date
on the label; the manufacturer may be consulted to verify whether the shelf life can be
modified.
For use in Yard lines or sidings, after expiry of the initial shelf life, the shelf life may be
again enhanced by testing weld samples created from that batch, provided the sample
test weld passes the UT test and other related tests.
The weld shall be tested with a calibrated 1.0 meter long straight edge placed centrally on
the joint. The alignment tolerances shall be as follows:
lt is also necessary to meet tolerances for finishing on the sides of the rail head at the
welded joint and for the finishing of the top table surface of the welded joint, using a
calibrated 20cm straight edge, measured not exceeding 400mm length on either side of
the weld.
The specified tolerances are as under:
Running surface flatness including head finish on sides and top table surface.
The gap/offset shall not exceed 0.15mm between the ruler and rail surface.
These tolerances are shown in Figure 24.2.
The straight ruler and feeler gauge shall be of accurate fabrication and calibration,
provided by a reputable manufacturer. As an alternative, standard Eleclronic Straight
Measuring (ESM) device may be used to determine weld geometry compliance to the
above stated tolerances.
24.4.3 Testing
The welds shall be tested according to the procedure laid down for this purpose. A
record of the test shall be kept for scrutiny at a later date. Australian Standard AS:
1085.25-2006, EN14730-1:2006 (Thermit Welding), EN14587-1:2007 (Flush Butt
Welding) and EN14587-2 Oct 2006 (Mobile Flush Butt Welding) may be adopted for this
purpose. The main tests that need to be done are as follows:
24.4.4.1 The two rail ends shall be aligned properly both horizontally and vertically.
24.4.4.2 The gaps shall be uniform and burrs removed. I! should be 25mm ± 1mm.
24.4.4.3 The rail ends shall be square and properly cleaned up to the end of the moulds.
24.4.4.4 Moist portions shall be rejected. They shall not be used after drying.
24.4.4.5 Before igniting. the alumina-thermic mixture, it shall be seen that the rail ends are properly
heated and the gap has neither reduced nor increased· due to expansion or contraction of
rails.
24.4.4.6 During fixing of the moulds, it shall be ensured that the centreline of the rail gap coincides
with the centreline of the mould to avoid cross joint. The mould jackets/shoes holding the
pre-fabricated mould in a snug fit condition, after fixing, shall be tightened by the
application of adequate pressure. Excessive pressure may cause breakage of mould and
dropping of sand inside the mould cavity. Care shall be taken during application of
adequate pressure. 11 is essential for the moulds to fit flush to each other across the
bottom of the rail flange which can be checked by feeling with fingers across the junction
of the two halves of the moulds and by looking down the riser aperture. The moulds
should touch the bottom of rail foot to ensure proper size of collar at the bottom.
24.4.4.7 After the moulds have been fixed, the gap between the mould and the rail shall be
packed firml)!' with luting sand to prevent leakage of liquid weld metal. To protect the rail
top table from metal splashes during reaction, the adjacent rail surface on either side of
the moulds shall be covered with a pair of metal cover (rail protector) or smeared with
luting sand up to 15cm on either side. Moisture in the luting material must be controlled to
avoid gas entrapment in the weld. (Luting: Liquid clay or cement used to seal a joint, coat
a crucible, or protect a graft). Refer to Annexure 24.2 for photos of installation sequence
of moulds.
24.4.4.8 A stop watch or thermo chalk (temperature stick) shall be used for controlling the
preheating time.
24.4.4.9 During tapping, crucible shall not move from its position. Tapping shall be done only after
completion of reaction and separation of slag.
24.4.4.10 Adequate care shall be taken to ensure proper fusion especially of the bottom flanges.
24.4.4.11 Flame cutting for removal of excess metal are not be allowed.
24.4.4.12 In-situ Alumino-Thermic Welding is not permitted, during rain unless special
arrangements are made to do it under cover.
24.4.4.13 The minimum time restrictions as prescribed by the supplier for allowing the traffic after
welding shall be strictly followed. This shall not be less than 20 minutes before the first
train can be allowed to pass over the welded joint.
a) After the portion is ignited, observed that the reaction is not too vigorous or
boiling. Allow about 20-25 sec for this process.
b) Once the reaction subsides, allow a few seconds (5-7 seconds) before separating
the slag from the metal and tapping the contents of crucible into the mould.
Tapping shall be done only after completion of reacti?n and separation of slag.
c) After pouring, wait for about 3-5min for the molten metal in the mould to cool and
solidify, timed with a stop watch before removing the mould.
d) After removal of the mould, trimming of the excess red hot metal of the weld must
be carefully done so as not to cut the parent metal resulting in cupping of the
weld. Leave about 2- 3 mm excess metal over the rail table.
e) All rail fastenings shall be securely fitted before final profile grinding of the rail
head.
f) The completed welded joints must be distinctly marked, numbered and the record
maintained so that any future joint failures are traceable.
The general defects noticed in alumina-thermic welds and the remedial measures to be
adopted are briefly indicated below:
• Crop the ends of old rails with fish bolt holes for a minimum length of 450mm.
Before welding, ensure that the cropped ends are free from hogging, roughness,
burns and defects.
• Rails with battering and hogging exceeding the above limits shall be cropped before
welding.
• Do not weld rails having wear at rail seat exceeding 2 mm in depth
• Rails shall be ultrasonically tested before welding to weed out defective rails.
• Only rails of the same quality (UTS), hardness and with similar pattern of wear shall
only be welded together.
• The end faces of the rails to be welded shall be thoroughly cleaned of loose scales,
rust, paint etc. by brushing and shot blasting or grinding. Cleaning of rail bottom shall
be ensured by placing a mirror and watching the cleaned surface. Oil and grease, if
present, shall be removed by Carbon Tetrachloride or Benzene. If any internal defect
such as piping is noticed during end cleaning, the rail shall not be welded.
24.6.2 Welders must be fully trained and hold a Certificate of Competency issued by the
Permanent Way Division.
24.6.3 Welders and welder's assistant and other personnel on site (where necessary) must wear
the appropriate Personal Protective Equipment (PPE).
24.6.4 A knapsack spray full of water (or equivalent firefighting appliance) MUST be on hand
before any welding work commenced. A dry chemical extinguisher must be made
available on site to extinguish fuel fires from grinders etc. A Fire Blanket must be ready to
be used if fire occurs on clothing etc.
24.6.5 Special precautions must be observed during welding in tunnels especially protection
from the welding fumes to minimise risk of inhalation of fumes by welders and team
members.
24.6.6 In areas where there is either dripping water (such as in tunnels) or water ponded near
the rail, ensure that the water do not drip ooto the weld by using a small tarpaulin or
similar blanket. Any water pooling on the Slab around the weld area must be removed
before welding commenced.
24.6.7 When working in enclosed station areas (such as in KL Sentral) activities need to be
managed to avoid exposing the public to inconvenience and irritation (noise, fumes and
smoke) and to avoid giving rise to concern (appearance of smoke or setting off of smoke
alarms).
24.6.8 ALL NON ESSENTIAL PERSONNEL SHOULD STAND AT LEAST 15M AWAY
DURING THE COURSE OF THE REACTION AND UNTIL THE WHOLE WELDING
PROCESS IS COMPLETE.
The flash butt welding process is a method of joining the rails, in which the heat
generated for forging the joint, is created by the resistance of the rails to the passage of
an electric current.
Thus, the parent metal is actually consumed during the welding cycle to an extent of
about 25mm per weld.
The welds shall be tested according to the procedure laid down for this purpose. A
record of the test shall be kept for scrutiny at a later date. Australian Standard AS:
1085.25-2006 may be adopted for this purpose. The main tests that need to be done are
as follows:
The requirements are the same as for Alumino-Thermic Welding of old rails, as per
Clause 24.3.8.
The weld shall be tested with a calibrated straight edge one meter long and tolerances
shall be as follows:
-O.Omm
Lateral alignment +0.3 mm
-0.3mm
The gap/offset shall not exceed± 0.15mm between the ruler and rail surface.
The straight ruler and feeler gauge shall be of accurate fabrication and calibration,
provided by a reputable manufacturer. As an alternative, standard Electronic Straight
Measuring device may be used to determine weld geometry compliance to the above
stated tolerances.
24.7.6 Marking of Joints
Every joint shall have distinctive mark indicating the weld number, month and year of
welding and the code of the plant as shown below.
XXXXMMYY AAA
This marking is done by permanent marker pen at the web of the rail.
LIST OF FIGURES
Figure 24.1 (a) Conventional Alumino-thermic Welding Process (Thermit)
LIST OF ANNEXURES
Annexure 24.1 Inspection of welded rails
Thermit Welding
Heat source
-chemical reaction between
tnermit mixture components
-Iron oxide and aluminium
powder Crnckle---.\t---jI
-Ignition fuse required Miclclle
steel
Slug
Shutter Risers
Fireday mould
-shapes joint
-allows slag removal
Firebrick
MOUld
SLAG
STRAIGHT EDGE~
.!.....------ !OODMM
~ 5CDM "
STRAIGHT EDGE
J------- 1000MI'l --------J
STRAIGHT EDGE
2:D0MM
}
ll.lSMI"l f
No!g:
1. On Curc'Od Track To~ Surfoce requlrem<nl ore a• for straight track.
2. Lotarol Allgnmant Toleroncs ore Bhowa fo,- Stral9ht Trod: only end Vl'lr~r 'oiJfth mdlus.
©KTMB Page 14 of 18
Permanent Way Manual Part IV
Welding of Rails Chapter 24
111!'----~.
prel:!e.at
bolder
adjustment
NOTE:
The FPH system comprises of a modified SkV-F burner (either acetylene or propane), and a new
burner holder, which attaches to the standard universal mounting. Using this system, the preheater
will be central to the mould cavity and vertical in the moulds.
TYP\>Of
~iJ$p~e~ic?f1 Or ,
aCtion
Walking ld\lntify and r\lport, visually obvious rail defects and conditions (i.e. indicators of a defect) that
inspections may affect the integrity of the track structure that includes the following:
1) broken rails and rail welds;
2) rail and rail weld deformations and discontinuities;
3) wheel burns;
4) damage to rail surface or section;
5) unusual patterns of gauge face contact;
6) unusual vehicle tracking patterns;
7) rail corrugation;
8) battered rails joints; and
9) gauge corner fatigue
10) other obvious indications of defects such as bleeding.
b) Failure of track circuits can be used as an additional method to detect rail failures.
c) Intervals between walking inspections shall not exceed 31 days.
Continuous Continuous ultrasonic testing- shall be undertaken every 12 months during the service life of
ultrasonic rails to identify and report defects detectable by ultrasonic inspection.
testing
Defects detected from inspections should be assessed and reported in accordance with the
classification, position and sizing codes as specified in Chapter 27 : Rail Defects and Their
Rectification
Chapter 25
Welded Rails- Laying and
Maintenance
Document History
Authorised By:
Signature:
~~ \
Date:
MOHD RAMLI MOHD NOH·
General Manaal!r Permanent Wav
2 8 MAY 2015
Kerettipl Tanah Melayu Berha.d
Kuala lumpur
TABLE OF CONTENTS
Annexure 25.2- Minimum Competence Requirements for Rail Destressing Operations ..................... 33
25.1 GENERAL
25.1.1 Standard rails are welded in a depot by the "Flash butt" welding process or at site by
mobile Electric Flash-Butt Welding plant or the "Aiumino-Thermic" welding process to
form panels of welded rails.
25.1.2 A long welded rail (LWR) is defined as a panel of welded rails of which upon laying in the
track, the central zone does not undergo any longitudinal movement with the variation in
temperature. Rails welded together into nominal lengths of 146 - 150m (depending on
elemental rails lengths) shall be considered as LWR.
25.1.3 Continuous welded rails (CWR) shall be defined as LWR panels that are joined by
welding (including turnouts and other non-moveable joints such as glued insulated joints)
in continuous lengths between fixed points greater than 146m and where adjustment
controls are in place and destressing of which has to be carried out in stages. CWR are
only put in service with use of 54kg or heavier rails and with a good track structure.
25.1.4 Rail that is not constrained will shrink as the temperature drops, and expand as it
increases. Since the ends of CWR are fixed, the rail will experience tensile stress in cold
weather and can fracture if the stress becomes too great. In extreme hot weather, the rail
will experience compressive stress, and if the compressive force becomes excessive the
rail and/or track may buckle.
25.1.5 This chapter specifies the procedures for laying, maintenance and monitoring of LWR
and CWR so that the stresses within the rails in the track are managed in a control
manner under varying ambient operating temperature condition.
25.1.6 Annexure 25.1 defines technical terms used in this chapter.
For a fully restrained rail and neglecting creep effect of the rail metal, the formula to
calculate the thermal stress in rail is:
where:
E = Modulus of elasticity of rail steel (usually taken as 200000 N/mm2)
a =thermal expansion coefficient of rail steel (Usually a= 11.5 x 10-6/ •c)
For a rail of length L, the formula to calculate thermal expansion gap (e) is:
3
e =(La L\T) x 10 where e is in mm, and L in metre
25.2.3 The variation in rail temperature may ranges from about 25°C above to 25°C below the
mean rail temperature. For a 480ft. LWR, the corresponding breathing length is about 35
m.
For a track structure with BS 80A rail on concrete sleeper, the calculated breathing length
and movement of rail ends is shown below:
= EaT N/mm2
Corresponding Maximum thermal force in rail = AEaT N
= 5065.11 X 200000 X 0.0000115 X 25 = 291,244 N
= 29.688 tonnes
Assuming average longitudinal ballast resistance to rail movement offered at each rail
seat per sleeper
= 0.50 tonnes
Number of sleeper seats required to resist the 29.688 tonnes longitudinal thermal force
= 29.688/0.50
= 60 sleeper seats
Breathing length depends on rail section, temperature variation from stress free
temperature, and resistance offered at rail seat to the longitudinal rail movement.
= laT/2
where:
= 5.2mm
This movement of 5.2mm can be accommodated by a standard fish plated joint.
• Rails are subject to heavy wear, corrosion or corrugation and need frequent
renewals;
• Formation is weak/prone to pumping failure;
• Track is vulnerable to flooding, subsidence and breaches.
25.3.3 For a LWR track, the PWI must ensure:
• To isolate the LWR by provision of one standard length rail on either side of
switches and crossings;
• To provide LWR on bridges in accordance with the criteria indicated in Clause 25.7;
• That LWR is not terminated at an insulated joint;
• That fishplated track butting a LWR is not subject to creep;
• Rail anchors shall be used to address rail creep where applicable.
• Level crossing shall not be located in the breathing length of LWR/CWR.)
25.3.4 For a CWR track, it is important that track stability is monitored and maintained at all
times through:
• Creep monitoring;
• Thermal stress control of CWR;
·..• Attention to sleeper/ fastening assemblies;
• Maintaining the ballast profile; and
• Keeping track geometry within required maintenance tolerances.
25.4.2 Formation
Formation shall be stable. Stretches of bad formation shall be treated suitably and
stabilized before laying LWRICWR.
25.4.3 Ballast
For existing LWR in service, the minimum cushion below the bottom of sleepers shall be
250 mm of stone ballast. Shoulder width shall be:
Shoulders on both sides shall be humped to the extent of 100 mm. as shown in Figure
10.2.
For CWR in Class I track, minimum ballast cushion shall be 300mm.
25.4.4 Sleepers
Concrete or wooden sleepers with elastic fastenings may be used for LWR. For CWR,
only concrete sleepers are allowed. The sleeper density shall conform to the standards
specified in table T-10.1 for Class 1 & 2 lines. (Chapter 10, Clause 10.3). Spacing of
sleepers under LWR is shown in Figure 25.1.
For CWR, sleeper spacing shall be uniform 600mm centre to centre.
25.4.5 Rails
25.4.5.1 LWR shall be laid with 80 pounds or heavier rail. CWR track shall only be with 54kg rail
or heavier. All new rails for new track shall be without fish-bolt holes, except in sidings
for goods lines.
25.4.5.2 In cases of conversion of existing fish-plated track into LWR, it shall be ensured that:
• Assess the availability of time for track maintenance during different parts of the
years;
• Plan destressing operations;
• Organise track patrolling; and
• To review the destressing temperature (t,).
25.5.2 The mean rail temperature tm shall be arrived at on the basis of the maximum and
minimum recorded rail temperatures over a representative period.
25.5.3 The destressing temperature (td) to be used shall be kept higher than the mean
temperature for the particular region. This is considering that the track is able to
withstand tensile force better than compressive force. Compressive force which builds up
as temperature rises, if not restrained adequately, may lead to track buckling whereas
tensile force causes the rail to be pulled apart and if the force is too high will result in rail
breakage. For the track in KTMB, based on consolidated experience gained in the field,
the destressing temperature to adopted for use is fixed at 45" Celsius.
25.5.4 Suitable monthly readings of rail temperature should continue to be taken and a register
maintained by the PWI to enable re-assessment of the mean temperature and
destressing temperature in his section and in KTMB. Measurement of ambient and rail
temperatures shall be carried out by an approved make of rail thermometer. Description
of types of rail thermometer available in the market is in Annexure 25.5.
Where LWR is proposed to be laid, a detail survey of the section shall be carried out to
determine locations over which LWR/CWR cannot be carried through, such as certain
bridges, curves, gradients, switches and crossings and unstable formation. A detailed
plan shall be made showing the exact location of joints and other features as in Figure
25.2. LWR/CWR shall be laid according to plan as approved by the Permanent Way
Division Headquarters.
Track with CWR designed for high speed train operation Class 1 line has been laid under
. the Double Tracking Project without any free joints and is provided with Switch Expansion
Joints (SEJs) to allow for the thermal expansion and contraction of the rail. The
installation, monitoring and maintenance requirements of SEJs are described in a
separate maintenance manual and Chapter 7, Annexure 7 .2.
25.6.2 Preliminary works
• Cleaning of ballast and making up the full ballast section necessary to bring the
track to final level.
• Realignment of curves.
• Introducing and/or improvement of vertical curves.
• Rehabilitation or weak bridges.
• Rehabilitation of poor formation.
• Ultrasonic testing of rails.
• Provision of glued insulated joints (in track-circuited territory).
• Removal of battered or hogged ends, if any in the rails.
25.6.3 Procedure for laying LWR/CWR
The detailed procedure for installation of LWR/CWR will be specified by the General
Manager Permanent Way, considering the facilities and equipment available from time to
time. The Regional Engineer (or Project Engineer where necessary) shall get the
procedure approved from the Permanent Way Division Headquarters.
25.6.4.1 Destressing operations shall be carried out by freeing the rail when its temperature is
within the temperature range of Id up to 1ct + 5 or by using rail tensors when rail
temperature is below the design stress-free temperature range.
(For the track in KTMB, 45"Celsius remains fixed as the stress-free temperature)
25.6.4.2 This operation shall be carried out on a length of LWR or CWR track which can be
conveniently tackled during the available line possession, but not exceeding 1 Km. (The
length is also limited by the capacity of the tensor). The required extension shall be
obtained by pulling the rail, (freed of sleeper fastenings) towards a pulling point, (where
the tensor is fitted) from an anchor of specified length. A closure weld will be made later
at the pulling point.
25.6.4.3 Destressing shall be done under the supervision of an experienced PWI who has carried
out similar destressing operations. lt shall also be ensured that relevant documentation
is maintained in the Section Register of the PWI and in the Regional Engineer's Office.
3. In LWR or CWR track without SEJs, a cut is to be made to create a gap to insert a
piece of short rail which will be welded subsequently at the end of the destressing
operation. Prior cutting of rail and installation of closure rail shall be done in an
earlier line possession, or it may be done earlier within the same possession. When
the track possession is taken, the closure rails shall then be removed, and where
SEJs are present, the SEJs adjusted (as per desired gap at td) and fastened.
4. The remaining sleepers fastening on both running rails shall be loosened/removed
starting from the proximate ends of the SEJs/free joint and proceeding towards the
centre. The rails are lifted and placed on the rollers at about every 15th sleeper to
permit rails to move freely. While distressing on curved track, provision of side
rollers may be adopted. The rails shall be struck horizontally with heavy wooden
mallets to free them from any horizontal resistance so as to assist in their
longitudinal movement. This hammering action over the entire stressing length will
induce rail movement towards a stress free state. Continue vibration until rail
movement ceases.
5. The rollers shall then be removed, the rails lowered to correct alignment and
fastenings tightened, starting from the middle of LWR and proceeding toward both
ends simultaneously. The tightening of fastening shall be completed within the
temperature range for td as specified. The actual range of temperature during the
period of tightening shall be recorded by PWI along with the time and date.
Note:
a. The tightening of the fastenings, and the arrangements for insertion of cut rails
between the SEJ/free joint and LWR shall be carried out simultaneously. The
four gaps shall be measured individually and the rails of required length cut by
rail saw keeping the required gaps for AT welding. The cut rails shall then be
placed in position, fastened to the sleepers and welded at each end. Fastenings
for 20 metre on each end of the LWR shall be removed before welding. Joints
shall be clamped for 20 minutes after welding.
b. For this operation it is necessary that the rail temperature is below td to rule out
the possibility of rail to be under a state of compression. However, in situations
where there is a possibility that the rail may be in compression, never use a
saw for the initial cut as the rail will close up causing the cutting disc to shatter
hazardously. Further cuts may be saw cut or flame cut. Flame cut rail ends
must be discarded and not to be re-used for the track. All rail ends shall be saw
cut prior to welding.
c. Do not remove fastenings completely before cutting the rail. If the rail is in
tension, it may pull back before the cut is complete, breaking the rail at the cut,
and may cause broken rail material to fly in a dangerous manner.
25.6.5.2 With the use of rail tensors:
Operations involved in destressing of LWRICWR using rail tensors are:-
1. Establishing Anchor Length
For resisting the pull exerted on the welded rail by a rail tensor, it is essential that
an adequate anchor length is provided at the fixed ends of the free rails. The length
of this anchor shall be equal to 5m per degree Celsius of the difference between the
stress-free temperature and the rail temperature at the time of stressing. If the
stress free temperature is 45°C and rail temperature at the time of destressing is
35°C then the anchor length is equal to 5 x (45 - 35) = 50 meters. The anchor
lengths are A 1 A2 and C1 C2 at either end of the length A2 C2 to be stressed (see
Figure 25.3). In this case, the anchor length shall not be less than 50 m.
2. Establishing Tell Tale Points
At each end of each anchor lengths, tell-tale points shall be established to monitor
the movement of rails to be stressed and the effectiveness of the anchor lengths.
For this purpose, one sleeper is freed of the rail at the tell-tale point and a mark
made on the rail foot in line with a suitable reference mark on the sleeper. See
illustration below.
t 1+ r
3. Establishing Reference Points
Reference points shall also be marked on the foot of the rail to be stressed at equal
intervals of about 50m to observe whether the calculated extension is obtained
uniformly throughout the length of the rail. These point shall be marked, in the same
way as the tell-tale points, after the rail is unfastened.
4. Extension Table
When rails are free to move they will expand and contract 0.115mm for every 1m
length for every 10° C change in rail temperature.
TableT -25.1 below shows the calculated elongation for different lengths of rail to be
stressed and for varying differences between stress-free temperature and rail
temperature.
5. Extension at Pulling Point
The total extension at pulling point for the length to be stressed shall be determ ined
from Table T-25.1. At the pulling point, a gap equivalent to the total extension as
worked out plus an allowance for the welding gap shall be made available.
.l
Permanent Way Manual Part IV
Welded Rails - Laying and Maintenance Chapter 25
(Extension in mm}
25.6.6 Examples:
Temperature t 0 = 45" c
Temperature tp = 35" c
to • tp = 10" c
Movement at inner tell-tale towards the pulling point equals 8 mm, but since this
movement occurs before the marking of the reference points it must be ignored in the
calculations.
Proportional extension for each 50 meters
Temperature lo = 45"C
Temperature tp = 38"C
10 - tp = re
Calculated extension (Table T -25.1 )= 24mm
Reference mark = 4 +3 = 7 mm
Reference mark 2 = 8 +3 = 11 mm
25.7.2 There shall be normally no unballasted girder bridges for CWR track in high speed lines.
For the Prai Swing Bridge, the CWR track stops short of the bridge at both ends and
Rail Expansion Joints are provided.
25.7.3 For LWR track on girder bridges (with unballasted deck), LWR shall be laid as below:
•.·.-o0etall.lengti\••··
-.- '--- -- __ - .;-i
tc>ncliii&~s t& be .
~(;rriririecl ~~~1\ •
<40m Continue LWR over the
bridge if track is laid with
80 lbs or heavier rail
Dog spikes or rail screws shall be deemed to have the characteristics of rail-free
fastenings for this purpose.
25.7.4 When the LWR is not continued over the bridge, the jointed track on the girders shall be
isolated from the adjoining welded track by at least one well-anchored standard rail-
lengths on either approach.
All regular maintenance operations like lifting aligning, packing, realignment of curves,
ballast cleaning and continuous renewal of sleepers shall be completed before the on-set
of hot weather; the actual work shall be confined to the hours when the rail temperature is
in the range td + 5"C.
The limits safe working temperatures and the speed restrictions to be imposed for various
maintenance operations are given in Table T-25.2.
Table T-25.2
Working Temperature Limits and Speed Restriction
b) 15 km/hr during
stabilisation period without
use of tamping machine
Note:
For normalisation of speed restriction, stabilisation is considered to be effective after passage of 0.4GMT of traffic loads or
with the use of Dynamic track stabiliser (DTS) after tamping.
After destressing operation, withdrawal of Temporary Speed Restriction can only be done 24 hrs after the operation is
completed and sub"ect to passa e of at least 10 trains throu h the section.
25.8.3 Oiling and Greasing for the mechanical fishplated joints in LWR Track
25.8.3.1 Fish plates and bolts on LWR track shall be cleaned and oiled at least twice a year
(during hot weather period).
25.8.3.2 The work shall commence at 7 A. M. and finish not later than 10 A. M.
25.8.3.3 Uneven expansion spaces shall be noted during oiling. In such cases the fish plates at a
wide joint shall be slightly slackened in the morning when the temperature is increasing
and tightened during hot period of the day. Similarly a tight joint shall be loosened during
hot period of the day when the temperature is decreasing to allow the free movement
when the rail cools, and tightened during the cool period.
25.8.4.1 Opening out of ballast shall be restricted to the minimum extent essential. Ballast shall
be well consolidated after the operation is over.
25.8.4.2 The following stipulations shall be ensured when sleeper spaces have to be opened out
continuously:
>!•···k'ai,•····· .. Nc).~fsleep~r$p~~.Js;o.bei··.
>t~mp~iatur,·•.· 9J)ened.o.u[C:o6tinuously
25.8.5.1 The following procedure shall be adopted for ballast cleaning in LWRICWR track:
.Steps ..
.
.
·.. • Sequence
..
of operation description
. . .
. .
· ... .. .
</ .···
2. Cut the CWR within the section of work and install temporary clamps for the
joints
10. Restore full speed after the track is properly consolidated. This can be done
only after third Tamping pass with DTS or after traffic load of 0.4 GMT
25.8.5.3 The following table gives a guide on the speed restrictions to be imposed for lhe above
operation·
~~-~%,/ ,; .LP·'·~''"-~, .•c·,.,._., •..._,. ,·.•, •: ·:.· .
•'··· . z•:.·~~ ... ii/ 1·/ ...........• . •.
:. · $~e~d ~~~lr\.;ti~ng, • .· . .. ·•· •·
Deep screening and initial packing 20 km/hr
Picking up slacks where required and fourth Normal speed after passage of not less than
through packing (Manual) 0.4GMT of traffic
25.8.6.1 For Class 2 & 3 lines, reference stakes or creep marker posts are provided along LWR
on the cess on either side of track at suitable intervals with chisel marks square to the
joints. Creep is measured by stretching a fishing cord over the chisel mark, with reference
to the joint. Periodical recordings of creep shall be recorded in the creep register at
intervals to be specified by the Regional Engineer.
25.8.6.2 For CWR track in Class 1 lines, creep marker posts are provided for monitoring and
recording of creep which need to be carried out at least every 3 months for the first year
of installation and once every 6 months for the second year and subsequently if the rate
of creep is minimal, once every 12 months.
25.8.6.3 Track shall be closely watched, wherever creep is noticed to have occurred and pulling of
the rail to be done once it reached the stipulated limit. Refer to Chapter 23.
1. Know the destressing temperature (td) of your section/panels and make sure the
track gang also know about it (Id shall be painted on a board prominently for each
LWR/CWR).
2. Confine essential maintenance to a period when the temperature is below (< Id +
5•c)..
3. Keep the ballast section to the specified profile and in compacted condition,
particularly in cribs and shoulders.
4. Keep close watch on pedestrian and cattle crossings, where the ballast profile is
frequently disturbed. Make up ballast deficiency promptly.
S. Keep patrolling equipment always handy and start patrolling of track as soon as rail
temperature exceeds !., + 1o• C or ss• C, whichever is less.
7. Train Patrolmen to keep a sharp look out for kinks in hot weather and to protect the
trains and report to superiors immediately.
11. Pack loose sleepers without lifting or opening track in hot weather.
12. Impose speed restriction of 30 km/hr at locations where ballast is not fully
consolidated, and sleepers are loose, if rail temperature is likely to exceed Id + s·c.
(If track stabilizer is not employed, the track shall be considered to consolidate after
traffic had passed for not less than 0.4 GMT). Once the track have been restored to
good condition such that ballast is made adequate and loose sleepers and
fastenings have been attended, normalisation of speed can be considered after a
period of 24 hrs and with a passage of not less than 10 trains through the section.
13. Pay special attention to joint gaps, approaches to Level Crossing and unballasted
bridges, and to horizontal and vertical curves. (Note: Level crossing shall not be
located in the breathing length of LWRICWR.)
14. Drill staff in detecting buckling, and rail fractures and protection of trains in such
cases.
1S. Check that reference stakes are correctly maintained.
16. Check and rectify the defects in the track such as;
4. Do not lift the track while manual packing the ballast around the sleepers within the
sleeper crib and shoulder or for replacement of fastenings or slewing after 11 am or
in hot weather.
S. In all maintenance operation, do not lift the track by more than 50 mm in one
operation.
6. Do not open the track for more than 30 consecutive sleepers in a stretch. Keep at
least 30 fully boxed sleepers between two such stretches opened out.
7. Do· not carry out realignment of curves when rail temperature is above (td +
5•c) or 55°C whichever is less.
8. Do not leave track 'opened out' during mid-day rest/break. This ruling is
irrespective of temperature.
9. Do not renew more than one sleeper at a time in a stretch of 30 sleepers during
normal maintenance.
25.9.2 The PWI and Ganger shall be vigilant and on their own. order hot weather patrolling such
that the patrols are in position when rail temperature exceeds 55•c or t, + 10• C,
whichever is less. lt is recommended that pilot run (road run) ahead of high risk trains
such as High speed passenger trains shall also be carried out. High speed inspection
vehicle shall be necessary to be used for this purpose.
Special Gang shall be equipped fully as Rapid Response team in the Regions equipped
with rail cum road vehicle, off track tampers, welding equipment etc. and multi skilled
team members capable of cutting rails, AT welding and tamping with hand held tampers.
This team could reach the site in shortest period of time to attend to exigencies like rail
failure, buckling, attend to bad spots conveyed by any inspection or jerk message by a
driver, etc.
The CPWI shall ensure supply of rail thermometers and enforce procedures for
observation of rail temperature.
25.9.3 The hot weather Patrolman shall walk over the track during such patrolling and look out
for sun kinks, areas of localized track weaknesses and any tendency towards buckling. If
any such tendency or actual buckling is noticed, the Patrolman shall immediately
suspend traffic, protect the track and report the details of occurrence to the Ganger and
PWI.
25.9.4 The Patrolman shall carry the following equipment:
25.9.5 The Ganger shall make sure that the men selected for patrolling are conversant with their
duties and are properly equipped and proceed on patrolling duty on time, as indicated in
Chapter 47.
25.9.6 The PWI shall check during his inspections that the patrol is being properly and
purposefully carried out and that Patrolmen are able to recognise hazards and to take
prompt action to protect trains.
Rev.(} Page 19 of 60
Permanent Way Manual Part IV
I<TM Welded Rails- Laying and Maintenance Chapter 25
25.9.7 The CPWI shall check on the extent and quality of patrolling carried out, during normal
and surprise inspections.
25.9.8 Particular attentions should be given to areas that are potentially subject to track
instability during hot weather including the following:
• areas known from experience to show signs of instability or having a history of track
buckling,
• sections where rail stress is not under control (e.g. where there is creep or the stress
free temperature is unknown);
• localized track weaknesses (e.g. at mud-pumping or where there is slack in the
packing or hollow under rail seat)
• ballast deficiency or where sleeper condition is poor; especially ballast deficiency on
the outer shoulder along curves.
• track that has been disturbed (e.g. from sleeper renewal or tamping)
• Hazard locations such as areas of change in track structure (e.g. track approaching
under-bridges or points and crossings) among others.
• Bottom of descending grades.
Annexure 25.4 shows a table that specify the minimum level of supervision for different
track maintenance activities.
25.11.2 The SEJs shall be inspected every fortnight, and packed and aligned if necessary. Oiling
and greasing of tongue and stock rails and tightening of fastenings shall be
simultaneously carried out. Any movement of SEJs is to be checked and destressing
shall be carried out if necessary.
25.11.3 Special attention shall be paid to the alignment and levels of the track in the buffer rail
portion. Lookout for any kinks or hogs that need to be attended to.
25.11.4 Inspect and ensure that fishbolts are kept tight at all times. All buffer rail joints shall be
kept lubricated at least every six months. Bent fish bolts shall be immediately replaced.
Close examination of the fishbolt holes and the rail ends shall be carried out at the same
time when lubrication is done in order to look out for rail cracks or any other defects.
25.11.5 Check the opening/closing gap at the buffer rail joints to lookout for signs of:-
25.12.2.1 Tendency towards buckling will usually show itself through kinks (sun-kinks) appearing in
the track with rise in rail temperature. By tapping sleepers for hollowness, it is possible to
see if there is any tendency towards vertical buckling.
25.12.2.2 As soon as a tendency to buckle is detected, traffic shall be suspended and the track
protected by the Ganger/Patrolman noticing the defect. Traffic shall be restored only after
the PWI certifies the track fit. In all such cases, track shall be inspected by the CPWI
who shall decide what remedial measures are called for, including destressing and
arrange to carry out those measures needed.
25.12.2.3 Particular care must be taken to see that the factors which contributed to the tendency for
buckling i.e. jammed joints, seized fish plates or shortage of ballast receive appropriate
attention without delay.
25.12.3.1 If the track actually buckles, traffic shall be suspended and the cause of buckling
ascertained. The condition of the expansion gap shall be checked.
25.12.3.2 Repair shall be carried out in the following stages by the PWI under his personal
supervision:
• Emergency repairs.
• Permanent repairs.
• Destressing.
25.12.4 Emergency Repairs
25.12.4.1 The buckled rails shall be cut at two places to create a gap not less than 6m apart. The
track shall then be slewed to the correct alignment and cut rails (closure rails) of the
required lengths shall be inserted to close the gaps, making due provision for welding of
joints on both sides. The cut rails shall then be connected by use of fishplates and screw
clamps (G-clamps) and the line opened to traffic with speed restrictions for the first train
at 10 km/hr and for subsequent trains at 15 km/hr. A lookout must be on watch at all
times at the site to monitor the situation under traffic.
25.12.4.2 lt is essential that the cause of buckling is ascertained and rectified before the rail
temperature rises again to about lct + 5°C. If the cause (such as deficiency of ballast)
cannot be removed during the above period, the speed restriction shall be continued and
the track kept under constant watch.
25.12.5 Permanent Repairs
As soon as the welding party is available, the clamped joints shall be welded using rail
tensor. Additional pair of cut rails and sawing equipment may be required to adjust the
gaps, in case they have been disturbed in the intervening period. The speed restriction
may then be removed after destressing and welding.
25.12.6 Local Destressing
The affected portion along with 100 m either side of the LWR panel shall be locally
destressed as soon as possible.
25.12.7 Reporting
Each case of buckling shall be investigated soon after its occurrence and a detailed
report made to the General Manager Permanent Way by the Regional Engineer.
If any fracture takes place on LWR/CWR, immediate action shall be taken to suspend the
traffic and protect the line, by the Ganger/Patrolman detecting the fracture, who shall then
report the fracture to the PWI/Ganger. The PWI shall arrange for making repairs in three
stages.
• Emergency repairs.
• Temporary repairs.
• Permanent repairs.
• Screw clamps, joggled fishplates (for fractures at welded joints) and standard
fishplates.
• Steel tape (graduated in mm).
• AT welding equipment (see clause 24.3)
• Punch hammer.
• Equipment for destressing (see clause 25.6.4).
• 4 m long sawn rail cut pieces of the same section.
• Rail closure 30mm long.
• Equipment for protection of track (see clause 52.2.2 and 45.8)
25.14.3 Emergency repairs
25.14.3.1 Join the fractured rail using fishplates with 4 screw clamps. (If the gap due to fracture
exceeds 30mm, insertion of a closure rail piece is necessary).
25.14.3.2 Restore traffic at 10 km/hr.
Note: - This work can be done by a Ganger/Patrolman.
25.14.3.3 Temporary Repairs
1. Punch two points on either side of the fracture on the rail at a distance equal to the
length of an available piece of rail (not less than 4m) plus the gap at the fracture plus
two gaps required for welding minus 1 mm for each saw cut.
2. During a Line Possession, cut the rail through these points by saw.
1. Such repairs shall be carried out by the PWI according to the procedure below:
2. The CPWI shall decide if local destressing is adequate or whether the whole
LWR/CWR needs destressing in the wake of rail fractures.
The sleepers shall be replaced one by one, ensuring that two sleepers tackled
simultaneously are separated by at least 30 sleepers.
1. The panels in the affected portion shall be cut in suitable lengths not exceeding 1 km
and provided with one closure rail of 6m length each at every cut
4. Tamp the renewed sleepers by 'on-track' tampers followed by crib and shoulder
compaction.
5. Impose speed restriction of 30 Km/hr.
6. Continue the restriction during the period of ballast consolidation/adequate tamping
has been carried out along with Ballast Stabiliser.
7. Introduce special night patrolling during the period of repairs.
25.16.1 In the interim, until a replacement SEJ is installed, replacement with a closure rail shall
be done with use of temporary fishplated joints with a screw clamp. The speed restriction
to be imposed shall be 15km/hr and normal speed resumed only upon completion of
installation of new SEJ and all necessary track destressing and welding of joints.
25.17.2 LWRJCWR shall be restored only after the formation in the damaged area has
consolidated and the ballast cleaned. Destressing shall then be done upon installation of
LWRJCWR in the affected stretch.
25.18.2 All unusual occurrences, temperature records and destressing operations carried out
shall be documented by the PWI.
25.18.3 LWR/CWR Register - The PWI/CPWI shall keep an annual record of LWR/CWR
maintenance and a register of measurements of SEJ gaps, creep measurement of
LWR/CWR in central portion and breathing lengths and gaps of fishplated joints of the
buffer rails. This is shown in Annexure 25.6 and Annexure 25.7.
25.19 TRAINING
25.19.1 The Regional Engineer shall ensure that PWI and Gangers on LWR/CWR sections are
trained in the special features of LWR/CWR. Arrangements for training shall be made as
directed by the General Manager Permanent Way Division.
25.19.2 Competency requirement to carry out Rail Stressing operations is described in Annexure
25.2.
LIST OF FIGURES
LIST OF ANNEXURES
-~-------T
I
II
I ~----1-T--l
----T !I
I
I
I
I
j m e! zi
:il 01
~I
I
! ;!i
I I ~~
I I I-I
e! 1 ~I
m I
::n
... 1 I
I
I
I
-~ I
I
!
!
< f-----t
. 1
r----,--t--1-1
i i ~i i i
I
I I i~i~i~i
i'UJ'E,_,_,
. ~--+ 1
i e!
I
I
I !5 I ~ I I I
I
I
~ 1 I
I ~ ~--1---1---1
1
I ~I o I I I
I
I
J
I
I ::ll.,.I I c)J
I zlj!EI
<I
I .,I
I I
I -~
m
I ,Et~lt()l
I
I I
I 1"11«1"'1
~I
I I I t
I I -1 I I
f 1
ell, L----+--i--..1------1
m
::lf I I mI I I
... 1 I I
I I
leJI~Ielel
I 1 I
-~ I
1a.. ~ E,E
1 1 1
I ~I t-=1
! f-----t 1
w
I ~i mI I I
I ~I
81161
co1
I
1
I
10
1
i ~~ I ~ r--t---t--1
I ~I I I I
L_ -+--___ L _________ l
I -1
I ~I .. I E I E I
I I I I I
It z~I, -~I E I E I
,,o,o,
I ~I ~I ~I ~I
L_j __ l__ L_J
Figure 25.1 -Spacing of sleepers in LWR.
"l1
c.O'
c: '.~ro-... ~--------------------------------~--------------------------+-------1
Cil
::0:
"'""
N
CD
0:
(/)
~
c: 150 mm 2.00 mm I 150 mm ;o"'O
< "'~3~
~ I :I
"'
"0
;o 1il reo
~ :::l POSITioN OF
FUl\JRE SIGNALS 1:) FACING PT 1:) LEVEL XING r-OVERALL LENGTH 45m I:J 1:) "' :I
'< -
0 0' 5'~
~ AND INSULATEO D • ---:1 !, D=2' ' <C Ill
1il ~J..,f\u I.JT f.,IT =
2
R•870m "''<
"S.
:::l
<Q
JOINTS J.'ft:'t•.ou o-a."'7n-. f_ •rT I _.TT wt.IT
as:
;;::"'
NO OF SEJS,LW RAILS "'
-· :I
<:::
:E
:0
AND LENGTH OF LWR Ill
:::l
ro-
""':::l
~:0
DISTRIBUTION OF WELDED
PANELS
2
REHABILATION WORK
"'"'
0
~
-.,
'0-a
~ :::1.
0> N-
0
"'<
Permanent Way Manual Part IV
Welded Rails- Laying and Maintenance Chapter 25
~
"w
"'zzw
"
--'
--'
I;! l_
"'
I;!
"'<
c::
rI
,_j
0
i'.i
~
l.,'-.._
Figure 25.3- Stressing using a Rail Tensor.
LWR:
LWR is defined as a long welded rail laid on a track out of which the central portion does
not exhibit any longitudinal movement on account of temperature variations. The
movements are exhibited by track lengths on either side of the central portion which are
called as 'breathing lengths'. In KTMB, an LWR is made up of standard rails (of 12.2m,
18m or 25m length) welded together up to a length of 146m and are laid on track
connecting each other with fishplated mechanical joints. In continuous welded rail (CWR)
track, as defined below, CWR rails that are cut into manageable length of up to 1050m
for purpose of destressing operation, are also considered as LWR.
CWR:
An LWR which continues through station yards including points and crossings is
described as a continuous welded rail.
Rail Temperature:
The temperature of the rail as measured by an approved rail temperature measurement
device.
Breathing length:
The lengths at the ends of an LWR on either side where the LWR "breathes" i.e. exhibits
movements due to temperature variations is called the breathing length.
Stress-free Temperature or Neutral Temperature (to):
The rail temperature at which an LWR is free of longitudinal thermal stress is called the
stress-free or neutral temperature.
Switch Expansion Joint (SEJ):
A physical device placed at the end of the breathing length of an LWR to accommodate
the expansion and contraction of the breathing length.
Buffer rails:
A set of free rails used in lieu of SEJs as a temporary or permanent measure to
accommodate the movement of the breathing length of the LWR.
Ambient temperature:
The temperature of the rail as recorded by an approved type of rail thermometer at site.
The average of the annual maximum and minimum rail temperatures recorded for a
particular section.
Destressing I Stressing I Restressing:
The operation undertaken to secure stress free conditions in the LWRICWR at the
desired rail temperature.
The average rail temperature during the process of fastening of the rails to the sleepers
at the time of installation of LWR/CWR.
The average rail temperature during the period of fastening of rails to the sleepers, after
destressing LWR, without the use of rails tensor. If rail tensor is used, Id for all practical
purpose is equal to 10 .
Prevailing temperature (tp):
The rail temperature prevailing at the time when any operation connected with
destressing is carried out.
Rail Tensor:
A hydraulic or mechanical device used for physically stretching the rail. They exert a pull
in the rails to free the rails of locked up stresses. The stressing is done at a temperature
t, lower than to.
Anchor length:
The length of track required to resist the pull exerted on the rails by the tensor at
temperature tp. There shall be no rail movement at the end of Anchor length away from
pulling end. Based on the provisions in this Manual, the anchor length is 5 meters per
degree Celsius of (!0 -t,), subject to a minimum of 50 m.
Ballast resistance:
lt is the resistance offered by ballast section to longitudinal or lateral movement of track.
The resistance to longitudinal movement of track, affects breathing length and creep.
Whereas the resistance to lateral movement governs the strength of track against
buckling.
Special patrolling (hot weather):
The patrol shall be carried out, when the rail temperature exceeds Id + 1ooc or 55oc
whichever is less.
Reference stakes/Creep posts:
Stakes or markers provided on the line side of LWR/CWR track to observe movement of
rails.
Thermal forces:
Forces built up in the central zone of the LWR which does not expand or contract due to
variation in temperature. The thermal compressive force requires lateral restraint, which
is provided by suitably designed track structure, to prevent buckling. The main
parameters which contribute to strength against buckling are:
Consolidation of Track:
This the process of building up ballast resistance to the tendency of movement of sleeper
either initially before laying LWR or making up subsequent loss of resistance by passage
of at least 0.4 Gross Million Tonnes (GMTs) of traffic load on the track after manual
compaction of ballast or with the use of tamping machines and dynamic track
stabiliser(DTS).
For newly laid LWR/CWR, at least three rounds of packing, last two of which should be·
with on-track tamping machines and the last tamping cycle at least with one round of
DTS.
Pull-apart condition:
This means a condition when the actual rail temperature is below the rail neutral
temperature at or near a joint where longitudinal tensile forces due to contraction
tendency of the rail may affect the fastenings at the joint or causing rail breakage.
