Professional Documents
Culture Documents
P5 C6 Materiel
P5 C6 Materiel
3rd Edition
PART 5 CHAPTER 6
SECTION1–SAFETY
SAFETY MANAGEMENT
Name:
Trained:
Duration in
Appointment:
Primary Duty:
Secondary Duty:
1. Is the Safety Officer qualified?
Ref: PU 9104-001 Part 3 Chap 1 Para 9 - 10
a. Appointed by CO/ OC
5.6 – 1 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
SAFETY MEETING 2.
3.
4.
6. Conduct of safety meeting at Sqn/ Unit.
Ref: PU 9104-001 Part 4 Chap 3 Para 1 - 6
a. At least once every 3 months.
Outstanding
Percentage
completed (%)
16. Has the processing of Hazard/ Incident Report been properly recorded and
managed?
d. On-going monitoring.
e. Confirmation of the effectiveness of corrective
action.
18. Place the Hazard/ Incident Report Box or other
methods at various places in base/unit to enable
personnel to make report easily.
19. Has the Safety Officer provided the originator with
verbal or written report of the follow up action?
Ref: PU 9104-001 Part 6 Chap 1 Annex A Para 8
DOMESTIC SAFETY
e. Designatedsmokingareaisavailableand
markedwithsignage.
f. Grassandundergrowthcuttingappropriately
carriedout.
29. Is the area of employment and its surroundings free from Electrical Hazard?
Ref: PU 1111 and Base Fire Orders
Lightfittingsandswitchesareingood
a.
condition.
b. Poweroutlets,powerleads,plugs,adapters
areingoodconditionandcorrectlyutilized.
c. Electricalappliancesandwiringcablesarein
properandgoodcondition.
30. Fire Order is in place and adhered.
Ref: PU 1111, Base Fire Orders and FOC Serial 26/2016
a. Base Fire Order is available and updated.
b. Base Fire Order is read and signed by all
personnel six monthly.
c. FireEvacuationPlanisavailableandposted
clearly.
31. Are the fire extinguishers well managed and maintained?
Ref: PU 1111, PU 1112 and Base Fire Orders
a. Fire signage, notice and poster appropriately
display.
b. Fireextinguisheravailableandserviceable.
c. Monthlyinspectioniscarriedoutandreport
senttoFireSectionbyuser.
d. Fireextinguishersixmonthlyinspection
conductedbybaseFireSection.Reportis submitted
to unit.
Ref:PU1111Part8Chap 2Para4&5
e. Fireextinguisheryearlyservicingconducted
bybaseFireSection.Reportissubmittedto the
unit.
Ref:PU1111Part8Chap 2Para4&5
Ref:PU1112Part3Chap 4
f. Fireextinguisherextendedserviceconducted.
Ref:PU1112Part3Chap 4
PART L – CORE: EXPLOSIVE STORE SAFETY
32. Does unit comply to the Licensing and Authorisation procedure?
Ref: PU 2302 2nd Edition Sect 4 Leaflet 1 & PU 2304-018 Sect N Leaflet N 5
a. TUB20-0140ExplosiveOrdnanceFacility Licence
b. TUB20-0141AuthorisedUsed&Explosive
ContentOfAnExplosiveFacility
c. Application for the renewal of EO Facilities
License(Armory/JUSEN/AWC/SafetyBay&
Destini Prima/ HANDAU/ ATC Tower/ SAR
(PUGK) is sent 6 months prior the license
expiry.
5.6 – 6 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
5.6 – 7 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
c. Issuing disc.
36. Are Hazard Division Signage & Supplementary Signage properly displayed?
Ref: PU 2304-018 Sec H Leaflet H1 Para 11.
a. Legible and clear illumination by
vehicleheadlights.
b. Correct position facing each approach road.
c. Supplementary signage display.
(depends on type of EO)
d. EO Hazard division displayed matches withstore
content.
PART M - CORE: TRANSPORTATION SAFETY
37. Are the factors that can cause the transports/ vehicles accidenthas been taken off?
Ref: PU 9104-003 Part 14 Chapter 1
a. Environmental Factors:
(1) Insufficient lighting.
(2) Excessive noise.
(3) Narrow pathways.
(1) Dusty workplace.
b. Vehicle Factors:
(1) Overloading of cargo.
(2) Design error.
(3) Insufficient machine safety equipment.
(eg: no warning light/ buzzer).
(4) Mechanical failure (eg: Brake syst).
(5) Electrical Failure (eg:warning light/ panel/
sensors).
(6) Inappropriate usage
(1) Wear and tear of vehicle parts
BFI/FUEL LAB/FUEL STATION
46. Are the identification and marking on the EO/boxes/containers and packaging following
the requirement?
Ref: PU 2304-003 Sect A Leaflet A3 & Leaflet A2 Para 10 - 12. PU 2304-018 Sect
NLeaflet N2 Para 10
a. Identification marking is legible.
b. Identification at container/ box/ packagingtally
with EO identification.
c. Legible hazard colour coding.
5.6 – 10 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
b. EO in good condition.
c. Classification, Group and NEQ detailsavailable
and adhered.
51. Restricted In Use (RIU) EO storage.
Ref: TO Explosive Ordnance Reclassification Message (EORM).
a. RIU Card available.
f. Speed limit.
g. Strapping.
MT FLEET
5.6 – 12 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
SAFETY
NOT
NOOFQUESTION COMPLIANCE NONCOMPLIANCE
AUDITED
57
SECTION2–READINESS
PWUI/ FSJN/
KPLU LUK REMARK
PWUII SJNU
ESTABLISHMENT
ACTUALSTRENGTH
TOTAL
PERCENTAGE(%)
PARTA–CORE:HUMANRESOURCE
Isthemanningsufficienttoperformandundertaketasks?
1.
Ref:PU2201Part4Leaflet2+ KPI
Abletoperformitsdailyassignedrolewiththepresentma
a.
nningstrength.
b. Strengthversusestablishmentismorethan70%.
HOTOofdutyandinventorycarriedout?
2.
Ref:PU43052nd EditionPart2Sec5
DoesKetuaFleetKenderaanappointmentiaw
3.
procedure?Ref:PU43052nd EditionPart2Sec1
PARTB–ROUTINE:INFORMATIONANDCOMMUNICATIONTECHNOLOGY
ArethefollowingInformationandCommunicationTechnology(ICT)equipmentavailable and
4.
functional?
Ref:UnitEquipmentTable/MATM-BIJ100-13/7/2-(6)bertarikh12Mac2015/Buku
PanduanKesiagaanATM
a. Telephone.
b. Facsimile.
c. Computer.
d. Printer.
e. P4/SPKB Terminal.
f. Provided WIFI/Internet.
PARTC–ROUTINE:OTHERADMINFACILITIES
5.6 – 13 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
5. Arethefollowingbasicadminfacilitiesavailableandfunctional?
a. Photocopier.
b. Shredding Machine.
e. Examinationcarried out.
f. Examresultavailableandrecorded.All result
submittedtoMTU-SISMAT.
g. Certificateofcompetencyare issued and record.
Doesthedrivercompetencycheckcarried out?
7.
a. Examinedbyqualified instructors.
b. Theoryassessmentcarried out.
c. Certificateofcompetencyare issued.
OnJobTraining(OJT)/FamiliarizationTraining/continuationtrainingforPPKTradecarriedout?Re
8.
f:PU4305 2nd EditionPart4Sec13
a. Trainingschedule available.
c. BookingIn/OutSystem employed.
d. Alltoolsareengraved/stamped/marked.
PARTF–ROUTINE:DISPOSALPROCEDURE
Arethescrapitemdisposalproceduresadhered?
10. Ref:PU4101Part1Sec 14.
5.6 – 14 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
PARTH–CORE:EXPLOSIVEORDNANCEREADINESS
Isthe explosive ordnance kept inside
12.
thestore/room/compartment/boxes securely locked?
Ref: PU 2304-018 Sec A Leaflet A4 Para 1.
Inspectionon explosive ordnance carriedoutat the
13.
Explosive Store House, done by LUK and above.
