Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 11

3.

Cost Estimation

PT BATUBARA SELARAS SAPTA (PT BSS)


East Kalimantan

No Description Amount (in USD) Remark

1 Land and Site Development 4,500,000

2 Jetty 43,624,066

3 StockPile 27,084,260

4 Access Road &Drainage in Mine Area 20,515,733

5 Conveyor Structure 376,000,000

6 Bridge 3,100,885

7 Material Handling System 93,100,000

8 Mining Equipment 8,433,500

9 Other Assets 29,300,000

10 Other Preliminary Expenses 2,850,000

11 Financing Costs 1.25% 7,606,356

12 Contingency 5% 30,425,422

TOTAL 642,040,222

Tax/VAT 10% 64,204,022

GRAND TOTAL 706,244,245


608,508,445
Project : PT BATUBARA SELARAS SAPTA (PT BSS), East Kalimantan
Subject : Port Estimation

MATERIAL EXPENCES / WAGES TOTAL


NO OF
ITEM DESCRIPTION QUANTITY ( in
UNIT COST SUB COST UNIT COST SUB COST
US $ )
I - PREPARATION WORK 1 ls - 3,618,225.00 3,618,225.00

II (MAIN
LoadingJETTY
Platform, Breasting Dolphin, Mooring
Dolphin, Trestle, Walkway, Linear & Pivot
1 Shiploader
Pile provided ) 7,356 ton 1,225.00 9,011,701.49
2 Pile Driving
a - Vertical piles 800 mm Ø 3,313 m1 71.32 236,255.35
b - Batter piles 800 mm Ø (1 : 5 ) 10,167 m1 75.48 767,427.69
c - Batter piles 800 mm Ø (1 : 8 ) 1,157 m1 71.35 82,571.31
d - Vertical piles 700 mm Ø 332 m1 71.28 23,690.62
e - Batter piles 700 mm Ø (1 : 5 ) 6,193 m1 71.15 440,618.14
f - Vertical piles 500 mm Ø 3,123 m1 64.27 200,735.78
3 PDA Test 30 nos 1,110.00 33,300.00
4 Concrete Work
a - For Main Jetty 4,205.00 m3 110.30 463,811.50 33.10 139,185.50
- For Pile head filling 505.00 m3 93.76 47,346.27 28.14 14,208.18
b - Steel reinforcement 565.18 ton 1,572.00 888,466.10 470.00 265,635.54
5 TRESTLE
- Pile provided 14,755.26 ton 1,225.00 18,075,194.16
- Pile Driving
- Vertical piles 800 mm Ø 1,946 m1 71.32 138,773.03
- Batter piles 800 mm Ø (1 : 5 ) 42,778 m1 75.48 3,228,853.58
- Batter piles 800 mm Ø (1 : 8 ) 1,648 m1 71.35 117,577.87
- PDA Test 40 nos 1,110.00 44,400.00
- Concrete Work
- For Trestle 3,823.00 m3 110.30 421,676.90 33.10 126,541.30
- For Pile head filling 400 m3 93.76 37,502.00 28.14 11,254.00
- Steel reinforcement 506.80 ton 1,572.00 796,689.60 470.00 238,196.00
- PC Girder , 20 mtr length 6 nos 9,041.00 54,246.00 888.50 5,331.00
- PC Girder , 24 mtr length 76 nos 10,849.20 824,539.20 1,066.20 81,031.20
6 Fender System
Rubber fender type UPI-2500H x 2600 L with frontal 4.00 124,051 496,204.00 622.00 2,488.00
a nos
pad 4250Wx6250L mm,
b Mooring System
100 tons capacity Quadruple Quick Release Hooks, 53,439.00 587,829.00 800.00 8,800.00
c 11.00 nos
including capstan
7 Walk way
a Steel platform and grating 33.62 ton 1,657.00 55,705.03 652.00 21,918.94
b Galvanized railing steel pipe 2" 1,128.00 m 9.00 10,152.00 2.00 2,256.00
c Steel pipe piles 500 mm Ø, # 14 mm 16 ton 1,225.00 19,714.85
d Pile coating 198 m2 8.23 1,629.54 3.44 681.12
e Driving Vertical piles 500 mm Ø 114 m1 64.27 7,306.21
h Concreting 8 m3 110.30 882.40 33.10 264.80
i Steel reinforcement 1.01 ton 1,572.00 1,579.86 470.00 472.35

TOTAL FOR MAIN JETTY WORK 31,794,869.9 6,239,773.50 38,034,643.40

III IN-LAND SUPPORT


A Rail Stacker Support
1 - Excavate 5,423.00 m3 - - 4.65 25,216.95
2 - Back fill 3,607.00 m3 - - 4.65 16,772.55
3 - Concrete grade K-350 3,485 m3 111.79 389,588.15 33.53 116,852.05
4 - Steel reinforcement 418 ton 1,572.00 657,410.40 470.00 196,554.00
B Conveyor & Transfer Building Support
1 - Provide 450 mm Ø, # 80 mm Spun Pile 4,365.00 m1 93.45 407,909.25
2 - In land pile driving 4,365.00 m1 13.86 60,498.90
3 - PDA Test 5 nos 1,110.00 5,550.00
4 - Concrete grade K-350 243 m3 111.79 27,164.97 33.53 8,147.79
5 - Steel reinforcement 29.15 ton 1,572.00 45,830.09 470.00 13,702.38