3. Have undergone and pass a 5 days theory and practical course conducted by KTMB
Permanent Way Instructor under the KTMB Railway Academy on Rail Destressing
operations module:
1.0 Introduction
2.0 Scope
3.0 Destressing
8.0 Equipment
9.0 Destressing with Hydraulic Rails Tensors
1.0 INTRODUCTION
Welded rail strings in nominal lengths of 150 m are laid in position and flash
butted welded in the field into long lengths to a maximum of 1050m, leaving an
un-welded joint with a gap in between such welded lengths. Alternately single
rails of nominal length 25m may also be flash butt welded in the field to form
such long lengths. Such long welded rails ( Maximum of 1050m in straight track
and 600m on curves) are to be fastened on to the sleepers and the resultant
joints welded at stress free condition to form continuous welded rails.
(i) The rails are not fastened at the stress free temperature range (i.e. 45+5,-
00C)
(ii) Where the track alignment after destressing has changed by more than 40
mm vertically or more than 25 mm horizontally from its original stress free
condition.
3.2 The welded panels of nominal lengths of 150 m are laid and fastened to
concrete sleepers. Initially rail ends are provided with fish plates and G or C
clamps. These rail ends are subsequently joined together by in situ flash butt
welding. Rails of nominal lengths of 25m (without holes) on Concrete Sleepers,
when laid in track diversions following permanent plan and profile, are also
welded at site, generally by utilizing mobile flash butt welding plant.
3.3 Destressing shall normally be done prior to commissioning of track. This shall
be done in all cases except in situations where a short length of permanent
track is required to be linked during a line block and traffic is to be allowed
immediately at the close of the block period. Such cases arise in the areas
between newly constructed/ commissioned track at either ends or at switch
over locations between two adjacent new tracks (UP to DOWN or DOWN to
UP). Such lengths will be de-stressed at a later date after tamping and
consolidation. Destnissing of temporary track can be carried out either prior to
or soon after commissioning of the temporary track for train service as dictated
by site situations. Until destressing, the joints shall be normally connected using
fish plates and G clamps. If circumstances warrant, such connection may also
be made using fishplates & bolts or by AT welding to be cut out at a later date.
For such lengths, rail to sleeper fastenings shall be fitted at temperature above
45°C pending destressing. If this temperature is not available during the line
block, the fastenings shall be re-fixed on the following day at temperature 45°C
+5,-0°C. In the commissioned track, a speed restriction of 30km/hr. will be
imposed and track monitoring done for safe working until destressing is
completed. If the traffic is allowed with G clamps at joints, then the speed shall
be restricted to 15 km/hr.
4.0 DEFINITION OF TECHNICAL TERMS
i) Installation Temperature (t;)
This is the average rail temperature during the process of fastening the
rails to the sleepers at the time of installation of LWR!CWR.
This is the rail temperature prevailing at the time when any operation
connected with destressing is carried out.
iv) Stress Free Temperature (to)
This is the rail temperature at which the rail is free of thermal stress.
Generally, this stress free temperature is considered as 45• C, which can
be reviewed I updated based on results obtained through continuous rail
temperature recorders. Stress free temperature range will be + 5,-0° C of
the specified stress free temperature.
v) Tensors
These are sets of mechanical equipment used to exert a pull in the rails to
free the rails of locked up stresses. The stressing is done at a temperature
tp lower than to.
vi) Anchor Length
This is the length of track required to resist the pull exerted on rails by the
rail tensor at tp. Based on the provisions in KTMB manual, the anchor
iii) Adjust alignment, longitudinal levels and surface close to designed line and
level (within a variation of 40mm with respect to vertical and 25 mm with
respect to lateral alignment as compared to the designed values).
vi) Prepare destressing plan with pulling point taking into account the
horizontal curve and other obligatory points, such as turnouts.
viii) Clear the rail seat area near the insets free from dirt and dust.
8.0 EQUIPMENT
Rail Knocker 1 No
T- Square 2 Nos
For carrying out destressing using Rail tensors, it shall be ensured that the
activity of pulling the rails with tensors is planned and executed when the
prevailing temperature is below the maximum of the stress free temperature
(t0 +5°C).
A length of track on one end of the rail (adjoining the already de-stressed
portion) to be de-stressed shall be well fastened down, before commencing
destressing activities and check and rectification as needed to be carried out at
stress free temperature, to form the anchor length to resist the pull exerted on
rail by the tensor. Anchor length shall be calculated at the rate of 5m per deg C
and shall be not less than 50m for t 0 -tp=1 O"C.
9.3 Establish Tell Tale Points
Fastening shall be released, commencing from the free end of the rail and the
rail shall be lifted on to rollers positioned at intervals of 12 sleepers. The rubber
pad of the sleeper shall be removed where roller is to be placed. In addition,
side rollers shall be used on curved track.
Based on the radius of curve as under·
The end of the anchor length shall be marked at the foot of the rail. Reference
marks, at about 1OOm intervals from this point, shall be provided throughout the
length of track taken up for destressing. These marks shall be made on the top
of the sleeper. Alternatively the edge of the insert could be taken as the
reference point. The last reference point (Nearer to the tensor location) rnay
have a lesser length. These reference marks are denoted as A2, A3, etc. The
reference marks A2, A3 etc. shall be transferred using T square on to the foot
of the rail, when the prevailing temperature is not more than the stress free (to)
temperature.
9.7 Gap at Rail Joint
Suitable gap shall be ensured at the rail joint at the location where tensor is to
be located, so as to have enough gap to accommodate the pull required for the
panel for the prevailing temperature (based on the statement at Appendix I)
and for AT welding. The rail is to be cut suitably to achieve this gap, before
commencing the tensioning operations. In the case of destressing with single
pull (Appendix ll(a)) the cut shall be made in the non-de-stressed length. In the
case of destressing with double pull (Appendix ll(b)), the cut shall be made in
either of the panels. The elongation calculations shall take into account the
reduction in length because of the cut.
9.8 Movement of Rail
it is important that account shall also be taken of any movement of the rail
which occurs at the tell-tale soon after the fastenings are released. The tensor
shall be fixed at the predetermined location and tension applied so as to
remove any kinks or misalignment and to minimise the friction in the rollers etc.
Then the tensor shall be released and movement at the end of the anchor
length, also termed as 'Slip' recorded.
9.9 Rail Temperature Readings, Calculation and Marking of Extension
Thermometers shall be placed at the web of rail on the shaded side of each rail.
At least three thermometers shall be used on one of the panels.
These shall be located near to the pulling point, at the midpoint of free panel,
and near to the anchor length. When the readings of all thermometers are
reasonably uniform an average shall be taken. Rail temperature shall be
recorded every 30 minutes during the destressing process. If the rail
temperature measured proves to be below the designated stress free
temperature, the work shalf be continued and completed.
If the rail temperature exceeds by more than 5° C from the neutral temperature,
destressing shall cease until the rail temperature returns to within specified
range. Measures will be taken to ensure the gap at the free ends does not close
and buckle the rails.
The thermal movement for the measured temperature for the length to be de-
stressed shall be obtained from the formula attached as Appendix I. The full
extension as calculated and after adding the movement of rail at the anchor
length (as explained in Clause 9.8) away from tensor location shall be marked
accurately on the rail foot (behind the reference points marked as at item 9.6
above), so that the rail movement may be monitored during tensioning.
9.10 Positioning of Tensors and Tensioning of Rail
The rail tensors are positioned at the destressing joint and tensioning of the rail
shall be commenced. During tensioning, the rail becomes elongated, which can
be measured based on the reference mark at the pulling point. The movement
shall be checked at the tell-tale and at each established reference points on
each of the sides pulled. The force applied by the tensors shall be adjusted
during tensioning to ensure that desired extensions at corresponding points are
achieved progressively.
9.11 Removal of Rollers and Fastening Down
After achieving the desired extension at the free end and the corresponding
marker points A2, A3 etc., the rollers shall be removed progressively and re-
fixing of the fastening shall be started. Care shall be taken for proper
positioning of rubber pads and liners.
Immediately after fixing the rail to sleeper fastenings in the de-stressed portion
on every sleeper for a length of 50 m from the weld, the gap at the end shall be
measured. 11 is expected that the gap would be more than 25mm. To get
requisite gap of 24mm to 26mm for welding, the fastenings of the panel, yet to
be de-stressed, shall be removed progressively till the requisite gap is
achieved.
9.13.1 For destressing subsequent lengths, an anchor length shall be provided at the
end of the already de-stressed length.
In such cases, the anchor length will have to be reckoned beyond this length of
50m in the already de-stressed length (please see sketch at Appendix ll(a).
10.2 Turnouts
10.2.1 Destressing shall commence I end at either end of the turnouts as defined in
Clause 6.0(vi).
10.2.2 For purposes of destressing the length of the turnout will be reckoned from the
Stock Rail Joint and up to the location between the last long sleepers and the
track sleeper in rear.
Destressing of this segment shall be carried out at the stress free temperature
range without applying any pull on either side.
10.2.3 As far as possible, all turnouts and connecting lengths of minimum 50 m shall
be installed at or near the stress-free temperature of 45"C +5,-0"C.
10.2.4 If installation of a turnout is not done within the stress free temperature of
45"C+5,-0"C, fastenings shall be released and the turn out including the
connecting length of 50 m shall be fastened within temperature range of 45+5,-
0"C.
10.2.5 Where turnouts are located under canopy or depot podiums a specific stress
free temperature will be determined for the turnout and approach portion of 20m
if the stress free temperature of 45"C+5,-0"C cannot be obtained.
10.2.6 The procedure for releasing and re-fastening will be in accordance with the
requirements of the turnout manufacturer.
10.3 Bridges & Tunnels
10.3.1 Guard rails shall normally be fixed after destressing. No special precautions are
required, while carrying out the destressing over the ballasted decks. Care
shall, however, be taken for safe working of staff while on the bridge.
10.3.2 The track over the Prai Swing Bridge will be separated from the CWR track by a
Rail Expansion Joint (REJ) and SEJ.
10.3.3 Installation of track through La rut tunnel and destressing will be governed by
the procedure for a plain track. As an additional precaution, entire length in the
covered portion of the tunnel will be de-stressed as a separate activity.
Following this activity, destressing of the track at either approaches will be
carried out, leaving the joints at extremities of the tunnel, without welding.
Locations at the extremities of the tunnel (for a total of 50m, 25m inside the
tunnel and 25m at the approach will be once again de-stressed at stress free
temperature range and the resultant joints welded.
10.3.4 Installation of track through Berapit tunnel will be governed by the specific
design requirements.
10.3.5 Method of installation of REJs and SEJs and destressing the approach track
will be governed by the requirements for installation of REJs and SEJs.
10.4 Connection to siding lines
New track laid up to the proposed connection point with the existing track inside
the Thai border will be destressed as laid out in this Method Statement. After
destressing the newly laid track fastenings of the existing Thai track will be
released for a length of 50m and the track lifted on rollers and tapped to release
any locked in stress. The track will then be fastened down at the stress free
temperature. Installation of SEJ will be carried out at the end of the project
boundary, where SRT's twin block sleeper track starts.
During the process of in-situ welding, gaps at the rail joints left for destressing
operations shall be so planned that welding can be done without pulling the
rails but by only cutting the rails as necessary. If the gap is excessive, it may be
necessary to pull the rails to obtain proper gap for fixing the tensor for
destressing. This shall be achieved by removing fastenings and pulling the
rails, adjacent to the length proposed to be de-stressed. Similar action shall be
taken to get the correct gap for Aluminothermic welding after destressing. lt
shall be ensured that the joint does not fall over the sleeper seat.
10.7 Local Destressing
Whenever:
(ii) any disturbance to the track profile involving more than 40 mm vertically
and I or 25 mm horizontally;
APPENDIX 1
Extension E{mm)= La {to-tp), where Lis the length of Segment of the Rail Qn m) to which the extension is applied,
a is the coefficient of linear Thermal expansion of Rail steel= 0.00001151 per degree Celsius
to Rail temperature (Le.) 45' C ( as at present)
tp is the prevailing temperature at the time of Oestressing
For every m of rail and when to-tp is one, the pull required will be
1x0.00001151x1 0.~0001151 mm
The pull required can be easily calculated based on the length to be destressed and the P,revailing temperature.
"i
stipulated under item 5.0 of the Method Statement o. Method Statement a. 0
• • c:
~~~~~.l,£:::::::::,:,::::::::::=,=,::::::::::,:,::::::::::::::::::::::::::<':;,o;,;u;c;e~R;a;l~l;(;lf~c;e;q;u;l,;e;d;}::::::::::::::::::::::::::::":::::::::::::::::::: m
z(")
provided & welded after Destressing
m
11111 <---1 OOm---> <---1 09m-----> <---1 00---> <---1 00---> <·<-Balance
0
Anchor Length--> ,.. "T1
Length Destressing I segment Destressing 11 segment
" 0
"1J
llll\l!!lli,,,,,' m
Anchor length --------> <--SO--~ ;o
" " " M
~
Breathing
length (see Point NO. 2 below)
PRELIMINARY 0
Rall Strings ( 150 m long or normal length Rails) laid in track are welded in lengths as stipulated in para 5, z :E
(1)
at site, by Mobile Flash 81..111 welding( for Permanent Track) and by a!umino thermic process for Temporary Track and at identified locations in permanent track.
PREPERATIONS
"T1
0
;o
g:
1 Mark Anchor length of SOm m in for (to-tp) up to 10°C. For (to-tp) above 10~c. anchor length to be increased at the rate of Sm per degree C.
c.
2 In subsequent stretches, in situations, c )>
;o;;jl
when welding does notimmediately follow destressing and the rail is fastened down without welding, SOm length of track from free end shall be
left as breathing length to be stressed again after welding, and the anchor length shall be counted beyond this SOm length.
I"
(J)
"1J
"tl
OJ
~3
~
3 Mark the end of the anchor length at the bottom of the railfoot as A1 -1 m I '"
;o z ""'
-
;o 4 Mark reference marks with paint on top of the sleeper approximately at every 100 m from the end of the anchor length. r
CD m c OJ
< 5 Calculate the movement required for the length of the panel from the end of the anchor length and upto the free end. (J)
>< "
5·:E
..,=
0 6 Make suitable cut(s) in the free end of the segment (J)
7
to ensure adequate gap to enable movement of the free end while applying tension.
Remove the fastenings in the length now proposed for destressing. z "''"
'"'<
starting from the free end and proceeding towards the anChor length and note the movement of A1. Gl ~ s:
::J
c.Q)
8
9
Transfer the marks (as referred in Note 4 above) to the outside of the foot of the rail, after removal of the fastenings.
Fix the tensor at the free end (one on each rail).
:E s:,
::j
~.~
10
11
12
Apply tension to get the rail staright (without any visible kinks).
Note the amount of pull given at this stage at the pulling point, at the end of the anchor length(A1 ).
Apply tension in the tensor to get the required elongation at reference point A2+ the elongation obtained
during initial pull at A1( the slippage at the end of the anchor length) and at the reference point A2.
::t:
-1
m
z
s--
::J
Q)
13
14
Fasten down the segment A1-A2.
Repeat the operations for Segments A2-A3, A3-A4 etc. For every pull, calculate the extension required and add the actual slippage at this point
during the intial pull ( to release kinks)
(J)
0
;o
"g
15 Check the final gap obtained, if it is between 24 to 26 mm, weld the joints. (J)
16 If gap is not matching the required gap (and when found excessive),pull the adjacent non destressed panel/segment with the help of
I
tensor and carry out welding with tensor in position. >
r
17 If gap is (found less), make a cut in the adjacent panel/segment and carry out welding with tensor in position.
-1
18 In exceptional cases, when the gap obtained is far in excess of the required gap, provide a closure rail by cutting the required length from the non destressed pane!. m
;o
"1J
I For providing closure, make marks in the track rail
=length of closure rail (6m) +two weld gaps- one saw cut.
z
~
.
"''"
CD
"'
Remove the tensor, cut the track rails, insert the closure and weld at one end.
Weld the other end also, if the gap is in order.
If the gap is execessive, apply tensor, pull the segment on the side yet to be destrsssed to achieve the required gap and
carry out welding, with tensor in positlon.
<
...
m
(")
::r
'"
-.,
""
~I
18 After completion of welding, remove fastenings for 50 m on either side of this location (now welded) and
tap the rails, to equalise the stresses.
..,_
~ ~
19 Repeat the operation in subsequent segments, yet to be destressed. <n<
Appendix 11 b
@
SEQUENCE OF OPERATIONS FOR DESTRESSING WITH TENSORS- Alternative 11
?.\ (J)
s:
OJ
m
"i
0
Segment No1- Length is dicated by site conditions
subject to a maximum as stipulated in para 4 of the
Segment No2- Length is dicated by site conditions subject to a c
maximum as stipulated in para 4 of the method statement m
method statement z
C'l
m
0
"T1
Lengtr. Length
<---100--> <--100----> <-1 00---> <-Balance
0
"C
Length-·-> m
;o
<--150 m----><-----150 m--------><-----------150 m--> ~
<<<<--------------- Destressed Panel ---------------------···········----
~ 3 panels-->>>>> !i
>>>>
oom 0z
Anchor
Length
Anchor
Length "T1 ~
0:
Destressing Next Stage 0 CD
;o 0..
PRELIMINARY 0 ;o"C
Rail Strings (150 m long or normal lengths) laid in track are welded in lengths as stipulated in para4, at site, by mobile flash butt welding {for Permanent track) and by Alumina Thermic welding for
m
I
>
"C "' ~
Temporarey Track and identified locations in the permanent track). (J) "C iif3
-l m I ~
;o PROCEDURE ;o z
''"'
CD 1. Mark Anchor length of min som for (to~tp) upto 10°C, at the ends of two panels to be destressed as shown in the figure. For (to-tp) above 10°C, anchor length is to be increased at m 0 "' ::J
"' the rate of Sm per degree C.
(J)
(J) x <-
s·::e
0 2.
3.
Mark the end of the anchor length at the bottom of the rail foot as A1 and 81.
Mark reference marks with paint on top of the sleeper approximately at every 100 m from the end of the anchor length. z = "' Cl
4,
5.
Calculate the movement required for the length of the panel from the end of the anchor length and upto the free end.
Make suitable cut(s) in the free end of the segment
Gl E
::e
"''"'
5.:;::
to ensure adequate gap to enable movement of the free end while applying tension. ;;:"'
6.
Double pull arrangement will normally need introducing a 6 m plug.
Remove the fastenings in the length now proposed for destressing.
=i
::t ~. ~
starting from the free end and proceeding towards the anchor length and note the movement of A1 and 81. -l et-
::J "'
7. Transfer the marks (as referred in Note 3 above) to the outside of the foot of the rail, after removal of the fastenings. m
8. Fix the tensor at the central gap for pulling both panels. z
(J)
"'::JCl
9 Apply tension to get the rail staright (without any visible kinks).
10 Note the amount of pull given at this stage at the pulling point, at the end of the anchor length(A1) 0
;o
2
11. Apply tension in the tensor to get the required elongation at reference point A2 +the elongation obtained during initial pull at A1( slippage at the end of the anchor length), and at
(J)
reference point 82 +the elongation obtained during the lntial pull at 81 (slippage at the end of the anchor length)
I
10. Fasten down the segments A1-A2, and 81-82.
11. Repeat the operations for segments A2-A3, A3·A4 and 82-83, B3-B4 etc. For every pull, calculate the extension required and add the actual slippage at this point during the intial pull. >
12. Check the final weld gas obtained for the two welds at either end of the 6 m plug., if it is between 24 to 26 mm, weld the joints. !:;
13. In exceptional cases, when the gap obtained is far in variance with the required weld gap, provide a closure rail by cutting the required length. m
For providing closure, make marks in the track rail ;o
"ll
=length of closure rail (6m) +two weld gaps- one saw cut.
Remove the tensor, cut the track rails, insert the closure and weld at one end.
z
!i
.
Cl Weld the other end also, if the gap is in order. C'l
<0
CD If the gap is execessive, apply tensor, pull the segment on one side to achieve the required gap and
< ::J"
"'
"'S, 15.
16.
carry out welding, with tensor in position .
After completion of welding, remove fastenings for 50 m on either side of this location ( now welded ) and tap the rails, to equalise the stresses.
Repeat the operation in subsequent segments.
m
= -.,
-o-c
~;:!.
"'
0 "'
tn< -
Permanent Way Manual Part IV
ICTIIII Welded Rails - Laying and Maintenance Chapter 25
APPENDIX IV
PHOTOGRAPHS I DIAGRAM OF RAIL KNOCKER AND ROLLERS
I
I/ ... · - --;__._ - ~- ·-·-·-·-------------T I '
,,
...
I
~ ~-
!
!
!
I
I
n _________
u
p.j_
.___... I
\
'"·~" 1
© KTMB Rev. 0 Page 49 of60
Permanent Way Manual Part IV
ICTIIII Welded Rails- Laying and Maintenance Chapter 25
I •
'·...~, \,\
'·. \~. 1
'' .\ .'
/ ' :
r
I
-- - - - - - -
1
I
I
!--- .
~ -...
l '·, -8
-h~·'~t'-, ·r-.· 12
'
~
-r - -
/ ,· ) .,
.r-7 I L_
I 1 I / /
~
I
c--\~tJ
I '
l.. .....
:i
1
1
(
I
/
/
•
~-.
\
•
..
',
•
·• ,
,/
~I /l~~
,/
-
.~
\
I
l..,
~.:"
~~I'
..... I ' \ i lI - _ . . ..,i
·-·--1-, . 1
·~1: lgi ~ . -r
1 •
\ ·-.. ·~.; 1 / r /i I
I 'ltr/
~I
I ~i ,--
r- T- .
I
-----
1
., 'L \
\J
~
s:
"i
OJ
c
:;
C)
::0
~
tn
OPTION 1 J:
~
.uJOlJt
~
<t>
zC) 0::
<t>
a.
tn :;:o"'tt
-t
)> )>
Ill~
C) "'tt ~3
C) "'tt ' ::I
AI
:::0 m m I (I)
Cl>
::0 z Ill ::I
~
z c '<-
:;· :E
0
C) x cc 11)
.,.,
0 < Ill'<
~s:
s:~»
OPTION 2 )> Ill
__ ::I
--
s::::
tn :::l 11)
-t <t>
m :I
z Ill
zC) :::l
@
PLAN FOR STAGGERING OF FASTENING SYSTBY
( ITEM 9:11 OF METHOD gr"A.TEUENT FOR DE -STRESSING } I ~
tn
-t
m
s:
"'0
Ill 0
(Q
Cl> :::r-
11)
~ STAGGERING OF FASTENING SYSTEM "C"'tJ
-11)
sa. M37~MR-SID - 009 ~~
0'> N -
0 Ul<
&····~··.·.·.····.··.··.+••····· Permanent Way Manual Part IV
<. I<TNI Welded Rails- Laying and Maintenance Chapter 25
APPENDIX VI
A3 A2 A1,--_-,AO
Chainage _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __,__ _ ____,Chainage
1. Date
2. Destressing length{excludinganchor length in meter)
3. Location (Between Stations)
4. Line (Up I Down I Loop1/ Loop 2 etc.)
5. Chainage from : to._ _ __
6. Left Rail/ Right Rail
7. Time of application of pull
8. Average Rail temperature at the time of pull
9. Rail gap as measured prior to de-stressing operation
Note: Left I Right rail shall be taken with reference to increasing chainage
Name: .............................. Name: ... ... ... ... ... .. .......... ... .. . Name: ................................ .
Designation: ..........•... ,...... . Designation: ... ............ .. .. ... ... Designation: ........................ .
Date: .........•................... Date: ...... ... ...... .. ... ... .. . ...... ... Date: .................................. .
,, i < --Lo~~~t_level;_st~ff!~.upervi_s~_r'
''',
'/,,
PWI
a) Ensuring that all creep anchors butt against sleepers Spiker
2. Rail, sleeper and during daily rounds
fastening b) Packing or renewal of single isolated sleeper not Ganger
requiring lifting or slewing of track Spiker
c) Renewal of fastening not requiring lifting
d) Renewal/recoupement of fastenings requiring lifting Ganger
e) Renewal of sleepers and fastenings over long PWI
stretches
f) Renewal of defective rails PWI
g) Carrying out welding of rail joint at site PWI/Oepot Technician
a) Making up shortage of ballast in shoulders at isolated
3. Ballast places Ganger
b) Replacement of ballast and checking ballast section &
PWI
Deep screening
c) Screening of ballast- other than deep screening Ganger
a) Realignment of curves
4. Curve realignment PWI
a) Imposing speed restriction if the temperature exceed
5. Hot weather work oo
td + 1 C or 55° C, whihever is less after Ganger
maintenance work is completed, manually or by
machines
b) Organising hot weather patrolling during hot weather PWI
period
c) Ensuring that hot weather patrolman turn out promptly Ganger
for duty during the required patrolling period and when
rail temperature exceeds td + 10° Cor 55° C
whichever is less
d) Hot weather patrolling, observing stability of track, Hot weather patrolman
presence of large number of sleepers with defective
packing, alignment of track, checking if the profile of
ballast is disturbed, tendency for lateral/vertical
deformation of track
e) Inspections during hot weather and checking on the PWI
workinQ of hot weather patrols
Rev.O Page 54 of 60
Permanent Way Manual Part IV
Welded Rails - Laying and Maintenance Chapter 25
,., ...
{.··
M·
,.~
~ ~ -
..., ~ - ,..
-
~· ·"f
....... ,._,
-
I
Liquid Type Thermometer (may be embedded inside rail piece or placed externally)
_--IIXING BO;_-
//
\_ BASE FRAME_ /
END VIEW FRONT ViEW
1. Maintenance Details
Year/Year/Year
Year/Year/Year
iii. Temperature at the time of destressing
i. Method of packing at the time of
iv. Reasons for carry out the distressing
laying, manual by machines
V. Subsequent distressing done-
ii. If by machines, type of machine/
temperature and date
tamper used
iii. Packing during maintenance -
manual beater/manual MSP/by 4. Unusual Occurrences
machines
iv. If by machines, type of i. Rail fractures
machine/tamper used ii. Buckling (location and reasons for
V. Whether directed maintenance/ buckling)
systematic through packing is done iii. Replacement of components in SEJ
and if the latter, the period when its assembly
done a. Fastenings
vi. Location requiring repeated b. Bolts
maintenance, if any c. Sleepers
vii. Quantity of ballast recouped d. Longitudinal ties
e. MS bracket
2. Climatic Details f. Chairs
g. Rubber pads
h. Tongue rails
(Measurements shall be taken on
i. Stock rails
representative LWR only)
iv. Derailments and accidents on the
i. · Maximum daily variation in
· temperature, vide para 5.2 LWRICWR portion (give km
ii. Max, rail temperature oc of the affected portion)
v. Replacement of sleepers (give km and
iii. Max, ambient temperature oc
the number of sleepers replaced and
iv. Minimum rail temperature oc
reasons)
v. Minimum ambient temperature oc
vi. Replacement of rails (indicate length, km
and reasons)
3. Details of Installation, Destressing etc.
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Note:
1. (a) and (b) will be always be positive, except when tongue stock rail crosses mean position. In such
case, a (-ve) sign will be prefixed
2. Left and right rails on double lines are determined looking in the direction of traffic
3. Left and right rail on single line are determined, looking in the direction of increasing kilometrage
4. If spacing of 2 central sleepers of SEJ differ by more than ± 1Onm, immediate rectification will be made
Right Distance (nm) between Ref mark & mark on Rail at various Measured by Rectification carried Remarks
or Ref Pillars' in non-BL of LWR/CWR out
Left
Centre of On date by
LWR/CWR at
km km ..... Km ..... Km .... Km ....
1 2 3 4 5 6 7 8 9 10
Chapter 26
Realignment of Curves
Document History
Authorised By:
r '
Signature:
Date: 2 8 MAY 2015
TABLE OF CONTENTS
26.1 GENERAL
When running on a curve is unsatisfactory, the curve has to be surveyed and adjusted
(realigned) either in part or on its whole length. This Chapter specifies the curve
adjustment procedure.
• The variations in curvature from station to station (as measured by the versines) do
not exceed the prescribed value.
• The measured versines do not vary from the designed ones by more than the
prescribed limits and,
o The cant provided suits with the curvature.
26.2.1.3 Whenever a curve is found to be not running satisfactorily, the PWI shall arrange for a
survey of versines (on 20 m chords), gauge and superelevation at stations 10m apart on
the transitions and on the circular curve.
26.2.2 Surveying of the Curve
The survey shall be carried out as below:
1. Mark stations 10 m apart on the gauge face of the outer rail. The first station,
numbered '0', shall be 30 m behind the apparent tangent point
(the start of the transition curve).
• Note any feature which will prevent or restrict slew at the station.
• Measure superelevation.
Table T-26.1
Note: For double track lines, note track centres at each station.
5. The PWI shall scrutinize the results of this survey and decide whether the curve
should be rectified in full or part of it adjusted. Guide lines are given in para 26.2.3
below:
26.2.3 Guidelines for deciding realignment
Versines at stations 10 m apart shall not vary by more than 15 mm, except in the
transition length.
The following guide lines may be adopted for the need to realign a curve by this method.
26.2.1.7 Example
Nle'asllred Difference
,_ vefS:irle
(2) (4)
0 1
2 3 2 1
3 7 4 3
4 5 6 1
5 6 8 2
6 7 10 3
7 6 12 6
8 11 14 3
9 14 16 2
10 15 18 3
11 19 18 1
12 24 18 6
13 24 18 6
14 24 18 6
15 20 18 2
16 12 18 6
17 22 16 6
18 12 14 2
19 12 12 0
20 10 10 0
21 10 8 2
22 5 6 1
23 3 4 1
24 1 2 1
25 0 1 1
• Total Stations: 25
2. A cumulative frequency curve is drawn from the above table and is shown in Figure
26.1.
3. 11 will be seen that the cumulative percentage of stations with versines varying up to
5 mm from the designed versine is 76; therefore the curve needs realignment. After
realignment the curve should be approximately equal to the position indicated by
dotted lines.
A decision on whether to adjust or realign the whole curve or part of it shall be on the
basis, as to how 'bad' the stations are distributed along the curve. If they are
concentrated in one part of the curve, only that part shall be adjusted.
• Survey
• Calculation of slews
• Stewing and packing
• Checking of adjusted curve
Note:
If the survey is not done within a week before the proposed adjustment, proceed as in
clause 26.2.2. The PWI shall forward the survey results to the CPWI.
26.3.3 Calculation of Slews
• the first summation of the differences in versines should be zero at the last station
which will mean that the sum total of existing versines should be equal to the sum
total of proposed versines.
• the second summation of the difference in versines should be zero at the last station
which will mean that the last station of the existing curve would coincide with the last
station of the proposed curve.
• the sign conventions used are + slews indicate slews away from the centre of
curvature and
• slews indicate slews towards the centre of curvature of the curve.
• the slews in any direction affects the versines at the adjacent stations by halve the
amount in the opposite direction.
• the objective of any curve alignment calculation is to obtain the best uniformity in
versines with minimum slews. This can only be achieved by using optimizing
technique in the calculation. Conventional computer programs for curve alignment
calculation do not usually incorporate optimizing techniques and hence may give
unnecessary large slews for a given uniformity in versines unless repeated trials are
carried out. A facility exists in Excel for the application of such optimizing technique
and can be conveniently used to carry out any curve alignment calculation.
26.3.1.2 An example of calculation to obtain optimized slews and versines is shown in Annexure
26.1.
26.3.1.3 Where there is a local kink, five stations are chosen and slews worked out by averaging
method as indicated in the example at Annexure 26.1.
26.3.1.4 The slews for complete realignment shall normally be worked out by the CPWI or in the
Regional Engineer's office so as to obtain an optimal solution, minimising slews.
Mechanical devices or, electronic calculators or a computer, can be used for this
purpose.
26.3.2 The CPWI shall forward the slews to the PWI, advising him on the portion to be adjusted.
26.3.2.2 Slewing and packing is best be carried out by lining and tamping machines. In cases
where slews are more than the limits for the lining machine (usually 50 mm). ballast has
to be opened out and the track slewed in successive runs.
4. Open the track (LWR/CWR shall be opened out in the early part of the day, when
the temperature is below the stress free temperature).
5. Slew the track to the correct distance from the pegs.
10. Relax the speed restriction in stages after tamping and shoulder compaction as in
Chapter 30, clause 30.5.3.
Check the distance to· the pegs during the course of speed restriction. If any major
discrepancies are noticed, the procedure for realignment of the curve shall be repeated.
LIST OF FIGURES
Figure 26.1 Cumulative frequency curve.
LIST OF ANNEXURES
Annexure 26.1 Example for calculation of Slews (Manual method).
Fig. 26.1
1--
zw 1--
:::;m :::;
6::1 z
l5 "
::1
0:: l5 0::
w
0::
~-
ro
~<
~
a::
~
0::
a a
<( m
~---------------------- ro
I
I
I
~---------------------- ~
I w
I >
0:::
I
~ ---------------------- m :J
(,)
gjl ~
ul ..,
,_1 "' E
>-
(,)
u~----- ---------------- ~
Zl E zw
~I .5
21 :J
~~-----
I
---------------- ~ tl
m w
0:::
~
u:i
N
~I
Fl
~ ----- ---------------- ~
~
a
Lr-
w ii:
0>
::>
::Ill w
z
>
"'I iii
i=
u~ - - - - - - - - - - - - - - - - - - - - j
~
N
I < :J
I ro
I ::l!
'~~}---- -------- ~ :J
~---
1
I
I
--------- (,)
g ~ g R g ~ i g ~
- 3!JV% 3AltVlOYIO:l
o o
. ·.· · . ·_,--R.f'
••••••••!sultan'
-'-'
••••••••••••••t -~
.'Stn. ttn~ Proposed difference First
summation Correcti
:- Fi~t~:. Second
Half slew
(Col.9 plus
Fu_n·: versine iri ·,'!t/c
slew. ··.·.··&·
.
·mffi(Ccil.3
......
No:
v~r~
sine
_--:
versme CoL3 minus
. Col.2
summation
.·
(half throw)
onto
versine
summa
'tion
summa
tion .·
Col.6)
.
plus: Col.?)
.
.··· .· .· ·. >
I
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)
0 2 2 0 0 0 -1 ·1 0 0 0 1
1 0 8 8 +8 0 ·1 -2 ·1 -1 -2 7
2 14 16 2 +10 +8 -1 -2 ·1 -1 ·2 7
3 28 24 -4 +6 +18 ·1 -4 -6 +12 +24 23
4 30 32 +2 +8 +24 -1 -5 -10 +14 +28 31
5 36 32 -4 +4 +32 -1 -6 -15 +17 +34 31
6 36 32 -4 0 +36 -1 -7 -21 +15 +30 31
7 24 32 +8 +8 +36 -1 -8 -28 +8 +16 31
8 32 32 0 +8 +44 -1 -8 -36 +8 +16 32
9 28 32 +4 +12 +52 . -8 -44 +8 +16 32
10 36 32 -4 +8 +64 . -8 ·52 +12 +24 32
11 34 32 -2 +6 +72 . -8 -60 +12 +24 32
12 32 32 0 +6 +72 . -8 -68 +10 +20 32
13 34 32 ·2 +4 +84 +1 -7 ·76 +8 +16 33
14 36 32 -4 0 +88 +1 -6 -83 +5 +10 33
15 24 32 +8 +8 +88 +1 -5 -89 -1 -2 33
16 24 24 0 +8 +96 +1 -4 ·94 +2 +4 25
17 28 16 -12 -4 +104 +1 -3 -98 +6 +12 17
18 0 8 +8 +4 +100 +1 -2 -101 -1 -2 9
19 6 2 -4 0 +104 +1 -1 ·103 +1 2 3
20 0 0 0 0 +104 +1 0 -104 0 0 1
Total 484 484 484
A 1.1 0 0 R
1 I Station 1 Exist Lower TriOII Upper Verslne First second Slew Absolute
2 No. Ver.sln& Sound ~ Ver( s1ne , Bo(~)nd Olff SummatlonSumma.tlon Slew
3 ' (1) ' (2) • (~) 41 , • (6) , (7 ) • (8) ' (9) (10)
' m -~ First
0 0 0 Summ.litlor
-S -S ..S ., ~ 16
13 ·2 -10 -18 -% Second
"
2$ 21
16
24
17
25 4 -S -24 -JS JS Summatlor -104
so 31 32 33 -2 -S -.32 .£< 6J
10 36 31 32 $~ ·J -72 72 r.i;xlmun
11 36 31 .32 33 0 -liS -72 72 Slew 208
12 24 31 ~2 33 ·B ·JJ ·SS u
,~ 13 32 31 32 .?-S ·8 ·52 -10J 10.! Objettive
IJ 28 31 32 33 ·12 -5J ·128 128 Function
15 10 36 31 32 33 ·B -72 -1-!4 1JJ Minimise
16
17
18
11
12
13
3J
32
34
31
31
31
32
32
32
ss
33
33
..
-6
-4
-78
-84
-SS
-156
-168
-1i6
1$13
168
176
Max. Slew
Screenshot 1
.. 30ala .t.11;ry;i;
- ~Sol. e r
I
A B G I D E G H J K
1 Station Exist Lower Trial Upper Verslne First Second Slew Absolute
2 ~ No. Versine Bound Verslne Bound Diff Summation Summation Slew
3 (1) (2)
First
5 Summatio.c:::::m
6 0
7 14 Second
8 28 Summation -104
4 30
10 I 5 36 Maxlmun
IC$S:IC125 <= 10$5:10125
11 6 36 IO$S:ID125 >= $C$5:1C$25 Slew [_·_-_-_-_-_2_Q'~1
12 7 24 lt~S = O
11~8 =0
13 32 Objective
14 28 Function
15 10 36 Minimise
16 11 34 Max. Slew
17 12 32 31 32 33 ·84 -188 168
18 13 34 31 32 33 ·4 ·BB -176 176
19 14 36 31 32 33 4 0 -88 -176 176
20 15 24 31 32 33 ·8 ·8 -96 · 192 192
21 16 24 21 24 25 0 -8 -104 ·208 208
22 17 28 13 16 17 12 -100 -200 200
rc-:r~-----------,
Screenshot 2
1 Click "Solver"
2. A dialog box entitled "Solver Parameters" appear
3 Under "Set Target Cells:" Click cell M11 corresponding to Maximum Slews
4 Set the Maximum Slews minimum by selecting the radio button "Min" under "Equal
To:"
5. Under "By Changing Cells:" select the range of cells under "Trial Versines" l,e 05 to
025
6. Under "Subject to Constraints: " make Trial Versines less than or equal to Upper
Bound
7. Under the same item make the Trial Versines greater or equal to the Lower Bound
8. Make 1st summation equal to 0
9. Make 2nd Summation equal to 0
10. Click the "Solve" button the table will change to the display given below .
r.l, .. "'· ; !.lilluc\ _lw•< t ~'l-- ..J, pe L'-0 1 !'iiJl .t.Jij '.r•.l:;c-tt:c.:
...
....
H"lmt ...!tri Jlo.;~l<'I)'Ciut F~rmo ~~ Dila Pt.•f Ot tLr-tt
~
1
~·I !f ..vr~or·H..1
... l.rlll • 10
.
A' A
if.,.
Gtntrll
-i#' ~
J • I n .;. A ;): ~~ :!f MtrgE&Ctf!1tr s ~. :.l ,'j CC>Oi.fll'tlal formit.a~ C:tl
,,
FormFtmg • TablE ... St1 1H •
I Jli~
A! ~~ t..l Station
A T B c Q E f G K t.l (l
' l st~llon !Exist lower Trl;l Upper Verslnt Flrtt Second Slew Absolute
2 llo. Vtnlnt Bound Versine Bound Diff summ.11io Summ;tion Slew
3 {1) {2) {3) {4) {S) { 6) '(1) {8) l9) {10)
FII'S!
'0 (2l · (')
,, SUimla5ol 7 56769E-07
.u
7 1
11 ·' .]
·6 " secono:t
"
25
30
13
21
31
13
21
31
<o
33 ·1
· 13
· 12
· 12
·26
·2•
2o
2•
2•
SUn'rnilbOI -1 Qtw2E·1·
·2'
10 35 31 31 33 6 ·1 ·U u f,lamHJl
11
12
3S SI
31
32
32
33
33 .a' 's '5 S!•• 26
2'
13
u
15 10
S2
26
S5
31
31
31
32
S2
52
33
33
33
.. .. ..
0
·I
-1
6
·2
-3
6
2
Olljet1he
Funttir;n
l..lrwnise
16 11 3' 31 33 33 1 ·I ·I l..tar SI-! ~
17 12 32 31 33 33 ·I 0 0 ·1
18 13 a• 31 33 33 3
lP
20
21
"
·~
16
30
2J
2J
31
31
21
:l3
33
2~
33
33
2~
.g
·I
..
·5
2
-3
12
'
-6
12
22 17 28 15 17 17 11 6 s 6
23 18 0 9 ·9 ·3
2J ID 3 0
25 20 0 0
26
14 ~ .~ H sh..u Sheer2 She•tl · 'Vj"" l!rl
~
Screenshot 3
11. The trial versines will automatically change to give the proposed versines. The
minimum slew 26 is obtained and the best uniformity in versines is obtained.
Example 1:
Versine at mark 2 = 100mm
Total = 270mm
=========
Average versine = 270/3 = 90mm
Slew at mark 3 = 90mm - 70mm
= 20 mm outwards
;::::::::::::::::::::::::::::::::::::::::::::::::::::::;
Example 2:
Versine at mark 2 = 50 mm
Versine at mark 3 = 140mm
Versine at mark 4 = 50 mm
Total = 240 mm
::::::::::::::::::::::::;:::;:::
= 60 mm inwards
=============
Chapter 27
Rail Defects and
Their Rectification
Document History
Authorised By:
Signature:
Date:
MOHD RAMLI MOHD NOH
General Manager Permanent Way
2 8 MAY 2015
Keret'tipl Tanah Metayu !emad
Kuala Lumpur
TABLE OF CONTENTS
27.1 GENERAL
This chapter describes the defects in rails, measures to be adopted to reduce rail
defects, detection of rail flaws, classification of flaws and action to be taken in case of rail
failures.
1) Seam
Seams on the rail surface appear as very fine lines. They may be caused by blow
holes near the surface, cracks in the ingot or by faulty rolling.
2) Lap
A lap is caused in the rolling mill when some protruded piece of metal is rolled on
the surface of the rail section.
3) Guide mark
This is a surface mark, usually straight and caused by the guides in the rolling
mill striking against the rail section.
4) Mill defects
These are other defects which may originate in the steel mills. They include
deformations, cavities or entrapped foreign material.
2) The types of flaws generally found in rails are indicated in Figure 27 .1.
27.3.1.1 Corrosion is caused not so much by the dampness as by acid gases dissolved in the film
of moisture which frequently coats the rails.
27.3.1.3 Corrosion is generally noticed on the web and foot of the rail.
Normally, such wear is of a very small order. The amount of wear increases with heavy
traffic density as is the case in suburban sections.
27.3.3.1 This phenomenon mostly occurs on the inner rail of a curve, caused by high contact
stresses when acting along with the horizontal forces. The vertical pressure may be due
to heavy axle load, large unsprung mass or speed below equilibrium speed on the curve.
27.3.3.2 Horizontal forces are associated with slow running on curved track, i.e. in condition of
cant excess. On curves, conditions also exist for the slipping and skidding of rigid wheel
sets. Spreading of rail table is an indication of overloading of one rail and such a
tendency can be reduced by providing correct cant.
27.3.4 Wear on Gauge Face
The outer rail of a curve has to withstand heavy pressure from the wheels due to cant
deficiency and this results in the running edge becoming worn or side-cut. The
abnormally high stresses at the rail wheel interface especially near outer rail gauge
corner gives rise to the phenomena of gauge corner cracking which can endanger safety.
27.3.5 Hogging of Rail-Ends
A hogged rail is one with its end or ends bent in vertical direction. A hogged rail end in
the track is ascertained by unfishing the joint, removing the fastenings and then
measuring the extent of hog at the rail end by placing a one meter long straight edge
over the rail table, centrally over the joint as shown in Figure 27.2.
27.3.6 Battering of Rail-Ends
Rail-ends batter occurs where the joint gaps are excessive. lt is caused by the impact of
wheels on the end of a rail, particularly if the fish plates do not fit snugly. Rail-ends
batter is measured as the difference in heights of the rail at its end and at a point 30 cm
away from the rail ends, as shown in Figure 27.3.
27.3.7.1 Wheel slipping occurs usually on adverse gradients or while starting on rising grades,
and when the train brakes are applied suddenly and the wheels lock and slide. At such
locations, considerable heat is generated and the lop of the rail is torn off in patches,
causing depressions. These are known as wheel burns, from which cracks may develop.
27.3.7.2 Wheel burns cause the wheels to hammer the rails and lead to difficulties in keeping the
sleepers packed firmly and fastenings tight. Such rails shall be kept under observation
and changed, in case repair by welding is not feasible.
27.3.8 Corrugation
At certain locations stretches, rails develop ridges and hollows called corrugations. When
vehicles pass over these rails, a roaring sound ensues. Such rails are called "roaring"
rails. Such rails cause excessive vibrations. Consequently fastenings and packing tend
to get loose and track needs frequent attention.
27.3.9 Welding defects
In the flash butt welding process, such defects could occur due to lack of fusion. In
aluminothermic welding, inclusions, porosity and voids could be the causes, in addition to
lack of fusion. Low hardness in welded area can cause cupping (local depression)
during service, in both the types of welds.
27.3.10 Service life and fatigue of rails
In general, the service life of rail and the fatigue it can withstand, depends on the
following factors:
i. Type of rail (Standard, wear resistant or head hardened grade and section profile
used)
ii. Passing tonnage, axle load, frequency, permissible speeds and pattern of traffic
iii. Compatibility between rail and wheel profile
iv. Maintenance quality and maintenance intervention
v. Location where the rails are laid (such as gradient, tangent or curve track and
degree of curvature)
vi. Environmental and weather condition
On an average, good quality and well maintained rail can be retained on the track
providing useful service life of approximately 225 GMT for BS 80 A section and 350 GMT
for 54 kg rail section. Rail failures originated from fatigue under traffic loading that result
in cracks leading to fracture if they are not detected in time. Thus the principal criteria for
rail replacement and de-classification of main line rails for use on secondary lines and
sidings are the various limits of rail defects that arise from wear and tear.
Painting of rails, with an approved anti-corrosive paint at locations which are prone to
corrosion.
27.5.2.1 On sharp curves where the tendency to wear on the outer rail is noticeable, lubricators
shall be installed. Trolley mounted lubricators or engine mounted lubrication system
provides more cost-effective solutions in sections with long lengths of sharp curves.