Ref: PU 2204 Bhg 3 Ris 5 Para 3.
(Related to Armament Technician only)
Inspection onexplosive ordnancecarried out at theExplosive Store House(Materiel).
14.
Ref: PU 2204 Bhg 3 Ris 5, Bhg 8 Ris 2 Para 22 19, PU 2304-003 Sec G and PU 4309 Sec
10 Chapter 1
Notes: All inspection above done by Armourers at Explosive Store House (Cawang Materiel) - PU
Sendayan, PU Subang, PU Kuching, KTU, Rejimen TUDM, ATU Ipoh, Sqn 322 Bukit Ibam dan
Sqn 323 Bukit Lunchu.
a. Stock Check
b. Routine inspection
d. Prereceipt inspection
e. Acceptance check
f. Special inspection
5.6 – 15 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
b. Tagging.
c. Condition.
d. Dues-out.
IstheReceivingofU/Sitemproceduresadhered?
16.
a. U/S labeltag.
b. Log Book.
c. LogCard.
d. DefectReport.
IstheIssuingofServiceableitemproceduresadhered?
17.
a. Transfer.
b. Condition.
c. IssueOrder.
d. On Loan.
Storageprocedureadhered.
18.
Ref:PU4301Part1LeafletA7/1.
a. Packaging.
b. Preservation.
c. Locationandstockquantity in SPKBtallywith
physical.
d. No items stored on ground.
f. NoimmediateactiononitemsStatus‘T’.
DaftarBarang-BarangBertarikhLuput(KEW.PS-6)
available?
19.
Ref: PU 4313 2nd Edition.
MaterialHandlingEquipment(MHE)sufficientto assist
store handling.
20.
Ref:PU4302Part1Leaflet2.
Registrationbook(Kew67)forclassifieddocumentavailable
21.
andupdatedatStationeryStore.
22. V&Astorekeys(originalandduplicate)managedandupdated.
5.6 – 16 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
a. V&Astorekeyssafelykeptinsidethekey
boxasperinstruction.
b. Withdrawal name published inPart 1Orders.
c. LaundryFormsignedbybarrackstore
staffwhentheysentandreceivedthe clothes.
d. Complaint/suggestion book available.
e. Contractoradheredtothecontract agreement
IstheTailorprocedureadhered?
24.
Ref:PU4101
a. TailorrequirementsorganizedthroughClothingStore.
b. Registrationbook available
c. StaffsigntheTailoringFormwhenthey
sendandreceivetheclothesattheclothing store
d. Complaint/suggestion book available
e. Contractoradheredtothecontract agreement
RATION STORE
BFI/FUEL STATION
5.6 – 17 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
c. Dippingandtemperaturecheckare donebefore
1000H.
d. Utilizationofcorrectprocedurefor receiving
andissuing item.
e. Stocksareabove80% capacity.
f. Allpump serviceability.
g. Waterseparatorfilterandcoalescing filterwithindue
date.
h. Hoseandcoupling/nozzleare serviceable.
i. CirculationandWaterdrainedaredone dailybefore
issuing.
j. Labapparatusaresufficientand calibrated
Registerbookforeachfuellabtest
k. availableandwellmaintained.(i.eSpecificgravity,
sulphide test, water reaction test)
AIR MOVEMENT
f. DocumentsforacquisitionofIn-
FlightRationfiledandmanagedproperly.
g. Acquisitionofflightrationfollowtheactualtimingofflying
hourssubmittedbyaircrew.
MT FLEET &TPPS
5.6 – 18 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
a. Daily Inspection
c. MinorandMajor Servicing.
PARTO–CORE:ASSETANDEQUIPMENTSTATUS
Aretheservicing/repairforClass1AGSV/AGSEcarriedout?
31. Ref:PU2205Part1Leaftlet1.
a. Daily Inspection.
b. Schedule Servicing.
c. Physicalcheck/Functionaltest&Road
Testcarriedoutduring inspection?
d. BondingCheckfor AGSV(Refueller/Dispenser).
Ref:PU2205Part2Leaflet 5
e. TeardownInspection/Pre
DeliveryInspectionbefore/afterServicingorRepair by
Contractor.
Aretheservicing/repairforDomesticVehiclecarriedout?
32.
Ref:PU2205Part1Leaftlet2.
a. Daily Inspection.
b. Schedule Servicing.
c. Physicalcheck/FunctionalTest&Road Test.
b. Schedule Servicing.
5.6 – 19 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
c. Physicalcheck/Functional Test.
d. TeardownInspection/Pre Delivery
Inspectionbefore/afterServicingorRepair by
Contractor.
PARTP–ROUTINE:AGSE&AGSVCOLOURCODING
DoallAGSVadheretoRMAFColourScheme?
34.
Ref:PU2205Part2Leaflet6.
a. SpecialVehicle(Base/Unit/Sqn)-
SemiGlossGreyColour(Code-595-26118)
SpecialVehicle(PrimeMover&TugTrailer(AirDefence
b. )SemiGlossGreyColour
(Code-595-26118)
c. TACCOMMCabin(AirDefence)-
SemiGlossGrey(Code-595-26118)
d. CrashAmbulance-SemiGlossWhite
(Code-595-27925)
e. SpecialVehicle(Operation)-
SemiGlossGoldenYellow(Code-595-23655)
DoallAGSEClass1,Class2,AP&ABOadheretoRMAFColour Scheme?
35.
Ref:PU2205Part3Leaflet3.
a. Class1-SemiGlossGreyColour
(Code-595-26118)
b. Class2(Squadron)SemiGlossGoldenYellow(Code-
595-23655)
c. Class2(AirDefence)-SemiGloss Grey
(Code-595-26118)
d. LoxDispenser-SemiGlossWhite
(Code-595-27925)
e. ABO/AP(PASKAU)-SemiGlossBlack
(Code-595-27038)
INSPEKTORAT BAHAN LETUPAN
5.6 – 20 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
a. Authenticitysealingavailablefor storageusage.
b. Recordofauthenticitysealing usage.
c. Vouchers,letters,reports&
publicationsrelatingexplosivesclassifiedas
'SECRET'.
AllEOaccountingrecordskeepunder
d. safelockandkeyonlyauthorisedpersonnel allowed to
access.
DoestheKeysmanagementsystemconducted,maintainedandupdated?
Ref:PU2304-018SecNLeafletN1Para9andSecOLeafletO2Annex BAppendix2, FAFSI 1961.
38.
a. Placeinauthorisedplace safe.
b. Clearlylabelled/ numbered.
c. KeysBookin/out recorded.
TOTAL
READINESS
NOT
NOOFQUESTION COMPLIANCE NONCOMPLIANCE
AUDITED
38
SECTION3:MANAGEMENT
c. Content/componentofeverymyPortfolio
adheredtoasfollows:
(1) OrganisationalChart.
(a) RMAForganisationchart.
(b) HQDivisionorganizationalchart.
(c) Base/Unitorganisationalchart.
(d) Branchorganisationalchart.
(e) Jobpositionismarked/showed.
5.6 – 21 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
b. MonthlySPUactivityconductedintheSqn/Unit.
c. Attendancesarekeptinrecordandsatisfactory.
ThesubjectgivenbyMTU-Perkhidmatanis
discussed and the issue raised are act
d.
accordinglyandpendingactionshallbe
discussedinthenextSPUmeeting.
e. Minutesofmeetingarereadandsignby allabsentee.
f. TheCO/OCsignsthemonthlyproceeding.
g. DiscussionofInnovationprojectinSPUmeeting.
PARTC–ROUTINE:INVENTORYMANAGEMENT
Does the equipment in the inventory properly managed?
3.
Ref: PU 4101, PU 4301 Part 2 Section 10, PU 4312 2nd Editionand
MTU.MAT.100-10/1/4 bth 14 Mac 2022.
a. AssignedInventoryHolderispublishedin Part One
Order.
b. HandingOverTakingOverprocedure adhered.
h. Equipment calibrated.
IsdocumentationandSPKBsystemproperlymaintainedandupdated?
4.
a. UnplannedReceiptofequipmentand accessories is
recorded in SPKB.
