Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

BASELINE NARRATIVE REV.

02

VILLA NOVA ‐ LA VIOLETA – POOL HOUSE & SWIMMING POOL PHASE 02‐ BASELINE NARRATIVE

4.11 Procurement Log

Commencement Date: 05 Dec 2023


BASELINE NARRATIVE REV. 02

VILLA NOVA ‐ LA VIOLETA – POOL HOUSE & SWIMMING POOL PHASE 02‐ BASELINE NARRATIVE

4.11.1 Short lead items

PROCUREMENT LOG (SHORT LEAD ITEMS)


MATERIAL SUBMITTAL MATERIAL APPROVAL MATERIAL ORDER MATERIAL DELIVERY
Description
Dur Plan Start Plan Finish Dur Plan Start Plan Finish Dur Plan Start Plan Finish Dur Plan Start Plan Finish

Civil & Arch.

Tiling Works of Pool House Works 6 17-Feb-24 22-Feb-24 14 23-Feb-24 27-Feb-24 6 28-Feb-24 05-Mar-24 53 06-Mar-24 27-Apr-24

Tiling Works of Swimming Pool Works 3 23-Feb-24 28-Feb-24 14 29-Feb-24 04-Mar-24 6 05-Mar-24 11-Mar-24 53 12-Mar-24 03-May-24

Aluminum Works 6 21-Feb-24 27-Feb-24 14 28-Feb-24 16-Mar-24 6 16-Mar-24 22-Mar-24 60 23-Mar-24 15-May-24

Block & Plaster Works 3 31-Jan-24 02-Feb-24 14 02-Feb-24 17-Feb-24 6 18-Feb-24 24-Feb-24 33 25-Feb-24 28-Mar-24

False Ceiling Board 6 14-Feb-24 20-Feb-24 14 21-Feb-24 07-Mar-24 6 08-Mar-24 14-Mar-24 53 15-Mar-24 06-May-24

Mirrors 6 13-Mar-24 22-Mar-24 14 22-Mar-24 17-Apr-24 6 18-Apr-24 24-Apr-24 53 25-Apr-24 16-Jun-24

Painting Works 6 21-Feb-24 27-Feb-24 14 28-Feb-24 16-Mar-24 6 16-Mar-24 22-Mar-24 30 23-Mar-24 15-Apr-24

Signage 6 13-Mar-24 22-Mar-24 14 22-Mar-24 17-Apr-24 6 18-Apr-24 24-Apr-24 23 25-Apr-24 17-May-24

Stairs Flooring Finish Treads & Risers 6 28-Feb-24 05-Mar-24 14 06-Mar-24 26-Mar-24 6 26-Mar-24 01-Apr-24 60 02-Apr-24 25-May-24

Stairs Handrail & Copping 6 06-Mar-24 13-Mar-24 14 13-Mar-24 04-Apr-24 6 04-Apr-24 10-Apr-24 60 11-Apr-24 03-Jun-24

Timber Doors Works 6 21-Feb-24 27-Feb-24 14 28-Feb-24 13-Mar-24 6 13-Mar-24 19-Mar-24 60 20-Mar-24 12-May-24

Plumbing

MEP Drainage & Water Supply Pipes 6 10-Feb-24 16-Feb-24 14 24-Feb-24 12-Mar-24 6 12-Mar-24 18-Mar-24 33 19-Mar-24 21-Apr-24

HVAC

MEP Duct Works 6 24-Feb-24 01-Mar-24 14 02-Mar-24 21-Mar-24 6 21-Mar-24 27-Mar-24 23 28-Mar-24 20-Apr-24

Commencement Date: 05 Dec 2023


BASELINE NARRATIVE REV. 02

VILLA NOVA ‐ LA VIOLETA – POOL HOUSE & SWIMMING POOL PHASE 02‐ BASELINE NARRATIVE

4.11.2 Long lead items

PROCUREMENT LOG (LONG LEAD ITEMS)


MATERIAL SUBMITTAL MATERIAL APPROVAL MATERIAL ORDER MATERIAL DELIVERY
Description
Dur Plan Start Plan Finish Dur Plan Start Plan Finish Dur Plan Start Plan Finish Dur Plan Start Plan Finish

Plumbing

Sanitary Wares Fixing & Toilet Accessories 6 17-Feb-24 23-Feb-24 14 24-Feb-24 12-Mar-24 6 12-Mar-24 18-Mar-24 53 19-Mar-24 11-May-24

Booster Pump 6 02-Mar-24 08-Mar-24 14 09-Mar-24 30-Mar-24 6 30-Mar-24 05-Apr-24 53 06-Apr-24 29-May-24

Solar Water Heater - Roof Floor 6 24-Feb-24 01-Mar-24 14 02-Mar-24 21-Mar-24 6 21-Mar-24 27-Mar-24 23 28-Mar-24 20-Apr-24

Electrical

Low Current Cables & ONU & Telephone data 6 17-Feb-24 23-Feb-24 14 24-Feb-24 08-Mar-24 6 09-Mar-24 15-Mar-24 22 16-Mar-24 07-Apr-24

Distribution Boards and Switch Gears 6 02-Mar-24 08-Mar-24 14 09-Mar-24 30-Mar-24 6 30-Mar-24 05-Apr-24 23 06-Apr-24 29-Apr-24

Light Fixtures - Switches - Isolators 6 17-Feb-24 23-Feb-24 14 24-Feb-24 12-Mar-24 6 12-Mar-24 18-Mar-24 33 19-Mar-24 21-Apr-24

MEP Facade Final Fix, Fire Extingusher & Fire Alarm 6 24-Feb-24 01-Mar-24 14 02-Mar-24 21-Mar-24 6 14-Apr-24 20-Apr-24 52 21-Apr-24 12-Jun-24

Swimming Pool Equipment (Filtration System, Heat Pump, etc...) 6 29-Jan-24 02-Feb-24 14 03-Feb-24 07-Feb-24 6 08-Feb-24 14-Feb-24 82 15-Feb-24 07-May-24

HVAC

Grills & Diffusers 6 02-Mar-24 08-Mar-24 14 09-Mar-24 30-Mar-24 6 30-Mar-24 05-Apr-24 23 06-Apr-24 29-Apr-24

AC Units Fixing - Roof Floor 6 17-Feb-24 23-Feb-24 14 17-Feb-24 04-Mar-24 6 05-Mar-24 11-Mar-24 52 12-Mar-24 03-May-24

Commencement Date: 05 Dec 2023

You might also like