27.5.2.2 Interchanging (Transposing) the outer and the inner rail or turning the rails. During this
operation the rail ends shall be properly matched by making suitable adjustments in rail
to sleeper fastenings.
27.5.2.3 Spot renewals with new rails shall not be carried out particularly if the heads of the
existing rails are badly worn out. Matching sections of old serviceable rails shall be used
for this purpose. Otherwise the worn-out rail need to be replaced throughout the length
of the curve. Rails subject to curve wear may be transposed and reused in tangent track,
subject to lateral wear on rails not exceeding the stipulated rail wear limits.
27.5.3 Use of Special Quality Rails
27.5.3.1 Standard 900 Grade A used in KTMB are of standard carbon and have hardness ranging
from 260 to 300 BHN. These rails may also be considered 'wear resistant rail' as they
are also effective to resist wear on straight track and flat curves of radius > 500 meters
because of the greater width of rail wheel contact zone.
27.5.3.2 On curves sharper than (radius 500m and less), special quality rails shall preferably be
used to avoid frequent renewals of rails on account of excessive side wear. These
special quality rails have a service life two to three times that of standard rails on sharp
curves.
27.5.3.3 For new rail installation or renewal in high speed Class 1 line, head hardened rails with
hardness value in the range of 330-340BHN shall be used for curves of radius less than
500m on account of the narrower band of wheel-rail contact and higher forces to the rail
head. Similar type of special quality rails includes also the U75V-H370" grade rail (from
China) equivalent to R350 HT rail of European standard with surface hardness not less
than 341 BHN (341 to 401 BHN) and UIC Grade 1100 rail with hardness range of 320 to
360 BHN.
27.5.3.4 For turnouts that are subject to busy traffic and heavy loads, R 350 HT (Heat treated) rail
with surface hardness in the range 350 to 390 BHN (not less than 350 BHN) are used.
These rails have their heads hardened (to a depth of 12 to 14 mm from the surface)
by a special heat treatment process carried out in the rail mills. They can be welded
into long lengths by a comparatively simpler process.
Note:
In situ welding shall be carried out by trained welders, using electrodes and
welding techniques, specifically approved by the General Manager Permanent Way
for the type of rail being repaired.
27.5.7 Corrugations
27.5.7.1 To remove corrugation, pitting, scabbing and other surface defects, grinding of rails
offers the only workable solution. Small hand held grinding equipment, or rail-grinding
trains are used for this purpose.
27.5.7.2 The progress with manual equipment is slow and is resorted to only at isolated spots
requiring grinding.
27.5.7.3 Rail grinding trains equipped with a number of grinding wheels are able to remove
corrugation to a depth of about 0.2mm in a single pass. Usually 5 to 6 passes are made
to completely grind off the corrugations. These grinding trains are also equipped for
complete re-profiling of the rail table, often needed to treat gauge corner cracking of rails
or worn out rails on curves.
27.5.7.4 Although the grinding of rail may not offer any permanent solution as the corrugations
may re-appear after a few years thus needing re-grinding, it results in reduction of Rail
Contact Fatigue and improved ride quality thus enhancing track performance and
extending the life of track and vehicle components.
27.5.7.5 Rails for used in Depot track and pit lines shall be installed with proper rail fastenings.
Welding of the rail foot to the base of the pit lines must not be carried out as this results
in rail breakage.
Rails in track shall be inspected to by trained and certified permanent way personnel.
Rail ends, particularly the area around bolt holes, shall be examined more thoroughly.
For this purpose, the fishplates shall be removed, the area cleaned with petrol and
cracks located with the help of magnifying lens. Reflecting mirrors and torches may be
used. Whenever a crack is noticed, the rail shall be replaced at the earliest. Such
inspections by trained personnel have a marked effect in the reduction of rail failures in
service.
27.6.3.1 A more efficient and effective method of rail flaw detection is with the use of ultrasonic
rail flaw detecting (USFD) instruments, either the manually operated instruments or the
self-propelling ultrasonic rail flaw detecting car.
27.6.3.2 The operators of manually operated instruments shall be properly trained and tested on
their knowledge of identification and classification of flaws. As a minimum requirement,
they shall be certified competent under the category of Non- Destructive Test -
Ultrasonic Test (NOT-UT) Level 2 carried out by KTMB. In addition, they shall be sent to
refresher courses as prescribed in chapter 49 (Training of Permanent Way Staff).
27.7.1.1 The minimum size (length) of flaw which can be detected is 5mm, which can be termed
as the least count of the system.
27.7.1.2 Rail defects hidden under scabbed rail surface or other rail table defects are not properly
detected.
27.7.1.3 After the RFDV car run, the suspected locations have to be manually tested for
confirmation of the defect and for further follow-up action.
27.7.2 Periodicity of Testing
27.7.2.1 Initial testing
At rail manufacturing planUflash butt welding depots or immediately after laying of rails.
(Testing before laying shall be mandatory)
27.7.2.2 Initial Test free period
After the initial testing, no further testing is required to be done within a year after
installation or when 25% of the stipulated service life tonnage is reached in less than a
year, whichever is applicable.
The initial test free traffic cumulative tonnage approximately may be taken as:
• Annually in all classes of lines, and twice a year after reaching service life.
Note:
1. After the rail has reached its stipulated service life in terms of Gross Million
Tonnes (GMT) of traffic carried, the frequency of testing shall be doubled.
2. The frequency of testing shall be suitably increased for sections/locations
prone to rail fractures, or with a history of fractures, as prescribed by the
General Manager Permanent Way Division.
• Those where Immediate Renewal of the flawed rail is required, classified as "X".
• Those where Renewal of the flawed rail may be necessary but not immediate,
classified as "R".
• Those where the flawed rail is to be kept under observation, classified as "0".
TableT- 27.1
Permissible Tolerances for Rail Defects Action Sheet
1
Defects·
1. Bolt hole crack either
·.
Abrv ...
BHC
.· ·•· . > si~e
....
i) More than 50mm either
I Action
.. ···.··•········.. ··.•·.•,
from:
i) Fishplated a) one hole or more Fit emergency clamps for
or Welded Joints.
ii) Welded For Fishplated Joints, impose
speed restriction of 25km/hr and
change rail within 36 hours
·•••·. /·•. ·.··.·····D"fects< .• ·•···· Abrv. ·si:Ze .. ···. >. •.· · ·.•......· 1····. ·. .•..•.. ··. ·.·.· .•·..•.· .··. Acti9 n· ·. • . y. .
·····.····
ii) One spot cover Impose speed restriction 40km/hr
more than 75% and take remedial action either by
of the head. welding or change rail.
iv) Head web separation HWS Any size Impose speed restriction 25km/hr
. and change rail within 36 hours .
vii) Web feet separation WFS Any size
- do -
5. Others detected
ultrasonically.
i) Vertical split head. VSH 2mm displacement Fit emergency clamps.
ii) Compound fissure CF Any size Impose speed restriction 25km/hr
and change rail with 36 hours.
iii) Big dipper BD Any size
Note:
(1) If any segregation, scabbing or wheel burn has a transverse crack-giving indication
on the Cathode Ray Tube (CRT) screen by angle beam probe between 2.5 to 5
Mhz, it should be marked as "R". Otherwise it should be kept in "0" category.
(2) In case of scabbing, wheel burn, segregation of chipping that does not have
transverse crack and is in "0" category, the decision to remove or otherwise should
rest on CPWI concerned.
27 .9.1.1 A flaw which is serious in nature and can lead to sudden failure is classified as "X".
27.9.1.2 Immediately after detection, locations with such flaws shall be marked with red paint
(three stars) on the web of the rail on both faces.
27 .9.1.3 The marked rail portion shall require urgent action and shall be replaced by a sound
tested rail piece, not less than 6m in length, within three days after detection.
27.9.1.4 Until the rail flawed portions are replaced, a speed restriction of 25 km/hr shall be
imposed. Clamped fish plates shall be provided at the flaw location. Until clamped fish
plates are provided, a flagman shall be posted to ensure that trains are stopped in time in
case of rail fracture.
27.9.1.5 For Class 1 line, this speed restriction of 25km/hr shall be imposed until the replacement
rail piece is welded into the existing CWR. This is to be done within 36 hrs. Rail stress
measurements need to be carried out to ascertain there is no undue rail stress in the
CWR track.
27.9.2 "R" (Removal)
27 .9.2.1 A flaw which propagates with time and can become serious enough to cause a fracture is
classified as "R".
27.9.2.2 After detection, such defective locations shall be marked with red paint (two stars) on
both faces of the web of the rail.
27.9.2.3 These locations shall be rescanned by USFD manual testing within a time limit (as
indicated in TableT -27.1 ). Based on the results of the second scanning, the rails can be
reclassified, in which case some "R" defects may qualify as "X" defects warranting action
as applicable to "X" defects. The remaining defective rails will continue to remain in track
with "R" classification. Rescanning at a periodicity of two/six months in respect of rails
marked "R" will thus continue, so that the propagation of the flaw is kept under watch.
27.9.2.4 The patrolman of the section shall, however, observe these defective locations during the
course of his patrol inspections, as they are potential locations for fracture. When "R"
defects are few and spread over long distance, it may be preferable to replace the
defective portion straight-away by a sound tested rail piece, not less than 6 m in length,
within six months after detection and thus dispense with rescanning.
27.9.2.5 For Class 1 line speed restriction of 100km/hr shall be imposed until the replacement rail
piece is welded into the existing CWR.
27.9.3 "0" (under observation)
27.9.3.1 If the nature of the defect is such that it is not expected to result in fracture, till
rescanning is done in a year's time, it is classified as "0".
27.9.3.2 Such defects shall be marked by red paint (one star) on both faces of the web and need
to be kept under observation.
27.9.4 Action Summary
Table T-27.2
Action to be taken on detection of defective rails .
'.·.
ClaS-~Itfi:a-ti6i1.' .·.·•· Painting <>n
/
...................... ··• bi>tt\'iac~,;······ .
·Actil>ntl>l:le taken
'/ .. . . . ·. .··•·
. ••.
·· .. ·
.
Interim Action
......
· . . . . . ..
··
. · ...·.
.· ·•··· .
.. .•..
· ·
•
"R" Red 2 stars Re-scanning not later Patrolman to observe during his normal
than six months. daily patrol inspections.
27.10.3 In about 80 per cent of the cases, the flaws have their origin in the foot, in 10 per cent of
the cases, in the head and in the remaining 10 percent, in other portions of the rail. This
is mainly due to the rail foot not heated to the required temperature, before the weld
metal is poured in. Consequently this leads to lack of fusion in the rail-foot area.
Insufficient duration to carry out the operation during line possession is a possible reason
for this poor quality of the weld ..
27.10.4 To detect defective AT welds before they actually fracture in service, a method of
ultrasonic testing of such welds is adopted, using portable ultrasonic flaw detector. In this
method, normal and angular probes are used for detection of flaws in the head portion
and in the foot portion. For the detection of flaws, their categorization and action to be
taken for their removal or for keeping them under observation, detailed instructions
issued by the Permanent Way Depot Engineer shall be strictly followed.
27.11.2 The Ganger/Patrolman/Gangman, who notices the rail/weld fracture shall first protect the
track, until emergency repairs (as indicated in para 27.10.3 to 27.10.6 below) are carried
out. He shall also send information to the PWI and the Station Manager of the nearest
Station.
27.11.3 If the fracture is with a gap of less than 30mm in the case of fish-plated track, the
fractured portion shall be supported on a wooden block or by shifting the nearest
sleepers on both sides under the gap. In the case of LWR/CWR, the fractured rail shall
also be clamped. (Speed restriction is as stated in para 27.8.1.4 above)
27.11.4 When the (fracture} gap is wider than 30mm, a closure of appropriate length shall be
used with a clamp and further action taken as in sub-para 3. Normal speed can resume
only after destressing and welding into LWR/ CWR has taken place.
27.11.5 In cases where a small portion or piece of rail has come off or in the case of multiple
fracture, the rail has to be changed. No train shall pass until emergency repairs are
completed.
27.11.6 In the case of weld failure, joggled fish plates and clamps shall be used.
27.11.7 After carrying out emergency repairs, the trains may be passed at 15 km/hr by a
Ganger/Patrolman, until the PWI replaces the rail and increases the speed restriction or
restores full speed depending on the action taken.
27.13.2 The PWI shall prepare the 'Rail Failure' Report in triplicate and shall forward two copies
to the Regional Engineer, who shall transmit one copy with his remarks to the General
Manager Permanent Way Division. Sketches and photographs illustrating the fractures
shall also be prepared and submitted along with the failure report for each case, duly
indicating the running face of the rail.
27.13.3 All case of failures of new rails occurring within the guarantee period, shall be immediately
reported to the General Manager Permanent Way Division
LIST OF FIGURES
Figure 27.1 Typical Defects in rails
LIST OF ANNEXURES
Annexure 27.1 Format for Reporting Rail Failures.
Annexure 27.2 Some common terminology
Annexure 27.3 Rail Defects Photographs/Illustrations
~ n
<
u
-'
<
z
5
• ;=:!
"z
3
-'
'&
z ;:
w 0 z
< 0"'
"'
:::>
1-
0
g t:!u
~;2
:r:u
0
<(
"'w ~~
-- 1---
"-
(I) G'i
"'>w uz
(I)
z<(
0
0
..
w
l ',
1'-
"'
U)
1- ::>
13
(\ ll ~
(h ll
Figure 27.1 (Sheet 1)- Typical Defects in rails
~
<
~
n:
n: ~
~
,_
:JP
:);~
....10
< _(.)
~z
c -
=>:I
!:::~
C> ••
zw
goo
:::>
..... <
<B
0
..,~
>
'
·~ ~
l:l
.~ VI
~
~ <.>
"<0
z
n:
5
~
Ill a.
ro ::J
Ill
13VI
~ oil
l__ <.>
;;:;
~
I ',
"iDz 0
0
l_ ...... ~
ID
52
{/)
<
0
,_
Ul ·tl
I:;
11
0
.~
/l
5
n ~
/l
Figure 27.1 (Sheet 3)- Typical Defects in rails
..._
0
"'
~
1-
0
2: .....
<z
·~ :.: p :~0
0 oF
< <0
"'0 ....~·
~ o:Z
u-~
"'<u "'z
0: ~
...J
<
z "
l_
v
()
~
~
i5 3 0
....(5:::> "'..
z w
0
...J "'<::>
...J e.
~
;::
"'>w
....0 ~
~
"'
"'
..."'l ~
"'0
"'"'<
l
0 w
(!) p
<
"'
0 :.:
<
0
~
l__ 1.-o
w
"'
w
0
....
....
vV
ID
r-- w 5
0
ffi
"'>w Ill..
"'
w
"'<z Ill
~
"'.... 0
~
n Vl
Figure 27.1 (Sheet 4)- Typical Defects in rails
Fig. 27.2
j I
1.1 Region ·
1.2 Section (name of line branch).
1.3 Between Stations ........................ and ....................... ..
1.4 Location {Track Kilometer)
1.5 Line.
1.5.1 Up/Down/Single
1.6 AlignmenUGradient
1.6.1 StraighUCurve (indicate degree/Radius of curvature)
1.6.2 Inner/Outer in case of curve.
Signature of
Permanent Way Inspector
Date:
Rev. 0 Page 21 of 38
Permanent Way Manual Part IV
Rail Defects and their Rectification Chapter 27
This is a progressive fracture that starts from a crystalline centre or nucleus inside
the head from which it spreads crosswise and outward as a smooth, bright, or dark,
round or oval surface substantially at a right angle to the length of the rail. The
distinguishing features of a transverse fissure from other types of fractures or
defects are the crystalline centre or nucleus and the nearly smooth surface of the
development which surrounds it.
A length-wise crack along the side of the web and extending into or through it.
This is a vertical split in a rail, usually in the web, due to failure of the shrinkage
cavity in the ingot to unite in rolling during manufacturing of the rail.
This occurs where driving wheels have slipped or skidded on top of the rail head. In
developing downward they may resemble compound or transverse fissures for
which the permanent way personnel should not be confused in classifying them.
(1 0) Flattened rail
This is defined as a short length of rail, not at a joint, which has flattened out across
the width of the rail head to a depth of about 5-Smm or more below the rest of the
rail. Flattened rail occurrences have no repetitive regularity and thus must not be
confused with rail corrugations, and have no apparent localised cause such as a
weld or engine burn. Their individual length is relatively short, as compared to a
condition such as head flow on the low rail of curves.
This is a rail progressive fracture, longitudinally separating· the head from the web of
the rail at the head fillet area.
~7"
IJII (C I
BOLT HOLE
" WHEEL
CRACK
FOOT CRACK
Rail Crack
Rail Spalling
Rail Corrugations
Dark spot
(Squat) ' - --, ·; --~ ~ - - -- ..=-- - =. -. ..,...-;-....~ .. . -. i
- -f Origin of crack
•· - Horlzont<lf
cr~ck T~ansverse
crack
Single squat
Section 3 to 6 above will detect vertically oriented lack of fusion defects and shall be
applied to both fusion faces. Before application of sections 3, 4 & 5 either side of the
weld shall be scanned for horizontal defects as per Section 3.
Fig-4 Fig-S
Prior to the application of Sections 3, 4 & 5, 500mm of the rail on each side of the weld
shall be tested to establish that the rail is free from horizontal or transverse defects. At
the same time the weld region on the top of head shall be scanned to detect blow holes
in head web and central region of foot.
2.1 Equipment
Timescale: Calibrate the timescale to 20mm per division for compression waves in steel,
which will cover test range up to 200mm on the screen.
Sensitivity: Obtain the signal from the bottom of the rail and set this signal to full screen
height. Record the rail depth for use in 3.2.
This scan shall be applied to detect Jack of fusion defects on both fusion faces, in the
head and that part of the web shown in Figure 1.
3.1 Equipment
3.2 Calibration
Return the Tx probe to the rig, connect both 45° probes to the
instrument and switch to double probe working,
Sensitivity A datum point is required to align the tandem probe rig with
respect to the welds fusion face to allow the two probes to fully
scan the weld. The rig datum point is the reading on its scale
equivalent to the rail depth as obtained in 2.2.
,
<::·..·.. ...... Tx Rig Rx
·-.b I
,6'--'
i
I "-....'~ ./ I
' •.. /
......? F u sion ~ ,?(
Faces
"·~ "\ l''
///
/ "'7-
F ig 6
3.3 Scanning
Remove the Tx probe from its carriage and replace it such that this probe also "looks
towards" the weld. See Figure 6. Having made sure that adequate couplant has been
applied to the surface of the rail head, move the probes backwards and forwards along
the probe guide. lt is important to note that during the movement of the probes, that
adequate downward pressure is applied to the probes to ensure proper acoustic
coupling.
Signals from any lack of fusion defect present at the fusion face will appear at the same
range on the timescale as that indicated by the rail bottom in 3.2 above. This scan must
be applied twice, once to each fusion face.
If a defect signal is detected the operator must record its amplitude as % of full screen
height and the distance 'D' of the Tx probe index measured from the fusion face of the
weld. See Figure 7.
Fig-7
5.2 Calibration
Timescale and Sensitivity are as in Clause 3.2
Remove the rig from the railhead and the unsecured probe from the rig leaving it
connected to the Tx socket of the instrument and switch to single probe working.
Note: This test must be carried out after each tandem rig scan is made to allow for the
different calibration levels for the two sides of the weld.
5.3 Scanning
Mark the probe standoff position on the railhead at the equivalent rail depth distance as
measured in 3.2.2 from the weld fusion face and further positions at 40mm either side of
the probe position. See Figure 8.
Scan the lower face by moving the probe backwards and forwards between the two
40mm marks, to scan adequately the area shown in Figure 8. Signals from lack of fusion
defects should appear, depending on rail depth, at a range of approxim ately 220mm.
This scan must be applied to each side of the weld.
If a defect signal is detected the operator must record its amplitude as % of FSH, the
distance 'D' of the probe index measured from the fusion face of the weld.
0 40mm
r
Fig-8
Fig-9
(i). Place the probe on the outer flat zone of the rail foot, such that the probe index is
approximately 60mm from the weld reinforcement. See Figure 10.
VVeld ... ~
~ >
I I
~ ,...
~ _.,..,. ~
F1g-10 6urn 60m
(ii) Th is zone of the fusion face shall be scanned, ensuring that the probe is moved
forwards and backwards with respect to the weld. This movement must extend to
60 mm on either side of the probe index stated in (i) above. See Figure 10.
(iii) W hilst scanning backwards and forwards, move the probe laterally along the weld
from the outer edge of the toe, to the ankle of the rail. See Figure 10. lt is essential
to ensure that a swivelling motion of the probe is added, particularly near to the
outer edge of the toe.
6.4 The Ankles
(L) Having completed the toe area, the probe shall be placed on the ankle of the rail foot
(see Figure 11 ), such that the probe index is 75mm from the weld reinforcement.
(ii) This area shall be scanned, employing the same manner of probe movement as
shown in figure 9. i.e. forward and backwards, together with a lateral movement up and
down the radius. (See Figure 11)
Fig-11
Welcl
The scans described in 3.6.3 shall be repeated 4 times, at each fusion face for both toes
and ankles.
7.0 REPORTING
If a defect signal is detected the operator must record its amplitude as % of full screen
height and the distance of the Tx probe index measured from the fusion face of the weld.
For each individual weld tested, the operator shall complete and submit a separate
points count form (see FORM PBUJ UT 1/2014).
If the flaw signal is within the threshold limit of all the defect signals, points are to be
accrued as per following point count system.
9.1 Point Count
For each pair of observations ( a pair consists of both "on and off "observations relevant
to the each of the eight fields of scanning), tal<e the largest observation and divided by
10 and write the result on the point count line in prescribed format for reporting (FORM
PB UJ UT 1/2014). For example, flaw signal of 30% screen height corresponds to 3
points and so on.
9.2 Sub Total of Point Count
Add up the points of each observation of eight scanning fields written in columns and
write the sub total in the box provided.
If the sub total is 11 or less, the weld shall be passed. If the total exceeds 11 the shape
factor must be determined,
9.3 Shape Factor
For a dipped weld a penalty of 1 point per 0.1 mm of dip must be written in the box
provided. For humped weld, a penalty of Y:z point per 0.1 mm hump must be awarded.
If the total of the point count (adding shape factor) is 12, the weld may be passed but if it
is more than 12, the weld shall be REJECTED.
Flow on
left hand
side
l_
35MM
T
Flow in
Middle
Veld
Veld
Flaw on
right hand
side
Fig 12
Threshold amplitude
% of Full Scale
Total Points
I Pass I I Fail I
Name of Operator
Name PWI/Technician
Signature of
PWI/Technician Date:
Chapter 28
MAINTENANCE OF TRACK
COMPENENTS
Document History
Authorised By:
r '
Signature:
MOHD RAMLI MOHD NOH 2 8 MAY 2015
Date: General Mana er Permanent W
Keret'l!lpi Tanah Melayu Berttad
Kuala Lumpur
TABLE OF CONTENTS
28.1 GENERAL
28.1.1 Proper maintenance of track components ensures integrity of track structure and
enhances their own life in track. lt also helps in the retention of track geometry for longer
period of time. This chapter deals with the system and methods that are adopted in
proper maintenance of track components except the rail maintenance, which has been
covered in chapter 27.
28.1.2 Methods of reconditioning and reclamation of track materials are described in chapter 33
(Reconditioning Track Materials).
1. Inherent defects:
Sleepers with inherent defects like Sapwood. Wanes, Split ends, Decay, Warp, Twist,
Bore holes and Knots shall not be laid on track. If such defective sleepers are noticed
during inspection, a special watch shall be kept on their condition. Sleepers with split
ends shall be provided with end binding or with a "S" hook. Sleepers with other type of
defects shall be renewed when they fail to provide adequate support for the rail or hold it
to gauge.
2. Service defects:
Wooden Sleepers develop damage or deformation during their service life resulting in
their being:
• Spike-killed.
• Burnt.
• Badly split or broken particularly at rail seat.
• Cut into by rails.
• Indentation.
• Rounded underside.
3. Precautions:
The following precautions and maintenance practices will effectively reduce decay of
sleepers. PWis shall ensure that:
• Sleepers are stacked before use as indicated in clause 5.3.9. (Also see Figure 5.2)
• Base plates are provided under the rails where stipulated.
• Sleepers are clamped or end-bound to prevent splitting.
• Old spike holes are plugged before re-boring new holes.
• The sleeper is moved laterally clear of indentation.
• Correct size of augers is used for drilling holes.
• Sleeper fastenings are correctly fixed using appropriate tools.
• Centre binding of sleepers is prevented.
• Corrosion of steel.
• Handle the sleepers carefully. They shall not be dropped from a height.
• Maintain ballast to the required standard profile.
• Clean ballast and provide full ballast cushion of hard stone.
• Prevent centre-binding of sleepers.
• At locations prone to corrosion, remove the elastic rail clips from the inserts
annually.
• Clean the clip and eyes of the insert.
• Apply special oil or special grease in the central leg of the clip and eyes of the
insert.
• Repair cracked concrete with epoxy.
• Lay and maintain sleepers square to the rail and to correct spacing.
• Lay Primary hardwood sleepers with sapwood on top and heartwood below.
• Lay secondary hardwood treated sleepers with heartwood on top and sapwood
below.
• Do not drill holes on treated secondary hardwood sleepers in the field.
• If new holes are to be drilled or adzing is unavoidable, the holes/surface shall be
treated with hot creosote or other equally effective chemical.
• Avoid beater-packing of wooden sleepers where possible.
• No beater packing of concrete sleepers. Use portable hand tampers
• Handle concrete sleepers carefully to avoid damage.
• Place rubber pads correctly. Inspect periodically to ensure that they are properly
seated and in good condition. Replace worn and missing pads.
• Do not allow fastenings loose on two consecutive sleepers.
28.5.2 Joints
• Joints on either rail shall be square, except on curves of radius less than 300 m,
where they can be staggered.
• Monitor creep and rail expansions
• Maintain rail joints properly as indicated in clause 23.3
• Tighten the rail fastenings to the prescribed extent.
• Use Junction Rails for joining rails of different sections.
• Lubricate rail joints regularly at prescribed intervals.
• Do not allow gaps between rails at joints to exceed 25 mm.
• Attend to the blowing and pumping joints by cleaning the ballast and packing the
joint and shoulder sleepers firmly.
• Crop defective rail ends or defective welds.
28.5.3 Curves
The PWI shall examine that the distribution of grease is performed efficiently, so that the
grease is carried by the wheels as far as possible along the rail in the direction of travel
with a minimum of grease wastage at the greasing plate and along the track.
Examination is carried out both visually and physically at the lubricator and along the
curve at the rail gauge face.
Maintenance servicing and repair of lubricators is carried out at regular intervals related,
generally to the density of rail traffic and the size of the lubricant reservoir and in
accordance to its supplier's Operation and Maintenance Manual under the jurisdiction of
the PWI.
Track maintenance personnel shall ensure that rail lubricators do not suffer damage
during ballasting, re-railing and other mechanised track maintenance operations such as
tamping, re-sleepering, ballast cleaning and ballast regulating etc.
Chapter 29
Procurement and
Distribution of Ballast
Document History
I
Authorised By:
Signature: '
Date:
tre ~ p1
Kuala Lumpur
TABLE OF CONTENTS
29.1 GENERAL
29.1.1 Ballast is an integral part of the track structure and performs many important functions,
which have been described in Chapter 8. Specification and standards for track ballast
are contained in Chapter 8 and 10. This chapter deals with the method of assessment
of deficiency of ballast and the system of procurement and distribution of ballast.
29.1.2 Rules for working of Ballast Trains are contained in Section 'C' and 'H' and Appendix
10 of. the General Manual in the current KTMB Rules and Regulation Book. In the
event of a contradiction between the provisions in the current KTMB Rules and
Regulation Book and the contents of this chapter of the Manual, the former shall prevail.
29.2.8 The General Manager Permanent Way will approve the quantities and the locations
where ballasting has to be done in each Region. An approved Ballasting Programme
will be sent to the Regional Engineer.
29.2.9 On receipt of the approved programme, the Regional Engineer shall take appropriate
action to procure ballast in time.
29.3 SOURCES
Ballast required for track maintenance or construction works shall be taken only from
specific quarries as approved by the General Manager Permanent Way. Ballast shall
conform to the specification indicated in Chapter 8 (Annexure 8.1).
29.4 COLLECTION
29.4.1 The collection of ballast in the region shall be done in a Ballast Stockpile Area
designated and approved by the Regional Engineer. The following points need special
attention:
a. Stockpile sites should be constructed on firm well-drained ground, and should not
interfere with drainage of other areas,
b. Sites should be graded to a uniform surface and provided with a minimum 100 mm
bedding layer of coarse sand or crushed fines over the whole of the stockpile area,
c. Stockpiles should been constructed to a maximum height of 4m and,
d. Edges of all ballast stockpiles should be kept at least 6 m clear of the centerline of
tracks and 3m clear of adjacent stockpiles.
29.4.2 Ballast from the quarries shall be carried in lorries to the Stockpile Area. Before leaving
the quarries, the lorries shall be weighed on a weigh bridge and the contents in tonnes
shall be reflected in the Computerised Lorry Slips.
29.4.3 Ballast received at the Stockpile Area shall be verified on the basis of the Computerised
Lorry Slips.
29.4.4 The PWI in charge of the Stockpile Area shall ensure that the lorries discharge the
contents fully in the Stockpile Area.
29.4.5 The PWI shall account for the ballast in units of tonnes.
29.4.6 The PWI shall be responsible for safe custody of the ballast until it is trained out.
29.5 DISTRIBUTION
29.5.1 Loading and Accounting
29.5.1.1 The ballast shall be procured at the Stockpile Area and distributed to the locations as
indicated in the Approved Ballasting Programme (Clause 29.2.8).
29.5.1.2 The PWI shall ensure that ballast is loaded to the full capacity in wagons.
29.5.1.3 The receiving PWI shall verify the receipt of the wagons.
29.5.1.4 A register shall be maintained by the despatching PWI to indicate all transactions of
collection and disposal of ballast from the Ballast Stockpile Area. The accounting shall
be tonnes/volume.
29.5.2 Unloading
29.5.2.1 For efficient transport of ballast, high capacity hopper wagons with automatic discharge
arrangements are used. Ballast from such hoppers can be unloaded, either on the sides
or at the centre of the track, when the train is moving at a slow speed.
• Minimum wastage,
• Avoidance of ballast contamination and unnecessary handling and regulation which
may degrade the ballast, and
• Minimum segregation.
29.5.2.3 Where the ballast profile or presence of ballast, is such that it may interfere with the
operation of infrastructure (e.g. signals or switch operation) or rolling stock (e.g.
interference with clearances or flangeway blockage at level crossings) the PWI shall
arrange for the required action to be taken by his men to maintain safe operations, as
follows:
• When unloading ballast along the line, care shall be taken to ensure that the heaps
at the sides and at the centre are clear of prescribed railway vehicle moving
dimensions.
• Ballast shall not be unloaded upon signal wires, point rods and other track side
signalling installations. While working in turnout areas, care should be taken to
ensure that no piece of stone is left inadvertently between the stock and switch rails
of turnouts.
• . When ballast is unloaded from trains, it shall be clear of rail level for a distance of
1.20m from the nearest rail.
• Ballast regulators shall closely follow the Ballast Trains to spread and regulate the
ballast to correct profile.
29.5.2.4 The PWI shall send every month a Statement to the Regional Engineer indicating the
locations (to the nearest quarter kilometre posts) where ballast has been unloaded.
A Ballast Train shall be worked only with the permission of the Station Manager on either
side and in accordance with Special Instructions.
29.6.2 Advice of running
When it is planned to run a Ballast Train, the Regional Engineer shall address the
Operations Manager in advance, indicating the locations and details of the work and also
the duration for which the Ballast Train is required. The programme will be published in
the Bi-Weekly Notice/Operations Bulletin. The locations shall be in accordance with the
approved ballasting programme indicated- in clause 29.2.8. In the event of change
from a Notice already issued, due intimation of the alteration shall be given to all
concerned by the Operations Controller.
Every Ballast Train shall be in charge of a Ballast Guard, who shall have a Competency
Certificate and shall be responsible for the safe working of the train. The Ballast Guard
shall take his orders for working, from the CPWI or the Regional Engineer.
29.6.4.1 A Ballast Train shall have sufficient brake vans (or vehicles fitted with hand brakes) to
control the train, taking into consideration the ruling gradient of the section on which it is
working.
29.6.4.2 The Ballast Guard shall be responsible to see that the brakes of all vehicles on his train
are applied as necessary. When working on a section with a gradient steeper than 1 in
150, the Driver, before moving the train, has to see that a sufficient number of brakes
have been applied to enable him to control his train. The Ballast Guard shall ensure that
this has been done by the Driver.
Unless a Ballast Train is going to work on the line, it shall be treated and worked as a
through Goods Train.
29.6.6 Procedure when Ballast Train is to work in a section
29.6.6.1 A Ballast Train shall always stop at the Station to the rear of the section in which the train
is to work. The Ballast Guard shall send to the Station Manager an application (as in
Annexure 29.1) stating at what time he will be ready to start and obtain the Station
Manager's reply, stating what arrangements he has made for the Ballast Train to start.
29.6.6.2 The Station Manager has to advise the Station Manager at the other end, about the
duration of the work of the Ballast Train and also inform whether it shall proceed to the
next Station or return to the Station from which it started. The Station Manager has also
to issue to the Driver a Caution order in KTMB 001 (as in Annexure 29.2) and duly
advising whether he has to return to the despatching Station or to proceed to the next
Station. (Vide Rule C.6.6.2 of General Manual 1994 ). The Ballast Guard shall ensure
that this procedure is adhered to correctly.
29.6.6.3 No Ballast Train working on a Double Line Section shall return on the same line to the
Station from which it started, but shall go to the next Station.
29.6.6.4 In Relay Auto Block (R.A.B) territory and sections with Full Automatic Signals, the Ballast
Guard shall arrange for the Stations at both ends of the Block Section to be "switched-in"
and he shall endorse so in the Train Signal Register. The Station Managers at either
end shall not "Through-Switch" until the Ballast Train has been withdrawn complete from
the Block Section.
29.6.7 Warning Before Moving a Ballast Train
When a Ballast Train is about to be moved, the Driver has to sound two clear long blasts
on the engine whistle as a warning to the workmen. After receiving the Guard's signal to
start, he has to sound one short blast of the whistle before starting his train. The Ballast
Guard shall ensure that this procedure is adhered to.
Before giving the signal to start, the Ballast guard shall see that all the workmen have
boarded the train and shall warn them to sit down.
When the unloading of a Ballast Train whilst in motion is authorised, the Ballast Guard
shall forewarn the Driver in writing, so that the Driver may exercise greater caution in the
movement of his train. The speed of the train shall not exceed 3 km/hr.
When working outside station limits, Ballast Trains shall not be divided, that is, vehicle
shall not be detached and separated except on the authority of the Ballast Guard who
shall take the following precautions for securing the safety of the vehicles:
• The Ballast Guard shall ensure that the points have been correctly set against the
train and secure the points with his clamps. He shall then inform the Station
Manager in writing.
• The Station Manager shall then lock the clamps with his own padlock in the
presence of the Ballast Guard and hand over the keys to the guard in writing.
• At interlocked Stations, lever collars shall be placed on the levers of points and
signals controlling entry into the line on which the Ballast Train is standing. The
Ballast Guard shall check and confirm this.
• In fully automatic signal station, the Station Manager will replace the reminder collar
on the knobs operating the point and signal leading to the line on which the ballast
train is stabled. This should be confirmed by ballast guards.
29.6.15 Monitoring
Productivity depends on efficient and expeditious working of Ballast Trains. The CPWI
shall monitor the performance and output of Ballast Trains closely and take timely
corrective action. Causes of delay shall be traced and reported to the Regional Engineer
who shall take appropriate remedial measures.
and:
• is in an uncompacted state, or
• is otherwise disturbed (e.g. where the track is undercut and ballast replaced on a
face, or following large lifts and stews),
the PWI shall assess the need to impose speed restrictions or other appropriate actions,
until the ballast has been consolidated by rail traffic, or mechanical stabilisation or
compaction. Additional compaction or operational restrictions may need to be applied
when the ballast has been disturbed during or before hot weather.
LIST OF ANNEXURES
Annexure 29.1 Form E-127 Notice to Station Manager about arrival
and departure of Ballast Train.
Annexure 29.2 Form KTMB 001
* Running through*.
Working at KM .........................................
Sent at. ..........................................................................................
Received at. ..........................................................
Ballast Guard.
Reply Sent at .................................................. ,.......................................... .
Reply
Arrangements will be made for your Ballast Train to leave
at. .............................................. .
CAUTION ORDER
You are hereby instructed to exercise caution and where applicable to observe
the speed restriction indicated, between the places shown below:
1.
2.
3.
4.
5.
6.
Signature of Issuing
Officer Staff
ON TRIPLICATE ONLY
PRRTNTAH AWAS
(Dhmnakan di luar kawasan Peneesan Tren Elektronik (PTE)
Pcmandu
No. Trcn ................................... .. NO: CO 00051
Pcngawal
Adalah dengan ini diarahkan supaya berhati dan mematuhi sebarang sekatan laju yang
diletakkan antara tempat-tempat seperti di bawah ini :-
ANTARA SEKATAN
DARIKM KEKM SEBAB
STESEN LAJU (KJ\1/J)
Chapter 30
Ballast Cleaning
Document History
Authorised By:
Signature:
~r'
Date:
MOHD RAMLI MOHD NOH 2 8 MAY zm~
General Manaaer n. I WAu
Ktre~ PI Tanah M• 1ayu Berhad
Kuala Lumpur
TABLE OF CONTENTS
30.1 GENERAL
30.1.1 An elastic bed of ballast is essential for obtaining satisfactory running quality of track.
The following items tend to choke up the ballast bed, thereby impairing its elastic
properties:
• Bad formation
• Attrition of ballast
• Dust and other soil particles blown over the ballast
• Droppings from running trains.
• Other environmental pollution.
30.1.2 A thorough cleaning restores the elasticity of the ballast bed to maintain its resiliency and
results in an improved ride quality of track and an efficient drainage.
30.1.3 This chapter deals with the systems (manual and mechanical) prescribed to obtain a
clean ballast bed.
30.2.1 The entire ballast section shall be cleaned and made up fully on completion of the
operation in the following situations:
30.3.1.1 The longitudinal profile of the track shall be surveyed and plotted indicating the following
details:
30.3.1.2 In station yards, cross sections at every 50m shall be plotted indicating details like
platform levels, rail levels, and clearances to adjacent structures.
30.3.2 On the basis of the longitudinal profile and cross sections, the final rail levels to be
maintained shall be decided. This shall take into consideration the depth of ballast
cushion to be provided and improvement to the existing profile (by elimination of humps,
sags and unevenness as possible).
30.3.3 Preliminary Works
30.3.3.1 Cess shall be brought up to correct level in relation to the final rail level,
30.3.3.2 Pegs shall be provided at intervals of 30m to indicate the final rail level.
30.3.4.1 The work shall be done only under the supervision of a PWI.
30.3.4.2 The daily output shall be pre-determined, depending on availability of traffic block, labour
and capacity of ballast cleaning machine. For guidance, the Plasser & Theurer ballast
cleaning machine features a single screening unit with a screen surface of 30m2 that
offers a cleaning output of up to 400 m3/hr. (equates to about 200m/hr). The rate of
cleaning however drops when there is a high volume of mud or caking in the ballast
layer.
30.3.4.3 Line possessions shall be planned and to be included in the Bi-Weekly Notice( Operation
Bulletin) and the 1-Caution on KTMB website.
30.3.4.4 Indicators and Speed Restriction Boards shall be put up in time at the appropriate
locations.
30.4 METHODS
Ballast cleaning shall be carried out either manually or by ballast cleaning machines.
The cleaning of the full ballast section shall be carried out in ten stages as illustrated in
Figure 30.1.
Note: The stages in Manual Ballast cleaning are described in Annexure 30.1.
30.5.2 Precautions
30.5.2.1 The cleaning work shall progress continuously from the beginning to the end of the
length planned for cleaning.
30.5.2.2 When ballast is being removed from below any sleeper, there shall be at least four fully
supported sleepers between it and the next sleeper under which ballast is being dug out
for cleaning.
30.5.2.4 The PWI shall check and ensure that packing, cross-levels and grade run-off are
satisfactory before closing the day's work.
TableT • 30.5
Speed Restriction to be Imposed
.· .. •.
Day
speed
Note:
Ballast cleaning machines can work only under Line Possession. A minimum duration of
four hours of Line Possession is desirable to have an effective, economical, working
period of about 3 hours. Longer working periods will make the cleaning operations more
effective and economical. The machines can work satisfactorily at night as well.
The key features of the modern ballast cleaning machines are indicated in Annexure
30.1. Ballast cleaning machines perform the following functions:
3. Return to the track all good screened ballast immediately behind the excavating
mechanism.
4. Discharge the spoil from the front of the machine in order to keep the track behind
the machine free for unloading of new ballast and for tamping operations or
discharge the ballast into muck wagons attached to the machines.
5. All the material in the ballast bed can be excavated without screening, if required
and,
6. Sand blanketing between the sub-grade and ballast can also be provided using
such machines.
30.7.4 Post-Cleaning Operations
~
~
;;::
OJ
tp:\: ,Auieet9.
1
-n
<0'
c
~
:;.sn ¥-i ;;{ c i( s/1 FINAL FORMA110N LEVEL
1 ';
Ai.2.1
Cl) STAGE VI
~\n;Aoo d
I F I I 7I
I
;;:: WOODEN BLOCK
s1 .SLI f J 11
j
"l''>f<>JBie-1'-" o""
I
I
t
STAGE I
~ '7 ~7 '7
~ 1
OJ
~
I S\9.: ;Lf1 .Si .iiL c P. J ~\~ ,. le )~.d~ ,ZJ "'C
<D
~
-"'
1i)
OJ 3
STAGE 11 STAGE VIII
'" "'"
--
( ")
=
!I '::>'""
:;·
c.a
t:E: SJUW. ;;t'; d l }# ? ~·:
I
2
.c
3
D J ~ 1 !. 1
A.fe.,{LJLZI
'" <D
"'
Q~
Cl)
::>
"'
Ul '" '<
§· s:
tE:;S\,A.;;;
iJ U,c,,si.g
Cl) STAGE Ill . STAGE IX
..0 1 3
c c.a "'
Cl)
::>
"
Cl)
9,
;7 l '7
.YL, .I t;2:8.A,£,ij,JLm5 .,lJ c:
2!.
"
FINAL STAGE
0 s~~GE l~l ~l 47
"iil
~d,_;,£ooi!i§~ ~~w~dkkl
Cl)
""::>0
STAGE V
"' THE STAGES IN MANUAL
BALL,A.ST CLEANING ARE
DESCRIBEC! IN 1HE NOTE
AITACHED. :1
MANUAL BALLAST CLEANING n
;;]
'g Fig. 30. I
"'~'" :::r
"'
"C "'C
.....
2. -"';::1.
~
~
~
w-
e<
Permanent Way Manual Part IV
Ballast Cleaning Chapter 30
Stage 1:
Ballast is removed from the spaces "A" and "B" on either side of sleeper '1' down to
final formalion level. Depend on the method and scope of the works, wooden blocks or
ballast in gunny sacks are provided in the spaces to support the rails to pass trains.
Stage 11:
Ballast is removed from under sleeper '1 ', down to the formation level or to the top of
sub-ballast.
Stage Ill:
The removed ballast is screened and placed back under sleeper '1 ', which is then
packed.
Stage IV:
The wooden blocks from space 'A' are removed.
Stage V:
Ballast from space 'C' is removed down to formalion level and, after screening is placed
in space 'A' up to the bottom of the sleepers. The left-over ballast in space 'C' is taken
outside the track for screening. The rail in space 'C' is supported by wooden blocks.
Stage VI:
Screened ballast is put under sleeper '2' and the sleeper well packed.
Ballast is removed from space 'D' down to formation level and after screening is placed
in space 'B' up to the bottom of sleepers; the balance may be taken outside the track
and screened. The wooden blocks are removed from space 'B' and placed to support
the rail in space 'D'.
Stage IX:
The procedure is repeated till the whole rail is provided with screened ballast up to the
bottom of sleepers.
Final Stage:
The track is lifted to provide additional cushion where required. The track is packed in
the final position and ballast section made up to the designed profile.
1.2 The excavator chain of the machine removes the ballast from underneath the track,
deposits it on the vibrating screens, where ballast is separated from waste. The
cleaned ballast is then deposited on the track by conveyor belts (just behind the
cutler bar) or directly from the screens, or a combination of the two. The waste is
either dropped to the side or loaded on wagons.
1.3 The working cabin is directly in front of the cutler bar, which provides a good view to
the working site. The engine is fixed to the rear part of the machine. The engine
housing is equipped with removable sides.
3.1 Engine
Air cooled Diesel Engine with an output of approx. 333 kw (453 HP).
3.2 Drive.
The· adjusting unit is composed of two vertical and two horizontal cylinders holding
the lateral guiding channels.
During work, excavation depth may be adjusted from the operator's cabin ranging
from 200 mm below lower sleeper surface to 900 mm below rail top. To avoid
unmovable obstacles, the chain guide may also be deviated from its central position
by a control from the operator's cabin.
5. SCREENING UNIT
5.1 The vibrating screening unit cleans and clarifies the excavated materials. The
screening unit has 2 screens made of wear resisting materials. The screens are
exchangeable. The mesh size is so chosen as to allow only ballast of the desired
grain size to be reintroduced in the track.
5.2 Usually the following mesh sizes are chosen:
Upper Screen: 50 mm
Lower Screen: 30mm
5.3 A hydraulic installation prevents the vibrating screen from depositing all the ballast
on one side on super-elevated track by always keeping it in horizontal position. For
super-elevations up to 110 mm, the ballast is evenly discharged.
5.4 The upper end of ascending chain trough system has a flap, by which it is possible
to discharge all excavated ballast into waste conveyor belts.
There are guide sheets, hydraulically adjustable, underneath the vibrating screens
by which the following ballast distribution is possible.
6.1 The entire reclaimed and cleaned ballast is deposited on the track, behind the cross
beam over the two automatically swivelling conveyor belts, fixed on either side of
the vibrating screen. In this way, sufficient ballast is also deposited to the track
centre. Heaped up ballast is evened up by the following ploughs.