Ref: MPBU/SISGPD/S.5570/1 bth 29 Mei 15.
b. Stockquantity,condition,partnumber
andserialnumberintheSPKBsystemtallywith
physical.
c. Tech,BarrackandRKATinventory
holdercopyavailableandrecordedin SPKB.
d. Senarai Aset Alih (KEW.PA-7) available.
PARTD–ROUTINE:PERSONNELADMINISTRATION
5.6 – 23 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
PARTE–ROUTINE:DAILY KEY
Is the Daily Key (original and duplicate)managed and updated?
7. Ref: PU 5310 – Publikasi Udara Manual HANDAU, PU 5406 Bab 3 Para 3 (Panduan
Pengurusan Pejabat) & Arahan BSPP 1987.
a. Keys orderly withdraw/ return from Balai Pengawal
and recorded.
b. Original/ Duplicate key updated accordingly.
PARTF–ROUTINE:DAILYMORNINGPARADE
IstheMorningParadewellmanaged?
8.
Ref: Perintah Tetap Pangkalan
a. Record book for daily Morning Prade.
PARTG–ROUTINE:PEMBERHENTIANPEGAWAIDANANGGOTALLP
Dokumentasi Pemberhentian processes are properly
9.
managed.
Ref: PMAT 3/18, PPAT 2013 & SATM6
PARTH–ROUTINE:PUSATPENDAFTARAN(ADMIN)
Sub Registry
10.
Ref: Panduan Urusetia Jil 3, Klasifikasi Rekod Urusan Am Angkatan Tentera Malaysia
&PU 5406 2nd Edition
a. Sub registry (with Admin staff):
b. Boardofsurveyconductedonallclosed files
(morethan5 years).
PART I–ROUTINE:MATERIELORDERS/PUBLICATIONS/INSTRUCTIONS
Are all publication valid, updated and well maintained?
12.
a. PU4101–ArahanMateriel Udara.
b. PU4301–PeraturanMateriel Udara.
s. DisseminationofHigherAuthority directives
& Instruction.
t. PU4312 2nd Edition –TatacaraPengurusanAset
Alih TUDM
u. PU 4313 2nd Edition – Tatacara Pengurusan Stor
TUDM
v. PU 4315 – Peraturan Hantaran Udara TUDM
z. SATM2–PengurusanDewan Makan
b. Amendment updated.
c. EORMRegister Updated.
d. ConsolidatedRegister Updated.
e. LocalRedCardRegister updated.
TUB20-145LocalRedCardRegister Sheets
f. inserted.
TUB20-149BlacklistRegister Sheets
g.
inserted.
TUB20-145RedCardRegister Sheets
h. inserted.
i. RestrictedInUseRegister inserted.
STOCKCONTROLANDACCOUNTINGFLIGHT (SCAF)
PARTJ–ROUTINE:SCAF MANAGEMENT
5.6 – 26 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
15. Isdemandforstockreplacementhasbeencarriedout?
Isdemandprocessproceduresadhered?
16.
a. REdemandactionaccordingto priority.
(Internal Demand)
b. Isthereoutstandingdemand(AOG) reflected
onserviceable aircraft?
c. Isthereoutstandingdemand(ROA) reflected
onserviceable radar?
d. NoRO1demandforstock replenishment.
DoesunitsubmittedSMP17(PenyataSenjatadan
17. Accessories) and details in SMP updated accordingly
with physical holding.
Ref::PU23022ndEditionSec7Lft12
Accountingledgerupdatedandproperlymanaged.
18.
Ref:PU4101andPU4301.
PARTK–ROUTINE:SCAFINVENTORY CELL
Does Holder and Asset Checks conducted?
19.
Ref: PU4101 and PU4301, PU 4312 2nd Edition&MTU.MAT.100-10/1/4 bth 14 Mac 2022.
a. Technical/Barrackevery6 months.
c. AllTech,BarrackandRKATinventory listrecordedin
SPKB.
d. HOTORKATcertificatebetween
inventorycellandCMOare available.
e. Inventory inspection datepublishedin Part One
Orders.
INSPEKTORAT BAHAN LETUPAN
PARTL–CORE:INSPECTIONOFEXPLOSIVEORDNANCE FACILITIES
AreExplosiveOrdnanceFacilitiesinspectionrecordsmaintainedandupdated?
20.
Ref:PU2204Bhg8Ris1&PU2304-018SecNLeafletN5&LeafletN7andSecOLeaflet O2 Annex
B Appendix 1.
a. TUB20-0277Temperature&HumidityRecord.
b. TUB20-0278BiWeeklyInspection.
PARTM–CORE:ASSETANDSTOREMANAGEMENT
5.6 – 27 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
ASSETACCEPTANCE
k. Officer in-charge in acceptance and
examinationof Aset Alih (inclusivetechnical asset)
process is qualified officer who appointed by
Ketua Jabatan. Ref: Ref:AM 2-2, Para 2.
l. Officer in-charge in acceptance perform a
physicalcheckingtotheasset.
Ref:AM2-2,Para 3.3.2.
m. Conditional acceptance is adhered.
Ref: AM 2-2, Para 3.3.3.
n. Verificationofacceptanceperformedbythe Officer
in-charge by using KEW.PA-1.
Ref: AM 2-2, Para 3.3.4.
o. Rejectionofasset(KEW.PA-2)isadhered.
Ref: AM 2-2, Para 3.3.5.
p. DocumentofPurchaseOrder,Deliveryorder,
invoice,warrantyletterandetcisprovidedby
suppliertoofficerin-chargeofacceptancefor
procurement under the center contract/centrally
procurement.Ref:AM2-2,Para 3.3.8.
q. Qualityofassetisfollowedspecificationas per
contract agreement (center contractprocurement)
Ref: AM 2-2, Para 4.
Duty and responsibility as an Officer in-
r. chargeofAcceptanceisstatedin.Ref: AM 2.2 Para
3.
ASSETREGISTER
s. Aset Alih were registered in Daftar Harta
Modal (KEW.PA-3) and Daftar Aset Alih
Benilai Rendah (KEW.PA-4)within2weeks
from the date of acceptance.Ref:AM2-
3,Para2,3& 4.
t. Registration of Aset Alih which is under
buying-renttermisadheredtoprocedure.
Ref:AM2-2,Para 5.
u. Registeredofrentassetisavailable
forrecordpurpose.Ref:AM2-2,Para 6.
v. Anyassetwhichreceivedfromother
sourcesispracticingofKEW.PA-3,KEW.PA-
4and KEW.PA 7. Ref: AM 2-2, Para 8.2/8.3.
w. KEW.PA-3&KEW.PA-4ismaintainedwith
complete and accurate information.
Ref:AM2-2,Para 9.3.
5.6 – 29 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
x. Ketua Jabatan/Bahagian/Section/Unit is
checked and verified KEW.PA-3 before
signed.Ref:AM2-2,Para 9.4.
Senarai Daftar Harta Modal (KEW.PA-5)
y. &Senarai Aset Alih Bernilai Rendah (KEW.PA-
6) is available and updated.
Ref: AM 2-2,Para 9.7.
z. Aset Alih register is always maintained
andupdated if any changes occur.
Ref: AM 2.2 Para 9.8.
aa. AssetLabellingpracticeisadhered.
Ref: AM 2.2 Para 9.10.
ab. Senarai Aset Alih (KEW.PA-7)practice
isadhered.Ref2.2 Para 10.
ac. Laporan Kedudukan Aset Alih (KEW.PA-8)is
prepared and submitted to
UPAAktiviti/Program/Kementerian.
Ref: AM 2.2, para 13.
ASSETUSAGE,STORAGE&INSPECTION
ad. PracticeofBorangPermohonanPeminjaman &
Pergerakan Aset Alih (KEW.PA-9)
isadhered.Ref:AM2-4Para 3.1.
ae. Anymovingoutassetfromofficemusthave
writtenapprovalbyKetuaJabatan/Pegawai
Aset/OthersappointedofficerauthorizedbyKetuaJ
abatan.Ref:AM2-4Para 3.2.
af. UnservicebleassetisreportedusingBorangAduanKer
osakanAsetAlih(KEW.PA-10).
