Supply and Installation of Gabion facia unit with integrated tail as secondary reinforcement of length 3m made up of hexagonal shaped

steel wire mesh as per IS 16014:2018,


IRC SP 116 :2018 , MORTH clause 2500 of required sizes, Mesh type 10x12 with mesh opening tolerances -10% to +10%, Mesh wire dia 2.7/3.7mm(ID/OD ) , (Front panel
with higher wire diameter compared to other panel), (Zn+ High Abrasion Resistance Polymer coated), mechanically edged/selvedged ,with partition at 1 m interval and shall
have minimum 10 numbers of mesh openings per meter of mesh perpendicular to twist,tying with lacing wire of diameter 2.2/3.2 mm (ID/OD), Dark Brown rust not more than
5 % after subjecting to 6000 hours of neutral salt spray as per ISO 9227 and polymer should be resistant to abrasion after 300 cycles and shall not expose metal wire in
accordance with the procedure described in ASTM A 975 complete as per detailed technical specifications attached and as directed by Engineer-in –Charge.

Code Description Unit Quantity Rate Amount Reference


Details cost of one Gabion box/Crates of Size 3mx2mx1x1m
=2 cum
A LABOUR
PL14 Mate Day 0.10 560.00 56.00 "Rajasthan Urban Infrastructure Development Project SOR 2023,
Basic Rates B-Labour Item No 0231
PL17 Mazdoor/Beldar Skilled Day 0.50 560.00 Basic Labour
280.00 "Rajasthan RateInfrastructure
Urban & Hire chargesDevelopment
Category III Item No 4
Project SOR 2023,
Basic Rates B-Labour Item No 0218
PL15 Mazdoor/Helper Day 1.50 480.00 Basic Labour
720.00 "Rajasthan RateInfrastructure
Urban & Hire chargesDevelopment
Category III Item No 4
Project SOR 2023,
Basic Rates B-Labour Item No 0216
B MATERIAL Basic Labour Rate & Hire charges Category III Item No 4
8577 Crates made of Mesh type 10x12 (D=100
mm)Zn90%+10%Al with High Abrasion Resistant
Polymer Coated. Mesh Wire Diameter 2.70/3.70 mm CPWD DSR 2023 item no 16.95
(ID/OD), (Front panel with higher wire diameter compared
to other area
Surface panel)
required = 20 sqm Sqm 20.00 320.00 6400.00
Sqm 20.00 400.00 8000.00 Considering Price 25% more for strong face and High Abrasion
Resistance Polymer coating
PM22 Stone boulder of size 150-250mm Cum 1.00 0.00 Supply rates of Stone boulder to be considered Seperately
06
TOTAL RESOURCE COST 9056.00
Add for contractor’s profit including overhead @ 15% 1358.40

Labour Cess @1% 104.14


TOTAL cost of 3x2x1x1=2.0 cum 10518.54
Say per Box of size 3x3x1x1 10519.00