6.2 Most of the reclaimed and cleaned ballast drops on to the track behind the screens
and is evened to rail level. The remaining ballast is distributed by the lateral
conveyor belts.
6.3 The guide sheets are adjusted to allow part of cleaned ballast to drop directly on to
the track and the balance is deposited to the sides, over the distributing conveyor
belts.
7.1 From underneath the screening unit, the waste drops on a fixed conveyor belt,
which transports it to an adjustable belt, controlled from the cabin. From there, the
waste may be discharged next to the track, on wagons in front of the machine, or on
wagon travelling on the parallel track.
7.2 The waste conveyor belt may be folded during transfer; no match wagon is therefore
needed as the belt protrudes outside only during work.
8. PLOUGH
A plough behind the ballast distribution unit sweeps the ballast from rails and sleepers.
9.1 For reducing the excavation depth (lifting) and for avoiding of obstacles (slewing),
this device is required.
9.2 The lifting and slewing device is located next to the cross beam; four roller clamps
moving under the rail heads, lift and slew the track in continuous operation.
Chapter 31
The Maintenance of Formation
Document History
Issue Date Descr iption
Authorised By:
Signature:
Date: 8 MAY 2015
TABLE OF CONTENTS
31.1 GENERAL
31.1.1 Formation refers to the prepared ground, on which ballast is laid to support track. This
provides ideally a smooth and regular surface with good drainage and distributes the
weight of the train (and track and ballast) over a wider area. lt is above the natural
ground level on embankment and below the natural ground level in cutting.
31.1.2 Modern construction practices call for mechanical compaction of formations and for
design of slopes to be in accordance to good engineering practice. Systematic analysis
of the soils is undertaken to produce stable and trouble-free formation to support the
traffic loads on the track. However, on existing lines, there are many locations where
formations are troublesome, leading to:
31.1.3 This chapter describes the common causes of formation problems and remedial
measures.
Table T-31.1
TRACK LEVEL VARIATIONS AND LOSS OF BALLAST
Causes and Treatment
I''
~''' · >.defect y. f•, i ....... ..···· ·. · .·. . . i• . • ,: ; .. . · ...
. ·.··
.· ..
1. Track level 1. Inadequate drainage due to lrriproving side drainage, Effective.
variations high cess, dirty ballast, etc. lowering cess and screening
ballast.
2. Weakening of soil at (i) Provision of a sub-ballast Most effective. Can be laid between
formation top on contact with rain blanket below ballast. trains under speed restriction.
water resulting in 'mud pumping'
(ii) Bitumen impregnation. Fairly effective.
under train.
3. Strength failure below (i) Provision of sub-ballast. Most effective. Can be laid between
causing heaving up of cess or trains under temporary speed
between sleepers. restrictions.
5. Gradual subsidence of the (i) Provision of lime piles. Fairly effective. Can be done
bank core under live loads due to between trains.
inadequate initial
(ii) Cement grouting of ballast Effective. Can be done between
compaction/consolidation of
pockets. trains.
embankment.
6. Gradual consolidation of earth (i) Lime piling in subsoil. Fairly effective. Can be done
below embankment. between trains.
2. Loss of 1. Weakening of formation top (i) Provision of a 'blanket' layer Most effective. Can be laid between
ballast. on contact with rain water below ballast. trains under speed restriction.
resulting in inter penetration of
(ii) Provision of asphalt below Fairly effective.
ballast and soil or strength failure
ballast.
below soil.
2. Subsidence of ballast into (i) Lime piles below ballast Fairly effective. Can be done
formation under liveMioads due to pockets. between trains.
inadequate initial consolidation/
(ii) Cement-sand grouting of Effective
compaction.
ballast pockets.
3. Ballast falling into shrinkage Provision of blanket and Effective. Difficult to lay. Long line
cracks in expansive soil. geotextile. possession essential.
31.3.2 Formulation of remedial measures at a location will depend on several factors and
should normally be done after a proper investigation has been carried out by experts
approved by the General Manager Permanent Way.
• Bulging of slopes,
• Heaving of cess and/or the soil between the sleepers. ·
• Shrinkage cracks.
• Drainage, especially in cuttings.
The objective of site investigation is to locate incipient failures and the shrinking/swelling
characteristics of the soil.
31.3.3.2 Review of the history of trouble like speed restrictions imposed, and incidence of
maintenance.
31.3.3.4 Collection and testing of undisturbed soil samples. Annexure 31.1 contains a list of the
features to be documented, the properties for which soils are generally tested and an
assessment of the suitability of the tested soil (for formation) from its properties. The
nature of the formation problem dictates the type of testing.
Introduction of geotextiles either directly below the ballast (density of geotextile being
2 2
400 - 600 gm/m ) or below the sub-ballast {density of geotextile being 250 gm/m ),
preferably sandwiched between sand layers (of 50mm to 75mm thickness for each layer
of sand}, will prevent intermixing of ballast and soil, distribute concentrated forces and
improve drainage.
31.3.4.4 Bitumen Emulsion Impregnation
Where the trouble is on account of 'mud pumping' only, there being no deep ballast
pockets, the embankment being stable, spraying of cationic bitumen emulsion may be
effective.
During their inspections, the Patrolman, Ganger, PWI and CPWI shall carefully inspect
the slopes of banks and cuttings, especially those with a history of causing trouble, for
any signs of nascent or incipient failure like slips, bulges, cracks, movement or signs of
settlement.
31.4.2 Where the soil is erodable, they shall be vigilant about run-off intrusions on the sloping
surfaces. Such intrusions, unless arrested promptly, may lead to serious erosion of soil
and failure of the slope.
31.4.3 Cuttings in rocky terrain
Permanent Way staff shall be on the look-out for large boulders which may roll down on
to the track, causing obstructions, if not direct danger to a train. Such boulders shall be
safely dropped.
31.4.4 Similar action is required for unstable trees on cutting slopes.
31.4.5 Protection of unstable slopes
31.4.5.1 Some of the types of defects, likely causes-thereof, and the type of possibly successful
treatment are indicated in Table T-31.2 below:·
Table T-31.2
3. Hydrostatic pressure built {i) Draining out of ballast pockets by drain pipes
e.g. vinyl pipes.
up under live loads in
ballast pockets containing {ii) Cement-sand pressure grouting of ballast
water, causing bank slips. pockets.
31.4.5.2 All cases of unstable slopes in banks and cuttings shall be reported to the Regional
Engineer who shall select, with the approval of the General Manager Permanent Way,
the remedial measures required.
31.4.5.3 There may be locations where flattening of the unstable slope or provision of a berm is
constrained by lack of space. There may also be cases where the toe of an embankment
is liable to erosion by water flowing alongside In such cases, an engineered design slope
protection such as toe walls, retaining walls, crib wall, stone pitching or sheet piling that
is based on the result of geotechnical investigation may have to be installed. The
measure may also include drainage improvement at the site.
LIST OF ANNEXURES
Annexure 31.1 Features to be documented for collection and testing of
undisturbed soil samples.
1.1 In case of formation trouble, undisturbed soil samples are collected from the formation
below the depth up to which the ballast has intruded. Where the bank has been found to
be structurally unsafe, soil samples are also collected from the bank along the probable
circle through which the slip had occurred. Besides, soil samples below the ground level
at the toe of the bank are taken where base failure has occurred in the past.
Undisturbed soil samples should generally be collected at every 50 m.
1.2 In cases where slips have occurred, samples shall be collected at two sections in the
slipped portion and one section each at the two adjoining sides where slips have not
occurred in the past. Cross sections of the bank in the sections should also be taken by
means of precise levelling.
2. Nature of soil testing:
2.1 The soil samples collected shall be tested for the following properties:
1. Index properties viz. grain size analysis and Atterberg limits {Liquid Limit, Plastic
Limit, Shrinkage Limit),
2. Natural Moisture Content and Natural Dry Density,
3. Optimum Moisture Content and Optimum Dry Density,
2.2 For banks which are structurally weak, determination of shear parameters of the soil is
very important. Sufficient number of samples shall be tested so as to get a fair idea of
the shear strength of the bank soil as well as the base soil.
3. Assessment of soil suitability from soil properties:
3.1 Grain size analysis:
Generally fine grained soil {particles finer than 75 micron more than 5%) is not good as a
formation soil. Well graded soils have better strength than poorly graded soils.
3.2 Liquid Limit {LL):
This index indicates the degree of plasticity of soil. Evaluation of the degree of plasticity
based on the value of the Plasticity Index is indicated below:
Soils having a Plasticity Index of more than 15 generally present formation problems.
3.4 Natural Moisture Content (NMC):
Generally, clayey soils having moisture content approaching the plastic limits will be
comparatively stiff and those having Natural Moisture Content approaching the liquid limit
will be comparatively soft. Even if such soils are firm, these will be very sensitive to
remoulding.
3.5 Activity of the clay:
Plasticity characteristics are usually adequate to understand behaviour of normal clays
but an abnormality may appear for inactive and active clay. Activity of the clay is the
ratio of Plasticity Index and the clay fraction and it is convenient to classify the activity of
the clay in three groups:
Activity Classification
< 0.75 Inactive clays
Soils under the category of active clays are generally not suitable for the formation.
3.6 Shrinkage limit (SL):
A soil having very low shrinkage limit will shrink considerably on drying, leading to
settlements.
This is the ratio of the Natural Dry Density and the Maximum Dry Density and gives an
idea of compactness of the soil. Wherever the degree of compaction is more than 90%,
settlement is likely to be insignificant.
3.8 Differential free swell (DFS):
This gives an idea of the swelling property of the soil. If the value is more than 60 the
soil is considered to be highly swelling type, while the value between 40 and 60 indicates
moderate swelling. If it is less than 40 then the soil is not likely to give trouble due to its
swelling characteristics.
Chapter 32
Track Renewal Systems
Document History
_.I
Issue Date Description
Authorised By:
Signature:
- A a
~
_,a '
Date: MOHD RAMLI MOHD NOH
~··
2 8 MAY 2015
"" ..,. -,
'Wau
Keretep• Tanah Melayu B.mad
Kuala Lull'pur
TABLE OF CONTENTS
32.1 GENERAL
This chapter describes the classification of track renewals, criteria for renewals, and the
systems adopted for renewal of track and disposal of released materials. Track laying
standards have also been prescribed to ensure quality control.
Table T-32.1
32.3.3.2 Corrosion
Material loss from top and bottom of the rail foot and base reduces fastener toe load and
also increase the possibility of rail roll over or track gauge widening on sharp curves.
Corrosion beyond 1.5 mm in web and foot is the criterion for renewal of rails.
32.3.3.3 Vertical and Lateral Wear:
Refer to Chapter 12, extract of Table T-12.4 below:
·limitsofLatera!W~ar(miTl)······
- -- --
'- _, "
Limits of
When the reduction of depth of the rail head reaches a point, where there is a risk of
wheel flanges grazing the fish plates, rails shall be renewed. The limits of vertical wear
at which renewals are to be taken up shall be in accordance to Table T-12.4 shown
above. Profiles of new and worn rails, showing vertical wear and measurement of lateral
wear are as shown in Figure 32.1 and Figure 32.2.
32.3.4 Maintainability of track to prescribed standards
There may be cases, where renewals are necessary on the following considerations.
o Poor running quality of track, inspite of extra maintenance effort put in.
o Disproportionate cost of maintaining the track in safe condition, due to excessive
scabbing, wheel burns and corrugation of rails.
32.3.5 Service life
As a guide, the rail shall be programmed for through renewal after it has carried a total
traffic as follows, irrespective of the fact that renewal is not warranted by any other factor
like rail wear, correction etc.
Table T-32.2
Note:
By definition, the fatigue limit (equates to service life) for plain to medium carbon steels
this occurs when a fatigue defect is initiated. For rail, the development of shelly surface,
fatigue spalling, gauge corner cracking etc. would suggest that a fatigue threshold has
been reached. To protect against the development of fatigue related defects, the primary
defences are Rail Grinding, Track Geometry Testing (which also measures rail wear) and
Ultrasonic Rail Testing (UT). The Permanent Way Manual outline the minimum frequency
for Track Geometry testing (twice per year on Main Lines and UT testing (at least once a
year).
32.3.6 Plan based renewal
Renewals to a predetermined plan with the objective of modernizing the track structure
on selected routes to a schedule are undertaken even if it involves premature renewals
by the Railway Administration.
32.3.7 Criteria for Sleeper Renewals
• hold gauge.
• provide satisfactory rail seat.
• permit rail fastenings being maintained within the required tolerances,
• retain the packing underneath the sleepers.
• retain its strength and resiliency.
32.3.7.2 Sleepers which cannot fulfil one or more of these functions shall be renewed.
32.3.7.3 Where re-sleepering is justified, it shall be carried out in continuous stretches.
Serviceable sleepers which are released are utilised for spot-renewals elsewhere.
32.3.8 Renewal or reconditioning of turnouts:
lt becomes necessary to replace or recondition the turnouts or parts of the turnouts if:
• The vertical wear or lateral wear on the switches exceeds 6mm. For high speed
turnouts, the limits shall be as per the manufacturer's recommendation.
• Vertical wear on wing rail or nose of crossing exceeds 10 mm.
• lt becomes difficult to maintain the gauge and the specified clearances within the
prescribed limits.
• The rail section on either side is changed to a higher section in through running
lines.
Spot renewals relate to replacement of isolated rails, sleepers and fastenings, when they
become unfit.
32.5.1.1 Track renewal proposals shall be initiated by PWI in the month of November every year
based on factual data of the condition of track and on observations by him during the
various inspections carried out during the year.
32.5.1.2 The proposal shall include the following:
The CPWI shall satisfy himself about the reasonableness of the proposal submitted by
the PWI. He shall ensure that every stretch requiring renewal is included in the proposal.
Since the programme is prepared a year in advance and a period of two years or more
may elapse before actual renewals are carried out, special care is required in framing the
proposal. The CPWI will then forward the proposal to the Regional Engineer.
32.5.3 Formulation by Regional Engineer:
The Regional Engineer shall personally check the details submitted by the CPWI. He
shall prepare the track renewal proposal for his Region and indicate the priorities. The
Regional Engineer will submit the proposal to the Headquarters by the end of March.
32.5.4 Finalisation in the Permanent Way Headquarters Office:
In this office, important items shall be verified by the nominated officer. He will
32.5.5.1 Renewals may be planned in, as long and continuous lengths, as practicable.
32.5.5.2 Short isolated stretches of less than 10 km falling between two sections of track being
renewed shall also be programmed, even if they are not due for renewal on condition
basis.
• Complete dismantling of old track and relaying with new track manually, or
• a "piecemeal" method, in which re-sleepering and re-railing are carried out
separately.
32.6.3 Mechanised relaying operations can be carried out by:
frame the time table and regulate the trains as considered necessary, providing
adequate engineering time allowance in the time table.
32.8.2 Arrangements for special rakes for movement of rails and sleepers shall be made by the
Regional Engineer in consultation with the Operation Division. Separate locomotives will
also be arranged where necessary.
32.8.3 In the case of major relaying works, additional sidings may have to be provided at the
depots for receipt and despatch of materials.
32.8.5 Provision of communication facilities shall be arranged at site of work for liaison between
the various work sites, adjacent Stations and the Train Control and Command Centre
(TCCC}.
32.11.1.1 The ballast shall be cleaned and ballast section levelled up to lhe bottom of sleepers to
facilitate relaying.
32.11.1.2 Fish boils shall be oiled and eased one day in advance of the actual day of line
possession/work.
32.11.1.3 Temporary construction and safety signage shall be erected at appropriate places.
32.11.1.4 A speed restriction of 15 km/hr shall be imposed at the site of work.
32.11.1.5 A couple of hours before the actual operation of the line possession, the ouler fish bolts
of each joint and fastenings of alternate sleepers are removed.
32.11.2 Work during the Line Possession Period:
• Spread new sleepers to correct spacing (use a tape or spacing rod on which sleeper
spacing is marked).
• Link new welded rails 146 m (480 feet) long (or as per the welded length).
• Ensure correct expansion gaps.
• Tighten lightly two fish bolts per joint.
• Straighten and align rails.
• Adjust sleepers to spacing marked on rails.
• Fix fastenings to sleepers and rails.
• Align the base rail (reference rail) and fasten.
• Adjust the other rail to gauge and fasten.
• Insert rail closures to join new and old track at the end of the day's work.
• Lift and pack the track.
• Provide ramps to the track as specified in Chapter 22, Clause 22.6.1.21.
• Line operation commissioning form to be filled in by respective officers as per Rules
• Surrender the line possession and impose a speed restriction of 15 km/hr.
While renewals are being carried out during the line possession, unloading of new
materials and picking up of released materials shall also be carried out.
32.11.4 Work after the Line Possession
After traffic has resumed, the new track shall be inspected and defects attended to, at
suitable intervals, particularly on the following items:
• Squaring of sleepers.
• Tightening of fittings.
• Gauging.
• Packing of sleepers either manually or by machines.
Table T-32.3
0 + Destressing and Raising speed Normal If DTS is employed, normal speed can resumed
20 after tamping, stabilising with DTS and
speed
destressing completed.
In this method, through sleeper renewal shall be carried out first. Through Rail renewal is
subsequently done after the track gets consolidated by three rounds of through
packing/tamping and by passage of trains and/or use of DTS. This method is only
applicable where the old and new rail sections are similar (especially the foot of the rail).
32.12.2 Preparatory work before relaying
32.12.2.2 The exact position of rail joints (after allowing for expansion gaps) shall be marked
accurately on the base rail using a steel tape.
32.12.2.3 The position of new sleepers is then marked on the base rail with white paint and
transferred-to the opposite rail by means of a Tee Squafe.
32.12.2.5 Temporary construction and safety signage shall be fixed at appropriate places.
32.12.2. 7 Ballast section shall be levelled upto the bottom of sleeper and renewal of the sleepers
carried out simultaneously. At the end of the day, the track shall be lifted and packed to
the final level. A ramp as specified in Chapter 22, Clause 22.6.1.21 shall be provided to
meet with the levels of the existing track.
32.12.2.8 After three rounds of packing or tamping, through rail renewal shall be carried out, taking
a suitable line possession. The final round of packing is undertaken and the
speed relaxed to normal as indicated in Clause 32.11.5.
32.12.2.9 Work after surrender of line possession/traffic resumption
During this period, special attention shall be given to the various items as indicated in
Clause 32.11.3.
• Engine.
• Brake Van.
• Mobile workshop cum tool van.
• Bogie wagons loaded· with portal cranes.
• About 8 flat wagons loaded with new panels.
32.14.1.2 A sketch showing the marshalling of the relaying rake is at Figure 32.3.
32.14.1.3 Removal of the old track, loading it on empty wagons and laying of the new panel are
concurrently done in the same line possession with the help of these cranes. The
service rails are replaced by long welded rails (146m long or longer) subsequently.
• Assemble track panels at the base depot ensuring correct spacing of sleepers and
all fastenings.
• Load assembled panels on flat trucks.
32.14.2.3 Work during the Line Possession
o Lift pre-assembled panels and lay on the prepared ballast bed using portal cranes.
o Link new track panels.
o Join with old track using rail closures (run out difference in level on a ramp length of
at least 24 m long).
• Pack/tamp track.
• Load portal cranes back on the relaying rake.
• Clear relaying rake out of the line possession section.
• Surrender line possession to Operations and impose speed restriction based on
track consolidation condition.
• Return relaying rake to the base depot.
o Unload old track panels.
32.14.2.4 Work after traffic resumption
32.14.3 In subsequent line possessions, after the necessary track consolidation, the service rail
shall be replaced by welded panels (146m long) received from the Flash Butt Welding
Plant. These panels are then welded in situ to form LWR/CWR. Restressing of the panel
shall thereafter be done at the designated temperature as indicated in Chapter 25.
32.14.4 The newly laid track shall be attended to by tamping, levelling and lining machines
following the renewal. Speed restrictions may be relaxed in stages as per the schedule
mentioned in Clause 32.11.4. Before relaxing the speed to normal, provision of ballast to
the profile specified for LWRICWR shall be ensured.
32.14.5 Special attention shall be paid to the items as indicated in Clause 32.11.3 during the
post-line possession period.
DO:
DONT'S:
32.15.2 Joints
DO:
• Do not provide rail joints within level crossings and 3 meters on either side of level
crossing and bridges.
• Do not provide rail joints on bridges with spans less than 6m.
32.15.3 Sleepers
DO:
• Adze and bore wooden sleepers correctly ensuring a cant of 1 in 20 towards the
centre of the track.
• Ensure the following spacing:
• Concrete/Wooden sleeper 600 mm.
• Bridge sleeper 550 mm.
• Wooden sleeper at joints 460 mm.
32.15.4 Gauge
DO:
• Provide gauge widening for sharp curve as detailed in Table T-32.4 below:
Table T-32.4
Note: Also refer to gauge widening guide in Chapter 12, Clause 12.17.
32.15.5 Alignment
DO:
• Check alignment especially on curves and transitions with reference to centre line
pegs.
32.15.6 Level
DO:
32.16.5 Ramps as specified in Chapter 22, Clause 22.6.1.22 shall be provided at the junction of
newly relaid track and the old track every day, to run out the difference in level.
32.17.2 Every component of track has permissible tolerances from the standard dimensions. Any
adverse combination of the tolerances in various components can therefore affect the
track geometry beyond the acceptable standards.
32.17.3 The standards of track geometry and dimensions as per Chapter 11 and 13 shall be
achieved for all classes of tracks renewed with new materials.
Before renewing turnouts, the ballast shall be opened up to the bottom of sleepers.
Drainage shall be improved. Centre line pegs must be fixed for the new assembly.
32.18.2 Renewal
In this method, all the components and materials required for the turnout installation are
brought to the site. The old turnout is dismantled and the new one assembled at site in
its correct position. This method may be adopted in the case of laying new yards or
remodelling of existing yards.
32.18.2.2 Pre-assembly and slewing in at site
By the side of the existing layout, the ground is levelled. Where adequate space is not
available, a working platform with old rails and sleepers is created. The new layout is
assembled adjacent to the existing layout. The assembly is built on a rail grid and the
top surface is greased to facilitate easy stewing of the new turnout. During the line
possession period, the existing layout is dismantled and removed. The new pre-
assembled layout is slewed to its correct position, aligned and packed. Alternatively the
new layout can be lifted by cranes and put in position in convenient lengths.
32.18.3 Pre-assembling in depots
32.18.3.1 In this method, the layout is assembled in a central depot on a platform specially built for
this purpose. After assembling the layout, the corresponding parts shall be suitably
numbered indicating the matching rail ends of the various components, before the layout
is split into components.
32.18.3.2 The layout is then dismantled and the component parts kept in proper sequence
according to their relative position. The old layout is dismantled and the new layout laid
in its position. In this method, the workmanship achieved is of a high standard and
therefore it shall be preferred to other methods.
32.18.4 Special precautions
32.18.4.1 Complete renewal shall only be carried out with standard rail section and turnouts.
32.18.4.2 Track at either end of the turnout shall be adequately anchored.
32.18.4.3 At least one rail length on either side of the turnout shall have the same rail section as
the turnout.
32.18.4.4 Stock rail joint and joints in lead rail shall be welded.
32.18.4.5 In case of LWR, one normal lengths of rails with fish-plated joints shall be provided
between:
32.18.4.6 For CWR in Class 1 routes with High Speed CMS turnouts, the requirement as per the
first 3 bullets of Clause 32.18.4.5 above are not required as the CWR will be welded
through the turnout.
32.19.1.1 Before the end of March each year, the PWI shall inspect all sleepers in his section to
determine the number of sleepers which will require to be renewed in the following year.
(in accordance to with Chapter 20).
32.19.1.2 Timber sleepers to be renewed shall be marked by a cross in white paint. Details of
such sleepers for every half a kilometre shall be listed out by the PWI. (See Annexure
20.2).
32.19.1.3 Information given by the PWI shall be verified by the CPWI by examination of not less
than 10% of the total number of sleepers to be replaced.
• Inspect all sections, where sleepers needing replacement exceeding 10% of the
total numbers in the region, and
• Advice the total requirement of sleepers to the Head Quarters office before the end
of April each year.
32.19.2 Operations
The operations involved in spot renewals of sleepers are described in Chapter 39.
Class A: Fit for use in running lines of class 2 after end cropping.
The ends of rails are to be painted with a daub of white.
Class B: Fit for use in class 3 line and in non-running lines. The ends of rails are to
be painted with a daub of yellow.
Class C: All unserviceable rails not fit for use on track. The ends of rails are to be
painted with a daub of red.
32.20.3 Sleepers and other track materials:
32.21.2 In classifying the sleepers, it shall be examined whether they can be reconditioned and
holes in wooden sleepers can be plugged. If the sleeper is not decayed throughout its
length, it can be cut to short lengths and spliced for use as a composite sleeper.
32.21.4 If the turnouts themselves are too badly worn to be reused, parts of it and its fittings such
as stretcher bars, distance blocks, heel blocks, check rails, bolts and nuts shall be
reused.
32.21.5 Switches and crossings may be reconditioned by welding, if the wear is not too severe,
subject to the type of material of the switches or the crossings. (Chapters 33 and 39).
32.21.6 The materials of each class including fittings should be separately stacked with suitable
indication plates for convenience of accounting and despatch.
32.22.2 Close attention shall be paid to the newly relaid track in the first few months. Inspection
and timely rectification to all track defects shall be done at this stage.
32.22.3 Maintenance organization for the new track shall be in accordance with the type of
maintenance to be introduced. Reorganization of the gang has to be done to suit the
same.
32.22.4 The permanent way men shall be trained in advance in the system of maintenance to be
introduced.
32.22.5 The permanent way diagram, standard yard diagram, index diagram, sectional register of
PWI and other relevant records shall be amended to reflect the new track particulars and
year of laying. Copies of the amended diagrams shall be supplied by the Regional
Engineer to the CPWI and the PWI for record in their offices.
32.22.6 The accounts for relaying work shall be closed within three months of completion
of the work and a completion report submitted.
LIST OF FIGURES
Figure 32.1 Vertical Wear Limits.
LIST OF ANNEXURES
Annexure 32.1 Proforma to be submitted for justification of track renewal.
Fig 32.1
(NEW PROFILE
BSSOA
rNEW PROFILE
1 jNORN PROFILE
_ _j_, -:.!
(.---- ~)_l 10.00 VERTICAL WEAR (V}
~\1
UIC54KG
VERTICAL WEAR
Fig. 32.1
~
~
OJ
14
6t:
f"EW PROFILE
~~ tW;~: P~O:~:
LATERAL WEAR (L)
14
~~---L;::_RN
;-NEW PROFILE
...
PROFILE
4.50
i
WEAR MEASURED WEAR MEASURED AT BSBOA
A POINT 14mm A POINT 14mm
BELOW RAIL TABLE. BELOW RAIL TABLE.
"T1
u:;·
c
~
"'N
"'
-j"IJ
03 ~
() 3
"'
I "'"'
::0:::1
-
r
"' "'
~I
:J :I
*
~
9!.
~
LATERAL WEAR (L)
··-'6'-··· ·--_i
f"EW PROFILE
/.WORN PROFILE
LATERAL WEAR (L)
10,
'
_j_
f"EW PROFILE
,-WORN PROFILE
I
"'~~
IJ)'<
r
~r
~
14 I
WEAR MEASUREliA'! UIC54
~I 3 c
"'
VI
:I
e!.
UIC54
A POINT 14mm
V
BELOW RAIL TABLE.
STRAIGHT CURVES
I
J? n
:::r
.,
<0
"0
"'g, LATERAL WEAR
2l
VJ
N
-"'
"0 .,
~ "'
..,_ ;:l.
~I 1.
2.
ENGINE.
BRAKE VAN.
3.
4.
CREW REST VAN.
MACHINE BFR TO CARRY PORTALS ~
5.
6.
7.
BFR's LOADED WITH NEW ASSEMBLED
PANELS.(FOUR PANELS IN EACH)
EMPTY BFR's FOR LOADING RELEASED
PANELS.
PORTALS CARRYING NEW PANEL$.
i
"T1
<0' 7
c 1
1 y 5 6
I I I
I
ro !
i i ),. i
)·,"
""
~
""'
!I
i
I
I
!I
i l /// "'·,,
/
/
""''· I """U
~ tD
s: / '" ~
'"
Ul
" 3
"' "'
-~
~I oil~
::0
Cl> "tD
"' "-
0
a
Cl>
_.,
~ :::
@l ~~
~
:e.Cl> "'"
3 c:
::0 NEit/ TRACK} MEN LEVELING BALLAST} UJ ~
"''Cl>"
I
'TJ
<.0
NOTE: NOT TO SCALE c
'
(!)
0J
Marshalling of Relav Rake N
;g Fig. 32.3 0J I
::T
n
"'
"'
~
0
~
-"'"' -"'
,
~ ~
"U
"'"' N<
Permanent Way Manual Part IV
Track Renewal Systems Chapter 32
Sleepers ....................... .
Density ........................ .
Observations
SI. Ki_lo:rri~tra9c( :f~O_rrf;:-the: ':b_~gi:n_r!_in·g_-·_=O_f :t)~stgn_3tiC>n: Of :the Offi-Ci3f,
:the:_:. ;pro{l_()SEid,-~:J~•;nww~i-:::- (exc_ludi_ng -:::~eCordinQ obS_e_rVations :-
No.
lcjopS-a~d SidiiiQs_ _in:-va~dS} --
0.1 1 . .2 3 ·4 . 5. 6
1. Rails
(a) Type
(b)Age
2. Sleepers
(a) Type
(b) Age
(c) Condition
4. Formation
(i) Soil
(ii) Condition
5. Spot Renewals
Date: ......................... .
P.W.I
Chapter 33
Reconditioning of Track Material
Document History
Authorised By:
r \
Signature:
Date: MOHD RAMLI MOHD NOH 2 8 MAY 2015
Keretepl Taoah Metayu Berhad
Kuala LumJtur
TABLE OF CONTENTS
33.1 GENERAL
Track materials in seNice deteriorate with time due to wear and tear. The rate of
deterioration depends on the traffic density, state of maintenance and the environment.
Defective components which are not expected to give a further seNice of 18 months are
programmed for replacement (Chapter 20). This chapter indicates the measures to be
adopted for reconditioning of suitable released materials to make them seNiceable.
33.2 PROCESS
33.2.1 The process of reconditioning shall be initiated at an early stage rather than at the end of
the life of the component. This can only be done by a thorough and careful check by the
PWI, while he conducts personal inspection of each kilometre of track during the
prospecting suNey mentioned at (Chapter 20, clause 20.9).
• Rails
• Wooden sleepers
• Concrete Sleepers
• Fishplates
• Coach screw & plate screws
• Switches and Crossings
33.2.3 Reconditioning shall preferably be done at a depot, where quality control can be better
exercised. The Regional Engineer shall decide where the reconditioning facility should
be located.
Grinding of rails shall be resorted to for removal of corrugation, pitting, scabbing and
other defects. Grinding is done by a small portable hand grinding equipment or rail
grinding train as indicated in (Chapter 27, clause 27.5.7.3).
Where sleepers are released in bulk due to relaying or other reasons, these shall be
reconditioned in a central depot as under:
• Sort out the sleepers according to the classification (see Chapter 32,clause 32.20).
• Clean the sleeper to be reconditioned of dirt.
• Provide end-binding.
• Enlarge the holes with a boring machine.
• Plug the holes with tapered wooden plugs dipped in suitable oil.
• Adze the sleeper to give necessary cant.
• Drill new holes.
• Spray with creosote.
o Sort out the sleepers according to the classification (see Chapter 32,clause 32.20).
o Clean the reusable sleepers of dirt
• Stack the sleepers accordingly
33.8.2 Resurfacing can be done either in the field or in a centralised depot depending on the
facilities available. Welding with electric welding process shall be preferred. The
welders shall be trained and the procedure prescribed by the manufacturer shall be
strictly followed.
33.8.3 Procedure for resurfacing and refurbishing High Speed Turnouts shall be referred
to in the High Speed Turnout manual.
33.8.4 Annexure 33.1 gives the procedure for repair welding of rails or crossings by the
Hedkote® process.
A. Inspection
The following work must be completed before the process can begin.
2. All sleepers, especially under the nose of the crossing, have been packed.
3. All check-rail bolts have been tightened.
4. Check-Rail effectiveness in steering wheels away from nose must be checked and
fixed if necessary.
8. All crossing bolts must be straight, in sound condition, of correct length, with nuts
fully threaded and properly tightened.
9. All Huckbolting is to be completed before welding begins.
If internal defects have been identified for removal, the inspection report must be
available to for examination. Report must show the location, depth, size and type of
defect. This will be used in determining if defect is suitable for removal. Bolt hole cracks
are not to be repaired.
Visual inspection of the proposed work is to be completed before any work is to begin.
Visual inspection is used to determine if the proposed work is suitable for
rebuild/resurfacing.
The spacing of wheel burn and squat repairs must be measured so as to determine the
repair method. Bent rail must be identified and noted for wheel burn and squat repairs
before work is to begin. Straight edges, taper gauges and P1 gauges should be used in
determining bent rail.
B. Preparation
1. The repair area must be cleaned. All previous repairs must be removed by grinding.
2. Check for old weld laminations and cracks, which will become noticeable when heat
from grinding is applied. Remove all laminations or cracks.
3. The damaged area plus 25mm on either side must be removed by grinding.
Once the area for repair has been ground out and all cracks, laminations, old welds and
defects have been removed, the area will be tested using magnetic particle inspection.
Any cracks shown up by the inspection should be removed and the area re-tested.
C. Welding
a) The area to be repaired, plus 100mm either side, is to be pre-heated to the proper
temperature depending on rail type, rail metal composition, size of repair, process
used and ambient conditions. Guidance must be sought from the Permanent Way
Depot Engineer on the proper temperature. A soak time of 2 minutes is required
before welding commences. If the pre-heat temperature is less than the required
minimum after the 2 minute soak time, then a further pre-heat is to be applied and a
further 2 minutes soak time allowed until the correct temperature is reached. The
temperature is to be checked using a thermomelt crayon which should be applied to
the bottom of the rail head.
b) lnterpass temperatures must be maintained during welding. This temperature is to
be checked after every 2-3 welds. Temperature is to be· measured using a
thermomelt crayon.
c) If the welding is stopped for 3 minutes or longer, then an additional pre-heat and a
soak time of 2 minutes should be applied. Temperature should again be checked
with a thermomelt crayon.
d) The welding is carried out using DC reverse polarity. The wire feed unit is connected
to the positive terminal of the generator and the negative is connected to the rail.
The connection at the rail should be cleaned with a grinder to ensure a good
connection.
e) Where possible weld starts and finishes should not be in a single line. If multiple
weld layers are necessary then the layers should not start and finish in the same
line. Stringers or weaving can be used depending on conditions.
k) The welder must paint his welding licence/certification number, location (km) and
date of the repair on the foot of the rail within 600mm of the repair. For crossing
repairs, if no ID number is present, then welder will stamp an ID on the wing of the
crossing. For wheel burn repairs, the start and finish of the repair must be marked
on the head and web of the rail. Each individual repair must be given an ID number.
I) The work will be checked for levels and alignment using a 1 meter straight edge.
m) A taper gauge can be used to check for bent or curved rail on wheel burn or squat
repairs.
n) A P1 gauge should be used to confirm that ramp angles conform to standards.
o) Final ultrasonic testing of the work is to be carried out by the Permanent Way
Ultrasonic Testing Team or outsource to a Third Party tester.
ii. Location
iii. Supervisor Name
x. Assistant name
xi. Equipment/Vehicle used
xii. Details of any unusual circumstances.
E. Follow up work
The following work is to be completed within 14 days of the welding being carried out.
i. Grind off any flow that has occurred due to work hardening (post grinding).
Chapter 34
Vegetation Control
Document History
Issue Date Description
Authorised By:
Signature:
Date: MOHO RAMLI MOHD NOH
General Mana r Permanent Wa
2 8 MAY Z015
Keretepl Tanah Melayu Bemad
Kuala Lumpur
TABLE OF CONTENTS
34.1 GENERAL
34.1.1 Vegetation control for the permanent way comprises the following key activities:
a) Weed management
b) Grass Cutting
c) Tree fouling to track.
34.1.2 Control of vegetation especially on the track ballast and formation is important to keep
down track maintenance costs and ensuring good quality track. The impact of poor
vegetation control will result in:
a) Poor track drainage - Growth of grass and weeds on ballast accelerates fouling of
ballast and prevents good drainage. These will lead to deterioration of formation
affecting the track top line and level.
b) Corrosion - Growth of vegetation keeps the track damp for longer periods and
accelerates corrosion of the rail and fastenings.
c} Slippages of traction wheels may occur due to grass and weeds on rail. Besides
affecting train performance, wheel slips may cause wheel burn damages to the rail
crown.
d) Impediment to maintenance work - Poor vegetation control and overgrowth of
bushes and trees impairs inspection works on the track, the formation,
embankments and cuttings. Normal maintenance tasks will be rendered more
difficult with vegetation on the cess and track.
e) Public image- Heavy growth especially in station platform lines and track in public
views such as near level crossings presents a bad image to the public.
f) Safety - Heavy growth posed a risk to the safety of train operations and for
personnel working on or near the track.
34.1.3 Special attention for Vegetation Control must be made for the following areas:
• Station Yards
• Around Structures & Wayside Equipment
• Spots with Noxious Weeds
• Track & Cess Vegetation Growth
34.1.4 As a minimum, grass cutting and weeding shall be carried out 7.0 metre from the nearest
rail.
34.2.3 Avoid cutting of weeds as much as possible as this causes them to seed and gives extra
work in weeding.
34.2.4 Ensure that. in chemical weed killing, the solution remains in contact with the leaves of
the weeds for a time. Avoid spraying during or just before rain.
34.2.5 Apply chemicals at the correct rate, evenly over the area, with maximum safety.
34.2.6 Apply chemicals before the weeds have seeded but after they have developed a fair
amount of young foliage.
34.2.7 Where growth is prolific, give a second application.
34.2.8 Do not cut the weeds treated with weed killers but allow them to die off.
34.2.9 Remove the weeds and grass at kilometre posts. gradient posts and other track signs. so
that they areeasily visible.
34.2.10 Clear all vegetation and obstructions from drains and waterways within railway limits so
as to allow water to flow freely.
34.2.11 Keep away weeds and grass from power signalling cable routes, (since the weeds, when
dry, are liable to catch fire and damage the cables).
34.3.2 The grass collected shall not pose risks of fire hazard. A "fire barrier" shall be
maintained for a width of three meters around all buildings and structures. These
"barriers" shall be kept free of grass.
Train runs are at risk from trees and branches falling onto tracks. Therefore the PWI
must ensure that adequate clearance is maintained to prevent vegetation growing too
close and fouling passage of trains. Tree siblings must be cut before it reached heights
above 1 metre. For existing grown up trees that are yet to be cut, they must be kept a
safe distance, away (D) greater than 1.5H + 1.5 metre (H = estimated mature height of
the tree) as shown in Figure 34.1 .
34.4.2 Trees and bushes which may interfere with the visibility of train drivers shall be cut.
Attention shall be paid for the line of sight along the inside/outside of curves from a train
or trolley.
34.4.3 The branches shall be lopped off wherever required to ensure clear line of sight for train
drivers and safety of the track against potential obstructions due to falling branches,
particularly in rainy and windy conditions.
34.4.4 The PWI shall
34.4.4.1 Make a special report to the Regional Engineer on trees which he considers should be
cut down.
34.4.4.2 Not fell any tree without the permission of the Regional Engineer.
34.4.4 .3 Ensure that the trees which are felled, fall away from the railway line.
34.4.4.4 Protect the line in accordance with the Rules when the felling operations is likely to
cause infringement of the fixed structure dimensions.
34.4.4.5 Cease felling operations at least ten minutes before a train is due to pass.
34.4.4.6 Refer to the Regional Engineer for instructions when it is necessary to cut trees or
bushes which are on private land.
34.4.4.7 Remove tree stumps and roots near the top of cuttings or adjacent to the track, which are
likely to fall.
34.4.4.8 Not damage rubber trees, fruit trees, standing crops or other private property.
34.4.4.9 Lop the branches of trees and trim the shrubs as necessary for proper line of sight for
train drivers and for safety of train operation
LIST OF FIGURES
Figure 34.1 Vegetation Fouling Track
VOLUME 2
PART V
TRACK MAINTENANCE
INSTRUCTIONS
Permanent Way Manual Part V
E?iiCTIIII Duties of the Regional Engineer Chapter 35
Chapter 35
Duties of the Regional Engineer
Document History
Authorised By:
,--'
Signature:
Date: MOHD RAMLI MOHD NOH
General M na
2 8 MAY 2015
Keret'6pl Tanah Melayu Berhad
Kuala Lumpur
TABLE OF CONTENTS
35.1 INTRODUCTION
The Regional Engineer is responsible for his Region to the General Manager Permanent
Way. He will receive orders from the general Manager Permanent Way or his authorised
representative. The Regional Engineer shall be generally responsible for the. proper
maintenance of track, and permanent way structures and for the safe custody of all
Permanent Way Department Stores in his Region. This Chapter of Manual deals with
the Regional Engineer's responsibilities concerning the Permanent Way under his
jurisdiction.
35.2 STAFF
The Regional Engineer's Permanent Way staff will normally consist of Regional
Engineer's assistants, Chief Permanent Way Inspectors, and Permanent Way
Inspectors, with support staff for office and store.
35.3 INSPECTIONS
35.3.1 The Regional Engineer shall inspect the track (including Turnouts), bridges, and tunnels
of his Region according to the procedures laid down in Chapters 40, 41 and 42 and
schedules laid down in Chapter 50 by inspection trolley and by train.
35.3.2 Ample time shall be allowed to enable thorough inspection of Gangs, the permanent way
and structures. The Regional Engineer shall verify that all systems and procedures are
correctly implemented.
35.3.3 When inspecting by trolley and subject to operating time slot available, the Regional
Engineer shall stop where Gangs are at work in order to:
35.3.5 The Regional Engineer shall arrange for charts to be maintained in his office showing the
track inspections carried out by the CPWI and PWis. Similar Charts showing the
inspections carried out by the Regional Engineer shall be forwarded to the General
Manager Permanent Way by end of June of every year. The format for such Charts is
illustrated in Figure 35.1.
35.4.3 To allocate the available resources according to the guidelines of the General
Manager Permanent Way, getting his approval as required.
35.4.6 To watch on the receipt and deployment of on-track machines, labour, track material and
tools and plant.
35.4.8 To report serious problems to the General Manager Permanent Way according to
procedures specified in Chapter 20.
Note:
The Regional Engineer shall be assisted by the CPWI in discharging the above
functions.
The Regional Engineer shall be responsible for the setting out of all new works .•
excluding works which are under the scope of the Project Management Division.
35.5.3 Approvals
The Regional Engineers shall ensure that no work affecting the safety of running lines as
specified in Chapter 51 is commenced without the sanctions stipulated therein.
35.5.4 Execution
The Regional Engineers shall generally ensure that the provisions of Chapter 45 are
complied with, especially in the preparation of the Operation Bulletin, the arrangement of
Line blocks and adoption of all safety precautions.·. They shall also personally liaise with
their counterparts in other Departments as required for smooth and timely progress of
these works.
35.5.5.1 The Regional Engineers shall personally inspect before opening to traffic any work or
alteration carried out like:
A new Station
Public or private siding
Junction
Bridge
Temporary bridge
Track Deviations/Diversions
Reconstruction or alteration materially affecting the structural character of any work
or works forming part of or directly connected with, running lines, or in any way
affecting the safety of travelling public or servants of the Railway.
35.5.5.2 Before opening the work, the Regional Engineer shall satisfy himself prior to
commissioning the work that the completed work will not pose danger to the public or to
passing trains.
35.5.5.3 Commissioning Certificates shall be issued as specified in Chapter 51.
35.6 STORES
The Regional Engineer shall fix stock levels for different items of Permanent Way
material on the basis of 'PTM 1' statements given by the PWis (Chapter 20). He shall
ensure, through periodic verification, that the stock is properly stored and that their
accounting is correct and up to date.
35.9.1 When handing over or relinquishing charge of a Region, the Regional Engineer shall sign
a Handing Over Certificate in which he shall enumerate:
35.9.1.1 The position of any bank, culling or length of Permanent Way which requires to be kept
under watch.
35.9.1.2 Any bridge or drain which calls for special attention or treatment.
35.9.1.3 Locations that are affected or are likely to be affected during severe rains or are subject
to flooding or potential flooding.
35.9.1.4 All prominent features in the past history of the Region like:
Slips
Damages
Accidents
35.9.2 The Handing Over!Taking Over Certificate shall be signed by the Regional Engineer
taking over charge also. A copy shall be forwarded to the General Manager Permanent
Way.
35.9.3 The relieving Engineer shall spend some days on the Region to enable him to travel over
it in company with the Engineer being relieved and to examine personally and discuss
any items mentioned in the Handing Over Certificate. Controversial points, if any, shall
be referred to the General Manager Permanent Way.
35.9.4 While assuming charge, Regional Engineers shall make themselves thoroughly
conversant with the past history of the Region by perusal of the Section Registers and
other records and by ascertaining information from the CPWI/PWis. This aclion is
especially necessary when, for any reason, it is not possible to take over from the
Regional Engineer being relieved.
35.9.5 After assuming charge of a Region, the Regional Engineer shall travel over the whole
length of his jurisdiclion as early as possible and salisfy himself as to its general
condilion and the adequacy of the system for efficient maintenance. The CPWI or PWI
shall accompany the Regional Engineer on these inspections.
LIST OF FIGURES
Figure 35.1 (sheet 1 & 2) Track Inspection Chart.
Designation PWI/Kl
Jan. Foot
Trolley
Loco
Last vehicle
Feb.
March
April
Note:
Hatch the Kilometres inspected and write the date of inspection as shown in Figure 35.1
(sheet 2.
.,.
"' ....
"'
0
"'"' 1-
"'..., -
"' n
~
"" ...,
~
~
"'
"'z "'"' -
0
_m
<(
-, ··-~i!5 "'"' "':;;
~
Le
I
0 - ,;
"'
>-'
0
z
" "' 1-
w
I
N
f-
"' n
"'
"'
0
{L
~
f-
"'J:
<(
0
z 0
0 N 1-
G "'
LU
0.
u;
-~-
z <L z
D ::J
.,.