Ref: AM 2.4 Para 4.
ag. V&Aassetiskeptinasafeplaceby
theresponsibleofficer.Ref:AM2-4Para5.
ah. Appoinment of 2 x inspector by Pegawai
Pengawal/JKPAKChairmanofministryis:
1. Gred19andabovewhichisnot
involved directly with the management
of the asset.
2. 2years appointment.
Ref:AM2-4Para 6.3.
ai. 100%inspectionofassetiscarriedoutthroughouttheye
ar.Ref:AM2-4Para6.4.
aj. InspectorareusingBorangPemeriksaanAsetAlih(KE
W.PA-11)duringinspectionand procedure of
inspection is adhered. Ref: AM 2.4 Para 7.3.
ak. Ketua Jabatan is taken action for Any
discrepancies found in KEW.PA-11 and write-
offactionimplementedforuntraceable asset.
Ref:AM2-4Para 8.
al. Laporan Pemeriksaan Aset Alih (KEW.PA-
12)isproducebyPegawaiAsetandreported in PTJ
JKPAK meeting than submitted to
theUPAActivity/Program/Kementrian. Ref: AM 2.4
Para 9.
5.6 – 30 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
5.6 – 31 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
DISPOSALOFASSET
az. Disposalfileisavailable,updatedandcompletelyrecor
ded.Ref:AM2-7.
PerakuanPelupusan(PEP)(KEW.PA-19)is
ba. preparedforall
typeofdisposalandadheredtoprocedure.Ref:AM2-
7,Para4.1.
Perakuan Pelupusan in KEW.PA-19 is verified by
bb. 2 x officer (1. Pegawai Kumpulan
P&P,2.PegawaiKumpulanPelaksanaGred19andab
ove).
Ref:AM2-7,Para4.4.
bc. ValidityofPerakuanPelupusanisonlyoneyearfromthe
dateofissue.Ref: AM2-7,Para4.5.
bd. Lembaga Pemeriksa Pelupusan (LPP) is
appointed by Pegawai Pengawal (KSU)/Pengerusi
JKPAK Kementerian using Surat Lantikan
Lembaga Pemeriksa Pelupusan (KEW.PA-20)
base on post and notmorethan2years.
Ref:AM2-7,Para5.1/5.3.
be. LPP consisted of 2 x officer which is not directly
involved in handling of the asset. (1.
PegawaiKumpulanP&P,2.PegawaiKumpulanPelak
sanaGred19andabove).
Ref: AM 2.7 Para 5.3.1.
bf. Inspection performed within one month from
thedateofdirectsbyJabatan.Ref:AM2-7,Para5.4.
bg. All Aset Alih which proposed of dispose is listed in
Borang Pelupusan Aset Alih (KEW.PA-21) and
submitted to UPA
Aktiviti/Program/Kementrianforapproval.Ref:AM2-
7,Para6.
bh. KEW.PA-19wassignedbyLPPand submittedto
UrusetiaPelupusanKementerian.
Ref: AM 2.7 Para 5.4, Para 7.4.
bi. AsetAlihdisposedaccordingtotheapproval
method. Ref: AM 2.7 Para 7.
bj. Sijil Penyaksian Pemusnahan Aset Alih(KEW.PA-
22) submitted to UPA
Aktiviti/Program/Kementerian for disposal
methodofdestructionandSea-dumping.Ref:AM2-
7,Para7.7.
bk. SijilPelupusanAsetAlih(KEW.PA-23) submitted to
UPA Aktiviti/Program/Kementerian.
Ref:AM2-7,Para7.7.
bl KEW.PA-3&4updatedforthe Assetdisposed.
. Ref:AM2-7,Para7.8.
bm. Disposalprocessusingapprovalmethodisdonewithin
6monthfromthedateof approvalletter.
5.6 – 32 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
bn. Applicationofextendstheperiodofdisposal
submitted to Kuasa Melulus in 2 weeks before
due date of first approval letter.
(extensionallowedonlyonceandtheperiod is not
exceeding one month). Ref: AM 2-7,Para9.
bo. Applicationofamendmentsdisposalmethod
submitted to UPA Aktiviti/Program/kementerian.
Ref: AM 2-7,Para10.1
bp. LaporanPelupusanAsetAlih(KEW.PA-32) submitted
to UPA Aktiviti/Program/Kementerian.Ref:AM2-
7,Para25.
LOST&WRITE-OFFOFASSET
bq. Lost of asset reported to Ketua Jabatan
immediately and Police Report is made
within24hoursofassetlost.Ref:AM2-8,Para4.1.
br. LaporanAwalKehilangan(KEW.PA-33)and Police
Report submitted to Pegawai Pengawal and
Ketua Setiausaha
Perbendaharaanwithin2workingdays.Ref:AM2-
8,Para4.2.
bs. Pegawai Pengawal appointing the Investigating
Committee by using Surat Perlantikan
Jawatankuasa Penyiasat
KehilanganAsetAlih(KEW.PA-34)within2 weeks
from the date of KEW.PA-33
beingsigned.Ref:AM2-8,Para4.3.
bt. Members of Investigating Committee made up of
officer which not involved with the lost
ofassetandnotfromthesameunit.Ref:AM2-
8,Para4.3
bu. InvestigatingCommitteeconsistedof:
(1) YDP-KumpulanP&P.
(2) Members–2xOfficer.
Ref:AM2-8,Para4.3.
bv. InvestigatingCommitteesubmittedLaporan Akhir
Kehilangan Aset Kerajaan (KEW.PA- 35) to
Urusetia Kehilangan & Hapus Kira (UPA
Aktiviti/Program/Kementerian) within one month
from the date of appointment.
Ref:AM2-8,Para 4.4.1.
bw. KEW.PA-
35submittedtoKuasaMeluluswithin2monthsfromthe
dateofKEW.PA-33 prepared.
Ref: AM 2-8,Para 4.4.4.
bx. KEW.PA-3&4forwrite-offassetisupdated.
Ref:AM2-8,Para4.5.
by. Sijil Hapus Kira Aset Alih (KEW.PA-36) is
producedwithinonemonthfromthedateofKuasaMelul
us.Ref:AM2-8,Para4.5.2.
5.6 – 33 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
bz. SurchargerecommendationsenttoPihak
BerkuasaTatatertibKementerian within3
monthsfromthedateofapprovalletterbyMalaysia
nTreasury.Ref:AM2-8,Para4.5.3.
ca. DecisionofPihakBerkuasaTatatertib
regardingthesurchargerecommendationis informed
to Malaysian Treasury within 6
monthsfromthedateofapprovalletterbyMalaysianTre
asury.Ref:AM2-8,Para4.5.4.
cb. LaporanHapusKiraAsetALIH(KEW.PA-37)
submitted to UPA Aktiviti/Program/Kementerian.
Ref: AM 2-8,Para6.
MANAGEMENTOFSTORE
cc. StorecategoryatPTJ&PusatKosisspecified.
cd. PegawaiStorisappointendinwrittenbyKetuaJabatan.
Ref:AM1-1Lampiran C.
ce. Officer in-charge in acceptance is appointed in
written by Ketua Jabatan which is
responsibleforacceptanceandinspectionto the
asset.Acceptance for technical asset must be
done by officer who have
expertiseonrelatedfield.Ref:AM6-2,Para 2.
cf. LaporanKedudukanStok(KEW.PS-14)is submitted
to UPA Aktiviti/Program/Kementerian for
everyquarteryear.Ref:AM6-4,Para10.1/10.2.
RECEIVING(STORE)
cg. BorangTerimaanBarang-Barang(KEW.PS-
1)practiceisadhered.Ref:AM6-2,Para 3.4.4.
ch. BorangPenolakanBarang-Barang
(KEW.PS-2)practiceforrejectionisadhered:
1.1xcopyforsupplier.
2.1xcopyforstore
Ref:AM6-2,Para3.4.5.
ci. AcceptanceofChemicalorflammablegoods is
directly stored to the respective storage.