TOTAL FOR IN-LAND SUPPORT 1,527,902.86 443,294.62 1,971,197.48

T O T A L JETTY 43,624,065.88
Project : PT BATUBARA SELARAS SAPTA (PT BSS), East Kalimantan
Subject : Stock Pile Estimation

9000
Unit Rate Amount (in
No Description Unit Quantity (in USD) USD)
Remark

A Stockpile 1 at Blok Bekoso ha 10


1 Land Clearing m2 100,000 1.11 111,111
2 Fill Soil 2m m3 200,000 7.78 1,555,556
3 Topography ls 1 13,272 13,272

B Stockpile 2 at Blok Libur Dinding 1 ha 10


1 Land Clearing m2 100,000 1.11 111,111
2 Fill Soil 2m m3 200,000 7.78 1,555,556
3 Topography ls 1 13,272 13,272

C Main Stockpile & Reclamation Area ha 97


1 Land Clearing m2 970,000 1.11 1,077,778
2 Fill Soil 3m m3 2,910,000 7.78 22,633,333
3 Topography ls 1 13,272 13,272

SUB TOTAL 27,084,260


Project : PT BATUBARA SELARAS SAPTA (PT BSS), East Kalimantan
Subject : Transportation Road & Drainage Estimation

1. ROAD
No Description Price /m2 Qty (m2) Amount (in IDR) Remark

1 Labour for Asphalt Penetration 20,000 624,000 12,480,000,000


2 Labour for Onderlaag 2 layer @ 20 cm and Spread 40,000 624,000 24,960,000,000
3 Land Clearing 10,000 624,000 6,240,000,000
Sub Total (in IDR) 43,680,000,000

Sub Total (in USD) 4,853,333.33

2. DRAINAGE

Drainage Pasangan Batu Kali (Both Side)


Volume = ((0.4+0.8)/2)x1x4x(78000) = 187,200 m3
196080
No Description Unit Quantity Unit Rate Amount (in IDR) Remark
1 Pasang Batu Belah Selokan m3 187,200 175000 32,760,000,000
TOTAL - A 32,760,000,000 -

Bill Of Material (BoM)


No Description Unit Quantity Unit Rate Amount (in IDR) Remark
1 Batu Kali m3 224,640 230,000 51,667,200,000
2 Pasir m3 112,320 70,000 7,862,400,000
3 Cement @ 50kg/bag bag 748,800 65,000 48,672,000,000
TOTAL - B 108,201,600,000

TOTAL A + B (in IDR) 140,961,600,000

TOTAL A + B (in USD) 15,662,400


Project : PT BATUBARA SELARAS SAPTA (PT BSS), East Kalimantan
Subject : Conveyor Structure Estimation

Sl. No. Description Unit Quantity Unit Rate (in USD) Amount (in USD) Remark
1 Conveyor Structure 1 (from Bolck Bekoso to Main Stockpile) m' 15000 8000 120,000,000
2 Conveyor Structure 2 (from Block Libur Dinding 1 to Main Stockpile) m' 32000 8000 256,000,000

SUB TOTAL 376,000,000


Project : PT BATUBARA SELARAS SAPTA (PT BSS), East Kalimantan
Subject : Bridge - total 150 m long

Si. No. Description Unit Qty Unit Price (In IDR) Amount (In IDR) Amount (In USD)
1 Abutment no 2 1,320,087,300 2,640,174,600
2 Pier no 3 1,924,528,200 5,773,584,600
3 Upper structure item 1 17,914,704,514 17,914,704,514
4 Worker refuge platform no 3 9,000,000 27,000,000
5 Cable support m 150 750,000 112,500,000
6 Enabling works item 1 1,440,000,000
SUB TOTAL - Bridge span 150 m 27,907,963,714 3,100,885
Project : Transportation Road and Port BSS, East Kalimantan
SUBJECT : MATERIAL HANDLING SYSTEM COSTING AND RELATIVE SPEC