0
0
m "'0: "'
0
N
,~
0
N
;;; 1- "'
0>
l"'i
N
"
z
0 0
;;; '-z
0
z F
u
0 w
F F
u
u_; 0 "-
Vl
w
"'""
Q_
vi LO
LL
U>
"' ?. z
"'
y
>- w >
~
z
0 0
z "'
<(
w
'"
f-
"' "'
Chapter 36
Duties of the
Chief Permanent Way Inspector
Document History
Issue Date Description
Authorised By:
Signature:
t~.ll.~-~ .~J2 -
~ -....
\
Date:
MOHD RAMLI MOHD NOH
General Manager Pennanent_Way
2 8 MAY 2015
Keretepl Tanah Melayu !erhad
Kuala lumpur
TABLE OF CONTENTS
36.1.2 The CPWI shall be responsible, in general, for the safe, efficient and economical
maintenance of:
36.2 INSPECTIONS
The CPWI shall:
36.2.1 Travel as frequently as possible on the locomotive or in the rear vehicle of fast trains to
observe the condition of the track and communicate freely with Drivers about locations
needing attention by Permanent Way staff.
36.2.2 Inspect, on foot or by trolley and by train, on each Section in his Region, (according to
the schedules laid down in Chapter 50) the following:
Note:
The CPWI shall not stay away from his Headquarters when on duty without the previous
sanction of the Regional Engineer. He shall give advice to the Regional Engineer
before-hand of what work or inspection he intends to carry out.
The CPWI shall enter every day in his weekly diary a complete record of the work done
each day, including locations and structures inspected and Gangs visited and checked.
36.4.1 Enclose a copy of his Weekly diary for the week indicating the Kilometrages of track
inspected.
Note:
36.4.3 Describe the general condition of track and other structures like bridges and tunnels
inspected, indicating special works required to be done in the near future, if any.
36.5 CORRESPONDENCE
The CPWI shall forward to the Regional Engineer:
• Correspondence
• Timesheets
• Important periodic returns, as indicated by the Regional Engineer from time to time
• Weekly and monthly reports of PWis with his remarks
36.6.1 See that the Ganger's check roll is correctly entered up and after calling over the names
of the employees, initial the book.
36.6.2 Inspect the work done on the previous days by the Gang and instruct the PWI/Ganger as
required.
36.6.3 Check the progress to see that it is commensurate with the Works Plan as per Chapter
20.
36.7.1.3 Report to the Regional Engineer any serious delay or bad practice.
36.7.2 In the event of a slip or washout or other emergencies, the CPWI is authorised to
arrange immediately for Ballast trains if the situation so warrants.
36.8.4 A correct account is kept by all the PWis of all materials received and despatched.
On the basis of the work load assessed as in Annexure 20.3, Line Possessions required
for carrying out maintenance and other works shall be planned. For this purpose, the
CPWI shall prepare a statement as in Annexure 20.10 and submit it to the Regional
Engineer. The Regional Engineer shall review the programme and submit to the
Permanent Way Headquarters office in order to. finalise the programme for Line
Possession duration and locations with the Operations Department.
The CPWI shall then advise the final programme to the PW/s concerned.
36.12 PATROLLING
The CPWI shall carry out the functions specified in Chapter 47.
• Line Possessions
• Speed restrictions
• Ballast Train working
• Other related issues
36.14.2 The Signalling and Communication Division for
36.16.2 The Officer handing over shall leave a written note with the following particulars:
36.16.2.1 List of special works planned or in progress and the Regional Engineer's instructions if
any.
36.16.2.2 Formation giving trouble or needing constant inspection.
36.16.2.3 Locations prone to heavy rain or liable to flood. Locations to be watched for any other
reason.
36.16.2.4 Stocks of serviceable sleepers and locations.
36.16.2.5 Requirement of ballast and particulars of Ballast Trains at work and the work to be done
by them.
36.16.2.6 List of Permanent Way materials in his charge.
36.16.2.7 List of curves with superelevation.
36.16.2.8 List of bridges which require special attention.
• All turnouts, and cross check their condition with the reports of the PWis.
• All sleepers in stock.
• All important Permanent Way material in stock.
• The alignment and superelevation of all curves
• All special works.
• Any other items required by the Regional engineer.
Chapter 37
Duties of the Permanent Way
Inspector
Do cument History
Issu e Date Description
Authorised By:
Signature:
Date: 2 8 MAY 2015
TABLE OF CONTENTS
37.1 GENERAL
The General Manual in the current KTMB Rules and Regulation Book contains Rules
on the responsibilities of the Permanent Way Inspector.
37.2 JURISDICTION
A Permanent Way Inspector (PWI) is appointed to be in charge of a section. The section
will consist of a number of maintenance unit, lengths, each maintained by a Gang or
mobile gangs.
• The condition of the Permanent Way and works under his charge.
• The proper supervision of the work of the Gangs.
• The general conduct of affairs relating to Permanent way throughout his section.
37.4 SAFETY
The PWI shall be responsible for the safety of track in his section. He shall bring to the
attention of the CPWI and, if necessary, of the Regional Engineer, conditions which are
beyond his powers to correct.
Permanent Way. The materials shall be properly stacked, and kept well clear of the
line. Some small fittings may be kept with Gangers, if necessary.
37.7 INSPECTIONS
37.7.1 The PWI shall inspect by trolley or on foot all the route length in his section as often as
may be necessary but at least according to the Schedule in Chapter 50. He shall carry
with him, during such inspections, a track gauge-cum-level. He shall periodically check
the gauge, cross-level and alignment of the track.
37.7.2 In addition to such visual inspections, the PWI shall accompany the track recording Car
runs on his length. He shall study its recordings as are made available to him to identify
the nature and location of track defects that need attention.
37.7.3 The PWI shall also ride on trains either in the locomotive or at the trailing end of the
fastest train on his Section, as laid down in Chapter 50.
37.7.4 The PWI shall give attention to drainage, and earthwork and inspect bridges and tunnels
in his Section as laid down in Chapter 23, 31, 41 and 42.
37.8 DOCUMENTS
The PWI is responsible for obtaining the following current documents:
• A copy of the current Working Timetable, with all correction slips and appendices
there to.
• Permanent Way Manual.
• KTMB Rules and Regulation Book
• Track Safety Handbook
• Track Register
37.11 PROSPECTING
The PWI shall carry out the prospecting work as specified in Chapter 20 to determine
the work to be done in the next year and the materials and manpower required therefore.
o Programme the work of Gangs in his Section to fit in with the programme of the
Machine Unit.
• Arrange such assistance as is required by the Machine Unit to ensure maximum
effective output.
• Mark out transitions, cant, station number, curve peg/monument, 1-Caution updates,
fixed points, obstructions and general lifts ahead of tamping and lining. (For details,
refer to Chapter 22).
• Spot check of work done by the Machine Unit for quality.
• Complete the work within the time limit of the Line Possession (Chapter 49).
37.13 TURNOUTS
37.13.1 The PWI shall inspect all turnouts in his Section according to the Schedule laid down in
Chapter 50 and the details in Chapter 40.
37.13.2 He shall lend all necessary assistance to Turnouts Gangs when they work in his Section
and check their work.
• Look-out men
• Flagmen
37.15.3 He shall arrange for periodical reading of the relevant Rules to all his staff essentially
required to know them.
• Submit the required notices, for Line Possession, speed restrictions and cautious
driving.
• Provide and erect Warning Boards at the appropriate places and times.
• Arrange for hand signalmen and look-out men.
• Send 1-Caution update everyday about speed restrictions and cautious driving that
are required ..
(Refer to Chapter 45 for details).
37.16.2 Where new lines or sidings are constructed but not taken over by the Operations Staff,
the PWI shall spike, wedge and clip lock the relevant switches and keep the keys with
him (see Chapter 51, clause 51.1 0).
37.17 PATROLLING
The PWI shall ensure that:
• The periodical patrolling as laid down in Chapter 47 is carried out regularly in his
Section.
• Special patrols in times of bad weather and on track with LWR in hot weather are
carried out as required.
• Any other patrolling ordered by the General Manager Permanent Way is effectively
done.
• Checking clearances of structures and any temporary erection on the line side.
• Reporting infringements to the CPWI.
(Refer to Chapter 11 for details).
• render assistance
• preserve and record clues and evidence
• report to his superiors
• make arrangements for deployment of the available manpower for emergency
duties.
37.20.2 On receipt of Driver's report of track defects, the PWI must inspect the sile, attend to the
track and arrange to remove or modify the speed restriction imposed on the basis of
Driver's report as laid down in Chapter 23, Clause 23.9.3
23.9.3 Reports from Train Crew and Traffic Staff regarding track defects:
23.9.3.1 The Driver who experiences or notices undesirable conditions of track (such
as, rough running, visual buckling tendency, water flowing across the track or
heading on the track, etc.) will stop his train at the next station and advise the
Station Manager as per clause 7 section C of the current Rules and
Regulations book indicating the defect noticed, like rough riding, floods, fallen
trees and slips. The Driver shall also use his mobile phone and inform TCCC.
The Station ManagerfTCCC operator will advise all concerned. Trains shall
be allowed into the Section only after the site has been inspected and
cleared by the PWI.
23.9.3.2 On receipt of Driver's report of track defects, the PWI shall:
• see that the Ganger's attendance record (Check Roll) is correctly entered up and
initial it after checking the number of employees present.
• arrange for all checkrolls to reach the Regional Engineer Office on the date fixed
according to Regulations, duly certifying that they are correct.
• fines
• degradations
• dismissals
• promotions
• loan to another department
• permission to leave service.
• join another department.
• Acquaint himself with the boundaries of all Railway Reserves on his Section.
• Report promptly to the Regional Engineer any obvious or suspected encroachment.
• Stop anyone from doing any of the operations shown below,
Pending instructions from the Regional Engineer.
Excavation.
Cutting or alteration to drains
- Erection of buildings
Cutting oflrees
Depositing earth
• Ensure that no survey stone on railway boundary is disturbed.
• Put rail posts, painted white for the top 0.5 m, where there is cultivation or mining
adjacent to Railway land. These posts shall be fixed at a distance of 1 m away from
the boundary stones.
• Report any activity likely to affect the Railway, even outside the boundary.
37.26.2 In execution of works involving the Signalling Unit, he shall liaise with the signal inspector
so that engineering and signalling works progress simultaneously (see Chapter 51,
Clause 51.5).
• Keep an account of all ballast unloaded in his section with reference to the numbers
of the quarter kilometre posts between which the ballast is dumped.
• Report in writing to the Regional Engineer if he receives ballast trucks not fully
loaded from the quarry or if the ballast is of the wrong size.
• Accompany the Ballast Train working in his Section except in case of emergency.
• If unable to accompany, supply detailed instructions to Ballast Guards on location
where the train is to work.
• Make all efforts to avoid delay and minimize working time of the Ballast Train.
• Ensure that the provisions in Chapter 29: Procurement and Distribution of
Ballast are complied with.
• Special works with their progress and instruction from superior Officers if any.
• Locations requiring special attention
• Locations affected by severe rain or prone to flooding
• List of Level Crossings
• Stock of materials in his possession.
• Number and location of serviceable sleepers in stock, which must tally with the
weekly report of sleeper renewals.
• List of other spare Permanent Way materials in the PWI's charge.
• List of curves with super-elevation and transition details.
• List of Gangers and other staff.
• Section Register posted up-to-date.
• List of bridges and culverts, turnouts and other details of the section.
37.32 CORRESPONDENCE
37.32.1 The PWI shall address all communications to his Regional Engineer or the General
Manager Permanent Way through the CPWI. Timesheets and relevant returns shall be
forwarded direct to the Regional Engineer. All other returns and certificates shall be sent
to the CPWI. For this purpose a calendar of returns to be submitted by the PWI shall be
maintained in his office.
37.32.2 The PWI shall submit a weekly report indicating the Kilometrages of the lengths
inspected by them during the week on foot, trolley or by train and giving brief particulars
of the conditions of the track (The Regional Engineer will maintain a diagram).
• Speed of trains.
• Non-observance of Signals and Caution Orders (See Chapter 45, clause 45.9).
• Slack system of working.
37.33.2 The Table T -37.1 below gives a ready reckoner for speed in km/hr from the time taken
for a train to travel a 250 m long stretch (quarter kilometre post).
Table T-37.1
Table of Speed Versus Time For A Train to travel a 250 metre stretch
I• ;,!,;c
. . {. . .. •" .· ..
5 180.0
10 90.0
12 75.0
15 60.0
18 50.0
20 45.0
22 40.9
25 36.0
27 33.3
30 30.0
35 25.7
40 22.5
50 18.0
60 15.0
70 12.9
80 11.3
90 10.0
100 9.0
110 8.2
120 7.5
130 6.9
140 6.4
150 6.0
37.34.2 He shall, in turn, examine his staff in such instructions and rules as apply to their work
like the exhibition of signals, protection, and working of Level Crossing gates.
LIST OF ANNEXURES
Annexure 37.1 List of subjects to be reflected in the Permanent Way
Inspector's Section Register.
1.0 Administration
2.1 Formation:
All locations giving frequent trouble with brief history and remedial measures adopted.
2.3 Grades:
• Details of length and locations of track laid with long welded rails.
• Incidence of buckling and their location.
• Maximum and minimum rail temperatures observed.
2.5 Curves:
2.6 Ballast:
2. 7 Creep Adjustment:
• Brief particulars of all types of rail failures, including weld failures connecting
references to the failure reports.
• Month-wise distribution.
3.2 Important repairs and renewal to bridges:
• Extent of damage.
• Particulars of rainfall,
• Arrangements made for restoration and
• Remedial measures adopted.
3.4 List of vulnerable locations
4.0 Miscellaneous.
Chapter 38
Duties of the Ganger
Document History
Authorised By:
~r I
Signature:
MOHO RAMLI MOHO NOH
Date: General ~anager Pennanent W@'L 2 8 MAY 2015
Keretep1 Tanah Melayu Berhad
Kuala lumpur
TABLE OF CONTENTS
38.11 WORKS NEEDING CAUTIOUS DRIVING OF TRAINS .............. ........ ................ ............... 4
38.1 GENERAL
Each PWI shall see that in every Gang. employed in his length of line, there is a Ganger
or other competent person in charge. The General Manual in the current KTMB Rule
and Regulation Book contains rules on the knowledge and responsibilities of the
Ganger. In Case of any contradiction between the contents of the current KTMB Rules
and Regulation Book and the provisions below the former shall prevail.
38.3 EQUIPMENT
38.3.1 The PWI shall ensure that every Gang is supplied with a Track Gauge, a hand level,
hand signal flags, hand signal lamps and obstruction signals, in addition to other tools
and equipment prescribed by the General Manager Permanent Way.
38.3.2 The Ganger shall see that the equipment supplied to him kept in proper order and ready
for use.
38.5 TRESPASSING
Each Ganger shall endeavour to prevent trespassing by any person or animal especially
buffalo, cattle and wild elephant on his length of line or within the fences of such line.
Animals found within the fences or on the line shall be removed immediately.
38.6 FIRE
If a fire occurs on any railway premise or near any portion of the Railway where
gangmen are employed, they shall endeavour to extinguish it and prevent it from
spreading.
commence the work before the PWI or his superior can arrive, the Ganger may
commence the work at once and shall himself see that the provisions of Section J of the
General Manual in the current KTMB Rules and Regulation Book are observed.
38.10 BLASTING
The Ganger shall ensure that no blasting operations are carried out on or near the
Railway except as permitted by the PWI or his superiors.
38.15 PATROLLING
38.15.1 Once a week, the Ganger shall interchange duties with the Patrolman and inspect his
whole length.
38.15.2 During periods of heavy rainfall, the Ganger shall organise patrolling of his length, action
as in Chapter 47, Clause 47.7.2.4 being taken in case danger is apprehended.
LIST OF ANNEXURES
Annexure 38.1 Items to be looked by a Ganger
1.1 Top
1.3 Level
1.6 General
Are there any gaps or loose wires in fences which might encourage trespassing?
If any excavation near or under the lines is in hand, is the track properly supported?
Is any work proceeding which requires a speed restriction?
Are all Level Crossing gates which are required to be kept closed in the normal position
are closed?
Is any work progressing close to the tracks, and if so, are proper clearances being
maintained?
2.1 Drains: - (As required by local needs and in anticipation of weather conditions).
Are the drains clear and working?
Is there any scouring round abutments and wing walls of culverts and river bridges?
Are there any springs issuing close from the slopes of cuttings or embankments?
Are there any signs of slips?
Are the drains and troughs in cutting or embankment slopes in good order?
Are there any cracks in the slopes?
Is any water from outside the railway flowing on to railway property without authority?
Are animals, (such as rabbits) harboring in the slopes?
Are there any signs of new settlement cracks or movement in retaining walls, bridge
piers or abutments, arches, etc.?
Are the highways and approach roads, maintained by the Railway, in good repair?
Are the men's and tool huts in a clean and tidy state?
3.0 PERIODICALLY
Are there any defects or cracks in the rail ends apparent when the fishplates are
removed?
Do any expansion gaps need adjusting?
Do any rails need anchoring?
3.3 General Repairs to Track
Is the length clear and tidy, free of rubbish and scrap materials?
Where grass, etc. has been burnt, has the fire been completely extinguished at the end
of the day's work?
Chapter 39
Track Maintenance Operations
Authorised By:
\
r
Signature:
Date: MOHO RAMLI MOHD NOH 2 8 MAY 20l5
Keret-api Tanah Melayu Berhad
Kuala lumpur
©KTMB Rev. O Page 1 of 59
e~I~TIIII
Permanent Way Manual Part V
Track Maintenance Operations Chapter 39
TABLE OF CONTENTS
39.1 GENERAL
39.1.1 Works Planning has been described in Chapter 20. The operations involved in
planning of track works are summarised in this chapter.
39.1.2 Track maintenance systems have been covered in detail in Chapter 21 of the
Manual. This chapter describes the steps that are required to be taken for carrying
out various track maintenance operations.
39.1.3 The chapter at its end, lays down the priorities for attending to track defects and
the action to be taken for their rectification.
39.2.1.4 Estimate the amount of work to be executed in the ensuing year and record in
39.2.1.5 Form PTM2 in Chapter 20, Annexure 20.3.
39.2.1.6 Summarize the man power requirement in Chapter 20, Annexure 20.3.
39.2.1.7 Draw up the Annual Maintenance Programme,
39.2.1.8 Prepare the monthwise work schedule for all 12 months in Form PTM3 in Chapter 20,
Annexure 20.4 and submit to the CPWI.
3&.2.2.5 Bring to the notice of CPWI & Regional Engineer, if there is a significant variation to the
original approved programme.
39.2.2.6 Send a copy of the revised month wise work schedule to the Ganger before the
beginning of the month.
39.2.2.7 Determine the works to be executed in each week for every gang.
39.2.2.8 Allocate the deployment of man power for each day in Form R1 in Chapter 20,
Annexure 20.6.
39.2.2.9 Send the weekly programme on every Friday to the Ganger (for the works to be executed
in the following week).
39.2.2.1 0 Collect the Form R1 from the Ganger at the end of the week, after the execution of the
work.
39.2.2.11 Check that the actual work in the field is carried out in accordance with the approved
programme.
39.2.2.12 Evaluate the output of work and man days spent in Form R2 in Chapter 20, Annexure
20.7.
39.2.2.13 Submit the weekly report to the CPWI as in Chapter 20, clause 20.9.4.
39.2.2.16 Send the Form PTM3 to the Regional Engineer before 5th of the following month.
39.2.2.17 Check frequently whether progress is according to the plan and whether quality is
according to the prescribed technical standards.
39.2.3 Action by the CPWI and the Regional Engineer.
• The CPWI shall satisfy about the correctness of the estimate of materials given by
PWis in Form PTM1 (Chapter 20, Annexure 20.2). He shall conduct checks of at
least 5% of the requirements.
• The Regional Engineer shall conduct check at random.
• Review the manpower requirement of PWis submitted in Form PTM2 (Chapter 20,
Annexure 20.3) and arrange for supply of additional manpower or reduce the scope
of the work to be executed.
• Scrutinize the month wise work schedule submitted by PWis in Form PTM3
(Chapter 20, Annexure 20.4) and modify the programme taking into account the
availability of resources and relative priorities amongst the needs of different PWis.
• Decide the works to be executed by outside agencies.
• Return the modified programme to the PWis.
• Programme for the deployment of "on-track machines" in a statement (Chapter 20,
Annexure 20.9) and forward to Permanent Way Headquarters.
• Obtain the finalized programme for machines from Headquarters and advise PWis.
• Plan for the Line Possessions in a statement in Chapter 20, Annexure A - 20.1 0.
• Finalise the programme for Line Possession in consultation with the Operations
Division and advise the PWis.
• Check that the work carried out in the field is in accordance with the approved
programme.
• Give directions if the PWis suggest a deviation to the approved programme due to
special circumstances.
• Get the weekly report from PWis in Form R2 (Chapter 20, Annexure 20.7) to
review the progress and to monitor the utilisation of manpower.
• Get the monthly report in Form PTM3 (Chapter 20, Annexure 20.4) from PWis on
5th of the following months.
• Check whether progress is according to the plan and quality is according to the
prescribed technical standards.
• Keep a Master Record of track maintenance works and evaluate unit cost of each
maintenance operation.
• Identify areas of weakness in maintenance procedures and take remedial action.
o Compare the performance of various PWis and rectify operations involving abnormal
costs.
o Send extracts from the Master Record to the Headquarters.
• Utilise the data generated for effective management of the work.
• Working hours
• Skill and expertise of the men in the concerned job
• Direction and supervision
• Environment and working conditions
• Duration of Track possession likely to be made available.
• Facilities for mobility of men and materials.
Note:
The manpower indicated does not cover the labour required for loading and transporting
materials and equipment to site and again taking them back after the operation is
completed. it does not also include the workers required for protection of track.
• Examination of rail ends and measuring of rail wear, hog and batter.
• Changing of a rail.
• Grinding burrs of rail ends.
• Cropping of rail with hogged or battered rail ends.
• Repair welding for wheel burns.
• Manual greasing of rails.
• lnsitu welding of rail.
• Pulling back rail creep.
• Destressing of LWR.
39.4.1 Examination of Rail Ends and Measuring of Rail Wear, Hog and Batter
39.4.1.1 No of men required
Ganger and one man.
39.4.1.2 Equipment required
• Protect the track as per General Manual in the current KTMB Rules and
Regulation Book.
Step 3 Cleaning
• Clean both the rail and the fishplates with a scraper and a wire brush.
• Apply petrol or kerosene and wipe with a cloth.
Step 4 Examination
• Inspect the rail with a mirror and magnifying glass for cracks and defects.
• Record the condition of the rail.
Step 5 Measuring wear
• Put a chalk mark on the rail at 20mm on each side of the rail joint and at
the same place on the fishplate for wear on fishing surfaces.
• Measure the wear of the rail using the special gauge (sketch at Figure
39.1).
• Record the wear of the rail.
• Measure the wear on the fishplate by putting the gauge perpendicular
and against the fishplate.
• Record the wear of the fishplate.
Step 6 Measuring hog and batter
• Place a one meter long straight edge over the rail table centrally over the
joint.
• Measure hog as indicated in Chapter 27, Clause 27.3.5 and record.
• Measure the rail end batter as indicated in Chapter 27, Clause 27.3.6
and record.
Step 7 Assembling the joint
• Rail tongs.
• Spanner.
• Tools for sleeper fastenings.
• Rail cutting machine.
• Rail of appropriate length (not less than 6 m) of same section. quality, age and wear.
• Joggled fishplates or ordinary fishplates as required.
• Clamps for LWR/CWR.
• Wooden Blocks.
• Welding Portion
39.4.2.4 Operations:
Step 1 Preliminary Work
• Arrange for half an hour line possession for fish plated track and 2Yz
hours for CWR/LWR track.
• Select a rail of the same section age and wear as the rail requiring
replacement.
• Test the rail ultrasonically prior to bringing to site
• Bring the rail to the site.
• Keep ready spare fittings, tools and equipment.
Step 2 Measurement
!
• Loosen fishplates of rail to be replaced. I
39.4.2.5 DONT'S
Two men.
39.4.3.2 Equipment required
• Protect the track as in the General Manual in the current KTMB and
Rules and Regulation Book.
Step 3 Cleaning
• Remove by a grinder all rough edges and burrs at the rail ends.
• Keep the rail ends free from brake dust, dirt and other foreign materials.
Step 3 Measurement
• Mark a distance equivalent to half the pitch of the fish bolt holes from end
of the battered rail with a chalk.
• Check that there is no rail flaw at this location.
Step 4 Cropping
2 men (Additional men for leading gas cylinders and other equipment),
39.4.5.2 Equipment required
Wire brush
Special torch
Microfine allo)( powder
39.4.5.3 Operations
o Clean the locations having wheel burns with a wire brush and keep it free
from any foreign matter.
o Grind the surface.
o Check for any crack.
Step 2 Preheating
• Spray micro fine alloy powder over the worn out surface with the help of
special equipment and bellows.
Step 4 Heating and finishing
• Heat the base metal to enable the powder deposit to get bonded by
diffusion. Grind and finish the top surface level.
39.4.5.5 Precautions
One man.
39".4.6.2 Equipment required
• Do not allow the grease to spill on the top of rail. Keep the top of rail table clean.
39.4.7 In-situ welding of rail
Rail thermometer.
39.4.7.3 Operations:
• Preheat the rail ends for 450mm on either side to make them slightly hot.
• Demould after the stipulated period.
• Remove the excess metal.
• Trim the rail top and sides when red hot.
• Trim the foot risers, after the rail has cooled down.
Step4 Finishing
Step 6 Recording
39.4.7.4 DO'S
o Deploy only trained welders whose fitness for the job is certified.
• Ensure that the techniques advocated by the firm for welding are complied.
39.4.8 Pulling back rail creep
39.4.8.1 No of men required
Depends on the quantum of work to be done.
39.4.8.2 Equipment required
Chamfering equipment
Rail cutting equipment
Hole drilling equipment
39.4.8.3 Materials required
Expansion liners
o Decide on the length to be dealt with in one operation. Pulling back has
to be done between two anchor location. This could be the portion of
track between two switches and crossings located at a distance apart.
• Calculate the amount ol pulling back required for each rail.
• Choose an anchor location from where pulling back can start.
• Arrange for block.
• At the anchor location keep the rails square (cut the rails to bring it to
square or to the amount of pulling if required).
• Pull back the rails with a creep pulling equipment or other mechanical
device.
• Measure rail temperature.
• Keep standard expansion gap to correspond to the rail temperature.
• Insert appropriate expansion liner at the joint.
• AI the finishing end of the work, put a closure rail or put a new rail equal
to the gap and available rail length.
39.4.8.5 DONT'S
20 men
39.4.9.2 Equipment required
Rail tensor.
Rollers.
Rail thermometer.
Mallets wooden.
Rail tongs.
Crow bars.
Rail piece.
3S.4.9.3 Operations (refer Chapter 25, clause 25.6.5)
• Crow bar
• Beater
• Spanner
• Tools for sleeper fastening
• Chalk .
39.5.1.3 Operations
• Pick the core of ballast under sleepers that are out-of-square or not
spaced correctly, with the "pick" end of beaters.
Step4 Squaring
39.5.1.4 DONT'S
39.5.2 Lateral Shifting on account of crushed rail seat (for timber sleepers)
39,5.2.1 No of men required
2 men
39.5.2.2 Equipment required
Step 4 Marking
Step 6 Gauging
• New sleepers
• Sleeper fastenings
39.5.3.4 Operations
Step1 Removal of ballast and sleeper fastenings
• Remove ballast (in the crib and shoulder and from under the sleeper to
loosen it).
• Remove (rail to sleeper) fastenings.
Step 2 Removal of base plate
• Drill holes in the sleeper for spikes with a jig and drill.
Step 5 Gauging
Step 6 Finishing
o As far as possible bring new sleepers with pre-drilled holes duly treated.
• If lifting of the track to remove the sleeper is done in exceptional cases, it shall be
done under close supervision. The track shall not be lifted more than 40 mm with
rail jack in one operation.
• The sleepers to be renewed shall be so selected that for every sleeper renewed, at
least 8 sleepers an either side remain undisturbed. Thus, at a time, only one in 9
sleepers may be renewed. If more than 1 in 9 sleepers are to be renewed, the work
shall be carried out in different stages, allowing a period of 7 days for consolidation
between two stages.
39.5.4 Renewal of concrete sleepers by manual method
Refer Annexure 39.4
39.5.5 Procedure for adjustment of gauge for timber sleepers
39.5.5.1 No of men required
Ganger and 2 men
39.5.5.2 Equipment required
• . Measure the gauge on all the sleepers systematically over rail length and
write variation as + and - on the sleeper with chalk.
• Mark sleepers requiring regauging in chalk, keeping in view variation
permitted in absolute gauge as well as sleeper to sleeper variation.
Step 2 Correction
• Drill the new holes correctly in sleeper if it is a direct type fastening. The
holes shall be drilled at a location such that the gauge on the sleeper will
be:
i. Within absolute gauge variation limits
• Where necessary, replace a few sleepers (one sleeper out of five will be
sufficient to obtain uniformity in gauge).
39.5.5.4 DONT'S
• Do not regauge frequently wooden sleepers with direct type of fastening to avoid
"spike-killing".
• Do not correct gauge without squaring the sleepers.
2 men
39.6.1.2 Equipment required
• Put a mark on all loose fastenings and missing fastenings with a chalk.
• Count the number of loose and missing fastenings
• Identify the cause of looseness if necessary by removing the fastenings.
Put them back immediately.
• Tighten loose fastenings, if it is found effective.
• Remove ineffective loose fastenings from one sleeper at a time.
• Check how many can be reused.
• Arrange for the requisite number of new fastenings.
• Check that all fastenings have been placed correctly and are tight.
• Check the track gauge.
Jack or crowbar.
Tools for sleeper fastenings
39.6.2.3 Materials required
Step 1 Identification
• Protect the track as in the General Manual in the current KTMB Rules
and Regulation Book.
Step 3 Replacement
• Check that rubber pads and fittings are correctly placed and are tight.
• Check the gauge.
4men
• Ballast fork/rake
• Handrammer
• Template
• Baskets
• Mono rail wheel barrow.
Ballast
39.7.1.4 Operations .
• Profile the ballast to the specified dimension using a template and forks.
• Consolidate the ballast by hand rammers.
• If there is deficiency in ballast, show it in centre of track
• Line the top and bottom edges of ballast section using a cord
• Where the ballast is in excess of requirement, remove the excess
quantity and stack on the ground.
Shovel
Pick axe
Basket
39.8.1.3 Operations
Ballast
39.1 0.1.4 Operations
©KTMB Page 23 of 59
Permanent Way Manual Part V
Track Maintenance Operations Chapter 39
Step4 Checking
Normally lowering of track shall be avoided, as it affects the ballast cushion under the
sleepers and disturbs the consolidated bed. Where it has to be resorted to, the following
action shall be taken
Step 2 lowering
• Check the final longitudinal level of track with reference to the pegs.
• Check that the cross levels and super-elevation are satisfactory.
• Check that vertical curves are provided in sags and summits.
• Surrender the line possession.
• Continue the speed restriction till the track is fully stabilised.
39.11.1.3 Operations
Step 2 Cleaning
Step 3 Measurement
• Spanner
• Tool for sleeper fastenings.
• Special gauge for measuring wear.
New fishplates.
39.11.2.4 Operations
• Find out the wear of the rail and fishplate as indicated in Clause 39.11.1.
• Arrive at the sum of rail and fishplate wear.
Step 2 Finding size of shims
The rail shall require replacement or the rail ends may need cropping if the wear exceeds
the limits specified in Chapter 12, Clause 12.13.
Step 3 Oiling
• Apply the approved lubricant (oil or grease) on both the rail and the
fishplates at the fishing surfaces.
Graduated gauge.
Rail thermometer.
Rail pulling equipment.
Spanner.
Step 1 Measurement
Step 4 Adjustment
Scraper
Wire brush
Approved lubricant
Magnifying glass.
Mirror
39.11.4.3 Operations:
Step 1 Protection
• Ensure all obstructions are clear of the line, safety requirements are met
and then PICOW to advise PICOP to surrender the line possession.
39.11.4.4 Precautions
• Complete Levelling.
• Partial Levelling.
• Joint Levelling.
• Lining.
• Realignment of curves.
• Attention to lurches in approaches of bridges and level crossings.
Levelling may be done continuously over a stretch by any of the following methods
• Beaters.
• Portable Tampers
• Machines.
39.12.1.1 No of men required
Tamping machine.
Manual lifting and packing equipment.
39.12.1.3 Operations:
• Tighten the loose fastenings and replace broken and missing fastenings.
• Check and adjust gauge.
• Check the quality of work.
• Consolidate the ballast.
• Bring the machine to adjacent station.
• Clear the block section and surrender line possession.
Step4 Submission of Proforma
2. Equipment required
Crow bar.
Pick axe.
Shovel.
Beater.
3. Operations
Step2 Sighting
• Ganger shall sight one rail (the sighting rail) from a distance of about 30
meters on straight track.
• On curves, he shall sight the outer rail.
Step 3 Stewing
Step 4 Checking
1. No of men required
2. Equipment required
3. Operations
Step 1 Preliminary Work
10 men
39.12.5.2 Equipment required
• Inspection by PWI.
• Mark station at 1Om apart.
• Measure the versines and record.
• Indicate if there is any restriction to slewing.
• Draw the cumulative frequency curve.
• Decide whether to realign the whole curve or adjust a part of it locally.
• Check the distance to the stakes once during the speed restriction
period.
• Recheck the versines and super elevation.
• If any major discrepancy is noticed, repeat the procedure.
1. No of men required
4 to 6 men for track with wooden sleepers.
2. Equipment required
• Resurfacing of Crossings.
• . Replacement of worn out or damaged Switches or Crossings.
1. No of men required
2men.
2. Equipment required
• Spanner
• Hammer
• Welding generator
• Welding electrodes
• Magnifying glass
• Grinder
• Profile gauges.
3. Materials required
• Spare fastenings .
4. Operations:
Step 1 Preliminary Work
• Weld on edge on the nose, starting from nose tip. Do not carry out
continuous welding.
• Weld on left wing rail at the edge.
• Weld on right wing rail at the edge.
• Provide weld layer to cover the entire worn-out area in separate beads
so as to keep the temperature low.
• Deposit the runs longitudinally following the weld sequence so as to
cover half portion of the previous run.
• Manipulate the speed to have uniformity in the built up layer.
• Lightly tamp the weld with a ball point hammer.
• Clean the weld bead with a wire brush to remove slag.
• Use a chipping hammer to remove spatters.
Step 6 Hot peening
• Deploy only trained welders, whose competency for the job is certified by
Permanent Way Division
• Ensure that the techniques and instructions of the firm supplying electrodes are
complied.
• Adjust the gauge and repack the sleepers.
39.13.2 Replacement of worn out switches and/or crossings
1. No of men required
3. Materials required
• New switches
• New crossing assembly
• Spare fillings like nuts, bolts, fishplates and distance blocks.
4. Operations:
• Arrange for line possession of about 2 hours for changing switches and
crossing and about 1/2 hours for changing crossing alone.
• Coordinate with signalling staff if the switch is interlocked.
• Inspect the switches and crossings and arrange for track components
which are missing or defective.
• Renew unserviceable sleepers and fix base plates/slide chairs in correct
position.
• Keep the new switches and crossing opposite the existing assembly.
• Check that the switch rails are not twisted.
• Provide the bend in turn out side of the stock rail at T.T.S., in case of
over-riding switches.
• Mark the position where new switches and crossings will be laid.
• Drill holes for signalling rods/stretcher bars etc.
• Open the stock rail joint, joint connected to lead rails and joints near the
toe and heel of crossing.
• Remove the rail sleeper fastening of the switches and crossing portion.
• Disconnect the stretcher bars.
• Take out the existing switches and crossing assembly.
• Clean the contact surfaces with a wire brush.
• Grease the fishing surfaces and slide chairs.
• Apply oil to all bolts and nuts.
Step4 Insertion of new switches and crossings.
5. Precautions
• Replace stock and switch rails as a complete set, including lead rails and one
approach rail.
o Ensure that ballast is clean and drainage is effective.
2. Equipment required
• Pick axe
• Crow bar
• Beater
• Shovel
• Tools for fastenings
• Spanner
0 Baskets
3. Materials required
• Rail
• Sleepers
• Fittings
• Bolts and nuts
• Distance blocks
• Anti-corrosive paint
4. Operations
Step 1 Preliminary Work
Step 3 Over-hauling
• Rail failure.
• We I~ failure.
• Buckling.
1. No of men required
8men
2. Equipment required
• Rail cutting machine.
• Rail tensor.
• Wooden blocks.
• Aluminothermic welding equipment.
• Equipment for destressing.
3. ·Materials required
• 6 m or longer rail piece of same section type and wear.
• Screw clamps.
• Special fishplates.
4. Operations
Step 1 Preliminary Work
• Join the fractured rail using special fishplates and screw clamps, if the
gap is less than 30 mm.
• If the gap is more than 30 mm, use a closure piece with clamp.
• Shift the sleepers on both sides near the fractured portion or support the
fractured portion on wooden blocks.
• Pack the sleepers.
• Restore the traffic at 10 km/hr speed restriction.
Step4 Destressing
Repeat the operations as in Clause 39.15.1 except the use of joggled fishplates and
clamps instead of special fishplates.
Step4 Destressing
Table T-39.1
1. Isolated spots with track parameters exceeding the prescribed tolerances in:
Gauge Spot gauging, if gauge is not uniform. Clause 3R5.5
Vertical alignment Lift the track & pack the loose sleepers. Clause 39.12.2
Attend to the joints Clause 39.12.3
Lateral Alignment Remove the kinks & slew the track if
Clause 39.12.4
necessary and pack.
Twist Correct the longitudinal levels over the Clause 39.12.1 & Clause
affected length. the twist. 39.12.2
2. Short scattered patches with poor running or where track parameters exceed the prescribed
tolerances in:
Gauge Regauge if gauge is not uniform. Clause 39.5.5
Replace the defective sleepers. Clause 39.5.3
Vertical Alignment Lift, level and tamp.
Attend to the approaches of Bridges,
Clause 39.12.2
Level Crossing and Switches &
Crossing.
Lateral Alignment Do local slewing and tamp Smoothen the Clause 39.12.4, Clause
curve by local adjustment. 39.12.5 & Clause 39.12.6
Twist Attend to longitudinal levels over the
Clause 39.12.1 &
affected length, which will improve the
Clause 39.12.2.
twist.
3. Long stretches of bad track indicated by Track Quality Index (TQI)-0 involving the following
parameters.
Gauge Continuous re-gauging Clause 39.5.5
Vertical alignment Lifting
Levelling. Clause 39.12.1
Tamping.
39.16.2 The PWI shall arrange to plan the required repairs, reporting to the CPWI where
such repairs are beyond his capacity.
Rev.O Page 43 of 59
Permanent Way Manual Part V
Track Maintenance Operations Chapter 39
Table T-39.2
Operations relating to track components
Wheel burns
Rolling defects
I I faults
Wooden Slit
Sleeper
Concrete
Sleeper
Loose inserts
Seizure of elastic clip within Apply oil or special grease on the central leg clip and
the insert. eyes of the insert. Repeat the process periodically at
prescribed intervals.
LIST OF FIGURES
Figure 39.1 Special gauge for measuring wear of rail.
LIST OF ANNEXURES
Annexure 39.1 Typical example of pulling back rail creep.
Fig. 39.1
\
\
l
I
I
I
/
l
/,.,...,,.., ......
I
I
I
I
I
I I
I I
I I
I
I
I
II
/WORN-OUT RAIL
I I ,
I
I
I I
I
I I I' '
1,;
I
..............
........
-.... --- -....
( )
L---------------------------~
Fig. 39.2:
2
Cl
z
<
:I: w
(.) 0..
bJ w
m w
-I
g (/)
ffi
n.
La..
UJ 0
~
(I)
l_ ~~
-,, 0~
~~ 0:: N
Wj:: oi
mo 0:: >0
om<x:
'~-w_w
~ ,;,
liii!'~ 1-
ii:
~o-'
,_<n (/)
-...
"-..
<O..U.
m::>o :5
-~
-I
<
m
La..
0
-I
<
>
0
:::;:
w
0::
'
' /
'y'
Fil} 39.3
(.!)
z
~ w
0:: (.!)
0 ::>
<(
..... (.!)
0
0
w
~
"'<»
ts/!!
0
:::t:
Q_
V)
"'r;:
0>
/:j<:Ji!i
~j..,~
w
:::;: u
!ii~J
i=
V)
t; j
~ifltJ
"'
flii$tt w
0::
0::
f!!l!2& 0
u
O,~aJ
Fig. 39.4
"'
w
Ill
:;!
w
-'
< 0: ffi
0
0 ~
"'... 1i1 "'zw
0
w ""-1 g""
"'z
~
Cl
I?"'
0
z
X
ID ;:;:
..... w
::.:
0
a: ....
-, Cl
0
:r: z
1- w 0>
w :.:
1-
()
U)
ii:
:::!: 0<
0
Cl
oi
"'
w
0<
0<
0
()
mi}i~o:
"'=> w
e,JiWD.
z3"' iE"'
~
9 miE"'
~~~\5
Fig. 39.5
(!)
z
X a..
:::::i
G: ()
4.
0 ...J
0
0 et: If)
0 0 ci
z
:c -<(
I-
w a..
"'
:::!i ~
tl
I- 0
()
w ()
~ ~
et: w
0
()
Fig. 39:€
CORRECT METHOD
THE CORRECT
CQ.MP[lESSION . .OF THE
CLIPS JS OBJAII:-JE(l. BY
UsiNQ A TORQUE OF
APPROX. ·250~350 Nm
HOW EVER THE
TORQUE VALUE IS NOT
THE G.OVERNING
\ CRITERIA
~ INCO.RRECT METHOD
\ I
\
Figure 39.6- Fixing of Vossloh Assembly
Fig. 39.7
Assume that the creep as recorded at Km Post No.63.00 is 160mm and 10 consecutive
joints have closed up. The creep is greater than 150mm and more than 6 consecutive
joints have closed up. Hence it is time to pull back the rails.
Procedure
1. The nearest anchor points are Bridge at Km 62.80 and level crossing at km 64.00.
Pull back the creep and confine the adjustment of the expansion gap between km
62.80 and km 64.00.
2. Measure the temperature and see the standard gap from the chart at Annexure
23.1
Let the temperature be 22•c
Standard expansion gap from chart = 4 mm
3. Start from the joint at Bridge approach at km 62.80 where the gap is maximum.
Proceed pulling back towards km 63, where the gaps are zero.
4. Keep the rails square at km 62.80. Insert an expansion liner of 4mm at this joint.
5. Loosen the rail fastenings of joints from km 62.80 to km 64.
6. Pull back the rails starting from km 62.80 with a creep pulling equipment.
7. Insert expansion liner of 4mm at every rail joint.
8. After every pulling operation, tighten rail fastening at the joints.
9. Repeat the operations and proceed up to km 64, which is an anchor location.
10. Check if a closure rail is to be put at km 64 or a new rail piece is to be inserted to
provide a standard expansion gap of 4mm at the joint at the approach of level
crossing.
11. Pack the disturbed sleepers.
1. Assume that the chart of track recording car has shown km 52 to 52.1 as having
gauge variations exceeding the planned maintenance tolerance + 6 mm and -2mm.
The field measurements of gauge are thereafter taken on the sleepers in this reach
and recorded.
2. The values obtained for the first 50 sleepers are given below
1 1002 +2 0&2
2 1103 +3 1&1
4-6 1004 +4 1&1
7-10 1005 +5 1& 1
11 1006 +6 1&1
12-16 1007 +7 1& 1
17-18 1008 +8 1&1
19 1007 +7 1&1
20-21 1008 +8 1&1
22-27 1009 +9 1& 1
28 1010 +10 1&3
29-30 1007 +7 3&3
31 1000 +10 3&1
32-33 1009 +9 1&1
39 1008 +8 1&2
35-41 1006 +6 2&1
41-42 1005 +5 1&2
43-44 1003 +3 2&1
45-46 1002 +2 1&1
47-50 1001 +1
3. Show the values exceeding the planned maintenance tolerances of +6mm and -2
mm in bold figures. Similarly show sleeper to sleeper variations exceeding 2mm in
bold.
4. From the table at para 2, it will be seen that the gauge is exceeding the planned
maintenance tolerance limits from Sleeper No.12 to 39. However sleeper to sleeper
variation is exceeding the limit of ± 2mm only from Sleeper No.28 to 31.
6. Take sleeper No.12. The adjacent sleeper No.11 is having a gauge of 1006mm.
11. Keep the gauge at sleeper 39 as 1004mm, since sleeper 35 has a gauge of
1006mm.
12. Follow the procedure in Clause 39.5.5 in adjusting the gauge from sleeper
14. Repeat the operations for the rest of sleepers beyond sleeper No.50 up to km 52.10.
Expansion gaps of 10 rail joints of 12.2m rails have been measured at a temperature of
22°. The total of the gaps is 50 mm.
Adjust alithe 10 joints by pulling the rails to get uniform gap of 5 mm at all the rail joints.
Example2
Expansion gaps of 15 rail joints of 12.2m rails have been measured at a temperature of
33°C. The total of the gaps is 30 mm.
Standard expansion gap as per chart at Annexure A-23.1 for 36°C =2mm
Average gap is greater than the standard gap by 3 mm.
The difference is > 2 mm.
Hence adjust the gaps systematically from nearest fixed point (anchor location) such as
level crossing, bridges and switches. The operations are similar to pulling back rail creep
and adjustment of expansion gaps as described in para 39.4.9 of this chapter. In this
case introduction of a longer rail or shorter rail at the end of the subsection will be
involved.
i. Hand-held machinery for removing fasten ings from the o ld sleepers. These
include coachscrewing machines, spike pullers and clippers for extracting the
elastic fastenings.
ii. One rail/road loader, fitted with an attachment for clearing the ballast from the
casings of the sleepers to be changed and for ensuring the necessary space for
inserting the new sleeper without lifting the track.
iii. One sleeper changing machine for extracting the old sleeper.
iv. A second sleeper changing machine for inserting of the new sleepers.
vi. A second rail/road loader with a ballast grab to fill the casings and reshape the
shoulders.
vii. One medium size portable or on-track ballast tamper with 1 or 2 tamping heads.
be half lifted and half dragged out of the trench and into the cess. Once out of the
trench the sleeper shall be able to be moved relatively easier.