Ref:AM6-2,Para10.
STOCKRECORDING(STORE)
cj. Allstockreceivedrecordedcorrectlyandcompletely
byusingKadDaftar(KEW.PS-3).
Ref: AM 6-3, Para 4.
ck. Allstockisrecordedwithin2weeksfromthedateofre
ceiving.Ref:AM6.3,Para2.
cl. KEW.PS-
4waspracticedforthestockhasanexpirydate. Ref:
AM 6.3, Para 6.4.
cm. SenaraiKadDaftarStok(KEW.PS-4)available.
STORAGEOFASSET
cn. All original packing (box, tin and etc) is
remainasreceivedandthelabelisvisible.
5.6 – 34 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
5.6 – 35 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
dg. BorangPenilaianPrestasiPengurusanStor(KEW.PS-
11)isavailable.Ref:AM6-6,Para 5.6.
dh. KEW.PS-
10&11submittedtoUPAAktiviti/Program/Kementeria
n.Ref:AM6-6, Para 5.7.
di. Sijil Verifikasi Stor (KEW.PS-12) and Laporan
Verifikasi Stor (KEW.PS-13) is
preparedandsubmittedtoKetuaJabatanforverificati
on.
Ref:AM6-6,Para6.4.
dj. Stock adjustment is performed as per stipulated
procedure by using Penyata
PelarasanStock(KEW.PS-15)andsentto Ketua
Jabatan for approval. Ref: AM6-6,Para7.2
Perakuan Ambil Alih (KEW.PS-16) is
dk
performedwithin2weeksfromthedateofHOTO.
Ref:AM6-6,Para 8.1.
DISPOSALOFSTOCK
dl. Lembaga Pemeriksa Pelupusan (LPP) is
appointedbyPegawaiPengawal/Pengerusi JKPAK
Kementerian using Surat Lantikan Lembaga
Pemeriksaan Pelupusan Stok(KEW.PS-19).
Ref:AM6-9,Para 4.1.
dm. LPP declared the stock condition and
recommendedthemethodofdisposalwith justification
using Borang Pelupusan Stok(KEW.PS-
20).Ref:AM6-9,Para4.4.5.
dn. KEW.PS-
20submittedtoUPAAktiviti/Program/Kementerian.
Ref:AM6-9, Para 5.1/5.2/5.5.
do. Sijil Pelupusan Stok (KEW.PS-22) is available
and submitted to
UPAAktiviti/Program/Kementerian.Ref:AM6-
9,Para6.5.
dp. SijilPenyaksianPemusnahanStok(KEW.PS-
21)isavailable. Ref: AM 6.9, Para 6.5.4.
dq. Disposalprogrammustbeconductedwithin 6
months from the date of approval letter.
Ref:AM6-9,Para7-10.
dr. LaporanPelupusanStock(KEW.PS-31)is
preparedandsubmittedtu UPA
Aktiviti/Program/Kementerianbefore15Febnextyear.
Ref:AM6-9,Para24.2.
LOSTANDWRITE-OFFSTOCK
ds. LostofassetreportedtoKetuaJabatanimmediately
and Police Report is made
within24hoursofassetlost.
Ref:AM6-10, Para 4.1.1 & 4.1.2.
dt. LaporanAwalKehilangan(KEW.PA- 32)and Police
Report submitted to Pegawai Pengawal and Ketua
Setiausaha
Perbendaharaanwithin2workingdays.Ref:AM6-
5.6 – 36 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
PARTN–CORE:LPO
IsLPOproceduresadhered?
27. Ref:PU4303and1PP and PK 2.1.
a. Authorization letter from the Base
CO/CommandanttoKCMtocarryouttheGovernment
Acquisition/Order.
b. Samplesoftheauthorisedsignaturesoftheofficers
dealing in the acquisition sent to
StateJANorAKPbyusingKEW2/290form.
c. Marketsurveyscarryout. Refer: AP 169.
d. JawatankuasaPembelianTeruswhichis chaired by
Base CO/ Commandant
establishedatPusatTanggungJawab(PTJ).
Refer: ABK 1/2023.
e. JawatankuasaSebuthargaestablishedatPTJ. Refer:
PK 2.9.
f. MaintenanceworksapprovedbytheBaseCO/Comma
ndant. Refer: ABK 1/2023.
g. ProcurementprogrampreparedbyPTJ.
Refer: PK 2.1 (1 (i)).
h. AreDirectLocalPurchasearrangementsand
Quotation A and B being adhered
andrecordedproperly?Ref:AP 169(D) PK 5.1.
i. Is the EDD recorded in Local Orders
accordingtotheperiodstipulatedbytheJPT and
Jawatankuasa Sebutharga complied by
contractor, supplier, service and works?
Ref:PK 5.1 Lampiran 6-3.
j. IsthepurchasedetailonLocalOrdersand invoices
specific?Ref:AP176.1, AP 169 D.
k. IssupplyprocurementkeyedinSPKB?
Ref:AP102(a), PU 4301 Bhg 2 Sek 1.
l. IstheassetsBOCwithin2weeksfromthe date of
received?Ref:PPP, AM2.3
(1.1.4)TatacaraPengurusan Aset Alih –
Pendaftaran.
m. Istheassetlabelledwith“HakKerajaan
Malaysia”?
Ref:1PPAM2.3Perenggan9.10– Pelabelan Aset.
n. Isthereapecahkecilinpurchasing?
Ref:PK2.1(ii), (iii).
o. IstheSebutHargaAprocessimplemented
online?Ref:PK2para7(iii), PK 5.1 (3).
p. IsSebutHargaAprocurementexecuted by
JawatankuasaPenilaianTeknikaldan Jawatankuasa
Penilaian Harga?
Ref:PK2para7(iii), PK 2.9 & PK 5.1.
q. IsthememberoftheQuotationCommittee
asauthorised?
5.6 – 37 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
r.IsthedateoftheDeliveryNoterecorded by
receivingofficer?Ref:PK 5.1 Lampiran 6 (B.1.7).
s. Isthereceivedofgoodsdonebythe
appointedofficer?Ref:AM2.2TatacaraPengurusanA
set Alih Kerajaan – Penerimaan & PK 5.1.
t. Istheactiontakenonalatedeliveryby
thecontractor?Ref:1PPPK8Para1(i)(b)(7) (i).
u. IstheDirectPurchaseawardedtoonlyone
particularsupplier?Ref:1PP–PK2.16(i).
v. DoestheIn-houseContractadhereto the
stipulatedrules?i.e.contractagreement, quotation
from supplier.Ref:1PP–PK2.1Bab 5.
FINANCE MANAGEMENT
PARTO–ROUTINE:FINANCE CONTROL
28. Isfinancialmanagementproceduresadhered?
Ref:PU4303and1PP.
a. Jawatankuasa Pengurusan Kewangan dan
Akaun (JPKA) established at PTJ and
financialmeetingcarriedoutatleastonceinevery3mo
nths. Ref: PS 5.1 (4).
b. Allocation received properly recorded?
(WarenPeruntukanAm,WarenPeruntukanLuar,Siji
lPengesahanPeruntukan).
c. BukuVotadequatelymaintainedandeverytransaction
endorsedbytheFinanceOfficer.
d. BillRegisterproperlymaintained. Ref: AP 103.
e. FinancialMonthlyReturnandOutstandingPaymentSt
atementforwardedtohigher authority every month.
f. MaintenanceworksbelowRM50,000approvedbyBas
e/Komandan. PK 7.8 Para 2.2.4.
g. Contractlistandacopyofthecurrentcontract.
h. IstheRegistrationandPaymentRecordusingthecorre
ctExpenditureCode? Ref: AP 41.1 PP PS 1.1.
i. Aretherepurchasesvialocalorders
recordedinGPIS?Ref:1PP– PK 5.2 Bil 6 Para 6-3
j. Isthereanyprocumentthatdonotcomply
withtheTreasuryCircular(1PP)andthe specified
rules?Ref:1PP,AP,PU.
k. IstheBukuVotcheckedeverymonth?