NO DESCRIPTION UNITS U/COST TOTAL COST

1 UNLOADING CONVEYOR (rated at 5000mt/hr) 2 X 250M USD 2.0 MIL/KM 1,000,000


2 INHAUL TRANSFER TOWER 4 USD 200000/TOWER 800,000
3 YARD FEED CONVEYOR 3 X 0.5KM USD 1.5 MIL/KM 2,250,000
4 INHAUL TRANSFER CONVEYOR 3 X 250M USD 2.0 MIL/KM 1,500,000
5 YARD CONVEYOR TO TO STACKER RECLAIMER 3 X 250M USD 2.0 MIL/KM 1,500,000
6 COAL PILE SPRINKLER SYSTEM 1,000,000
7 STACKER / RECLAIMER 3 USD 5.0 MILLION 15,000,000
8 OUTHAUL TRANSFER CONVEYOR 2 X 500M USD 2.0 MIL/KM 2,000,000
9 OUTHAUL TRANSFER TOWER 3 USD 200000/TOWER 600,000
10 FLOP GATES TO JETTY CONVEYOR 6 USD 100000/UNIT 600,000
11 SAMPLING UNITS 2 USD 400000/UNIT 800,000
12 JETTY CONVEYOR 2 X 500M USD 1.5 MIL/KM 1,500,000
13 SURGE HOPPER (for three barges) 3 USD 250000/hopper 750,000
14 BARGE FEED CONVEYOR 2 X 500M USD 1.5 MIL/KM 3,000,000
15 Barge Loading System at Ex BHP Port 3 USD 5.0 MILLION/UNIT 15,000,000
16 DUST SUPPRESSION SYSTEM (20 locations) USD 2.0 MILLION 2,000,000
17 PILING WORK FOR MATERIAL HANDLING SYSTEM 5000 MTRS USD 200/METRE 1,000,000
18 CIVIL WORK FOR TOWERS 10 USD 100000/TOWER 1,000,000
19 CIVIL/SETTLEMENT FOR STOCKPILES, DRAINAGE, RESER USD 5.0 MILLION 5,000,000
20 ELECTRICAL SYSTEM 1 USD 8 MILLION 8,000,000
21 FIRE FIGHTING SYSTEM 1 USD 1.0 MILLION 1,000,000
22 COMMUNICATION & CONTROL SYSTEM 1 USD 2.0 MILLION 2,000,000
23 WEIGH BRIDGE 2 USD 250000 500,000
24 ENGINEERING 1 USD 5000000 5,000,000
25 WORKSHOP & STORES 1 USD 250000 250,000
26 FUEL TANK FARM OF CP 5000 LITRES 1 USD 2000000 2,000,000
27 CONTRACT EQUIPMENT AND LABOUR 10,000,000
28 GENSETS 3000KW 7 USD 1000000 7,000,000
29 GENSETS 300KW 3 USD 350000 1,050,000

TOTAL CAPEX FOR 25MMT 93,100,000


PT BATUBARA SELARAS SAPTA (PT BSS)
Mining Equipment - Estimate of Capital Expenditure

Si.No. Description Unit Qty Unit Rate (in USD) Amount (in USD)

1 Excavators 45 MT No 4 205000 820000


2 Excavators 30 MT No 2 132000 264000
3 Excavators 20 MT No 2 83000 166000
4 Dump trucks No 30 166000 4980000
5 Dozer SD32 No 1 250000 250000
6 Dozer SD16 No 5 90000 450000
7 Swamp Dozer No 2 240000 480000
8 Front end loader No 5 39500 197500
9 Road grader No 2 100000 200000
10 Vibratory Compactor No 2 63000 126000
11 Diesel tanker No 2 115000 230000
12 Water tanker No 2 115000 230000
13 Service Truck No 1 40000 40000

Subtotal 8,433,500
PT BATUBARA SELARAS SAPTA (PT BSS)
Other Assets - Estimate of Capital Expenditure

All amounts are in USD


Sl. No. Asset Description Capital Expenditure Remarks
Unit Quantity Unit Rate Amount

OTHER ASSETS

(a) Excavators Nos. 2 175,000 350,000


(b) Dozers Nos. 4 250,000 1,000,000
(c) Dump Trucks Nos. 10 175,000 1,750,000
(d) Loaders/Graders Nos. 4 200,000 800,000
(e) Crane/Fork Lift Lot 1 6,000,000 6,000,000
(f) Material Handling Equipments Lot 1 5,000,000 5,000,000
(g) Flat Bed Trailor Nos. 2 500,000 1,000,000
(h) Construction, Office and mobilisation Nos. 20 100,000 2,000,000
(i) Bus/Fire Engine/Ambulance Nos. 15 100,000 1,500,000
(j) Pickups/Cars Nos. 20 45,000 900,000
(k) Track Maintenance Machinery Nos. 1 5,000,000 5,000,000
(l) Other Utilities Lot 1 4,000,000 4,000,000

Subtotal Other Assets 29,300,000


PT BATUBARA SELARAS SAPTA (PT BSS)
Other Preliminary Expenses - Estimate of Capital Expenditure

All amounts are in USD


Sl. No. Asset Description Capital Expenditure Remarks
Unit Quantity Unit Rate Amount

1 Amdal & KP Exploitation Costs ls 1 50,000 50,000


2 Topography ls 1 100,000 100,000
3 JORC complaince report ls 1 100,000 100,000
4 Preoperative expenses ls 1 1,000,000 1,000,000
5 Transport ls 1 500,000 500,000
6 Engineering ls 1 500,000 500,000
7 Contract Labor ls 1 100,000 100,000
8 Other costs ls 1 500,000 500,000

Sub Total 2,850,000

You might also like