\.,
Photo 1: Pulling sleepers out from under the rails
Chapter 40
Inspection and Maintenance of
Turnouts
Document History
Authorised By:
Signature:
Date:
MOHD RAMLI MOHD NOH
eral Mana er Permanent Wa
8 MAY 201
Keretepl Tanah Melayu Berhad
Kuala Lumpur
TABLE OF CONTENTS
40.1 GENERAL
This chapter deals with the functions of Permanent Way Staff in the inspection of
turnouts and their maintenance.
40.2 INSPECTION
40.2.1 Turnouts shall be inspected by the PWI, the CPWI and the Regional Engineer, as per the
schedule laid down in Chapter 50. Reference shall also be made to Chapter 6 for general
understanding of turnout design and maintenance.
40.2.2 The PWI, CPWI and Regional Engineer shall be in possession of a diagram for each
yard, each turnout being given a unique number by which it will be identified in all
documentation.
40.2.3 The check list for detailed inspection of turnouts are given in Annexure 40.1 and sample
Turnout Inspection Forms are in Annexure 40.2 (Conventional Turnout) and Annexure
40.3 (High Speed Turnouts).
Drainage
Creep adjustment.
Ballast cleaning.
1. Gauge shall be uniform except just ahead of the toe of switch where it shall be slack
(enough to house the tip).
2. Stock rail (on the turnout side) shall be bent to the correct extent at the theoretical
toe of switch.
3. The switch shall flush fully against the stock rail for its full tapered length; if not, the
switch rail shall be replaced.
4. Cracked/chipped switches shall be replaced.
5. Switch rails shall bear evenly on all slide chairs which shall be lubricated.
6. Vertical wear on the switch rail shall not exceed 6mm.
7. Lateral wear measured 15mm below the rail table shall also not exceed Gm m.
8. Gauge tie plates shall be provided at the toe of switch on turnouts with timber
sleepers.
9. Creep shall not exceed 25mm in track adjacent to switches.
2. Vertical Wear on wing rails and at nose of crossing shall not exceed 10mm.
3. Gauge tie plate shall be provided at the nose of the crossing on turnouts with timber
sleepers.
The curvature of turn out curve shall be within acceptable limits. (Refer to Chapter 26).
4. Sleepers shall be spaced as marked on the rails, square to the straight except in the
crossing assembly where they shall be square to the centre line of the crossing.
The PWI, on his own, shall not alter the position of switches and crossings. Specific
sanction shall have to be obtained for alteration, insertion and removal of switches &
crossings in existing lines, as indicated in Chapter 51 clause 51.2.
LIST OF ANNEXURES
Annexure 40.1 Check list for detailed inspection of turnouts
Annexure 40.3 Turnout Inspection Form (Class 1 Lines, High Speed Turnouts)
Angle of crossing
I. General:
1. Condition of sleepers
2. Condition of ballast and drainage
3. Alignment (Versine on 10 metre
chord near toe of switch and nose
of crossing).
(b) On turn-out
(i) Sleeper No.
Gauge
Cross level
(ii) Sleeper No.
Gauge
Cross level
(iii) Sleeper No.
Gauge
Cross level
(iv) Sleeper No.
Gauge
Cross level
(v) Sleeper No.
Gauge
Cross level
Note:
• Item 20: T he off sets should be measured at fixed distance from heel of switch as per
standard design drawing of various types of angle of crossing.
• For High Speed Turnout (HSTo) in Class 1 route, please refer to the Annexure 40.3 and the
separate Maintenance Manual for Vossloh Co~ ifer High Speed Turnouts.
• Creep marker or creep monument shall be installed for measuring amount of creep at
turnout to enable adjustments to be made. Creep shall not exceed 25mm in track adjacent
to turnouts
Similar/contrary flexure: _ __ _ _ _ __
A: GENERAL CONDITIONS
ISleeper No.
Condition
2. Condition of Ballast: _ __ _ _ _ __
3. Condition of Drainage:
4. Condition of Ballast Shoulder: - - -- - - - -
5. Measurements:
(PLEASE USE THE AlTACHED DRAWING)
B. SWITCH ASSEMBLY
1. Condit ion ofTongue Rails (HDCtype) Vertical/Lateral Wear shall not exceed 6 mm
Location A.T .s. (12 mm) 600mm (22 mm) 1600mm (45 mm) Action Taken Date
Right 1.
Left 2.
2. Condition of Stock Rails (80A height: 133.35 mm) Existing Height: .........................
@
:::"\
-I
s
~
O:J
~KTM
ITURNOUT INSPECTION FORM I
Gauge I
MAIN LINE
I L:J I
Part A-5: Measurements
I I I I I I I c::::J
i
Cross level I I L::J I I I I I I I I I I
TIOS 150mm from ATS HQS Lead ,centre 1 metre 150mm 1 metre ::l
(/)
,. i -.; -o
1 CD
I
------ I
$4
Alignment TOS I I
I
I a· .,
:::! CD
I I Ill ...
::l 3
a.SII
;:o s:~
CD Ill ::l
:::. M/L T/0
0
Throw of Switch I I I I ~i
::l Sll
tu'<
~s:
CD Sll
0 ::l
TURNOUT -c
-I SII
c -
....
Gauge I::::J I I I
L::J I I I I ::l
0
c
Cross level C:J I I I
I
I
I::::J I I I I Ui
M/L T/0 T/0
I_ I Crossing alignment M/L
Wear I I I I
Measure at NOC r-1
Action to be taken Date
"'0
Ill
(0
0
CD ':r
....
~
Sll
~.,
Q. CD !»
., ::1.
....
~
~<
Permanent Way Manual Part V
I~TIIII Inspection and Maintenance of Turnouts Chapter40
C. CROSSING ASSEMBLY
Clearance
TURNOUT
Clearance
Pa e3of 5
0: LEAD PORTION
Straight
Cross level 2.
Turnout
Cross level
Date: _ _ _ _ __
Date:------
:=::
PWI:
G KTM
TURN OUT INSPECTION SUMMARY (RINGKASAN PEMERIKSAAN SESIMPANG)
CPWI: _ _ _ _ _ _ _ _ _ _ _
;
c
Point Turnout angle 0 Condition of Sleeper Condition of fittings General Condition
'0:: llJ
No. Location "'llJ ...
(U
Notes
No. a.O :::J
en
1:9 1:12 1:1S "'
.5 Switch lead Crossing Switch Lead Crossing Ballast Drainange "0
Cl)
(')
1. g.,
:::J C1)
2. ru ...,
:::J 3
a. I»
3.
;;u ~~
(!) ru ::s
:< 4.
0
5.
~i
:::J I»
ru'<
6. ~:5:
Cl) Ill
0 ::s
7. -s::::
-1 1»
c:::-
...,
8. :::J
-
0
c:::
9. en
10.
- - · --
lJ
Ql
(Q - -------- - -- - -- - - n
::;
(!)
..... Ill
Name: Name : ~.,
-....
0)
0 C1) Ill
'""::I.
w Date: Date: ~<
Permanent Way Manual Part V
I~TIIII Inspection and Maintenance of Turnouts Chapter 40
I<Tifll
PERMANENT WAY DEPARTMENT
TU RNOUT INSPECTION
{For High Speed Turnouts Sector lpoh Padang Besar)
Similar/contrary flexure: - - -- -- - - -
A : GENERAL CONDITIONS
Item
Item Maintenance Action and Date
No.
1. Conditions of Sleepers (Crack at seat,
fasteners and rebars areas):
Please marked unacceptable sleeper condition
Sleeper No Defect
2. Condition of Ballast
Item
Item Maintenance A ction and Date
No.
4. Condition of Drainage
©KTMB Page 19 of 31
Permanent Way Manual Part V
Inspection and Maintenance of Turnouts Chapter40
b1 1000 b2 1000
" 1004 o2 1004
dl 1003 d2 1003
" 1000 e') 1000
: 39 f1 1000 f2 1000
48 q1 1000 " 1000
' 62 h1 1000 h2 1000
• 64 " 1000 a 1000
••••• ·••• .•. Gap I J :i,i,l1{ < ; '"I > .•· .• ·.' •. ·.·.·., .· . ·. ·•· · .· · · . .•. . ·.· / / .· . •.. . . . . . · •· . . . . . . · .·
1 1
2 2
3 3
4 4
5 5
6 •
7 7.
.Gap ~etWeenSiide • • .·· .• · . ••
.··
.
--
.··
.
/
,·...·. .. ..·" . ...·
IG:
....·.. ...·· · .. · ..
IG: N: N:
· ... .· ..
""
,, .· ·. 1 and Date . .
T•
page 2/4
TURNOUT NO: • . ' ··.·• ,··· MAtN1ENMc;S:Acnl>'N:Ailtiol'.rE · •• ·.·.· ·.... ·...·.··:•:.··•.• ·:·.·
~-==='~~'==~'~~~--------------------~·
I', ·..•....·•·.·'.. ··:, / ">·· ' ·, '' •
CO'!tingo~fe;l$&9!1slidJ>chair . . •
Yes r No
!
Yes I No
-- BaCk:tfove_· _condition ••
r--'A"'c"'iceptable I Not acceptable
':
I I I
---' .Sal_ancihg·:_of-the'{lua_id:·raii_S:-: ± Smm
•.. .· •.··.. ·,·.>·.·.·...· m:l<!5minl.o;04Smm ·
Des. Ga~,tge Gap Total Des Gauge Gap Total
m1 ~1
n1 n11
m2 m22
n2 n22
frog protectiohjng·9_56--~1/+.4mm
Des. Gauge Gap- Totat oes Gallge Gap Total
~ ~1
o2 o22
Wear of wing rails 4mm
Curved S#. R !Straight Sw.R
TURNOUT NO:
Mi_ssing/un·sc_r~_wji)Q:ot-fasbming
. <5o/oat
bearerS-0_1-:at
_Cheok raiU at
Acceptable I Not acceptable
c:J I I
Sleeper quality
Crack at sea~ fasteners
&-rebarS-.area
Acceptable I Not acceptable
c:J I I
Opening-Of Switch (at-40omm)
nworeHcal :160 +101-5
b~,~~-:.~~~~~-::i
- "
NAME SIGNATURE
PWI
CPWI
~
• •TU.; .._;; ,./,.iri
• ... "' ..· . ·:·. . • . . •. >;.>
Z.f
.... ·..
[] . @]
' ·········-········· ............. ····-······---·-
.,!
L ~"""''
. L{ ..
--·-
.. r'l'-· .
-~-~===if-.Jjji._:l,: ~~
. .. . --·- ...
,j,• ;J
-··-········ .. ·····-·
~----~t= ~~ c
-~~\Jitj
'• ~ ;;o~""'...t~~4t::.~=-
Oil
~k •
•. ' . ·•.· ...... .••. ·:.·.:~ ..... .•••.• <; •••••
.~. ·.•. '•pMe·.·.········ '··•~•'/; t
11'!ahlin~ Curved line
·,··.•
Reol
,,'·····
• 1000
·....
2 .b1 1003 b2 1003
7 o1 1002 1002
12 d1 1000 d2 1000
21 o1 1000 o2 1000
25
29
(1
g1
1000
1000
12
g2
1000
1000
I·
39 1000
41
h1
i1
1000
1000 "'
i2 1000
"'""" ...
I
..
Curved SVt.R. Straight SW.R
G: N: ;G: N:
.. I .>samm • ..
Dmed Sw.R. St~;ght Sw.R
·: ·.
'
~ T'
~
I '"'IT")
r--'A-"c"jceptabte
I
Page 3/4
Page 4/4
===~
PWI
CPWI
Page1 of3
~ ~in line
1
2
3
4
5
6
'
G:
... .·.···. ~'"'"'
Slrnlgh! SwK
N:
·,..·.,·. ...
I ·.·
.:. ·.·.
Roller
st,.loht Sw.R.
I Not acceptable
0 D
Page2of3
·I
Page3ol3
PWI
CPWI
Chapter 41
Inspection and Maintenance of
Bridges
Document History
Authorised By:
r '
Signature:
Date: MOHD RAMLI MOHD NOH 2 8 MAY Z015
Keret-Bpi Tanah Melayu Berhad
Kuala Lumpur
TABLE OF CONTENTS
41.1 GENERAL
41.1.1 This chapter deals with the inspection and maintenance of bridges, viaducts (including
culverts} and track !hereon by the Permanent Way staff. Road-under bridges, viaducts
and culverts are classified as bridges in this Manual and are referred to as such in this
Chapter.
41.1.2 Procedures for detail inspection of bridges and their maintenance by the Bridge Engineer
Headquarters' unit, the Regional Engineer and the Regional Bridge·Unit are beyond the
scope of this Manual. They are described in more detail in the current KTMB Bridge
Maintenance Manual.
41.2.2 During their normal inspections, the PWI and CPWI shall be on the lookout for any
changes in the condition of bridge and viaduct structure, which are likely to interfere with
the safe running of traffic. They shall report such changes to the Regional Engineer, for
taking appropriate action in the matter. Features to be monitored include:
41.2.3 Passage of heavy loads on and damage by road vehicles to road-over bridges across
the track, road-under bridges and indication of river boats or vessels causing damages to
the bridges structures shall also be checked by the PWI. Where necessary in such
cases, immediate steps shall be taken to protect the rail traffic. He shall also send a
report to the CPWI with full details.
41.2.4 If any danger needs to be apprehended, Permanent Way staff including the Ganger and
his men shall act in accordance with the General Manual in the current KTMB Rules
and Regulation Book as applicable to stop or regulate traffic.
41.3.1.2 All applicable items among those indicated below and any others as necessary shall be
inspected. Remarks shall be recorded in a register (proforma at Annexure 41.1) which
shall be forwarded to the CPWI before the end of February of each year with necessary
photographs. Figure 41.1 indicates the system to be followed for numbering the various
components of a bridge.
3.4 Bridges of span 30.5 m. and above are provided with camber. Track on these
bridges are laid correctly following the camber of the girder. While re-timbering is
done it should be ensured that the longitudinal level of rails follows the camber of
girders.
4. Slabs/Boxes/Arches etc.
4. Creep.
5.4 Sleepers
1. Condition
2. Spacing
3. Thickness
4. Bolting to girders
7. Detail inspections, taking of records and measurements for Bridges shall be carried
out by Bridge Unit personnel under the management of the Permanent Way
Headquarters Head of Bridge Unit.
41.3.1.3 The PWI shall carry out all repairs within his competence and capability without delay or
request assistance from the Regional Engineer /Bridge Unit if required.
41.3.1.4 On receipt of the PWI's register, the CPWI shall:
The register shall be so prepared that at least five consecutive previous year's records
for a bridge are available in it at one place.
41.3.1.5 Standards to be followed for track on bridges are specified in Chapter 10. The inspection
of track on bridges shall be with reference to these standards.
41.3.2 B~ the Regional Engineer
The Regional Engineer shall inspect bridges as necessary during his normal inspections.
He shall also inspect all the bridges, once a year, according to the procedures laid down
by the General Manager Permanent Way. He shall bring to the notice of the Bridge
Engineer any defects or anomalies noticed.
Note: The Bridge Engineer shall carry out a detailed inspection of all bridges every year
according to procedures specified by the General Manager Permanent Way and in
accordance to the current Bridge Maintenance Manual.
13. Fastenings fixing the sleeper to the girder or rail bearer grip firmly.
LIST OF FIGURES
Figure41.1 System for numbering components of a Bridge
LIST OF ANNEXURES
Annexure 41.1 Proforma for PWI's Bridge Inspection Register
Fig. 41.1
NO.~ SPAN
N0.2
GRIPER BRIDGE
N0.1 RE1URN N0.3 RE1URN
1llllE....;.
WHERE lHERE ARE MORE lRACl<S lHAN ONE lHE BRIDGES ARE
TO BE NUMBERED CONSECUllVELY COMMENCING FROM lHE EXTREME
RIGHT fACING lHE DIRECllON OF INCREASING I<ILOMETREAGE.
ffi ffi
a: a:
NO. 1 PARAPET
ARCH BRIDGE
I I
I I
NO. 1 FACE WALL
Type Span
Previous History:
',, < ' ' !tf' - >,.,,,.,., ' , . .,.,,,,. , ' , ., , . . ,,.,. ',' .,',,,.,.
i,i~~\ ''\''<':'·•'\' .;. •··•· ••• ··~··:~,.
., '·i s• ..:.••\:',
"•.\'' ( '"" ,?•<;;; cc .,,, i\;qc·;'
.· · .;uraers: J"~tf<;'!i
.·. '&.< .· . /;~!
.
1. Water Way and protection works.
1.1 Obstruction to waterway.
1.2 Protection works (pitching, drop walls,
flooring, aprons, guide banks etc.) scour,
slips/settlement.
2. Foundations and substructure:
2.1 Scour noticed near foundations.
2.2 General soundness of abutments, piers,
wing walls, bed blocks.
2.3 High flood level/danger level marks.
3. Girders:
3.1 Position of spans relative to piers/
abutments.
3.2 Bearings.
3.3 Significantly noticeable defects such. As
excessive corrosion, loss of section,
distortion and damage due to accidents.
4. Slabs/Boxes/Arches
4.1 Cracks/sags etc.
5. Track and approach.
5.1 Line and level and position relative to
girders.
5.2 Gauge and Twist
5.3 Condition of rails & fastenings
1. Type (LWR etc.) and condition.
2. Position of joints, and extent of gaps.
3. Condition of rail fastenings.
4. Creep.
5.4 Sleepers
1. Condition
2. Spacing
3. Thickness of timber bearers
4. Bolting to girders of timber bearers
5.& Protection rails/Guard rails
5.6 Man-refuges.
5.7 Fire precautions
5.8 Other items.
~,,,
"'"
Name PWI CPWI PWI
PWI
CPWI
Date
Chapter 42
Inspection and Maintenance of
Tunnels
Document History
Authorised By:
(
Signature: '
Date: 2 8 MAY 201
TABLE OF CONTENTS
42.1 GENERAL··· ······· · ····· · ····················· · ··························· · ·········· · ···· · ·· ··· · ············· ~ ··························· 3
42 .2 SCOPE OF INSPECTION ................................... ........ ......................................... ........ ............... 3
42.3 ANNUAL INSPECTION ............................................................................ .................... ............... 3
42.4 MAINTENANCE OF TRACK IN TUNNELS ................................................................................ 5
LIST OF ANNEXURES ........................................................................................................................... 6
Annexure 42.1 - Proforma for PWI's Tunnel Inspection Register ........................................................... 7
42.1 GENERAL
42.1.1 This chapter deals with the inspection and maintenance of tunnels and tracks therein by
the Permanent Way staff. Procedures for detailed inspection of tunnels and their
maintenance (in accordance with extant orders of the General Manager Permanent Way)
to be carried out by the Bridge Engineer, his staff, the Regional Engineer and the
Regional Engineer's Assistant are beyond the scope of this Manual.
42.2.2 All unlined portions of walls and roofs of the tunnels shall be carefully examined and
sounded by the PWI once in six months (unless otherwise ordered by the Regional
Engineer). All serious defects noticed shall be reported to the Bridge Engineer.
42.2.3 If any danger is apprehended, Permanent Way staff including the Ganger and his men
shall act in accordance with the General Manual in the current KTMB Rules and
Regulation Book as applicable to stop or regulate traffic as required.
• Portals
• Profile and clearance
• Walls and Roof
• Tunnel drainage
• Drainage pattern above the tunnel
• Refuges
• Shafts
• Adits and Shafts point
• Track and condition of track on transition slabs/ tunnel approaches
• Slab track
• Protection rails on tunnel approaches
• Lighting and special equipment
However track and drainage items which are scheduled for closer interval of inspections
shall be carried out as stipulated in Chapter 50. Detail inspection above the tunnel shall
be done by the PWI together with the Bridge Technician.
42.3.1.2 All applicable items among those indicated below and any others as necessary shall be
inspected. Remarks shall be recorded in a register (Proforma at Annexure 42.1 ), and
forwarded to the CPWI, by a date to be prescribed by the General Manager Permanent
Way.
1. Portals
2. Profile
2.1 Clearances
Measurement of track offset to tunnel face and tunnel structure - markers that are
installed to check clearances must also be regularly checked.
3.2 Seepage.
3.3 Unsound lining/loose rock.
4. Tunnel drainage.
5. Drainage pattern above the tunnel.
6. Refuges.
7. Shafts.
8. Track.
8.1 Line and level and reference pillars
8.2 Corrosion.
8.5 Bonding of twin block sleepers and surrounding concrete for slab track
42.3.1.3 The PWI shall carry out all repairs within his competence and capability without delay.
42.3.1.4 On receipt of the PWI's register, the CPWI shall:
42.3.2.1 Inspect tunnels as necessary during his normal inspections and bring to the notice of the
Bridge Engineer any defect noticed, and;
42.3.2.2 Carry out a general inspection of all tunnels in his jurisdiction every year, according to
procedures specified by the General Manager Permanent Way.
(Detail inspections of tunnels are to be carried out by the Bridge Unit)
42.4.2 Lookout men with whistles or air horns shall be posted to lookout for approaching trains
and give timely warning to enable all men inside the tunnel to reach the refuges
provided, if not to get out of the tunnel before the train enters the tunnel. Those unable to
do either, shall lie down close against the wall of the tunnel until the train has passed.
See rules 3.6.4 of section B of Rule Book.
42.4.3 The general level of the track in a tunnel shall not be raised without the permission of the
Regional Engineer. The track shall be carefully kept true to the centre line. Reference
pillars for line and level shall be maintained in position.
42.4.4 For tunnels with ballasted track, ballast shall normally be unloaded outside the tunnel
and carried inside as required. Ballast shall not be thrown up higher than the specified
level.
42.4.5 Sleepers and other track material shall not be unloaded/left in the tunnel.
42.4.6 Before a trolley is taken into the tunnel, the trolley headlight and lamp and the Inspector's
head lamp shall be lit.
42.4.7 The PWI shall ensure that no hasty work is done. Track components shall be carefully
examined for signs of corrosion and painted with specified compounds as required. The
standard of maintenance shall be such that frequent attention to track will not be
necessary.
42.4.8 The PWI shall leave the tunnel after maintenance work, only after careful check to make
sure that:
A separate High Speed Tunnel Operation and Maintenance Manual shall be referred to
for specific inspections and maintenance requirements related to tunnels in Class 1 high
speed lines.
LIST OF ANNEXURES
PWI Section:
Special arrangements:
Lighting:
Ventilation:
Gradient of track:
Geotechnical information:
Signatures:
Names: PWI:
CPWI:
Date:
Chapter 43
Precaution Before and During Rainy
Season
Document History
Issue Date Description
Authorised By:
Signature:
~,-'
Date:
MOHO RAMLI MOHD NOH
General Manager Permanent Way
2 8 MAY 201~
p Janan Melayu tsemaa
1\ere-:eJ)t
Kuala Lumpur
TABLE OF CONTENTS
43.1 GENERAL
This chapter describes the precautionary measures to be taken before and during rainy
season. Follow-up action to be taken after slips and floods has also been indicated.
43.2.1 All drains and waterways shall be cleared of silt and vegetation. Digging below the invert
level of culverts shall not be done.
43.2.2 Repairs to protection works shall be completed and scour holes filled.
43.2.3 Marks indicating the safe limit of the flood water level (to be observed by patrolmen or
watchmen) shall be painted to be clearly visible, at indicated locations as on
abutments/piers of bridges and culverts and approaches to causeways.
43.2.4 In hilly areas where boulders are likely to fall on the track, loose boulders shall be
identified and disposed of safely.
43.2.5 Patrolmen and Watchmen shall be nominated and trained and their equipment made up.
43.2.6 Reserve stocks of materials like boulders, earth, empty cement bags and wire netting
and equipment like temporary bridge spans, cribs, trestles, pavement breakers, and
welding sets, for use in emergency restoration works shall be made up to scales
prescribed by the General Manager Permanent Way.
43.2.7 Locations with a past history of damage by flood and those considered vulnerable due to
special features (such as a reservoir or development upstream, that are outside the
railway reserve, that may release unsafe volume of surplus water during heavy
rains/floods) shall be identified and reviewed by the Regional Engineer. Arrangements
shall be made to keep these locations under watch. The Regional Engineer shall identify
sections with such history so that additional regular patrolling at night will be carried out.
(Definition of heavy rain: When the precipitation (rainfall) is with an intensity in excess of
0.30 inches (7.6mm) per hour) measured with a rain-gauge. Violent rain - when the
precipitation rate is> 50 millimetres (2.0 in) per hour)
Wet Weather patrolmen nominated by the PWI, on sections approved by the Regional
Engineer and sanctioned by the General Manager Permanent Way Division during wet
weather period.
The Regional Engineer shall instruct for certain sections of the railway line to be patrolled
to detect damage by flood, such as breaches, settlements, slips and scours and
immediate action taken to protect trains, wherever necessary. PWis must take note that
short periods of intense rainfall can cause flash flooding whilst longer periods of
widespread heavy rain can cause rivers to overflow.)
43.3.2 If the line is unsafe, they shall take action in terms of the current KTMB Rules and
Regulation Book. In case of emergency, Gangers are empowered to put their gangs to
watch the line for the night and" take precautions to ensure safe working.
43.3.3 Look out men shall be stationed in pairs at places where trouble is anticipated in the
rainy season. If the line becomes unsafe, one look out man shall proceed showing
danger signals in one direction and the other in the opposite direction, showing hand
signals and placing detonators as prescribed for protection of track.
43.3.4 Sections with a history of damage by floods, as approved by the General Manager
Permanent Way, shall be patrolled at night (covering the period during which passenger
trains traverse the section) by patrolmen in pairs. Chapter 47 describes the details of
the system of patrolling.
43.3.5 Permanent Way Staff who discover that the line is unsafe and take proper steps to
protect traffic shall be suitably rewarded by the Regional Engineer.
Chapter 44
Accidents
Document History
! Issue Date Description
I
Authorised By:
Signature:
~~ '
Date:
MOHD RAMLI MOHD NOH
General Manaaer Permanent Wav
2 8 MAY 201 p
Kere~pl Tanah Melayu Berhad
Kuala Lumpur
TABLE OF CONTENTS
44.1 GENERAL
44.1.1 This chapter describes the various types of accidents, action to be taken by permanent
way staff in dealing with accidents and documentation of the special occurrences.
44.1.2 Chapter F of the General Manual, Paragraph 4, Section A of the current KTMB
Rules & Regulation Book and Chapter 17, part 2 of Working instructions (KTMB),
as currently in force (refer to latest update), specify:
44.1.3 In case of contradiction between the provisions of this chapter and the rules in the
current KTMB Rules and Regulations book shall prevail.
44.2 DERAILMENTS
44.2.1 Derailments are classified as follows:
Major Affecting train on main running line.
Minor Other derailments.
Potential Averted derailment
For classification see Appendix VI Chapter XVI of working instruction Part 11.
KTMB OSHEN shall update on any changes to these classification.
Notes:
1. In the event of a derailment occurring at a location nearer to another Region
Headquarters, the officials of that Region shall proceed to the site. They shall hand
over the work to the concerned Regional officials when they arrive.
3. Before proceeding to the site, officers shall acquaint themselves of all the
information available. They shall also arrange for all men, equipment, and material
required for restoration of traffic to be sent to the site promptly.
All assistance shall be rendered in provision of First Aid to ·injured passengers and
others, and in operations to rescue trapped passengers.
44.2.4.1 After a rapid survey at the site, information as required by the Train Driver shall be
given to enable him to advise Train Control and Command Control Centre (TCCC)
Operator/the nearest Station Manager, and/or others concerned.
44.2.4.2 If necessary, the first Permanent Way official to reach the site shall convey information
by the quickest possible means to Train Control and Command Control Centre (TCCC)
Operator/the nearest Station Manager, in respect of:
• Location.
• Train (number and description).
• Time of accident.
• Particulars of casualties, if any
o Nature and cause of accident, if known.
o Estimated damage to permanent way, works, bridges, signalling gear etc.
o Probable duration of blockage of line/restoration of traffic
• Whether transshipment is required/feasible.
• Assistance required (breakdown equipment, medical aid, materials, staff, labour,
security requirements and media relation)
44.2.4.3 The Train Guard or Driver has conveyed information, it shall be verified. Any corrections
found necessary, shall be advised to all concerned.
44.2.5 Recording of details and preservation of clues
44.2.5.1 The CPWI or PWI shall try to record all details of relevance to the derailment and to
preserve all clues. Relief and rescue operations, however; shall not be hampered on
this account. Wherever possible, photographs shall be taken showing the damages to
and marks on:
• Rails,
• Sleepers,
• Track fastenings, and
• Rolling stock.
• Any other relevant items that has probable impacVcauses to the derailment or
accident
44.2.5.2 In all cases where restoration of traffic is likely to lead to disturbance or obliteration of
marks on the track or other evidence, the senior official at site shall arrange all details to
be noted and sketches to be made. A Rail Incident Officer shall be appointed who shall
maintain records of activities during restoration works and control all operations.
44.2.5.3 Material released from the track shall be properly marked and preserved to enable
future re-construction of the damaged track if required for investigations.
44.2.5.4 Permanent Way staff attending derailments shall be vigilant to observe and record all
relevant details including those of:
• Rolling stock,
• The position of point levers,
• Position of Block Instruments and
• Position of Signals in case of accidents at stations.
• Position of Electrification equipment
• Equipment and apparatus in tunnels and bridges
44.2.5.5 Photographs shall be taken before any evidence is disturbed; if possible, a video
recording may be made after suitably marking the points of drop and/or mount of the
derailed wheel (s), and marks on rails and sleepers and other details.
44.2.6 Reporting
44.2.6.1 The Regional Engineer shall, on arrival at site send a brief report to the General
Manager Permanent Way, including the following particulars, at the first opportunity.
• Nature of accident.
• Cause if known.
• Particulars of loss of life and injuries to passengers or others, if any.
• Extent of damage to permanent way, works and bridges or culverts.
• Particulars of rainfall and patrolling in cases of damage by floods.
• Steps taken to restore traffic.
• Estimated time of restoration.
• Whether transshipment is necessary.
• Whether track deviation is necessary; if so, estimated time for rerouting traffic to
the deviated track.
• Assistance required (staff, labour, material, equipment etc.).
44.2.6.2 A sketch showing the following details shall accompany the report:
• Important dimensions,
• Position of vehicles after the accident,
• Conditions of tracks made by derailed vehicles,
• Marks on rails,
• Particulars of condition of track behind the point of derailment and
• Any other information useful in arriving at the cause of the accident.
44.2.6.3 This preliminary report shall be followed up by supplementary reports as and when
more information becomes available.
44.2.6.4 If the Guard or Driver has conveyed information, it shall be verified. Any corrections
found necessary, shall be advised to all concerned.
44.2.7 Temporary Track Diversions
44.2.7.1 Temporary diversions are required when traffic has to- be restored without waiting for
the obstructed main line to be cleared. The TableT - 44.2 below indicates approximate
lengths for temporary diversions. These details can be used to determine the feasibility
of a track diversion at site, for estimating material requirements and· for lay out.
TableT- 44.2
Length of Temporary Diversions
44.2.7.2 The following formula may be used for calculating track diversions, keeping the same
unit for all dimensions/measurements.
2
L = ,f C + 4RD - 0
2 +~
2
RD
T
l-_£_+C
2
T s T
~· ,I' 'I
/~
••
J"
::
~
I
R
I
A
44.2.7.3 In laying the deviations, the following aspects shall be kept in view.
1. Curves shall normally have radius not less than 300m; in difficult terrain, minimum
radius shall not be less than 125m.
2. Gradient shall not be steeper than the ruling gradient of the section.
(Refer gauge widening guide: Chapter 12, Clause 12.17 and Chapter 32, TableT -32.4.
R>200 nil
5. All trains shall stop and proceed at Dead Slow speed (< 5 kmlhr) on the deviation,
where flagmen shall be posted and caution, speed indication and termination
boards installed.
44.2.8 Detailed survey and preparation of drawings in the case of major derailments:
44.2.8.1 In all cases of major derailments, a detailed plan shall be made out on the lines
illustrated in Figure 44.2
44.2.8.2 Observations shall be made after inspecting about 800m of track over which the train
passed immediately before derailment, to look for unusual features, especially fallen
parts of rolling stock on or by the side of the track.
44.2.8.3 Gauge, cross-level and versine readings shall be made before any repair work is
done on the track. The repair work shall, under no circumstance, be done before the
arrival of officers at site and before permission is given by the Regional Engineer, or the
CPWI. Particulars of track shall be recorded by the PWI (by the CPWI in the case of
serious derailments) jointly with an official from the Operations, Fleet Engineering, or
Signalling and Communications Division and/or Electrification Division, as listed below.
• Longitudinal levels at intervals of ten meters for 300m to the rear and 1OOm aheac}
of point of derailment.
• Track measurements at each station (for 100m to the rear and 50m ahead of the
point of derailment) as below:
1. Station number (0 for point of derailment i.e. point of mount or (drop}.
2. Distance apart (normally three meters).
3. Gauge (tightness and slackness in mm from exact gauge).
o under no load.
o under a loaded vehicle.
44.2.8.4 Records of work on track last done (prior to the derailment) shall be examined and
details ascertained and documented. If any work is in progress at the site, the following
details shall be collected:
• Nature of work,
o Speed restrictions,
• Locations of caution and speed indicator boards and
o Issue of caution orders to Drivers of trains.
44.2.8.5 A dimensioned drawing shall then be prepared covering the entire site of accident
indicating all relevant features leading up to the point of derailment and the position of
the derailed vehicles and their parts, the locomotive and other vehicles on rails. Details
which shall be normally shown are listed below:
6. The locations where displaced parts of the permanent way and rolling stock
were found, and where any extraneous materials was found on or near the
track.
7. If the derailment is at or near a Station, the concerned signals and their
aspect at the time of accident along with the station layout may be shown.
8. The extent of disturbance to the permanent way and to the train composition,
details of marks/breakages indicating distances along the track measured
from a known fixed point.
9. Any other local feature, especially those useful in reconstruction of the scene
of accident for a person who has not seen it.
10. Details of track structure and of bridges and level crossings involved.
44.2.8.6 A preliminary drawing shall be submitted by the Regional Engineer to the General
Manager Permanent Way within three days of a serious derailment where the Regional
Engineer considers another division/party other than Permanent Way defects as the
cause of the accidenVderailment, containing as many details as available.
44.2.9 Identifying causes of derailment
44.2.9.1 Some of the obvious causes of derailment classified under failure of permanent way
are:
6. Load:
Description:
• Weight:
• Distribution:
• Remarks:
7. Position:
• From Locomotive:
• Orientation:
• Wheel diameters.
• Tyre profile.
• Slack tyres.
o Marks on tyres.
• Axle journals.
9. Axle boxes and bearings:
10. Bogies:
• Condition of springs
• Condition of spring shoes and shackles.
• Condition of spring hangers.
12. Couplings draw gear & buffers:
0 Buffer heights to be gauged and recorded.
0 Type of coupling and condition.
0 Condition of buffer springs.
0 Condition of buffer bracket.
13. Brake gear:
• General condition.
• Details of defects and damage.
44.2.10.1. Enquiries
Enquiries are ..u, .,,alo held as below:
1/ ··~f.,, .., ~~
,::-,
••• I ' t>Jo..J''#'•"i;',:}.~
~'Ji.··.·.··.·
1. Accidents resulting in
...
Joint Enquiry/ As directed by the Authority
·····
concerned.
a) loss of human life
3. Accidents other than (1) above Joint enquiry convened by the Head
where the officers attending the Operational Safety, Health and Environment
site do not reach agreement as (OSHEN)
to responsibility.
Permanent Way staff shall attend enquiries of different types as indicated above
whether they pertain to a derailment or otherwise, when summoned to do so by any of
the Enquiring Authorities (whether as indicated in Clause 44.2.10.1 above or by any
other legally constituted Enquiring Authority). They shall give evidence and/or answer
questions. They shall be prepared to present all relevant records as called for, including
the observations taken at the site of accident.
44.3.1 Permanent Way staff shall proceed to the site of the accident and act according to the
applicable stipulation in Clause 44.2, on receipt of information about a collision.
44.3.2 If it is known that there is no damage to the permanent way, works, bridges or culverts
and that their assistance will not be necessary for restoration of traffic, presence of
Permanent Way Staff at the site of collision is not essential.
44.4.2 In the case of a collision at a Public Closed level crossing, they shall jointly:
• Assess and report on the visibility of a rail vehicle 400m away from the level
crossing to an observer on the road 5m from the nearest rails.
• Ascertain whether the head light/buffer lights of the locomotive were lit, if the
collision was at night or when conditions of visibility were poor.
• Verify the existence of whistle boards and warning boards as prescribed in
Chapter46.
44.4.3 The procedure as indicated at Clause 44.4.2, shall also be adopted in the case of
accidents at accommodation crossings and private crossings.
• Location
• Whether bank or cutting.
• Length affected.
• Whether trains can pass.
• If not, approximate quantity of earth required to be filled in (in the case of
embankments) or removed (in the case of cuttings) before trains can pass.
• Assistance required in terms of ballast trains, equipment and labour.
44.6.2 In the case of flooding, the first Permanent Way official to reach shall note and report:
44.6.3 "Refer Clause 21.1 to 21.4 of Appendix 1 to the General Manual in the current
KTMB Rules and Regulation Book".
44.6.4 Before passing trains, the PWI shall ensure that the track is safe, by wading over it and
checking by means of probing. Due care must be taken for his and his staff safety.
44.6.5 In the case of damage by floods, it is usually advisable to wait until the flood has
partially subsided before attempting to fill in the breached portion or to build a
temporary bridge. Traffic shall be resumed only after the PWI inspects it thoroughly
and certifies it fil. All such locations shall be inspected at the earliest opportunity by the
CPWI and the Regional Engineer. They shall send a detailed report to the General
Manager Permanent Way, detailing the accident, causes thereof, and remedial
measures proposed.
• Location
• Train number and description if involved.
• Time of occurrence
• Particulars of casualties, if any
• Nature of occurrence
• Cause if known
• Damage
• Whether trains can pass
• If so, permissible speed
• If not, probable duration of blockage of line
o Whether transhipment is required I feasible.
o Assistance required (break down equipment/medical aid, materials I staff I labour I
security requirements I media relation).
Arrangements shall then be made either to pass trains at the restricted speed or for
urgent temporary repairs according to the directions of the Regional Engineer. After
inspecting the site, the Regional Engineer shall propose permanent remedial measures
to the General Manager Permanent Way.
44.8.1 All cases of Railway employees run over in the course of their employment shall be
reported to the Regional Engineer who will advise the KTMB Talent Management &
Organisation Development Department, Department of Labour and the Commissioner
for Workmen's Compensation.
44.8.2 All fatal accidents to Permanent Way staff shall be reported to the General Manager
Permanent Way immediately. The Regional Engineer shall personally enquire into
every case and make a full report including preventive measures implemented.
Cases of unauthorised persons run over by trains coming to the notice of Permanent
Way Staff shall be reported to the nearest Station Master and to the Regional Engineer.
All assistance required for first-aid to injured persons and for removal of dead bodies
shall be provided by Permanent Way Staff. No enquiries need be held into such cases,
44.10.1 All cases of derailments shall be reported to the General Manager Permanent Way by
the Regional Engineer.
44.10.2 All cases of accidents, slips in banks and cuttings, subsidence or submergence of track
and flood or other damage to Permanent Way, works, bridges and culverts shall be
recorded by the PWI in the section register.
• The location,
• Date and time,
• Description of the occurrence,
• Cause (as and when known)
• Extent and cost of damage to permanent way or other assets,
• Record of repair/restoration works/cost of repairs
• Time of restoration of traffic,
• Remedial measures taken (temporary/permanent).
This register will provide the basis for statistical and other information as required.
44.10.3 The Regional Engineer shall maintain a map of his Region with all such occurrences
duly marked. He shall forward an updated copy to the General Manager Permanent
Way at the end of each year.
LIST OF FIGURES
Figure 44.1 (a) Sketch of an accident site - Example 1
~
$
~
{])
"'T1
cCi"
...,
c
i
CD
~
""""
.-s.
~N
....>.
POD
I MP 71.3 Truck from Truck from
(/) Red Deer s ub. AOUX 5061 CGTX 22219
7\ ""0
CD
0~ ....
CD
+
- 3
0 11.1
)>a:
!I -
! l)
::l (") :I
!l)
(")
(")
a:~
(")
CD 1!.1
a: ;:!..'<
CD
;:!..
6 cars derailed on their side (/) s:
I)J
(/)
Train200-19 :I
~ AOUX CGTX r::
5061 North bound e!..
I 22219
m
><
!l)
3
"0
(j)
V)
<J
Ql
(Q 0
(1) ::r
..... 1).1
00 ~""0
Q, CD 11.1
... :::1.
N
0
t<
Permanent Way Manual Part V
Accidents Chapter 44
. ·PptllaOO,.OR~nl~st(MP}O.U
• 'lallQoW(!t,cV"'il\ ;. MP 9.0
~
@ p!'-Aij 'DE ed;rn&NJ su'!;'
~
~
;;: KM \~~ ~:·~~ ~-
-.---5--CO-.. __:;_;_.;_._ _ ,
--1
S$'7 3~
"i
KUALA LIPIS
"' 7
1x6,1Joa
l-3_.!! .~ T1.5-"'
G.B. No.BS
KH 301-+'SI::SD I A~ E~GIN£-
··~~ ·· ..
..~.u.;~~
..............
-G;B :Na.as
INDEX QIAtjBAM - KH 300+500
"T1 TRAIN No 4!50 UP
<0" DATE OF" AC.CIDENT~ .15· -F'EB· ·2006 TIME: 0101' HRS
LOCAnCJN~·
"ro I<.H ·3Q1+500_ -to 30HO_OO-· lOI"',-
h·321"'..11 7' ·'.·12i<
'"'~FI
..
"'
RIGHT RAIL
ICUALA LIPIS t...c. . ;' ·d. 1
se
l . . I .· • "rh. ll!f#ffUfflflf!JJ
; ...- ., .. · ·_,...•..
· _,...._ \ -'I~,J-~V!}j> . . .
_.. _. -· _.') 3
"'fi KH 30_1+8_:50
DIRECTTriH DE TRAIN
. " ....
_;L
15iol;;;o'"
- '--- ·---- 'j. )> ""~
!I :::r (") :l
9, c> C!.l_l::tYE. 'N0:-'.-10
. -DEGREE. -3!
n. -
a.::
OJ
::J
OJ
RAmu.S-<:se3"'
CANT·--so;,:i-1
-TRMISITI[]'II.' LENGTH ''7:5rli'
"''"--<
en ;;:
""
(")
Q. 0)
0. :l
t:
"' 2!.
=-
en
$"" TRACK SOA RAtl, L 'W'R
\W'DDDEN _SLEEPERS
SLEEPERS
(;RAME;NT 1 I.N 150. . __
;>; 3• TRANSITiro.IED R:·t6()07
-1 i~~~S-r· -15QM I:L.E)\N D~RAILED
;;: kLD'W ·SLEEPERS
CO NIL DPRING
RAJNF'"AU..
<4 DAYS ·- Q
PRECEDING Tt£:
DER~ILHENT
rORMATIONIST~BLE
.. " R _250:51 _
cAPSIZ£n···.'
' - - - - - 5 ...
•c .
-·- ;,': /: ·. ·-
.
.·
~~1:£1).
-~(-:.JJ
-u
0) 0
(Q DEIAIJ'.S At 'ij;{ :::r
"0 ""
"2.-c
"'Sl, LEGEN:P (0
~ ""
;:l.
Chapter 45
Execution of Works, Speed
Restrictions and Indicators
Document History
Issue Date Description
-1
Authorised By:
r,
Signature:
Date:
MOHD RAMLI MOHD NOH
General Mana er Permanent Wa
8 MAY 201
Keretapi Tanah Melayu Berhad
Kuala Lumpur
TABLE OF CONTENTS
45.1 GENERAL
45.1.1 This chapter describes the categories of works to be executed, the arrangements to be
made for undertaking a work and the signals to be displayed at the site of work to ensure
safety.
45.1.2 Section J of the General Manual in the current KTMB Rules and Regulation Book
specifies the procedure to be followed for execution of works and the precautions to be
observed for protection of trains. These instructions shall be complied with by all
Permanent Way staff. In cases of contradiction between the provisions of this chapter
and the current KTMB Rules and Regulation Book, the latter shall prevail.
45.4 BLASTING
No KTMB personnel employed on the permanent way or at any work shall carry out any
blasting operation on or near the railway, except as permitted by Special Instructions.
45.6 FLAGMEN
45.6.1 The term flagmen shall cover those who exhibit flag signals by day and those who exhibit
lamp signals or signals by Tri-colour torchlight by night.
45.6.2 The PWI shall arrange to post suitable flagmen who are properly instructed in their
duties. He shall ensure that:
• Flags, hand signal lamps and lights on the indicators are in working order.
• Reports from Drivers of night trains about the following are attended to urgently:
The lights on indicator being are not lighted or dim, and
Flagmen neglecting to show proper signals.
• Track renewals,
• Bridge repair or construction, and
• Deviations.
45.7.3.2 Indicators shall be used as specified in Section K of the General Manual in the current
KTMB Rules and Regulation Book, to caution Drivers of trains about the speed
restriction and to display to them:
45.7.3.3 Major operations shall be carried out to a programme which has been advised to all
concerned in advance.
45.7.4 Works requiring approvals.
Works specified in Chapter 51, Clause 51.2 shall not be undertaken and commissioned
without the statutory approvals stipulated in Chapter 51, Clause 51.1. (Refer to Chapter
51 for details}.
45.10.2 In cases of restrictions continuing for three days or longer, reports shall be submitted as
below indicating the reasons why the restriction cannot be removed and the details of
assistance needed to relax/remove the restriction. The reports shall be submitted at
such intervals as prescribed by the General Manager Permanent Way.
45.11 Figure 45.1 Location of Flags and Obstruction Signal for minor operation
outside station.
Figure 45.2 Location of the Indicators to be displayed for Major Operation
3 013S1RUC11otJ OF DANGER
SIGr~ALS
::0 "'
"' :s
!!l, "
6· 9!.
6'
"
<J)
~
DOUBLE LINE c.