Ref:AP95 (e).
l. IstheBukuVotprintedattheendof
themonthbythecustodian? Ref: AP 95 (e).
m. Isthepaymentcertificateauthoritylimitas
authorisedintheAP101?
Ref:AP101,SPANMBil1-2008.
n. IstheDepositListavailable,complete,updatedandrevi
ewedbythesupervisor? Ref: AP 156.
o. IsPanjarWangRuncitupdateddaily?
Ref:AP97,AP113(d).
5.6 – 38 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
IsFinanceManagementControlbeingpracticeefficientlytoachievetheobjectivethathas been
29.
set?Ref:PU4303and 1PP.
a. Organizationchartpreparedcompletelyandupdated.
Ref:PKPA4-2018para4(i).
b. Allofficersinvolvedinfinancialmanagement is
authorized by Pegawai Pengawal and updated
when changers occur. (Updated
inAP11andiGFMASSystem.Ref: AP11.
c. Peraku II dilaksanakan mengikut penetapan yang
digariskan.
Rujuk: MTU.PTU.900-4(07) bth 17 Jun 23.
d. AllrecordsandfilesregardingPenurunanKuasamustb
ekeepproperly.Ref:AP101.
e. Jawatankuasa Pengurusan Kewangan dan
Akaun (JPKA) established at PTJ as stated
inPekelilingandJPKAmeetingatPTJmust be
carried out before meeting at Programs
levelsevery3months.Ref:AP95(e).
f. MinutesofJPKAmeetingmustbeprepared
including5elementsasstatedinPekeliling. Ref:PS5-
1andJPKAreportsmustbe prepare, properly filing
and sent to the
Programfollowbygivendates.Ref:PS5-1.
g. Allauditfilesmustbeproperlypreparedandtheauditfee
dbackisansweredwithinone month.
Ref: AP 306.
PARTP–ROUTINE:BUDGETTINGCONTROL
Didthebudgetingisdistributedbaseonpriority,operationalcontrolandtomanagedthebaseexpen
30. sesperformanceproperly?Ref:PB1-1.
a. Rancangan Perbelanjaan (RP) is prepared
usingtheinputfromPusatKos,andtheRPdocumentisfil
ingproperly.Ref:PB1-1.
b. Allocationreceivedproperlyrecorded?(WPA,WPKan
dWPP)Ref:PB1-1,Para4.1.
c. VirementWarrant(WPP)ofOperatingexpensesisappr
ovedbyPegawaiPengawal or authorize
representative in writing or treasury approval.
Ref: PB 2-6, Para 1.1.
d. WPKwhichissuedbyPTJmusthaveapproval from
Pengurus Program or
appointedofficerbyPegawaiPengawal(Mej Gen and
above/Jusa C) for the approved purposes only.
Ref: SAK 2-2013.
e. NewpolicyWarrant/One-
Offisspentfortheapplicationpurposeonly.Ref:SAK9-
2-2012.
f. MonthlySpendingPerformanceReportissubmittedtot
hePengurusProgram/Aktiviti before or on 10thof the
next month.
Ref: Arahan Pegawai Pengawal B60.
PARTQ–ROUTINE:RECEIVINGCONTROL
Didthepaymentcollectionproperlyrecordedandadheredtoprocedure?
31. Ref:AP66,67&68.
CONTROLLINGBORANGHASIL
5.6 – 39 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
a. CollectorhavetomaintainallBorangHasil (Kew.
67) and every transaction of stock issuance
need to be signed by the officer and Borang
Hasil (Kew.68) must be keptsafely.Ref:AP 67.
b. All official receipt and coupon received must
becheckedandverifycorrectlyregardingtheserialnu
mberandsignedatthebacksheet of the first office
copy. Ref: AP 66(a).
c. Kew 38 & 38e (receipt book) issued by
sequenceserialnumbercorrectly.Ref:AP 66(c).
d. All Borang Hasil which still in stock and
currentlyusemustbesafelykept.Ref:AP68.
e. StatementofBorangHasil(LampiranN)is
preparedwhenexchangeofcollector.Ref:AP66A.
AUTHORIZATIONOFRECEIVINGPAYMENT Ref: AP
69, SPANM 6-2018 & Perkara 97 Perlembagaan
Persekutuan.
f. All officer who received money in any terms
ofreceivingmustgetwrittenapprovalbythe Pegawai
Pengawal (KSU).
Ref:AP69/SPANM6-2018.
g. Form of Special appointment available
(LampiranB1-B8).Ref:SPANM6-2018.
h. Form of Special Appointment must be
updatedinwrittenwhenexchangeofofficer occurs.
Ref: SPANM 6-2018.
i. Role and access in IGFMAS/Sistem
TerimaanPTJmustbeinlinewiththe special
appointment in written.Ref:AP69/SPANM6-2018.
j. AllrevenueisaccountedintheKumpulan Wang
Disatukan.
Ref:Perkara97PerlembagaanPersekutuan.
k. Allrevenuethatcollectedisbasedonthe
allowable/approved rate.
Ref:AktaFi1951(Akta209)/WP10-1.
l. Allrevenuemustbeaccountedusingthe right Kod
Hasil. Ref: PS 1-1.
SECURITYPRACTICEDURINGCOLLECTION
m. Noticeofrequestingreceiptsafterpaymentforciviliandi
splayedaplacethateasytosee.
Ref: AP 61.
n. Segregation of duty for issuing receipt,
recordingofcollection,checkingandrecordincashboo
kisproperlypractice.Ref:AP 11(a).
o. AvailabilityofSecurityandinternalcontrol features for
online receiving transaction:
(1) Receivingcode.
(2) Dateandtimeoftransaction.
(3) Operatorcode.
(4) Machinecode.
(5) Listofofficialreceiptnumber.
(6) Listofcancelledreceipt.
Ref: AP 63(b)
CANCELLATIONOFRECEIPT
5.6 – 40 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
p. Allamendedreceiptmustbecancelled.
Ref: AP 62(a).
q. The cancelled receipt with copy were
preparedduringauditingprocess.Ref:AP 62(a).
r. Official receipt must be cancelled by
authorizedofficer(inwritten).Ref:AP62(b).
CASHCOLLECTIONINTOBANK
Ref:AP78/AP126.
s. CashcollectionoverRM500oraccumulated collection
over RM2000 (inclusive cash, cheque, postal note
and etc) must be
transferredtothebankatthesamedayorat least next
working days. Ref: AP 78.
t. Collectionbychequetransferredtothebank not more
than 1 week from the date of receiving the cheque.
Ref: AP 78.
u. Collection which is not transferred to the
bankafterreceivingmustbekeptinsafebox or vault.
Ref: AP 126.
PREPARATIONOFCOLLECTORSTATEMENT
v. AllCollectionwhichtransfertothebankmust
be tally with the Collector Statement and
recordedincashbook/ onlinecashbookat
thesamedate.Ref:AP79 (a)/ (b).
w. Collectorstatementcancelledbyauthorizedofficerapp
ointedbyPegawaiPengawalin written.
Ref: SPANM 6-2018.
RECEVINGACCOUNT/REVENUE-
BOUNCECHEQUE(AP 76).
x. RegisterofBounceChequeisavailableandupdated.R
ef:AP76(b).
y. Bouncechequewasreplacedoractionedaccordingly.
Ref:AP76(b).
z. ListofunsettledBounceChequebeing
prepared and submitted to Pegawai
Pengawalattheendofeachyear.Ref:AP76(b).
AKAUNBELUMTERIMA(ABT).AB89A.
aa. PTJismaintainedAkaunBelumTerima(ABT)complete
lyandupdated.Ref:AP89A.
ab. StatementofAkaunBelumTerima(ABT)mustbesubmi
ttedtoAccountDepartmentat the stipulated period of
time. Ref: AB 89A.
ac. AnyOutstandingbillandbaddebtwereactionedbyPTJ.
Ref:AP 328.
PARTR–ROUTINE:PROCUREMENTMANAGEMENT
IsProcurementManagementproceduresadhered?
