Mep Procurement Log - Long Lead - Short Lead
Mep Procurement Log - Long Lead - Short Lead
Plumbing
Sanitary Wares Fixing & Toilet Accessories 6 17-Feb-24 23-Feb-24 14 24-Feb-24 12-Mar-24 6 12-Mar-24 18-Mar-24 53 19-Mar-24 11-May-24
Booster Pump 6 02-Mar-24 08-Mar-24 14 09-Mar-24 30-Mar-24 6 30-Mar-24 05-Apr-24 53 06-Apr-24 29-May-24
Solar Water Heater - Roof Floor 6 24-Feb-24 01-Mar-24 14 02-Mar-24 21-Mar-24 6 21-Mar-24 27-Mar-24 23 28-Mar-24 20-Apr-24
Electrical
Low Current Cables & ONU & Telephone data 6 17-Feb-24 23-Feb-24 14 24-Feb-24 08-Mar-24 6 09-Mar-24 15-Mar-24 22 16-Mar-24 07-Apr-24
Distribution Boards and Switch Gears 6 02-Mar-24 08-Mar-24 14 09-Mar-24 30-Mar-24 6 30-Mar-24 05-Apr-24 23 06-Apr-24 29-Apr-24
Light Fixtures - Switches - Isolators 6 17-Feb-24 23-Feb-24 14 24-Feb-24 12-Mar-24 6 12-Mar-24 18-Mar-24 33 19-Mar-24 21-Apr-24
MEP Facade Final Fix, Fire Extingusher & Fire Alarm 6 24-Feb-24 01-Mar-24 14 02-Mar-24 21-Mar-24 6 14-Apr-24 20-Apr-24 52 21-Apr-24 12-Jun-24
Swimming Pool Equipment (Filtration System, Heat Pump, etc...) 6 29-Jan-24 02-Feb-24 14 03-Feb-24 07-Feb-24 6 08-Feb-24 14-Feb-24 82 15-Feb-24 07-May-24
HVAC
Grills & Diffusers 6 02-Mar-24 08-Mar-24 14 09-Mar-24 30-Mar-24 6 30-Mar-24 05-Apr-24 23 06-Apr-24 29-Apr-24
AC Units Fixing - Roof Floor 6 17-Feb-24 23-Feb-24 14 17-Feb-24 04-Mar-24 6 05-Mar-24 11-Mar-24 52 12-Mar-24 03-May-24
PROCUREMENT LOG (SHORT LEAD ITEMS)
MATERIAL SUBMITTAL MATERIAL APPROVAL MATERIAL ORDER MATERIAL DELIVERY
Description
Dur Plan Start Plan Finish Dur Plan Start Plan Finish Dur Plan Start Plan Finish Dur Plan Start Plan Finish
Tiling Works of Pool House Works 6 17-Feb-24 22-Feb-24 14 23-Feb-24 27-Feb-24 6 28-Feb-24 05-Mar-24 53 06-Mar-24 27-Apr-24
Tiling Works of Swimming Pool Works 3 23-Feb-24 28-Feb-24 14 29-Feb-24 04-Mar-24 6 05-Mar-24 11-Mar-24 53 12-Mar-24 03-May-24
Aluminum Works 6 21-Feb-24 27-Feb-24 14 28-Feb-24 16-Mar-24 6 16-Mar-24 22-Mar-24 60 23-Mar-24 15-May-24
Block & Plaster Works 3 31-Jan-24 02-Feb-24 14 02-Feb-24 17-Feb-24 6 18-Feb-24 24-Feb-24 33 25-Feb-24 28-Mar-24
False Ceiling Board 6 14-Feb-24 20-Feb-24 14 21-Feb-24 07-Mar-24 6 08-Mar-24 14-Mar-24 53 15-Mar-24 06-May-24
Painting Works 6 21-Feb-24 27-Feb-24 14 28-Feb-24 16-Mar-24 6 16-Mar-24 22-Mar-24 30 23-Mar-24 15-Apr-24
Stairs Flooring Finish Treads & Risers 6 28-Feb-24 05-Mar-24 14 06-Mar-24 26-Mar-24 6 26-Mar-24 01-Apr-24 60 02-Apr-24 25-May-24
Stairs Handrail & Copping 6 06-Mar-24 13-Mar-24 14 13-Mar-24 04-Apr-24 6 04-Apr-24 10-Apr-24 60 11-Apr-24 03-Jun-24
Timber Doors Works 6 21-Feb-24 27-Feb-24 14 28-Feb-24 13-Mar-24 6 13-Mar-24 19-Mar-24 60 20-Mar-24 12-May-24
Plumbing
MEP Drainage & Water Supply Pipes 6 10-Feb-24 16-Feb-24 14 24-Feb-24 12-Mar-24 6 12-Mar-24 18-Mar-24 33 19-Mar-24 21-Apr-24
HVAC
MEP Duct Works 6 24-Feb-24 01-Mar-24 14 02-Mar-24 21-Mar-24 6 21-Mar-24 27-Mar-24 23 28-Mar-24 20-Apr-24