NOTE;
ON SEC110NS WHERE VIEW IS OBS"TRUCTED OR WHERE 1HERE IS STEEPER
GRADIWT FALLING TOWARDS THE POINT OF OMJGER THE DISTANCE SHOWN
SHALL BE SUITABLY INCREASED TO ENSURE ABSOLUTE SAFETY AtlD IF
NECESSARY THE NUMBER OF DBSTRUCTIQtJ SIGNALS MAY BE WJCREASED.
C'l
""0
LOCATION OF FLAGS AND OBSTRUCTION SIGNAL FOR MINOR OPERATION OUT SIDE STATION LIMIT ::1 :r
'1"'5 "'
"'S,
(VIDE RULE F 25 OF GRR)
Fig. 45.1
.
'P
!" .. ""'
'0
~
~
;::1.
.... ~
"' <
Permanent Way Manual
Part V
Execution of Works, Speed Restrictions and
Chapter45
Indicators
Fig. 45.2
r---
I
'
I
•
~~I ~--
'
~i U1
' ' I lE ! z
,_0
"I ~I ' '"' I
~, ~, I I~ ~ -<>:
I' ~~ I
~
I'::!~
'
I '
~~ :
' I '
L!-~
.
0
~
il I
'
I
'
I 0
' ~
<( i_l "'
0
"-~
0
"'"'
1_~-:-
w "
' j
l "':::1z , "':::1z 0..
Vl eN
0
~ N
~
1: w
-' "'-'w CJ L..
ij "'inz
----T
::>
0
0
w ~
m =>
~
,- '
-~11
Wol
I'
,- 1 ~~
'
I
'
I
0
1-
U1
"'0
~
"'
w
Cl
>
~
~~
(.)
I
J8'
Cl
' ' z
I I : "-
' ' ~I I 0
J
~
J I
w• ' z
§
§ 1'll I 0
~
1 1 I
Chapter 46
Level Crossings
Document History
Issue Date Description
Authorised By:
~~~
Signature:
MOHD RAMLI MOHO NOH l8 MAY 201 p
Date: G1meral Manager Permanent Way
r.tre~p• taoan Metayu ~emaa
Kuala Lumpur
TABLE OF CONTENTS
46.1 GENERAL
46.1.1 This chapter prescribes the functions of Permanent Way Staff in respect of the inspection
and maintenance of Level Crossings and the precautions to be observed at such
crossings.
46.2 CLASSIFICATION
46.2.1 Level Crossings are classified as under:
46.2.2 A Public Level Crossing refers to the crossing of a public road by the Railway.
46.2.3 Where a road is necessary across a railway line to serve a particular requirement of the
Railway, like giving access to the Station or Goods yard or railway staff quarters, an
Occupation Crossing is provided.
46.2.4 An Accommodation Crossing refers to a crossing provided within three years of
construction of the Railway , for use by the owners and occupiers of adjacent land whose
access was interfered with, consequent on the construction of the railway line.
46.2.5 A Private Crossing is a crossing constructed after the Railway was built to meet the
needs of a particular person or persons.
Table T-46.1
. .·· ·• ,.,·. _:-:-\ _ _f'lJbl_!<:. l,eY_~I: _
1/~0.
' ',
_,:;::;-, :--: >_O,~,C::!JP~ti~n - · ACC0nlffl0d3tio0:::'; ,. ' ' ., >;c•,'
:·-P~rticu_l_ar--/-- ·
I ·_ -, _ crf?s_sio·g: '" ,d't_tissi~gc!.:-_.:-::r:~ -,.;<~:~r;~;~~~--6~{~;-};V
Private;' _ Ctos_sj_rig
,._,-- ___ ,- -.-_.,_.,_,,_,_
1. Normal position of gates Kept closed across Kept closed across Kept closed across Kept closed
or barriers: the Railway the road. the road. across the road.
*Note:
At all Level Crossings with non-interlocked barriers. Warning Boards shall be provided in
accordance with Rule 2.2A Chapter 7 of Appendix to the General Manual in the current KTMB
Rules and Regulation Book. They are erected along. the track at an adequate distance as
approved. by the Regional Engineer and Regional Signal Engineer, on either side of the Level
Crossing, to warn train Drivers to stop at the Warning Board, until a hand signal is exhibited from the
barrier. The Warning board shall carry the following inscription:
Communication
2. Gates/barrier (whether they swing easily, close properly and are painted
satisfactorily).
3. Gates with barriers padlocked (check, in addition, whether the padlocks are in good
order).
4. Gate slops (check whether of right length and in good order).
5, Gate lamp socket (whether in order and whether lamps can be easily placed in the
socket).
6. Visibility of approaching trains (check whether visibility is adequate if a person in a
road vehicle 5m from the rail on either side can see the train 500m away in either
direction, in the case of Public Level Crossings, Occupation Crossings,
Accommodation Crossings and Private Crossings).
Note:
If the visibility is not adequate according to the standard indicated above, speeds of
trains shall be restricted according to the available visibility as shown below:
Table T-46.3
450 80
360 55
260 50
200 40
140 30
90 25
50 15
46.9.2 Each Level Crossing shall be opened out periodically at intervals as specified by the
General Manager Permanent Way. The sleepers. rails and fastenings in the road shall
be thoroughly checked, cleaned and a coat of anti-corrosive paint applied. Flange-way
clearance, cross leve~. gauge and alignment shall be checked and corrected. Track shall
be packed thoroughly before reopening the Level Crossing to road traffic.
46.9.4 The PWI shall ensure proper upkeep and maintenance of all indication boards provided
at the Level Crossing.
46.9.5 The PWI shall arrange to remove the branches of trees, bushes or undergrowth that
interfere or tend to interfere with the visibility from the Railway or the road, when
approaching the Level Crossing.
46.10.2 The PWI shall prepare the draft of the notice regarding the programme of maintenance at
the Public Level Crossing (to be published as an advertisement) and forward it to the
concerned PWD Engineer for approval of the wording and issue. The Railway shall bear
the cost of the advertisement issued on this account.
LIST OF ANNEXURES
Annexure 46.1 Sample draft for the notice to be advertised for closing a public
road for maintenance of Level Crossing.
PEMBERITAHUAN AWAM
(b) Whether the gate has been painted white and red discs provided?
6. Whether red light meant for road users is blanked off towards the approaching trains
(except for a level Crossing with gates closing across the
track)? ................................................ .
7. Distance of gate posts from centre of track ............................................. .
8. Type of fencing and length .......................................................................
4. Interlocking and communication devices:
1. Normal position of gates (whether closed or open to road traffic}.............................. .
2. Whether barriers/gates are interlocked with separate signals or with the station
signals? .............................
4. Whether warning boards (on road) for road users have been provided? If so the type
and distance at which they are provided ............................
5. Whether "own risk" boards on road have been provided for occupation,
accommodation and private crossings? ................................................... .
5. Traffic:
1. No. of trains per day........................................ .
2. No. of road vehicles per hour.......................... .
6. Track Structure:
1. Type of track .................................................. .
2. Date of last overhauling ................................. .
3. Date of painting of gates ................................ .
7. Safety items:
1. Whether locking arrangements have been provided for both
gates? ..........................................
2. Whether spare chains have been provided for emergency
use? ............................................
3. Whether Working Instructions for the Level Crossing are available with the
Gateman? .................................. .
ON
sr
~~ UP ...
------------ ~
I
I
GATE FENCING I
5t I
OK OK
I
I _.;
Missin Damaae I
I '
Damaae Missin
I 0 D I
.. ~
Permanent Way Manual Part V
Patrolling of Railway Lines Chapter 47
Chapter 47
Patrolling of Railway Lines
Document History
Authorised By:
Signature: -- - ~-- Q
-A-LQ. \
TABLE OF CONTENTS
47.1 GENERAL
47.1.1 This Chapter deals with the types of patrol, system of patrolling and duties of various
Permanent Way_ Personnel associated-with patrolling. While performing patrol duty, Rule
6.7 of Section B (Part I - General) of current KTMB Rule and Regulation Book will
have to be followed, in addition to the procedures and regulations issued by the General
Manager Permanent Way Division.
47.1.2 Definition
47.1.3.1 When carrying out patrolling duties, the Patrolman must have with him at least six
obstruction signals, a red and green flag and, on a track circuited line, track circuit
operating clips and during the hours of darkness or heavy rain a hand-lamp must also be
carried. He must make an inspection in the manner laid down by the Permanent Way
Division. He shall carry with him the hand phone with the assigned phone number in
working order and adequately charged, to enable him to communicate with his
supervisor, colleagues or Station Managers in the area of his patrolling.
The Regional Engineer/CI/PWI shall instruct for certain sections of the railway line to be
patrolled to detect damage by flood, such as breaches, settlements, slips and scours and
immediate action taken to protect trains, wherever necessary, based on his own
information or upon advised by Station Masters or Train Drivers.
(Patrolman: competent permanent way employee instructed by the PWI to carry out
patrolling duties)
47.1.3.2 While examining the track in Track Circuited Double Track Bi-directional areas, the
Patrolman must select UP or DN track for walking such that he faces the normal direction
from which trains approach and must observe Clause 3.3.4(c) of Section B (Part I -
General) of current KTMB Rule and Regulation Book. However, this may not be
followed if UP and DN tracks have to be inspected in alternate cycles of patrol.
47.1.3.3 Before commencing his patrol he must communicate with the TCCC Operator or Station
Manager and obtain his assurance that trains will not be permitted to operate in the
reverse direction over the section of line concerned until the Patrolman has again
reported at the signal specified by the TCCC Operator or Station Manager.
47.1.3.4 After giving such an assurance the TCCC Operator or Station Manager must not permit
any train to operate in the reverse direction over the track concerned until the Patrolman
has reported from the signal specified, or in the event of a telephone failure at the signal,
from some other location, and has been warned of the reverse direction movement.
47.1.4 When the reverse direction movement is clear, the Patrolman must again communicate
witn the TCCC Operator or Station Manager. The TCCC Operator or Station Manager
may then give a further assurance that trains will not be permitted in the reverse direction
and give authority for the patrolman to continue and report from the next specified signal.
This shall be carried out daily by the Patrolman (or other nominated patrolman) on a
designated track length of 10km. For a double track area, two patrolmen must be
assigned to carry out patrolling for each line. For safety, every patrolman must be
accompanied by a Lookout man. If, in the opinion of the Regional Engineer, there is no
need to carry out the patrol every day (on track which is robust enough or on lines with
light and infrequent traffic), he may apply to the General Manager Permanent Way
Division to reduce the periodicity of patrolling.
47.3.2 The Regional Engineer shall ensure that the Instructions are understood by all the men
nominated to carry out patrols. During his or his CPWI inspections, he shall verify that
his Instructions are being. properly followed by the concerned staff.
47.3.3 Instructions for security patrolling by men, motor trolleys or special train will be issued by
the General Manager Permanent Way Division in consultation with the Operations and
Security Units.
47.4.1.1 The CPWI shall ensure that person selected for patrol duty understands fully what
constitutes a danger and what action shall be taken to protect trains. To this end, he
shall cause his PWis to select, from their Permanent Way gangs, intelligent, experienced
and trustworthy men, for patrolling duties. Twice the number actually required shall be
selected, trained and tested to be conversant with their duties, procedure for protection
of trains and vulnerable locations needing special surveillance in their beats. A list of
such men shall be obtained from the PWis.
47.4.1.2 The CPWI/ PWI shall ensure the following, with respect to the man selected to perform
patrolling duty:
a. He must have basic literacy in reading kilometre, writing and communicating in
Bahasa Malaysia (Malay Language).
b. He must be physically fit to walk long distance on track, with no colour blindness.
47.4.1.3 In case of heavy requirements of patrolling, the strength of the Gangs shall be recouped
to the extent reduced by withdrawal of men for patrolling, as directed by the Regional ·
Engineer or the General Manager Permanent Way Division. Additional lookout men will
be required to be deployed in Double Track areas.
47.4.2 Equipment
The CPWI shall ensure supply of adequate equipment required by patrolmen in time
according to the lists below.
47.4.2.1 Equipment for Patrolman
Periodical Patrol:
• Whistle
• Tri-colour torchlight during darkness or Heavy rains.
• Electric or Gasoline lamp for illuminating the inside of long tunnel (day or night}
• Personal Protective Equipment (PPE}
• Raincoat
• Trunk radio (or Mobile/Satellite telephone where required)
• Patrol Form
Special Patrol - (night)
A. The system shall be such that the Station Masters at either end will advise
each other and issue Caution Orders to trains unless the designated patrolman
has reached the station after covering his beat, signifying that all is well. The
CPWI shall ensure that suitable instructions to this effect are included in the
Standard Instructions issued by the Regional Engineer, with the concurrence of
Operations Division/Regional Manager. He shall work out schedules for
patrolmen (assuming a walking speed of three kilometres per hour, beats of
about five kilometres, rest periods of half an hour between beats, and
B. The CPWI shall check that the level of the previous highest flood (HFL) has
been marked on the bridge structures so as to be clearly visible to a patrolman
on the track. On those bridges with a history of damage by floods, the CPWI,
with the approval of the Regional Engineer, shall cause a 'Danger Level' (DL)
to be marked, so as to be clearly visible to a patrolman on the track. An
Operating Standing Instructions shall provide for the traffic to be stopped
by the patrolman in case flood level exceeds the DL on any bridge.
Observations to be carried out and actions to be taken during Hot Weather Patrolling
shall be as specified in Chapter 25.
47.4.5 General
The PWI/CPWI shall check on lhe extent and quality of patrolling carried out, during
normal and surprise inspections, especially at night as well as periodically checking the
nominated patrolmen's techni.cal competency and knowledge of the Rules. Patrolmen
who, due to their alertness and prompt action, avert accidents shall be suitably rewarded.
The PWI shall report shortages of equipment, if any, well in time to enable the CPWI to
make it up before the need for patrolling arises. He shall inspect all equipment once a
month and ensure adequate supplies of consumable items like detonators and cell
batteries for torches.
47.5.3 Periodical Patrol
The PWI shall familiarise himself of track stretches vulnerable for the development of
Sink-holes (adjoining functional and non-functional lime quarries), flood-prone areas,
weak cuttings and embankments with history of slope failures, falling of boulders, etc.
He should in turn notify the Patrolmen/Gangers about these locations of potential
dangers.
The PWI shall check during his inspections that:
1. The PWI shall pass on to the Gangs promptly any warnings he may receive about
heavy rainfall or storms and verify that during such occurrences the Gangs go out
on patrol.
2. Where night patrolling is in force, he shall carry out surprise night inspections, by
train or trolley, and verify that patrolling is according to the Standard Instructions and
if Station Masters have received and are acting on these Instructions.
3. The PWI shall ensure the implementation of the type indicated in Clause 47.4.3
above.
The Ganger shall do part of this patrol, if instructed by the PWI. Once a week, he shall
exchange duties with the patrolman and patrol the section so as to be in touch with the
whole length of the Gang. He shall also arrange to be briefed by the patrolman on
return from patrolling about any special features noticed, especially on the items
indicated below. He shall in turn advise the PWI of defects needing urgent attention as
necessary.
1. General alignment and level.
2. Articles fallen on track.
3. Fractured/damaged rails. Those marked red by ultrasonic testing shall be
examined carefully.
14. Fires.
15. Bridges - general condition, blockage of waterway (observe from track level on
every patrol, but look under each bridge and above each overbridge once a
fortnight where practicable).
47.6.2.1 The Ganger and the patrolman shall carry out a special patrol of the gang's length during
heavy rains. On receipt of advice from the PWI warning about bad weather the Ganger
shall be prepared for emergency deployment of the gang if required.
47.6.2.2 The Ganger shall also make sure that men selected from his Gang for patrolling duties
are:
47.7.1.1 The patrolman (or the Ganger) on patrol duty on single line section shall walk outside
one rail on the outward trip and outside the other rail on the return trip at an average
speed of 3 km/hr generally looking out for the items listed in Table T- 47.1 below. In high
speed Class I lines and in busy Commuter trains sector, the inspection procedure shall
remain the same and the patrolling shall be carried out for the Up and Down line every
72 hours facing the direction of the train. He should judiciously take care of his personal
safety, while walking on the track, as far as possible, in order to get good visibility of the
defects. Additional lookout men will be required to be deployed in Double Track areas to
watch for the safety of the patrolmen.
47.7.1.2 He shall be especially vigilant at locations:
Items to be inspected:
Table T-47.1 list the items that shall be observed for changed/deteriorated/unsafe
conditions as revealed by visual inspection. Any further detail inspections or
measurements deemed necessary shall be reported to the PWI for further action.
TableT- 47.1
Rail Crack, Breakage, etc., Rail-top surface defects (wheel burn/scab), Closer look at
known defects locations marked by Ultrasonic Testing.
Drainage Drain blockage, overflowing, breakage of pipe carrying water near track, likely to
erode the bank
Turnouts (TO) Breakages, Line and Level, Bolts, Fasteners and fillings (missing, bent, cracked
or broken), Unusual gap at the lip of a switch rail housing with the stock rail, as
noted on the main line over which the patrolman walks
Non-interlocked TO Clamps and Locks of the switches in position or not, Spike-locking in good order
or not (While walking on UP/DN track, non-interlocked points in DN/UP track
should also be inspected.)
Slab track Condition of fasteners, Shaking of Rail bearer blocks, concrete cracking
Switch Expansion Joints Condition of rails, if the gap falls outside the specified range.
(SEJ)
Rail Expansion Joint Condition of rails, Any misalignment of gauge face, as per special maintenance
(REJ) in Prai Swing instructions governing the REJ.
Bridge
Track on Prai Swing Rail fasteners /fittings missing, Guardrails and its fasteners, movement of pads,
Bridge condition of steel sleepers and their fillings
Vegetation Obstruction to line of sight, Fire hazard, fallen or falling trees, potential tree
branches or fronds and other overhangs on Overhead Catenary System
'
TableT- 47.1 (Continued)
Encroachment, squatters Any sign of unauthorized occupation and activities being attempted
and unauthorised
construction activities
Slopes & Banks Sign of erosion/Slips/bulging and potential factors for the same,
Passing Trains ObseNe any unusual noise or sound, hanging parts, unusual or foreign items
etc.
Signalling and Noticeable damages or vandalism, loose connections to rails and track
Electrification Installations components or hindrance to rail and track components
47.7.2.4 During the patrol, he shall carefully lookout for the incidence of items listed below.
Items to be looked for by Special patrols during the rainy season.
Formation:
Note: In all these cases, danger is to be apprehended and action taken to protect trains.
47.7.2.5 If he apprehends danger, immediate action shall be taken to protect traffic in terms of the
KTMB General Manual in force and inform the nearest Ganger/Senior Permanent Way
worker and the TCCC operator and the Station Manager.
47.7.2.6 When no danger is apprehended, the patrolman shall stand on the cess, facing the train,
in case one approaches, and exhibit his number plate, throwing the light of his lamp on it,
so that the number can be clearly seen from the train. He shall also blow his whistle
when the locomotive and brake van pass him.
47.7.2.7 He shall heed instructions from Drivers (verbal communication through telephone or
direct instruction when the driver stop his train to convey his message to the patrolman)
who may report apprehended danger at a location, to which the patrolman shall proceed
and take necessary measures.
Every patrolman should submit a written Report in the prescribed format to the PWI on
the day of patrolling, on finishing his duty. He should record the Adverse Observations
made by him along with the location or a "NIL" statement. PWIICPWI shall create a
system for collecting these Reports from all patrolmen on the same day.
Every patrolman should also maintain his handbook in which the same observations
should be recorded in chronological order. One handbook will be assigned for each
patrol beat and this will not be individual based. In other words, if Person B takes over
patrol duty from Person A for the same beat, the handbook will pass hands from A to B,
through the Station Manager. The handbook will be deposited with the Station Manager
at the end of Patrol duty. This will be taken by the next person on duty.
The PWI will compile the salient observations screened from the Adverse Observations
in the prescribed form on monthly basis, making entries from time to time. Rectifications
should be carried out as per the priority and importance, without waiting for the
compilation of the entire monthly report. This monthly report should also receive entries
regarding rectification. PWI, CPWI and the Regional Engineer shall share the information
and take action at the appropriate levels depending on the importance and urgency.
Relevant observations shall also be advised to the concerned Division or Units, such as
Signalling, Electrification, Facility Management, Bridge Unit, etc.
The Regional Engineer shall ensure implementation of the above procedures and record
in suitable formats the "Monthly Report of Patrolmen's Observations and Actions Taken",
PWI wise, and CPWI!Regional Engineer wise. EXCEL software may be adopted, so that
sorting is possible. Also, sharing on real time basis is enabled among the concerned
officials and the Permanent Way headquarters office.
LIST OF FIGURES
Figure 47.1 Specimen Patrolling Chart
LIST OF ANNEXURE
Annexure 47.1 Proforma Patrolman Report (Patrolman Form)
HOURS HOURS
17 17
1.R
@ r-- f(i)_ __.. (18.22 )
~k- _N_o.'2. l-(2)-
19 ~
19
f(. .Jil' 1-"
. '1 ( 19.41 ) R"'
20 20
404.DN.20.18(d) r---
( 21.00
:ll.llllOJ
( 22.25
-
I-· ·-
lz1y~
~ r---
I-· ·-
--- 1--- ~~
r-· I-• ·-
\.2)-
--r-
1--- 20.2B(a}
21.00
21.02{d)TRAIN.241.UP
?'>
22.25
t--- f...-
23
I& -No.2 ~ 1(.-~
23
23.50(o) 1--- -- -- 1--{ 23.44 ) - - --- --- r--- 23.39(d) TRAIN 405 UP
24 24
1 1
2 2
3 3
( 3.51 )
4
1)
......- -- r-.... \2)..
4
5.10 5 e¥-;:::. ~ ~ ~
~~
5( 5.10 )
•• 3(d) - - - - - - - - -
- -- --
6
r 1 2
~---------~~K~---------~
:l
---
4 J
5
~
6
-'
7 8.~5
8'
5.23(o)
6
STAllON A STAllON B
Km 0 Km 8.~
REFERENCE : -
I) --0-D---INDICATES PATROLMEN
:u
91.
-.,
:E
~ .,s:
::0 '<
-
(!)
--- . - -- - - - ---·- --- - --- -- --- --·----
"t:! '<
0 c:
::+
""'"' ""!!!.
..-...
~
"tJ
...,3
::I
-3 I
n
.,
:r
~
"'... .,;:l.
~
"S. "'C
"'Sl,
~
:;, <
"'
(51~TIIII
Permanent Way Manual Part V
Working of Trolleys and Trailers Chapter 48
Chapter 48
Working of Trolleys and Trailers
Document History
Authorised By:
~ _, ......0 -
~
DQI \
Signature:
Date: ,..,MOHD RAMLI pMOHD NOH 2 8 MAY 201~
-· :WaY
Kere(oDpt Tanah Melayu Berttad
Kuala Lumpur
TABLE OF CONTENTS
4801 GENERALoooo ooooooOooooooooooooooooooooooooooooooooooo ooooooooooooooo oo oooooooooooo oooooo Ooooooo Oooo oo oooo ooooooooooooooooooooooooo3
4802 GENERAL PRECAUTIONS 00 00000000 00000 00000 00 0000000 0000000000000000000 0000 000 0000 .. 00 0000000 0000000 000 0000 000000 00 00 03
4803 WORKING OF TROLLEYS AND RAIL INSPECTION CARS 0000 00 00 0000 00 00000000 000000000000 000000 0000 3
48.4 OPERATING AND MAINTENANCE CERTIFICATIONoooooooooooooooooooooooooooooooooooooooooooooooooooooo4
48.1 GENERAL
48.1.1 Any mechanically operated 4-wheeler rail vehicle used . for inspection purposes and
conveyance of workers and materials is called a trolley.
48.1.2 A road-rail vehicle is a vehicle designed essentially for operation on road but fitted with rail
guidance equipment to permit the vehicle to operate on rail.
48.1.3 A rail trailer is a small non-powered vehicle filled with rail wheels which enables it to be
hauled on rail by a road-rail vehicle or a trolley. lt is attached to the trolley with a coupling
and is principally used for conveyance of materials.
48.1.4 The rules to be followed for working of trolleys is the same as for working of trains (Section
C of the General Manual in the current KTMB Rules and Regulation Book.).
48.1.5 All drivers and permanent way staff in charge of trolleys must hold a valid driving
certificate issued by the Operations Division after duly testing on the rules.
48.2.2 No trolley shall be placed on line unless it is accompanied by a person certified competent
by the Regional Engineer to work a trolley.
48.2.3 No Material trolley or Inspection Trolley loaded with material shall be placed on the line
without receiving permission of the Station Managers concerned in writing and unless in
charge of an Engineer, Inspector or an official authorized by the General Manager
Permanent Way.
48.3.2 Motor trolleys and Rail Inspection Cars shall be governed by the Rules and Regulations for
the working of trains and shall be treated as light engines for the purpose of protection in
case of breakdown or accident, as specified below:
immobilise and secure the trolley and be governed by the rules applicable to a train failing
in the Block section. The Driver shall then report to the nearest station explaining the
circumstances.
When trailers are hauled or pushed by Motor Trollies, the speed shall not exceed
the following limits:
Through turnouts and station yards, the speed of Motor Trolleys and Rail Inspection Cars
shall not exceed 10 km/h.
48.3.3 Every loaded Material trolley shall have six men with it, two men acting as flagmen.
48.3.4 The speed of a Material Trolley shall not exceed a walking pace.
48.3.5 Protection as for Trolleys working in line possession shall be as follows:
48.3.5.1 Be furnished with obstruction signals and place three on the line, ten meters apart,
immediately the Trolley comes to a stand for the purpose of either unloading or loading and
48.3.5.2 Continue to show Danger hand signal and keep the obstruction signals on the line until a
messenger arrives with an order from the Ganger or other person in charge of the operation
to withdraw the signal, and
48.3.5.3 The distance between the trolley and the flagmen exhibiting signals shall be not less than
BOOm and further increase if the working area is on a curve and in gradients, where sighting
distance are less.
48.4,;2 Vehicle certification will be dependent on the vehicle having appropriate and auditable
maintenance and inspection records. Such vehicles shall have their rail operating suitability
status re-certified annually. The Regional Engineer is responsible to liaise with the
Permanent Way Depot engineer to ensure that any road-rail vehicle, trolleys and trailers are
certified fit for operation and each vehicle pre-work inspection checklist is sighted and
endorsed the Permanent Way Depot Engineer, before such vehicles are placed on rail.
Such documents shall be retained and filed by the Permanent Way Depot Engineer for audit
purposes.
Chapter 49
Working of Self-Propelled
On-Track Machines
Authorised By:
Signature:
~- '
Date: A
MOHD RAMLI MOHD NOH
••. . ... iWA\1
2 8 MAY 2015
Kere~pi Tanah Melayu Berhad
Kuala Lumpur
TABLE OF CONTENTS
49.1 GENERAL
49.1.1 This chapter summarizes the rules governing the running of heavy machines used for
maintenance of track, with emphasis on certain important precautions. Such machines
are termed self-propelled on-track machines as they cannot be off-loaded from the track
and can run under their own power.
49.1.2 The technical aspects of working of these machines are contained in Chapter 22 - On
Track Machines for Track Maintenance Works -of this Manual. The rules for running and
working of the machines are contained in Chapter 14 & 15 in Appendix of the General
Manual of the current KTMB Rules and Regulation Book.
49.2.2 The Regional Engineer shall ensure that no on-track machines work on the Open Line in
his Region unless covered by the General Manual in the current KTMB Rules and
Regulation Book, or by Special Instructions.
49.3.2 When more than one machine is used in the same Block Section, the Permanent Way
Officer in charge of the Line Possession shall be personally responsible to coordinate the
movements of the machines to and from the point of work and to ensure safety in
operations. The Permanent Way officer in charge of the work will act as PICOP.
Permanent Way Division in accordance with the conditions as envisaged in Part Ill
section J of the General Manual in the current KTMB Rules and Regulation Book.
49.4.3 Equipment
Each machine on line shall be equipped with the documents and equipment listed below:
1. Awatch
2. Tail lamps
3. A copy of the Working Time Table in force.
4. Notices of any special trains.
11. A trunk radio (walkie talkie or mobile telephone where applicable) for each group of
machines.
12. Two sprags per machine
13. Two banner flags for use by day,
and such other equipment as instructed by the Regional Engineer I CPWI I PWI or as
may be prescribed under Special Instructions.
49.4.4 Responsibility of the Driver/Operator
1. The machines shall not run at speeds more than that prescribed by the manufacturer
or those indicated below, whichever is lower.
2. These speeds are for the machines in use at present, restricted by Special
Instructions, if any, for a particular type of machine. For equipment acquired later,
permissible speed shall be specified for each machine by Special Instructions. All
speeds shall be subject to local restrictions.
An on-track machine may be attached to a Goods train provided the Driver/Operator also
accompanies the machine and the maximum speeds as indicated in Clause 49.4.5 are
not exceeded. When so attached, the machine shall be immobilized, ensuring that it
cannot move under its own power {according to the relevant operating instructions for the
particular machine). The Driver/Operator shall be responsible to see that this is done
while accompanying the machine.
When driving under its own power on a running line, the machine shall be kept in gear.
When left unattended, the machine shall, in addition to being left in gear, be secured by a
Hand Brake.· If on a line with gradient, sprags shall also be used, to prevent the machine
from rolling down the gradient.
2. The tablet/token or train staff forming the Section Authority shall also be obtained by
the PWI or the Chief Operator of the machines.
3. AI the site of work, trunk radio {walkie talkie or mobile wherever applicable)
telephone system of communication shall be established with the TCCC or by any
other suitable phones provided by the Regional Engineer.
4. During the period of Line Possession, all movements within the area of the Line
Possession shall be regulated by the PWI of the Line Possession who shall also be
responsible for safe operations.
5. The PWI shall endeavour to finish the work so that the time limit of the Line
Possession as agreed with the TCCC Operator is not exceeded.
6. Before the withdrawal of Line Possession working, the PICOP or PICOW must
endorse in KTM 032 that line is clear and safe for trains to run.
7. In the case of a Line Possession in a Tokenless area, the relevant provisions of the
General Manual in the current KTMB Rules and Regulation Book must be
complied with until the Line Possession has been removed.
49.4.9 Failure of On-Track Machineries in a Block Section
In case an on-track machine fails in the Block Section and is not able to run under its
own power, it may be assisted by a locomotive, the speed not exceeding 30 km/hr on
plain line and 20 km/hr over switches and crossings along the diverging track, the
Driver/Operator riding on the machine.
In case an on-track machine derails but on re-railing the Driver/Operator is satisfied that
no serious damage has resulted, the machine may continue on the work. Otherwise, it
shall be taken to the nearest Station or stabling point by the Driver/Operator at a slow
speed. Before the machine is again put into operation a Fit Certificate from authorised
staff (after examination) shall be obtained.
49.4.11 loose-Shunting
On-track machines shall not be loose-shunted. No vehicle shall also be loose-shunted
against such machines.
Chapter 50
Schedule of Inspections
Document History
Authorised By:
Signature:
Date: B· MAY 20 5
TABLE OF CONTENTS
50.1 GENERAL
50.1.1 This chapter indicates the maximum intervals between successive inspections, by
different categories of Permanent Way Staff, of various items of Permanent Way and
related structures. Their functions during the inspections are detailed in the Chapters
dealing with inspection and maintenance (Chapter 40 for Turnouts, Chapter 41 for
Bridges, Chapter 42 for Tunnels and Chapter 46 for Level Crossing) and with the duties
of officials. 11 shall be understood that more frequent inspections may be necessary to be
carried out, based on the conditions of the Permanent Way.
50.1.2 The Regional Engineer shall maintain a system (preferably computerised), to monitor
the inspections carried out by his staff. He shall obtain and forward to the General
Manager Permanent Way, every month, a list of shortialls in inspections with reasons
therefore.
50.1.3 The Regional Engineer shall forward once in six months to the General Manager
Permanent Way, a chart indicating the Permanent Way inspections done by him during
the preceding half year.
50.1.4 The dates on which the list of shortfalls and the Regional Engineer's charts are to be
forwarded will be specified by the General Manager Permanent Way Division.
50.1.5 11 is the duly of an inspecting official of the rank of CPWI and above to record his
observations during the inspection in brief in an Inspection Note. He shall ensure that
instructions arising from the inspection are received promptly in writing, acknowledged,
understood and implemented by the staff concerned. A copy of the Inspection Note shall
be promptly forwarded to the immediate superior of the inspecting official to enable the
latter to be briefed about conditions observed during the inspection.
50.1.6 In addition to the inspections, opportunity shall also be taken where practical to observe
the track under traffic especially for stretches of track with reported poor riding
conditions. An unscheduled detailed inspection shall also be made where an unusual
occurrence or incident has been reported from any source since the last inspection. This
might include derailments, rail breakages, mud pumping locations, subsidence in the
track, a wildfire or a trespass report.
The PWI shall travel over his entire section in the locomotive or rear vehicle of the fastest
day-time train, or by trolley once every two weeks.
50.2.2.2 BytheCPWI
The CPWI shall cover the entire Region in a locomotive of a train at intervals of not more
than two weeks. However the entire Region must be covered by trolley once in a
month.
50.2.3 Inspection by the Regional Engineer
The Regional Engineer shall cover his Region once by trolley or by the locomotive or
rear vehicle of the fastest day time train (s) on his Region at intervals not exceeding one
month. However the entire section must be covered by trolley once in two months.
50.3.1 Turnouts shall be subject to detailed inspection as indicated in the schedule below when
all parameters specified in Chapter 40 shall be checked and documented.
50.3.2 All turnouts over which trains run through on the straight at the maximum permissible
speed of the section shall be subject also to a less detailed inspection where the
alignment, cross level near the crossing and wear at the crossing shall be checked
according to the schedule below:
Note:
50.4.1.1 The PWI shall inspect each Level Crossing once in every three months to check items
as per Chapter 46, clause 46.7.2
The Regional Engineer shall carry out general visual inspection of all Level Crossings in
his Region at intervals of not more than one year.
The PWI shall inspect all bridges and tunnels once a year. He shall also visually inspect
bridges and tunnels as necessary during his normal inspections and bring to the notice of
the Bridge Engineer/Bridge Unit any defect noticed.
50.5.2 BytheCPWI:
The CPWI shall inspect those bridges which are referred to him by the PWI as soon as
practicable. The CPWI shall inspect all the bridges and tunnels in his jurisdiction once a
year.
50.5.3 By the Regional Engineer
The Regional Engineer shall inspect all bridges and tunnels on his Region once a year
(he shall also inspect bridges and tunnels as necessary during his normal inspections
and bring to the notice of the Bridge Engineer any defect noticed). The General Manager
Permanent Way may specify certain bridges on structural/hydrological considerations to
be inspected by the Regional Engineer periodically.
50.9.2 In cases where planned urgent immediate remedial works have to be postponed such as
Tamping Machine breakdown or cancelled line possession, then the work must be re-
planned as a the first priority item instead of being placed at the end of queue in the list
of pending remedial works.
50.9.3 A weekly report shall be submitted by the PWI on the actions taken and outcome of the
actions to the Regional Engineer. The Regional Engineer shall prepare a monthly
summary of exceptions where further actions or assistance are needed from the General
Manager Permanent Way. A typical format is shown in Table T -50.3 (Priority Defect
Action List).
50.9.4 The electronic storage of each record shall be initiated by the official making the
inspection within 24 hours following the completion of that inspection. Paper copies of
electronic records and- amendments to those records shall be made available for
inspection by the Regional Engineer and/or the General Manager Permanent Way.
Table T-50.2
Schedule of Inspection
.L1 I~b~~n';~i i": > ,, I ~ ' , • , > ..·.'·Frequlillc~ Pre~trlbE!d t()r' .•.. ·'·,.· · · •·..·•.·..·••:••·. ·••
..
'····..· ' . . . CPWI<
,• •• .J /;··r•
r~.f i> ''1:!. !•''>• t!WI ...
.· . .. .. i ···y,R~Q,ional···. •.·
Note:
Slope inspection and maintenance can be referred to Civil Works Maintenance Manual
(2014) documents produced under the lpoh to Padang Besar Double Tracking project.
Table T-50.3
Typical Priority Defect Action List
INSPECTING OFFICER:
Name:
Position:
z
~ 0i=w ...
z
Qw ow
on. wa. DATE
DATE LOCATION
t-O
<o DEFECT
go
"' :n
0 U.>-
Wt-
ACTION TAKEN REMOVED BY
REMOVED
-' "'
a. <I)
~
0
Chapter 51
Procedure for Obtai_ning Approvals
Document History
Authorised By:
\- ~ _Q #~~~
--(/
Signature:
Date: MOHD RAMLI MOHD NOH
General Manaaer PennaneotW_~tv_
2 8 MAY ZOl
Kere~pi Tanah Melayu Berhad
Kuala lumpur
TABLE OF CONTENTS
51.1 GENERAL
51.1.1 Approval of the competent authority is required for execution and commissioning of any
work affecting safety of running trains, including the temporary arrangements necessary for
carrying it out. This (statutory) approval shall be obtained before commencement of the
work, which shall be inspected and certified by a nominated authority before the work is
commissioned.
51.1.2 This Chapter prescribes the system to obtain approval of the authority specified in Clause
51.3 for execution and opening of works (new works or additions and alterations to existing
works of the type indicated in Clause 51.2) affecting the safety of running lines. Aspects
covering the precautions to be taken before commencement and during execution of major
and minor operations and for undertaking emergency repairs have been covered in Chapter
45.
51.1.3 Section F of the current KTMB General Manual prescribes the procedures for operations
involving obstruction of line or danger to trains or traffic. In case of any contradiction
between the contents of this chapter and the provisions in the General Manual, the General
Manual shall prevail.
51.3.1 The Government (where applicable) shall approve the execution of all new lines, doublings,
permanent deviation of existing lines and extensive yard remodelling. KTMB shall be
competent to approve the execution of all other works.
51.3.2 Inspection shall be carried out by the authorities specified in Clause 51.6 before they
authorise a new asset to be commissioned.
During or before execution of approved work, if any deviation (from the approval) which will
affect the layout of lines arrangement of signals or the working rules is found necessary, the
specific approval of the authority which issued the original approval as referred to in Clause
51.3, shall be obtained.
Where the works involve the Signalling and/or Electrification Unit, the CPWI shall liaise with
the Regional officer of the Signal and Communication Division and/or the Electrification
Division so that Permanent Way and the respective Signalling and /or Electrification works
progress simultaneously. Testing of installation and issue of certificates shall be done by the
designated Officers of the respective Divisions/Units.
51.6 INSPECTION
On completion of the work, the CPWI shall advise the Regional Engineer who shall arrange
for the inspection by the concerned authorities as indicated in Table T-51.1. After
inspection, a certificate shall be issued and advice sent to the General Manager Operations.
Table T-51.1
AUTHORITY COMPETENT TO INSPECT AND CERTIFY
(a) For convenience G.M. G.M. G.M Operations G.M. Permanent Way
of public. Permanent Way Permanent Way can delegate to
Regional Engineer.
5. All other works Regional Engineer Regional Engineer Regional Operation G. M. Permanent Way_
Manager can delegate to
Regional Engineer.
51.7.1 General
No new work affecting the running of trains or the system working at a Station shall be
brought into use until staff of all departments has been notified and those concerned certify
that they have understood the new/ revised Working Rules. The Operations General
Manager shall arrange for timely intimation of the date of commissioning to all concerned so
that the staff get acquainted with the new or revised Working Rules.
"1/We hereby certify that 1/We have personally inspected and tested ...................... and in
my/our opinion this ............................. .is fit to be brought into service ........................... .
51.7.4.2 The representative of the Operations Division shall endorse in the commissioning certificate
as under:
"I hereby certify that I have personally witnessed the above mentioned testing and have
taken over for service at .................. on .................................. .
51.7.4.3 The certificates shall be prepared and despatched immediately direct to the:
During construction of a new line or siding, Ballast Trains shall be permitted to operate with
the following safeguards:
• When the siding points are within the Station Section, the Operation Division shall
be responsible for safeguarding them by clips and padlocks in accordance with Rule
26 of Section J, Part I, General Manual in the current KTMB Rules and
Regulation Book.
• When the siding points are outside the Station Section, the Permanent Way Division
shall be responsible for safeguarding them in the same manner prescribed above.
51.10.1 When new lines or sidings are constructed, the entry to them shall remain under the control
of the Permanent Way Division or his authorised representative, until the new lines or
sidings are formally taken over by the Operations Division. The relevant switches shall be
spiked, wedged and clip locked and the keys shall remain with the PWI.
51.10.2 If, for any special reason, traffic is to be permitted on such lines before the formal handing
over, the following conditions shall be complied with.
Chapter 52
Safety on Track
Document History
Issue Date Description
Authorised By:
(
Signature:
Date: 2 8 MAY 2015
TABLE OF CONTENTS
52.1 GENERAL
52.1.1 This chapter deals with the duties of Permanent Way staff in keeping the track safe for
trains carrying the travelling public and goods and for the employees working on or near
the track. The current KTMB Rules and Regulation Book contains rules applicable to
Permanent Way staff. These rules are to be implemented rigorously by all Permanent
Way staff. In case of any discrepancy between what is stated in this chapter and that in
the current KTMB Rules and Regulation Book, in force the latter shall prevail.
52.1.2 Requirements for safety related to a specific operation are spelt out in the relevant
chapters, as, for example, execution of works in Chapter 45 and the working of trolleys
in Chapter 48. In this chapter, procedures for general adoption are described.
52.2.2 Wear approved clothing correctly. During darkness, have a torchlight or lamp with you.
52.2.3 Use the cess which is normally the safest place. Never walk on the track.
52.2.11 Do not enter a tunnel, unless your duties require it and must be accompanied by another
person. Always take a torch light. When a train is approaching, reach the nearest
refuge.
52.2.12 Cross the track by bridge or subway whenever you can. Otherwise choose a route with
the best view, clear of obstructions and cross at right angles.
52.2.13 Look in both directions before crossing each line.
52.2.14 When stepping from one line to another, do not move into the path of a train.
52.2.15 Do not step in the gap between stock and switch rail.
52.2.16 Keep clear of signal wires, point rodding and other equipment or material.
52.2.17 Do not cross in front of or between moving vehicles. Do not go under any stationary
vehicle. Cross the track beyond the stationary vehicles after ensuring that they will not
be moved and there is an adequate safety buffer clearance of minimum 15 metre to the
nearest vehicle.
52.2.18 If you are caught between adjacent lines with trains approaching on each side of you and
you cannot reach a position of safety, lie down flat between adjacent tracks.
52.2.19 Where obstruction signals are placed on track, stand at least 30 meters away with your
back to the detonator, if a train passes.
52.2.20 Always regard overhead line equipment and its attachments as being alive at all times.
• Keep yourself and your clothing and equipment at least 2.75m from:
Anything live attached to or hanging from the overhead line equipment.
Any broken or displaced live wire connecting to the overhead line equipment.
• Do not attempt to climb any structure which might bring you, your clothing or
equipment within 2. 75m of the overhead wires.
• Do not work on any plant or equipment which could bring you within 2.75m of the
overhead line equipment.
• Observe the instructions in the Personal Track Safety Handbook.
52.3.2.1 Works executed on or near the track shall be under the control of a nominated person
referred to as PICOW (Person-In-Charge-of-Work). He shall possess a competency
certificate as in Annexure 52.1.
52.3.2.2 He shall ensure that a safe system of work is adopted to safeguard employees on or
near the track. He shall also take necessary measures to prevent anyone from being
endangered by trains.
52.3.2.3 Duties of PICOW are given in Annexure 52.2.
52.3.3 Look-outs
PICOW shall decide the works reqUinng look out protection. He shall make
arrangements for appointing and positioning of the Look-outs. The duties of Look-outs
are given in Annexur~ 52.3.
52.3.4 Caution orders
52.3.4.1 When P1COW or the PWI finds it necessary that Drivers be given special instructions
concerning repairs to the track, restrictions of speeds etc., he shall hand over a written
advice to the Station Manager of the station immediately preceding the affected Block
Section. He shall request the Station Manager to take the necessary action to warn
Drivers to exercise caution or observe speed restriction as the case may be. He shall
also specify the points between which the caution or speed restriction is to be observed
and the cause. Installations of the necessary caution boards, speed boards and speed
termination boards shall be carried out not later than 24 hours after hand over of the
written advice of the speed restriction to the Station Manager.
52.3.4.2 When the necessity no longer exists for the issue of the Cautions Orders, PICOW or the
PWI shall notify the Station Master on either side of the affected Block Section to this
effect.
52.3.5.1 The procedure illustrated and described below is based on the current KTMB Rules and
Regulation Book. PWis shall ensure that those detailed on patrolling duty and other
duties are trained and drilled in this procedure.
52.3.5.2 "Clause 2.2 Section 'B Part 1 of the General Manual in the current KTMB Rule
Book" in force shall be complied with.
• When a Lookout has been appointed, make sure you know the method by which
warnings will be given. Also know the position of safety to which you must go when
a warning is given.
• When the Lookout gives the warning, immediately acknowledge the warning by
raising on arm above your head, and go to the position of safety.
• When the train has passed, remain in the position of safety until your PICOW has
indicated that work can safely be restarted.
• If for any reason you cannot see the Lookout or it is possible you may not hear the
warning, move to the position of safety and inform the PICOW.
• Leave tools and materials clear of the line and not within 2 meters of the rails during
the passage of a train.
• Do not leave tools or materials where they obstruct refuges, recesses, walkaways or
walking routes.
• Do not put flammable material near cables or cable troughs or allow fires to burn
near them.
• Do not obstruct warning notices indicating high voltage cables, and markers
indicating cables.
• Enter or leave the machine only on that side where there is no adjacent track open
to traffic.
• If it is necessary to attend to the machine from the side where there is an adjacent
line open to traffic, obtain the look-out man's permission.
• Figure 52.1 indicates the free and restricted areas.
• Do not ride on material wagons when travelling to or from the site of work.
• Do not get off the train on to an adjacent line, except under the protection of a
lookout.
• When walking alongside a train which is moving, take particular care where you are
treading.
• Do not use metal measuring tapes or chains across the lines or place metal objects
across the rails.
• When trees are being felled or trimmed or undergrowth cleared, ensure that the
debris does not endanger the passage of trains.
• Do not attempt to clear more trees, branches or undergrowth than you have been
told to do.
• Avoid damaging railway equipment.