32. Ref:PU4303and1PP,PK2-1.
a. RancanganPerbelanjaan(RP)isprepared and
submit to Finance Department
before15thDecemberyears.Ref:PK2-1 para 1(i).
b. Penyelia GPIS is appointed by Ketua
Jabatan/PengurusPTJandallcategoriesof
procurement is registered correctly in thesystem.
Ref:PK 5.2 para 6 (6-2) (ii).
5.6 – 41 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
(1) Procurementorcontractwhich:
(a) RM50,000toRM100,000-bumiputera
supplier only.
(b) RM100,000toRM500,000–open
supplier.
(2) Consist at least 5 local suppliers (Perolehan
Kerja) that meet the criteria which registered
with FinanceMinistry.Invitationnoticeisopenat
least 7 days.
(3) Pegawai Pengawal appointed the
JawatankuasaSebutHargawhichconsistat
least 3 officers.
(4) KetuaJabatan/PengurusPTJappointed the
Specification Committee consist of:
(a) Chairman.
(b) 2xmembers.
(5) AppointingofsecretaryforSpecification
Committee – non committee.
(6) PTJappointedtheJawatankuasa
Pembuka Sebut Harga consist of:
(a) Chairman.
(b) 2xmembers.
(7) AppointingofsecretaryforJawatankuasa
Pembuka/ Penilaian – non committee.
(8) EvaluationofSebutHargaconductina level of
Evaluation Committee.
(9) KetuaJabatan/PengurusPTJappointed the
Evaluation Technical and Finance Committee
consist of:
(a) Chairman.
(b) 2xmembers.
5.6 – 42 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
(10) AppointingofsecretaryforEvaluation
Committee – non committee.
(11) LetterofIntentispreparedwithin3days after
approval and feedback from suppliers not
more than 5 days.
(12) Pricesurveysisprepared.
(13) All discussion and results of
JawatankuasaSebuthargarecordedinthe
minutes and signed by Chairman and
committee.
(14) Feedbackforacceptanceofsupplier must
be 7 days after date of SST.
(15) Integritypackpracticesadhered.
Ref:PK2-1,Para7,PK5-1Para5.1.3(b)(iv) ,
PK 2.9.
i. AreDirectLocalPurchasearrangementsandQuotatio
nAandBbeingadheredand recorded properly? Ref:
AP 176.1.
PARTS–ROUTINE:EXPENDITURECONTROL
Isfinancialcontrolproceduresadhered?
33. Ref:PU4303andPS 5.1.
a. Jawatankuasa Pengurusan Kewangan dan
Akaun (JPKA) established at PTJ and
financialmeetingcarriedoutatleastonceinevery3mo
nths.
b. Allocation received properly recorded?
(WarenPeruntukanAm,WarenPeruntukanLuar,Siji
lPengesahanPeruntukan).
c. Laporan Kedudukan Vot/dana (electronic)
adequately generate (softcopy), check, and print
(hardcopy) on 1stworking day in the
followingmonth.Everytransactionendorsed by the
Officer (sign,name,post and date ofchecking).
Ref:AP95(e).
d. Sijil Pengesahan Baki Vot need to be prepared
and forward to Accounting Office (AO) within 14
working days in the following month.
Ref:LampiranI,Para2.7.4,LampiranI-2,LampiranI-
3.
e. The officers stated in the AP11 is the same officers
that stated in the Borang Capaian
PenggunadanHadKuasaPTJiGFMASand the limit
of payment is same for both (AP11 and iGFMAS
system). If any changes of officers, PTJ must
forward it to AO.
Ref:SPANM6-2018/LampiranA,Para2.1/3.2.1.
f. Peraku I and II is a different officer followed by
seniority and it depends on 7 levels of
HadKuasaMemperaku(HKP).
5.6 – 43 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
5.6 – 44 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
5.6 – 46 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
d. Allocationreceivedproperlyrecorded?(Sijil
Peruntukan Komitmen).
Iscontractorizationproceduresadhered?
35. Ref:ArahanPerlaksanaanKonraktorisasi-MPBU–R&P.
a. IstheEDDrecordedinAM75accordingto the period
stipulated by the JKTEK and
JKRHcompliedbycontractor?
Ref:PekelilingPerbendaharaanMalaysiaKP 8/2013.
b. Istheactiontakenonalatedeliveryby the
contractor?
Ref:1PP,PK8Para1(i)(b)(7)(i).
PARTU–CORE:STOCK TAKING
b. BarrackStore.
c. ClothingStore.
d. RadarStore.
e. SpecialtoAirStore.
f. StationeryStore.
g. RationStore.
h. POLStore.
i. V&AStore.
j. ExplosiveStore.
PARTV–CORE:BFI/FUELSTATION
Ref:PU4101,PU4306 2nd EditionandSATM14.
5.6 – 47 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
PARTW–CORE:AIRMOVEMENT
ArefileanddocumentregistrationatAirMovementSectionwellmaintained?
39. Ref:PU4304 2nd Edition.
a. Passenger list registration.
PARTX–CORE:DOCUMENTATION,ASSETANDACCOUNTINGOF'B'VEHICLE
Documentation,assetandaccountingof'B'vehicleareproperlymanaged.
40.
Vehicle Register Document (BAT N 2) Report sent
a. to MTU-Khidmat Materiel and MTU- Perolehan
twice a year?
Ref: PU 4305 2nd Edition Part 3 Sec 5 and 6.
b. Driver Standing Order signed by drivers?
Ref: PU 4305 2nd Edition Part 2 Sec 4.
c. SMP 11 and SMP 13 submitted to respective
department monthly and yearly?
Ref: PU 4305 2nd Edition Part 5 Sec 6.
d. e BAT J 6 properly recorded, maintained and
updated in BAT L 93?
Ref: PU 4305 2nd Edition Part 3 Sec 17.
e Movementofvehiclerecordedandupdatedin
BATL91.
Operation,ServicingandAdministrationBoardmaintai
f. nedandupdated.
Ref: PU 4305 2nd EditionPart 1 Sec 3.
g. Fuelconsumptionratescomparedtotraveldistanceas
perguidelinegiven. Ref: PAAT.
h. Fillingoffuelexceedstankcapacity.
Ref:PATMJILIII.
5.6 – 48 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
i. KadPetakoneveryvehiclesparepartsrackavailableat
FAMTOstore. Ref: 1 PP WP 4.1.
j. BATM59forBvehicleavailable,maintained
andupdated.Ref:PU43052nd EditionPart3Sec9.
Vehicleaccessoryandtoollist(TUB20-
k. 00017)available,maintainedandupdated. Ref: PU
4305 2nd EditionPart 3 Sec 13.
PARTY–ROUTINE:DOCUMENTATION,ASSETANDACCOUNTINGOF'B'VEHICLE
Movementofvehicleadheredtoprocedure.
41.
Ref:PU43052nd EditionPart3Sec14,PATMJilIII.
a. Everyvehiclemovementauthorizedbythe
appropriate authority.
Ref:PU43052nd EditionPart3Sec 14.
b. Traveldistancebetweenresidencetoplaceofdutydidn
otexceedspermittedlimit. Ref: PATM JIL III.
c. Useoffuelforunofficialtravelpaid back.
Ref:PATMJIL III.
WorkTicket(BATJ7)maintainedandupdated?
42.
Ref:PU43052nd EditionPart3Sec8.
a. Keptinsafe place.
b. BukuDaftarPengeluaranavailable andupdated.
c. Closedaccordingly(every month).
d. Surcharge applied.
e. Fuelconsumptioncalculationrecorded
inDaftarBulananBahanapiKenderaan(BATM 3051).
DrivingLicenseATM(BATD41)manageaccordingly.
43.
Ref:PU43052nd EditionPart3Sec11andPU4305 2nd EditionPart3Sec15
a. Keptinsafe place.
b. BATD41recordavailable,maintained and
updated?
c. Applicationdocumentproperly kept.
d. BATD41convertedtoJPJL6 Application
Folder available?
Ref:PU4305 2nd Edition Part3Sec 18.
e. PersonnelDrivingLicense(BATD41) and
AirfieldDrivingPermit(BATB3017) available and
valid.Ref:PU4305 2nd Edition
Part3Sec11andPU 4305 2nd Edition Part3Sec
15.