52.4.10 General
52.5.1 Protect the sites of work so that trains are alerted in time to stop or slow down short· of
such locations. For details refer to Chapter 45.
52.5.2 Maintain clearances to structures adjacent to or above the track to the prescribed
dimensions, so as not to. foul with coaches or with passenger's limbs, even if they
happen to be projecting outside the coach profile. For details refer to Chapter 11.
52.5.3 Anticipate and detect failures like rail breakage, failure of formation/bridges during heavy
rains/floods, in time by means of timely and adequate inspection and patrolling and
adoption of emergency measures to protect trains. (Refer to Chapter 47 for procedures
with regard to patrolling, Chapter 40, 41 and 42 with regard to procedures on
inspections and Chapter 43 on measures before and during periods of rainy weather).
52.5.4 Distinguish between works which do not require imposition of speed restriction
immediately after execution and the works which necessitate imposition of speed
restriction after the work is undertaken. Typical examples in each category are indicated
in Annexure 52.5. Special precaution is required in handling works which require
imposition of speed restriction immediately after completion of the work.
52.5.5 Execute routine track maintenance operations in such a way that normal train operations
are not affected. The desirable practices are:
• Report promptl)l any defect or adverse feature in the condition of bridges which is
likely to interfere with the safe running of trains, taking immediate action to stop or
slow down trains if warranted.
• Maintain man-refuges, wherever provided, adequately
52.7.2 Tunnels
The PWI shall:
• Report promptly any defect in tunnels likely to affect safety of traffic, taking
immediate action to stop or slow down trains, if warranted.
• Carry out all maintenance work in tunnels under protection as specified in Chapter
42.
• Post look-out men with whistles to give timely warning to staff working inside the
tunnel.
• Maintain man-refuges in a serviceable condition.
• Not raise the general level of track beyond the specified level without the permission
of the Regional Engineer.
LIST OF FIGURES
Figure 52.t Safe entry and exit while operating on-track machines.
LIST OF ANNEXURES
Annexure 52.1 Competency Certificate for Person in charge of work (PICOW).
Annexure 52.5 Typical works which do not affect the stability of track and
works which reduce the stability of the track.
~~~~~~~~
;>;
-<
;;::
"' I LINE OPEN TO 1RAFF'IC
-n
<15'
c
(il OBTAIN LOOKOUTMAN'S PERMISSION IF YOU HAVE TO WORK HERE
(J1
!"' . ·: . ·: ·. ·.. r-: ::::·::;;iiJ;;EJ:i ':S=rAv..·~~·.. .A. ·. ·:. ·,c-: ::A~.::M~~JA.v:-::-:.-:-:;::· .·. ·. ·.< J.
~
·.·. ··.. ··.·. ·.~. ··.. ·.·.··.·.··.·.. ·.·.··.·.. ·.·.··.·.··. ' ~ .........._·':_"'\.... ··~-·...:·._·.··~;._:·.-~.-~ ·.·.. :~~--···.'.
.. - ...... ·-·
(f) ·t·'I .·..·. ..··.. ·. ·.·.·. · .·. ..· ·.···.·CLEAR
.. . . .. . , .. . . ..·OF·UNES
. . .. . . ·. . . ..·.·..·..·.·.. M A .C"""""""
H I N E. .·.·• ..··.
. .··.·CLirAR·'Of.'l:INES·
. • .• . . .. . . .. . . .. • . ·• .·..·..··.
. •·• ·.
. .·•.•.. ..·•.·
. . •..
"'et
ro ..-. ·.. · ·•·. · · ·, ·.. ·. ·.. · · ·. ·. ·OP.EN'. 'to. ·tRAFFIC• '. · ·. ·.
'-'·-----·-""-'---~......
"''Il" ··. ·. ··oPEJ\1·
· ·. ........,;,J _ _ _'ro·
__ ·mime·.··.·.··.·.·.
__ •·•
· ·. · · ·
._~.:.,
:;:.
-< OBTAIN LOOKOUTMAN'S PERMISSION IF YOU HAVE TO WORK HERE
"':J0.
~ ~ ~ ~ ~ ~ ~ ~ b n n n ~"n~ ronm~mcn n n n J~ ~ ~ ~ ~. ~ ~
ro
X
"" cn3
"' .,
"'2:
ro et"
!I 0
'0
ro
~ PASS, ENTER OR LEAVE MACHINE ONLY
.:tfg
0-
:::s ::E
-I'"
Ol'<
:J
"' .IF SATISFIED IT IS SAFE TO DO SO " s:
0
:J "'"':::s
'
o; ~
'""'
A'
3
"'"
...
:=!'
s·
ro
~
0
s. . .,
-g..,
.., ::l.
~<
~
A
!-----' Name ........................................................................
Has passed the PICOW test
GRADE ......................................................................
STAFF NO ..................................................................
VALID UNTIL. ............................................................ .
Examiner's :Name ................................................ .
: Signature ............................................ .
Date of Issue: ..............................................................
SIGNED .................................................................. ..
SUPERVISOR/MANAGER
c
SIGNED ....................................................................
SIGNATURE OF HOLDER
Note:
This certificate is valid for two years (as shown above). If, however, PICOW duties are
not undertaken for twelve months, the certificate must then be considered to have
lapsed.
1. Identification of PICOW
• A safe system of work is adopted so that the work group is not endangered by
trains.
• Everyone in the group is briefed and understands the system of work, before the
work starts.
• Whenever any change in conditions or circumstances makes it necessary to change
the system of work, everyone understands the new arrangements.
• The work is stopped and everyone moved to a position of safety immediately,
whenever there is any doubt to continue the work safely.
3. Aspects to be kept in view by PICOW
3.1 lt is safer to carry out work on or near the line under a line possession. If this has
not been arranged, everyone working on or near the line must have sufficient
warning of the approach of trains, including all movements within a line possession,
to enable each person to reach a position of safety.
3.2 Before any work is started on or near the line, PICOW must decide whether lookout
protection is necessary. In certain circumstances, lookout protection is ALWAYS
necessary (See Clause 6.2 below). In others, PI COW must determine whether it is
necessary.
3.3 Whenever lookout protection is necessary, it must be provided. If, however, this is
not practicable FOR ANY REASON, the passage of trains must be stopped before
the work starts.
3.4 If PICOW is satisfied that work can be done safely without lookout protection, he
must first make certain that everyone in the group understands what is required to
ensure each person's safety.
3.5 Guidelines for deciding about lookout protection and other related items are given in
the ensuing paragraphs.
4. Determination of Warning Time
4.1 Warning Time is the minimum time required for everyone in the group to:
• reach the position of safety and to be in that position atleasl1 0 seconds before
arrival of the train.
4.2 The minimum warning TIME required for work of a minor nature is 15 seconds, and
for all other works, the minimum warning TIME is 30 seconds. In either case, this
TIME must be increased whenever any of the following circumstances make this
necessary:
• the means by which everyone in the group will become aware of approaching
trains.
• the nature of the work, and the tools and equipment to be used.
• the number, age and experience of the group.
• the location of the position of safety and whether there are restricted
clearances.
• visibility.
• weather conditions.
• working conditions.
• noise which will be created by the work and any background noise.
4.3 Where the activities of the group require different warning times, the longest warning
TIME must be used.
4.4 PICOW shall determine the warning time on the above lines for the specific work
under execution.
5. Determination of Sighting distance
5.1 PICOW must lake the speed of approaching trains as the permissible speed of
trains without placing reliance on:
5.2 Taking account of the warning TIME required for the work as in Clause 4 and the
SPEED of approaching trains as in Clause 5.1 of Annexure 52.2 above, PICOW
must then determine the DISTANCE at which trains must be clearly within view.
Guidance in determining this DISTANCE is given in the Sighting Distance Chart at
Table T-52.1 below.
6.1 Lookout protection is necessary if everyone in the group is not able to observe
approaching trains at the sighting distance determined at Clause 5 of Annexure
52.2 above.
6.2 Lookout protection is always necessary for any of the following cases:
PICOW must decide the number of lookouts required and position them so that
adequate warning of approaching trains will be received by everyone to be
protected.
In Single Line, he must ensure that adequate warning is given of trains approaching
in either direction.
7.2 Noise from mechanical plant or other sources
When noise will arise from the use of mechanical plant or other sources, PICOW
must arrange for the warning of approaching trains to be given by:
8.1 PICOW must not permit work to start until the arrangements to provide lookout
protection are complete and as far as practicable he shall test the arrangements to
ensure they are effective. He must ensure that everyone to be protected is aware of
the means by which the Lookout will give warning and the position of safety to which
each person must move, when warning is given. He must also test the
arrangements to make sure the warning will be effective.
8.2 PI COW must not permit work to start or restart after the passage of a train, until it is
safe to do so.
8.3 PICOW must ensure the Lookout does not have other responsibilities, nor take any
part in the work, nor is distracted, while the work is continuing.
9. When work is to be carried out without Lookout
9.1 Before permitting work to start on or near a line where lookout section is not
provided, PICOW must ensure that:
• everyone understands that each person is responsible for their own safety and
they must look up frequently to ensure there is sufficient warning of the
approach of trains to enable each person to reach the position of safety.
• everyone is aware of the permissible speed of trains and the directions in which
they normally approach on each line.
• everyone is aware of the position of safety to which they must go when a train
approaches.
9.2 PICOW must not permit work to start or restart after the passage of a train, until it is
safe to do so.
10. When work is to take place on or near a line under line possession
When work is carried out on or near the line under line possession, the person in charge
of the possession must ensure that a safe system of work is maintained in accordance
with the instructions issued for protection of Permanent Way Work.
TABLE T-52.1
<wt~~~~~·(
TRAIN SPEED 00
°'·,·,, TIME. •
. ', ·- ·.- 00
. :.·.-·.·.' 00
700 650 600 550 I 500 I 500 I 450 I 400 I 350 I 300 I 250 I 250 I 200 I 150 I 150 I 100 I 15 sec
SIGHTING I 900 I 850 I 800 I 750 I 700 I 650 I 600 I 500 I 450 I 400 I 350 I 300 I 250 I 200 I 150 I 1oo I 20 sec
DISTANCES
IN I 1150 I 1050 I 1000 I 950 I 850 I 800 I 700 I 650 I 600 I 500 I 450 I 350 I 300 I 250 I 200 I 150 I 25 sec
METRES
TO PROVIDE I 1350 I 1250 I 1200 I 1100 I 1000 I 950 I 850 I 750 I 700 I 600 I 500 I 450 I 350 I 250 I 250 I 150 I 30 sec
WARNING
TIME I 1600 1500 1400 1300 1200 1100 1000 900 800 700 600 500 400 300 250 150 35 sec
1800 1700 1600 1450 1350 1250 1150 1000 900 800 700 600 450 350 300 200 40 sec
2000 I 1900 I 1750 I 1650 I 1500 I 1400 I 1250 I 1150 I 1000 I 900 I 700 I 650 I 500 I 400 I 350 I 200 I 45 sec
1. Appointment
PICOW shall appoint any staff having a current competency certificate (as in
Annexure 52.4) as Lookout. As far as possible, the same man is posted daily as
Lookout, while the work lasts.
2. Identification
3. Equipment
• A whistle or horn
• At least 6 detonators
• A red flag during daylight
• A three colour torch during darkness, or in a tunnel
4. Duties of Lookouts
4.1 Lookout must take up the position as directed by the PICOW. He shall remain there
until told by the PICOW that the work is finished and everyone is clear, or he is
relieved by another Lookout. Except when relieved, he must not leave his post,
while the work is continuing.
4.2 Lookout must be alert for the approach of trains and not allow his attention to be
distracted nor take any part in the work.
4.3 When a train approaches, he must immediately give warning by sounding the
whistle or horn or if necessary by shouting. If anyone being protected fails to
acknowledge this warning immediately by raising on arm above the head and
moving to a position of safety, an urgent warning must be given by a series of short,
sharp blasts on the whistle or horn until everyone has moved to a position of safety.
4.4 Where warning is given by touch, he must immediately give such warning, when a
train approaches and repeat the warning to anyone who does not immediately move
to a position of safety.
4.5 If the Lookout is acting as a Distant or intermediate Lookout, he will indicate
approaching trains to the Site Lookout by a hand signal. He will do this by waving
his flag slowly from side to side above the head until acknowledged. The Site
Lookout will give this acknowledgment by waving his flag above the head.
4.6 Lookout must sound the warning if he is unable to give adequate protection due to:
A
1 - - - - " Name .............•..........................................................
Has passed the LOOK OUT test
GRADE ......................................................................
STAFF NO ..................................................................
VALID UNTIL. ............................................................ .
Examiner's :Name ................................................ .
: Signature .............................................
Date of Issue: ..............................................................
SIGNED ....................................................................
SUPERVISOR/MANAGER
c
SIGNED ................................................................... .
SIGNATURE OF HOLDER
Note:
This certificate is valid for two years (as shown above). If, however, LOOK OUT duties
are not undertaken for twelve months, the certificate must then be considered to have
lapsed.
• Changing of sleepers .
• Renewal of ballast.
• Increasing ballast cushion .
• Cleaning of ballast.
• Realignment of track .
• Lifting or lowering of track .
Chapter 53
Plant and Machinery
Document History
Authorised By:
Signature:
Date: MOHD RAMLI MOHO NOH
General
8 MAY 201
Kereatspl Tanah Melayu Berhad
Kuala Lumpur
TABLE OF CONTENTS
53.1 GENERAL
This Chapter deals with the custody, maintenance and upkeep of plant and machinery
used for maintenance and renewal of track. The general procedures for maintenance
and servicing of such equipment are .described for the guidance of Permanent Way Staff.
Specific instructions of the manufacturers of the equipment shall also be strictly
followed.
53.2 CLASSIFICATION
Plant and machinery are classified broadly into three categories.
• Light Plant.
• Heavy Plant.
• Special Plant.
53.3 GROUPING
Plant and machinery are grouped as under:
53.3.1 Light Plant:
• Motor Trolleys.
• Light Duty On-Track Tampers.
• Off-Track Tampers.
• Ultrasonic Rail Flaw Detectors (portable)
• Other similar equipment.
53.3.2 Heavy Plant:
53.4 CUSTODY
53.4.1 Permanent Way Depot
A Permanent Way Depot in Shah Alam, under the Charge of a Plant Depot Engineering
Manager (nominated by the General Manager Permanent Way) is the home base for all
Permanent Way Plant and machinery. These shall be sent to the Regions for operations
as specified by the Headquarters. The Permanent Way Depot shall manage the training
and execution of work of plant and machinery operators and other maintenance staff and
shall be responsible for:
P X X X X
~~~
~ .,.
'
Departme nt
::
Machinery Type Machine Model Group Serie; nulllber_ I
P Permane ntWay 0 Trolley 1 Fairmont (FT) '1,2,3 ...xx
2 Wickham (WT
3 UMW
4 China JY100A
- ---··
1 Ballast Regulator 1 PBR101
.:
2 PBR202
3 PBR202 (11)
4 PBR400
·-
5 SSP103
-··-----
2 Tamping Machine 1 07-16BRBS
2 07-16G
3 07-16GS
----·- --
4 09-16CAT
5 08-75 GS
6 08-3S Unimat
~------- ·-
7 09-32CSM
, __ ___
_,
·- --
2 Tamper UT
--·------
3 EM120
r----· . .
4 Ultrasonic Car
9
. ----~------
Bridge Inspection 1
---.--------
Combi Sarin
I
-·--- - - ·-
10 Rail grinder 1 GWM250
--~
54.4.3.1 Plant register is for all other small machinery e.g rail cutting machine, rail drilling
machine, generator, tie tamper, trailer shall be tagged using the code system below:
PBUJ ,X XYX X,
/
Department
~
Asset serial
Initial numbers
53.4.2.2 The Permanent Way Depot shall maintain the assets register for all Permanent Way
Department plant and machinery. lt is the obligation of the users in the Permanent Way
region to periodically notify the status and condition of the plant and machinery under
their custody to Permanent Way Depot for maintenance and/or asset write-off purpose.
An annual return of the plant in the Depot showing the balances at the end of the year
and indicating the condition of the plant shall be submitted annually to the Headquarters
office.
53.4.2.3 Log Book
A log book shall be maintained for each individual plant. lt shall indicate the following:
A maintenance record of each plant shall be maintained in the Permanent Way Depot.
Essentials such as major overhaul or complete replacement of a part shall be extracted
from the log books (Clause 53.4.2.3) and posted up to date.
One copy of the Operating Manual along with relevant drawings of all components and
parts shall be maintained at the Depot for each machine. Another copy of the Manual
shall be kept with the plant for reference in the field by the Regional Engineer and his
officers.
53.5 OPERATION
The plant shall be operated strictly in accordance with the instructions contained in the
Manual supplied by the Manufacturer, read along with general instructions issued by the
General Manager Permanent Way.
53.6 MAINTENANCE
53.6.1 All plant and machinery shall be maintained so as to be ready for effective and efficient
use. Testing of plant shall be done at the intervals prescribed by the manufacturer.
53.6.2 All plant and machinery maintenance shall follow the maintenance manual prescribed by
the equipment manufacturer up to the latest standards. Details maintenance protocols
shall be available with the Permanent Way Depot.
53.6.3 Preventive maintenance shall be carried out by servicing plant periodically, as specified.
Suggested Maintenance Schedule for on-track machines are:
The schedules above are purely indicative and shall be modified to conform to the
recommendations of the manufacturer of the machinery.
53.6.4 Overhauling
53.7 SUSTENANCE
For efficient functioning of the plant, the following shall be ensured:
53.8 BREAKDOWN
In the event of a breakdown, the Depot shall be advised for assistance. No part of the
equipment shall be opened out, pending the arrival of a competent mechanic from the
Depot. All failures shall be investigated and causes determined to take corrective action.
53.9 TRAINING
Training shall be arranged for the Operators, Maintainers and Supervisors as indicated
below. The duration and syllabus for each course shall be as specified by the General
Manager Permanent Way.
LIST OF ANNEXURES
Annexure 53.1 Daily Schedule (after every 8- 10 operating hours).
Annexure 53.2 Weekly Schedule (after every40- 50 operating hours).
Annexure 53.3 Half yearly/Annual Schedule (after every 1000- 1200 operating
hours).
A. DIESEL ENGINE
1) Fuel Check
5) V - belt check
B. PNEUMATIC SYSTEM, BRAKES
D. ELECTRICAL SYSTEM
E. MECHANICAL SYSTEM
1) General inspection of the tamping banks.
A. DIESEL ENGINE
1) Exterior cleaning of engine (inspecting: cylinders, cooling fins, ventilator blades,
tightness of the air channel).
A. DIESEL ENGINE
E. MECHANICAL SYSTEM
Chapter 54
Training of Permanent Way Staff
Document History
Authorised By:
Signature:
L-0 - _Qr \
Kere~p1
.
- :
. ....
..,
lJI,
TABLE OF CONTENTS
54.1 GENERAL
This chapter lays down the broad outlines for training to be provided to Permanent Way
Staff at different levels.
• The trainee obtains the required degree of practical job competence as early as
possible.
• Those attitudes which contribute to attain better performance in his job are
developed adequately.
54.5.1 These courses are run for new entrants. The courses for new Gangmen will be arranged
by Permanent Way Division Headquarters and the courses for newly recruited Inspectors
will be held centrally at region/ MyRA.
54.5.2 Initial Course for Gangmen
This course shall be undergone by all new Gangmen within the first three months of
service in two phases.
54.5.2.1 Phase I (In the first month)
1. A 3 day course in safety and basic job skills shall be arranged by the Permanent
Way Division Headquarters. The training staff shall be either from Malaysian Railway
Academy (MyRA) or external trainers wherever applicable.
2. The following subjects shall be included:
1. Personal track safety
• Handling tools
• Carrying out manual work safely and efficiently.
4. Track Construction
• Identifying components.
• Learning the way they are built up.
6. Treatment of Accidents
• What to do?
• What not to do?
• First Aid equipment issued to Gangs.
7. Permanent way Maintenance
• Practical session to learn to do simple tasks safely and efficiently using the
correct tool the correct way.
• Introduction to Mechanised Track Maintenance
• On-track and off-track machines and their functions
8. Conditions of service
• Terms and conditions of employment (Salary & Privileges)
54.5.2.2.1 A five (5} day course shall be arranged by the Permanent Way Division Headquarters ..
54.5.2.2.2 The following subjects shall be included:
o Personal safety
• Equipment
• Duties
• Special arrangements (for working with on-track machines, in unfamiliar
situations, etc.)
• Emergencies
• Demonstration and practice.
This training course for new entrants will be arranged by the Permanent Way
Division HQ with duration of about a year. The course content shall include class
room lectures, field demonstration and practical training.
2. Class room lectures
• KTMB railway operating rules that are applicable to the PWI, as in the current
Working Timetable, Rule and Regulation Book.
• Administrative, office work and personal time management
3. Practical Training
Table T -54.1
Training Module for PWI
• Lookout duties.
• The Ganger's function in execution of planned work.
• Action during emergencies.
• Documentation and reports.
• Use of tools and equipment.
• Safety of work men on track.
• Skills in management of his team.
54.6.3 Phase 2 and other subsequent trainings shall be organised by the Regional Engineer in
consultation with the Permanent Way Division Headquarters.
54.6.4 The course for PWis promoted as CPWis shall be held at MyRA. The duration shall be
two weeks. The contents of the lessons shall include:
54.7.2 The duration, syllabus and the category of staff for each course shall be laid down by the
Permanent Way Division HQ ..
Chapter 55
Maintenance of Track in Track
Circuited Areas and near Track Side
Signalling Installations
Document History
Authorised By:
Signature:
Date: 28MAY201
TABLE OF CONTENTS
formation level to prevent any short-circuiting and must be designed to be able to absorb
the load of the material above them as well as the train loads. Allowance shall be given
for settlement after installation.
55.1.5.4 Care shall be taken to see that no damage is caused to track-circuit fittings (like
bootlegs, rail bonding wires, lead wires to rails, and jumper wires) during track
maintenance operations.
55.1.5.5 Use of steel tapes shall be avoided.
55.1.5.6 The top of the rails shall be kept free from sand, rust and other foreign matter as it may
affect proper functioning of the track circuit.
55.1.5.7 Proper drainage shall be ensured so as to avoid flooding of track during rains.
55.1.5.8 Valves of water pipes near the track shall be regularly checked and maintained to
prevent leakage. For new construction, valves or manholes shall be kept beyond the
railway reserve boundary.
55, 1.5.9 Pulling back of rails for creep and gap adjustment shall be done in the presence of
Signalling staff.
55.1.5.1 0 Ballast shall be kept clean and clear of the rails and rail fastenings. Care must be taken
to ensure that ballast are not unloaded over signalling rodding, motor points or other
wayside signalling equipment. The clearance from the foot of the rail shall not be less
than 55mm. During every packing, this clearance shall be ensured.
55.1.5.11 Insulating liners and pads on concrete sleepers shall be carefully observed and if found
crushed, broken or loose, shall be refitted. Missing liners and pads shall be reported to
the PWI for replacement.
Track-circuited sections, (unless provided with jointless track circuits), are 'insulated'
electrically from the adjoining track on either side by insulated joints. Failure of insulated
joints results in failure of track circuits. Hence care has to be exercised in the installation
and maintenance of insulated joints, which are the combined responsibility of Permanent
Way and Signalling staff. Also refer to Chapter 3 for detail.
55.2.2 Requirements
55.2.2.1 An insulated rail joint shall have flexural strength and stability comparable to a full rail
section and stilt maintain a specified degree of electrical insulation between the rail ends
under adverse conditions of temperature, moisture, oil, dust etc.
The joint shall not bend or fail under vertical or lateral wheel loads and shall not
deteriorate during its service life. lt shall perform its function reliably in such a manner
that signal failure shall not occur as a result of electrical conduction occurring across the
joint.
55.2.2.2 Apart from the d;-namic loads (whose magnitude depends on the axle load and the
stiffness of the rail joint), the joint is a~so subject to forces due to temperature changes
and creep. The damage due to the latter can be partly avoided by minimising the
longitudinal movement of the adjacent rail ends by providing anti-creep devices.
55.2.3 Type
The following precautions shall be taken during the installation and maintenance of
insulated joints:
55.2.4.1 Insulated joints shall be maintained as square joints. Where staggering cannot be
avoided, the distance between staggered joints shall be kept to within 1 to 2 metre and
shall never exceed 6 m.
55.2.4.2 Rail ends of insulated joints shall be square and true. All rough edges and burrs shall be
removed from bolt holes. Cutting of rails by gas torch is prohibited. Mechanical rail saws
shall be used to cut rails.
55.2.4.3 The gap between the rails shall be equal to the thickness of the end post.
55.2.4.4 Fish bolts at the joints shall be tightened to the torque specified by the manufacturers:
Joints fitted with Huck or similar fasteners (instead of bolts and nuts) shall be inspected
for signs of failure of the joints/fasteners. Sleepers shall be kept well packed in the
vicinity of the joints to prevent undue rail movement.
55.2.4.5 Rail ends shall be kept free from brake dust, iron dust from wear and tear of the wheel
and rail, dirt, sand, rust, and other foreign materials. All rough edges, burrs and lipping at
the rail ends shall be removed.
55.2.4.6 Regular monitoring shall be kept on the smooth profile of the rail to ensure that
projections and burrs do not cut into the insulation.
55.2.4.7 Rail fastenings shall not be allowed to touch the fish-plates.
55.2.4.8 Particular care shall be taken to ensure that the spikes/screws do not protrude below the
sleepers.
55.2.4.9 The ballast used in track in the vicinity of insulated joints shall be clean to ensure efficient
packing and drainage.
55.2.4.10 To avoid crushing of end posts of insulated joints, creep shall be effectively arrested. At
least one rail length on either side of the insulated joint shall be well anchored.
55.2.4.11 In the case of an insulated joint between long welded rails, one standard (12.2m) length
of rail. shall be installed on either side, adjacent to the insulated joint. This is only
applicable for LWR sections on conventional Class 11 routes.
55.2.4.12 Any separation of rail/fish-plate in a glued joint shall be carefully looked for and the joint
shall be replaced if such separation is observed.
55.2.4.13 Glued Insulated joints for CWR track are designed to function as a continuous rail as
they are welded to the adjoining rails.
The consecutive calculations of the number of axles entering and leaving the railway
section allows the system to establish if the section itself is free (if the number of leaving
or exiting axles is equal to the number of entering axles) or is still occupied by a train.
This information is then used to enable or to forbid the next train to enter the section.
The PWI shall take cognisance of these installations beside the railway track and ensure
that Permanent Way maintenance work do not damage them. Permanent Way staff shall
immediately report to the Signal Inspector and the TCCC Operator if these equipment
are found to be damaged or vandalised.
55.4.1.1 Maintenance of switches, their connecting rods, gauge tie plates and bolts and cotters for
pad locks is the responsibility of the Permanent Way Inspector. In addition, all non-
interlocked switches, hand points, and spring loaded points are to be maintained by him.
55.4.1.2 The Signal Inspector is responsible for keeping in working order the interlocking parts
and apparatus.
55.4.2 Installation of interlocked switches
Before the switch layout is handed over for carrying out interlocking work, the Permanent
Way Inspector shall ensure that:
55.4.2.1 Track is brought to the correct level and alignment.
55.4.2.2 Layout is fully ballasted and switches are well packed, especially under the rail joints.
Ballast shall be kept clean at all times.
55.4.2.3 The switches are not liable to movement, laterally or longitudinally.
55.4.2.4 Sleepers on adjacent tracks are arranged suitably to facilitate crossing of rods and wires.
55.4.2.5 Gauge is maintained properly and gauge tie plates are fixed correctly.
55.4.2.6 Special timbers or concrete bearers have been provided at the switches to fix signaling
gadgets.
55.4.2.7 Adequate means are provided to prevent creep in the vicinity of switches.
55.4.2.8 Correct throw of switches is maintained at their toe.
55.4.2.9 Fixed heel switches are so adjusted that:
(i) They normally lie in mid-position and flex equally in the normal and reverse posilions.
(ii} The planed surface of switch rails is able to flush fully against the stock rails.
55.4.2.1 0 Switches have been fitted with flexible stretchers so that they flex equally in the normal
and reverse positions.
55.4.2.11 Formation is cleared and brought up to the level to facilitate laying of rodding, wire run
and cables.
55.4.2.12 If a Level Crossing falls in the area, the road surface is brought to correct level and
section so as to enable casing pipes for carrying signalling wires to be put in their final
position.
55.4.2.13 At all turnouts in track circuited areas split stretcher bars and gauge tie plates are
properly insulated according to the requirements of the Signalling & Communication
Division.
55.4.3 Installation of electrically operated switches (Point machines)
55.4.3.1 In the case of electrically operated switches, the PWI shall, in addition to the above,
ensure the following:
1. The Signal Inspector takes expeditious action to maintain proper alignment and level
of the connection between the electric point machine and the point gear. The PWI
shall alert the Signal Unit to rectify the alignment and level and assist them for any
adjustments if necessary to the turnout.
2. The sleepers supporting the point machine shall be tied together by means of a
suitable fixture, on both sides of the track, to prevent movement of the point machine
relative to track. The point machine installation may already include brackets which
effectively tie the sleepers together. In that case, additional tie bars need not be
provided.
3. At places, where point machines are installed, extra care shall be exercised to
ensure that drains and culverts are always well maintained in order to prevent
damage due to floods and stagnant water.
55.4.4 Maintenance of interlocked switches
55.4.4.2 Sleepers under switches of interlocked points shall be kept well packed, packing of
sleepers being undertaken in the presence of Signal staff, to avoid damage to
interlocking installations and failure of interlocking.
55.4.4.3 Stewing of track at switches is likely to throw the interlocking out of adjustment; hence
such works shall not be undertaken except in the presence of signal staff.
55.4.4.4 Special care shall be taken to ensure that, during maintenance operations, no
obstruction like ballast, dirt, replaced nut/bolt or other fitting is left either between stock
and switch rails or under the lock bars; such obstructions result in failure of switches and
signals.
55.4.4.5- All bolts and nuts in the permanent way fixtures on turnouts shall be tightened.
55.4.4.6 Proper drainage shall be ensured, all drains being kept clear to avoid flooding.
55.4.4.7 On receipt of advice of track defects from Signal staff, the PWI shall promptly rectify
them.
55.5.1.1 All runs of rodding and wires, also all wheels, cranks and rollers shall be kept free from
obstructions such as grass, weeds, dirt, cinders, ballast, chippings, sleepers or any
material accumulation that will prevent their free movement.
55.5.1.2 No material shall be unloaded on runs of rodding and wires.
55.5.1.3 it shall be ensured that the top of rod run under tracks remains at not less than 25mm
below the bottom of the rails.
55.5.1.4 Rodding elements crossing the tracks shall not, as far as practicable, be under rail joints.
55.5.1.5 Wire runs under the track shall be clear of rails, ballast and sleepers.
55.5.1.6 At locations where track machines are deployed, the PWI shall ensure that all
obstructions such as signal rods, cables, and treadles in the approach of level crossings,
which are likely to be damaged by the tampers, are clearly marked and made known to
the track machine operators. Care shall be exercised in protecting these installations
during operation of track machines. Prior notice shall be given to the Signalling Inspector
of all work by track maintenance machines in track circuited areas or of work which is
otherwise likely to affect any signalling apparatus.
55.5.1.7 If any bond wire is damaged inadvertently by the tampers, immediate report to Signal
staff shall be made.
55.5.1.8 Proper drainage has to be ensured to avoid damage to signalling installation due to
flooding of track during rains.
55.5.1.9 While carrying out spot welding (e.g. for repairs of wheel burns on rail table), suitable
precautions for the safety of the signalling installations shall be taken in consultation with
Signal staff.
55.5.1.1 0 While working Material trollies in a block section, the official in charge of the Material
trolley shall ensure before starting the run of his Material trolley that:
1. There is no hanging chain, material or any other such article on the Material trolley
which could damage the point equipment or any other signalling apparatus installed
on or near the track.
2. No part of material· such as rail or sleeper is protruding sideways so as to strike any
signal post or any other equipment installed near the track.
55.5.1.11 Any inadvertent damage to signalling equipment shall immediately be reported to the
concerned Signal stall for rectification.
i. The formation along the cable route shall be maintained at the designed-level, care
being taken that, during heavy rains, the cable is not exposed by erosion of the
formation.
ii. No heavy materials like rail and- sleepers shall be unloaded on the cable route near
joint markers.
iii. Digging or maintenance work along the cable route, shall not be undertaken except
under instruction from the PWI and with the supervision of the Ganger and with prior
notice to the SI.
The PWI shall be alert to avoid damage to cables while attending to cleaning and repair
of drainage arrangements like drains, sumps and manholes.
55.5.1.13 The PWI shall be alert to see that no damage is caused to signalling equipment within or
near the track as indicated below:
i. Ground receivers (last vehicle detection device for tokenless block system).
55.5.1.14 Road vehicles or plant and machinery must cross cables or cable troughs only at
specified locations and with adequate safeguards and protection to these cables.
LIST OF FIGURES
Figure 55.1 Schematic sketch of a Track Circuit with Insulated Joints.
LIST OF ANNEXURES
Annexure 55.1 List of items to be checked during Joint Inspection by
Permanent Way and Signal Inspectors.
...z
0
... -, m
lt... .~ 0
~
1-
z
<
..J
0
....,
::>
!/)
L-- I
...
!/)
<
_,
..J
1'1
I;
1
:::J
()
0::
~ < ...z ()
~
!/)
0
m r- 0-, ll)
ll)
~
z
0
_, ()
m ;;: <( C)
..J a: 0::
< ..J 1- G:::
a: <
::;
r=
~------
a: <(
0
L_ --- flt-_
z
-- u..
1 -
------- --.I w 0
""-'
l_ ---
'L ---- 0
I --._
~r-- ____ -----J 5
w I
0 ()
--- -- 11 I~
C>
z
F
<
..J
1-
w
~
m
::>
C> ()
w IL
a:
I 0>-
w-'
oa.
1-
<(
LJ a: C. ::::1:
"'"' w
l o"'
IJ) I
()
11----- it----
...z m
-- t---- --- - 0
---- -,
0
w
JOSUBB
:;:;'
w
1-
Vl
>-
Vl
0::
w
1-
z
:::>
Q) 0
0 0
·;;: N
Q)
w I{)
"... --'
X
I{)
0 <(
0
.!:!l
"
.s I.<.
0
I.<.
0
i=
<(
:;:;'
w
J:
0
Vl
J09UD8
1. Is proper (cross and longitudinal) drainage provided to ensure that the rails are not
short-circuited by water? Are there any signs of flooding in the vicinity of the track?
Check whether the drains are choked and require to be cleaned.
2. Are there any leaking valves of water pipes in the vicinity of track?
3. Is the ballast kept clear of earth?
4. Is the ballast kept clear by at least 55mm from the foot of the rail?
5. Are the rails clear from scale, brake dust, dirt or other foreign material?
6. Is the packing below the insulated joint proper?
7. Is the gap between rails within the specified limits at the insulation joints? Is there
any apparent evidence of crushing of insulation joint? Are there any signs of rail
creep? If so, investigate, record the reasons thereof, and take remedial action.
8. On track-circuited switches, are the ends of rails, where insulation joints are fitted,
square and smooth?
9. Check out any burnt out or damaged sleeper and take protective measures.
10. Note missing liners and insulation pads on rails for recoupment.
2. SWITCHES AND CROSSINGS
1. List fastenings and other Permanent Way fittings which are missing, including nuts
and bolts of slide chairs, fish plates and the bolts of heel block etc. for each switch.
2. Check the condition of switch for damages and chipping.
3. See if the switch is bent or worn-out and whether any burr on stock/tongue rail is
obstructing the movement of lock bar/housing of switches?
4. If the switch is out of square or level, the extent by which it is so (out of square or
level), shall be recorded.
5. Is the creep at switches and crossings within permissible limits? Is the layout
provided with means to prevent creep in the vicinity of switches? Are these means
effective?
6. Are the stretcher bars of correct length and throw of switch is maintained correctly?
7. Is the layout fully ballasted and properly packed?
8. Is the gauge tie plate fitted correctly? Twist or damage shall be noted.
10. Is the gauge correct in the rear of the switches and on the entire length of the
switches and crossings?
11. Are the special timbers as required provided and fixed? Is the condition of sleepers
on which point equipment is installed satisfactory?
12. Are the sleepers on track in such an alignment so as to keep space for point-rodding
and signalling wires to cross under the tracks?
13. Are the fish plates at joints kept tight in the vicinity of switches?
14. Are stretchers fitted in such a manner that they flex equally in normal and reverse
position of the switches?
15. Are the fixed heel switches so adjusted that they normally lie in the middle position
and flex equally in normal and reverse position? Does the planed surface of the
switch rail fully house against the stock rail?
1o. Are the switches out of adjustment on account of wear in the fittings, creep of track
and poor track maintenance? Are there any slack fillings?
3. MISCELLANEOUS
1. Are any tree branches interfering with Driver's sight of signals (This is the
responsibility of Signalling Department, PWI is to report to SI)
2. Are all runs of rodding and wires including fittings and fixtures free from
obstructions?
3. Are the gauges and levels of Permanent Way staff correctly insulated? (Staff shall
be educated to ensure that trolleys move only under block protection and on proper
signals).
4. Are the staff generally conversant with the rules of working of trolleys and material
trolleys? Do they understand the implications of unloading Permanent Way material
and ballast in the vicinity of signalling gears including rod and wire runs?
Chapter 56
Maintenance of Track in Electrified
Lines
Document History
Authorised By: \_
l,- D - ~
_..,.,Q_,
-;...-'
Signature:
Date: ,..MOHDu.,.,.,.,.,r
RAMLI MOHD NOH
t Way 2 8 MAY 2015
Keretapi Tanah Melayu Berhad
Kuala Lumpur
TABLE OF CONTENTS
56.1 GENERAL
56.1.1 This Chapter deals with the precautions to be observed in maintenance of track and
execution of works in electrified lines.
56.1.2 Rules framed for working in electrical traction area specify the procedure to be followed
by the Permanent Way staff in execution and maintenance of works. These shall be
strictly observed by competent staff..
56.1.3 All electrical equipment, every power line or cable shall be regarded as being 'live'
at all times. No work shall be commenced adjacent to any electrical equipment except
on authority issued in writing by a certified Nominated Person (N.P.) of the Electrification
System Division to the effect that the equipment has been made dead and earthed.
56.2.1.1 In electrified areas the return current fully or partially flows through the rail. To ensure
reliable electrical circuit continuity and ensure proper earthing in case of leakage of
current, traction bonds are provided at suitable places and maintained by the
Electrification System Division.
56.2.1.2 Care must be taken to ensure that damage is not caused to any traction bonds in
electrified sections, particularly when the fishplates are being removed for lubrication or
replacement. Any broken or disconnected bonds should not be interfered with but
should be reported immediately to the Electrification System Division.
56.2.2 Structure bonds
All structures supporting overhead equipment in track circuited areas are connected to
the running rails for ensuring good earthing. Failure of insulator or leakages of current
switches off the supply from substation, so that men coming in contact with the
supporting structure do not get electric shock. Removal or tampering of such bonds can,
therefore, result in unsafe conditions. Since the structures are grouted in concrete, they
are likely to become charged, in case such bonds are kept disconnected. Similarly other
steel structures such as foot-over bridges, sheds etc., in the vicinity of Over-head
Electrification (OHE) lines are also connected to rails through similar structure bonds.
56.2.3 Track Markers
56.2.3.1 On lines electrified with the overhead system, the track has to be maintained in its
correct position relative to the contact wire. Track markers are installed to indicate the
correct cant and alignment. The correct rail level will also be indicated at over-bridges,
tunnels and masts. Alignment, level and cant niust be checked regularly, with particular
attention being paid at over-bridges, in tunnels and in platform areas. The maximum
permissible amounts by which the track may be allowed to vary from its correct position
without endangering the safe passage of the pantograph are:
56.3.1.1 Instructions listed below shall be followed while walking near the track in electrified lines
and while executing works in traction area.
In electrified section:
(i) Keep yourself and your clothing and equipment at least 2.75m from:
(iv) Carry long articles horizontally - take extra care with pipes, rods and poles.
56.3.1.2 No work shall be done within a distance of 2.75 metres from the live parts of the Over
Head Equipment without a 'permit-to-work'.
56.3.1.3 For work adjacent to overhead equipment, the Permanent Way Inspector shall apply to
the proper authority sufficiently in advance for sanctioning the line possession and
electrification power isolation required.
56.3.1.4 Electrical Control Operator (ECO) through the Electrification System Division Nominated
Person (N.P.) will arrange to isolate and earth the section concerned on the date and at
the time specified in consultation with the Traffic Controller. The N.P. shall then issue
'permit-to-work' to the PWI.
56.3.1.5 On completion of the work, the PWI inform the N.P. who shall cancel the 'permit-to-
work' and advise the Electrical Control Operator (ECO} who will then arrange to remove
the earth and restore power supply.
No part of a tree shall be nearer than 4 metres from the nearest live conductor. Any tree
or branches likely to fall on live conductors should be cut or trimmed periodicafly to
maintain this clearance. The PWI shall intimate to the Etectrification Unit to enable
cutting or trimming to be done by authorised Electrification staff or agency appointed by
KTMB. The work shall only be carried out in the presence of Permanent Way staff.
No fallen wire or wires shall be touched unless power is switched off and the wire or
wires suitably earthed.
All fallen wires shall be considered "live" until cleared by the Electrification staff.
Staff working on station roofs and signal gantries and similar structures adjacent to OHE
lines shall not use any measuring tools and materials, when there is a possibility of their
being dropped or carried by wind on to the overhead equipment.
56.3.5.1 When carrying out any excavation work near locations, where electric cables, signalling
cables etc., are laid underground, greatest care must be exercised. Where cable runs
(cased or uncased) are above the ground, they must be kept free from grass or weeds.
Grass and rubbish must not be burnt near cable runs. Lamps, lit or unlit, must not be
hung on or near the cable runs, particularly if they are in tunnels.
56.3.5.2 Cables on hangers attached to retaining walls, platform walls and bridge parapets are
particularly vulnerable. Care must be taken to ensure that rails, sleepers and scrap
materials are not placed against cables or on cable ducts. Road vehicles or plant and
machinery must cross cables or cable troughs only at specified locations and with
adequate safeguards and protection to these cables.
56.3.6 Track and jumper cables
Ballast and other materials must always be kept clear of track and jumper cables,
especially at places where these enter ducts.
56.3.7 Alteration to Tracks
56.3.7.1 The relative alignments of the entire line of the track with respect to the alignment of the
contact wire must be maintained within the specified tolerances. This applies to both
horizontal and vertical clearances. Slewing or lifting of track must not be done outside
the agreed maintenance limits unless the position of the contact wire is altered at the
same time. Adjustment of cant has a magnified effect of the horizontal displacement of
the centre line of the track with respect to the alignment of the contact wire.
56.3.7.2 Horizontal clearances to structures within the limits laid down in Chapter 11 must be
maintained. For slewing or alterations to track involving adjustment of contact wire
(outside the agreed maintenance limits) sufficient notice shall be given to the
Electrification System Division so that they arrange to adjust the overhead equipment
and to carry out re-registration of the alignment and clearances.
56.3.8 Alterations to Track bonding
56.3.14.1 During maintenance or renewal of track, continuity of the rails serving electrified tracks
shall invariably be maintained. For bridging gaps which may be caused during removal of
fish-plates or rails, temporary metallic jumpers of approved design shall be provided. The
necessary jumper shall be provided by the Electrification System Division on requisition.
56.3.14.2 In case of rail fracture, the two ends of the fractured rail shall be first temporarily
connected by a temporary metallic jumper of approved design (as shown in Figure 56.1 ).
In all cases of discontinuity of rails, the two parts of the rail shall not be touched with bare
hands. Gloves of approved quality shall be used.
56.3.14.3 In the case of defective or broken rail bond, a temporary connection shall be made as
shown in Figure 56.1.
56.3.15 Unloading of rails
56.3.15.1 When unloading rails along tracks, care shall be taken to ensure that rails do not touch
each other to form a continuous metallic mass of length greater than 300 metres.
56.3.15.2 Permanent way staff shall keep clear of the tracks and avoid contact with the rails when
an Electrical Multiple Unit or Electric Locomotive hauled train is within 250 m.
56.3.16 Clearing Ballast from under the Rails in Electrified Lines.
i. Traction power return current in the rails is searching for ground. Some amount of
the current will follow routes other than the rail in an inverse relationship to the
electrical resistance of that path.
ii. This is stray current. The ballast is a slight conductor. Wet ballast has marginally
more conductivity and muddy ballast can be much worse. lt is therefore important
that ballast does not touch the rail. If ballast continuously touches the rail, the track-
to-earth resistance test will generally fail. Therefore, the ballast in the cribs between
the sleepers must be removed from under the rail, usually to a minimum clearance
of 1 inch [25 mm) between the top of the ballast stone and the underside of the rail
or any other metallic part of the track structure.
iii. This is achieved by using a track shovel to push the ballast from beneath the rail
with a final clean-up and disposal of surplus ballast. This operation is not necessary
on non-electrified lines.
iv. Another good practice that can provide better insurance of passing the electrical
isolation testing is to use compressed air to blow any ballast fines off the rail
fastenings. Ballast fines, when mixed with rainwater, can result in a "paste" that
coats the rail fastenings and provides a conductive path to ground.
56.3.17 Permanent Way Tools
Permanent Way tools (insulated and un-insulated) along with gloves shall be used in the
manner as approved by the General Manager Permanent Way Division.
56.3.18 Rules for working in AC Electrified Lines
56.3.18.1 The precautions prescribed in the Rules framed for working in electrical traction area
shall be strictly observed. Refer to Instructions booklet for Working in AC Electrified Line.
56.3.18.2 In an AC Electrified Line, no track work shall be carried out when the track is inundated
with flood water unless the line has been isolated and verified by a Nominated Person
and permission granted to the PWI.
56.4.4 When persons received electric shock, in practically every case they can be revived with
the prompt application of First Aid. Artificial respiration shall be the method of
resuscitation. The efforts to restore breathing must be continued regularly and with
perseverance, and must not be discontinued until a Doctor has taken charge of the case.
LIST OF FIGURES
Figure 56.1 Temporary Jumpering of rail in case of Rail Fractures
Fig. 56.1
,
L NAKED COPPER WIRE 4 mm DIA