SmartPaymanagementadheredto procedure?
44.
Ref: Arahan Pematuhan pengawalan penggunaan Smart pay and PU 4305 2nd Edition
Part 3 Sec 20.
a. Smartpayholderrecordavailableand updated.
b. HOTOsmartpayrecordavailable and
updated.
5.6 – 49 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
c. Smartpayusagerecordavailable and
updated.
FuelusagerecordandPetronas fuel
d. statementsubmittedtoMPOU-A4(Sel Bahan Api)
monthly.
Trafficsummonspaidby personnel.
45.
Ref:PU4305 2nd Edition Part2Sec 4.
Vehicleaccidentproceduresproperlymanaged.
46.
Ref:PU43052nd EditionPart2Sec 11.
a. Accidentfileavailableand updated.
b. Registerbookforkawat/utusan
(KEJARA)maintainedand updated.
c. BATD42availableand updated.
PENGURUSANKENDERAANKERAJAAN(KEWANGAN)
SMART TAG AND TOUCH & GO CARD CONTROL
47.
Ref: PU 4305 2nd Edition Part 3 Sec 19.
a. TouchNGoCardiscontrolintherecordof procurement
list and distribution.
b. SmartTagCardisrecordedasAsetAlihBernilai
Rendah Kerajaan.
c. TouchandGoandSmartTagRecordis
maintainedandupdateasperstipulated procedure.
d. SmartTagCardHandingOvertoMTOafter tasking
completed.
e. Monthly usage of fuel must be calculated and
analyzeevery6monthlyandyearlybyHead Of
Department as per format stipulated.
48. KENDERAANRASMIJAWATAN
a. KadIndenMinyak,Touch&Gocardsandsmart tags
kept by the officer responsiblewhich maximum
value does not exceed RM 500 per month.
b. Maximumusage(exeedRM 500)mustbepaidby the
owner of the card.
49. VEHICLECARDMANAGEMENT
a. Anylossofcards:
(1) KadIndenMinyak.
(2) Touch&Go Card.
(3) SmartTag.
MustbereportedtoMTOforreplacement/ identify the
credit balanced.
b. RespectiveOfficerisresponsibleofreplacement of
loss card due to carelessness.
PARTZ–CORE:AGSE/ AGSV/ DOMESTICVEHICLE/ APDOCUMENTATION
AretheRMAFSTATSmaintainregularlyandsenttorespectivedepartment?(SPKB)
50. Ref:PU2201Part13& 14.
5.6 – 50 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
a. MonthlySTATS51-MonthlyReturnofClass
1&2AGSE.
b. MonthlySTATS61-MonthlyReturnofAGSV.
ArethefollowingdocumentsmaintainedandupdatedatTPPS?
51.
BAT M 35 – Penyata Pemeriksaan Kenderaan ‘B’.
a. Ref:PU4305 2nd Edition
Part5Sect2/PU2205Part1Risalah 2.
b. BAT M 59 – Buku Rekod Kenderaan Domestik.
Ref:PU4305 2nd Edition Part3Sect9/PU2205Part 1
Risalah 2.
c. BAT M 61 – Pemeriksaan Teknikal Kenderaan
Jenis “B” (UTI).
Ref:PU43052nd Edition Part5Sect 1.
d. BAT M 430 - Buku Rekod Alatan Pelbagai
Ref: PU 2205 Part 1 Leaflet 8.
e. WorkScope–forContractorRepair only.
Ref:PU2205Pt1Lt 2.
f. PDI/TDIForm–PreDeliveryInspection Form / Tear
Down Inspection Form for contractor repair only.
Ref:PU2205Pt1Lt 2.
52. ArethefollowingservicingdocumentsmaintainedandupdatedatFLAITBANTUAN?
a. BAT M 3015 – Rekod Serah Menyerah dan
Pemeriksaan Harian Kenderaan Khas dan
AlatBantuanUdaraKelas1(Pindaan01/19).
Ref:PU2302Sect5Leaflet3/PU2205Part 1Leaflet12.
b. BATM3093-RecordofServicingClassII.
c. BATM3114–DokumenRawatan
KenderaanKhasDanAlatBantuanUdara Kelas 1
(Pindaan 03/07).Ref:PU2205Part1Leaflet3.
d. BATM3115–JobCard.PU
Ref:2205Part1Leaflet11.
e. BATM430-BukuRekodAlatanPelbagai
Ref:PU2205Part1Leaflet8.
f. PDI/TDIForm–PreDeliveryInspection
Form/TearDownInspectionFormfor contractor
repair only. Ref:PU2205Pt1Lt1.
53. Arethefollowingdocumentsavailableandupdated?
a. KEW.PA-19-PerakuanPelupusan(PEP)
AsetAlihKerajaan–Rujuk:PU2302Sect5 Lt 9
b. KEW.PA-10-BorangAduanKerosakanAset Alih-
Rujuk: PU 2302 Sect 5 Lt 8
c. ScrapControlBook,BATM3020–Scrap Label. For
items ‘Class C’.
d. ServicingandrepairWork Scope.
e. JK Tek/JTP/JPT (Jawatankuasa
Teknikal/Jawatankuasa Tapisan
Perolehan/Jawatankuasa Perolehan Terus).
5.6 – 51 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
PARTABCORE:EXPLOSIVEORDNANCEMANAGEMENT
DoestheunitrecordedandupdatedallEOloanregisterform?
55. Ref:PU2204Bhg1Ris4andPU4309Sec5Chapter6.
a. TUB20-0280EOMagazineLoanBook (LongTerm)
b. TUB20-0295EOMagazineLoanBook.
b. TUB20-0281ExplosiveOrdnanceStock
RecordSheet.
c. TUB20-0282ExplosiveOrdnanceBinStockCard.
d. TUB20-0283ExplosiveOrdnanceStackCard
e. SPKB-EOAccounting.
f. IssuingofEOtallywithArahanPengeluaran (AP)from
MPBU.
Arethesafecustodyexplosiveordnanceproceduresbeingfollowed?
59.
Ref:PU2204Bhg1Ris11andPU4309Sec3Chapter4.
a. Authorityforstoragesafecustody EO.
Arethereturnedemptycases/ cartridgecasesproceduresbeingfollowed?
60.
Ref:PU2204Part1Leaflet9andLeaflet10Para8.
a. Knocked.
5.6 – 52 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
b. Packedwithsuitable container.
c. Indicate weight.
d. Notmixwithlinksornon-brass material.
e. Certifiedfreefrom explosive.
f. Thesamepersonnelwhodemandthe ammo
shouldbereturned it.
TOTAL
MANAGEMENT
NOT
NOOFQUESTION COMPLIANCE NONCOMPLIANCE
AUDITED
60
SECTION4:OTHEROBSERVATIONS
ADDITIONALOBSERVATION(ISSUETHATARENOTCOVEREDINTHECHECK-LIST)
(This part permits the auditor to highlight issues that are significantly important to be brought to the
attention of the respective authority. This part may also be used to highlight any non-compliance to
current orders and instructions that are not included in this checklists).
1.
2.
3.
4.
5.
SECTION5:OVERALLSTATISTICS
LOCATION:
NO OF NON NOT
COMPLIANCE
QUESTION COMPLIANCE AUDITED
SAFETY 57
READINESS 38
MANAGEMENT 60
5.6 – 53 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
REFERENCESUSEDDURINGAUDIT
SER REFERENCES
DasarPerkhidmatanBombaDanMenyelamat TUDM
1. PU1111
PanduanPerkhidmatanBombadanMenyelamat TUDM
2. PU1112
(Pengurusan Aset)
3. PU1204 Base/UnitFireOrders
4. PU4101 ArahanMaterielUdara
5. PU4301 PeraturanMaterielUdara
6. PU4302 PeraturanPenyimpanandanPembungkusan
7. PU4303 PeraturanKewanganTUDM
8. PU43042nd Edition PeraturanPergerakanUdara
9. PU43052nd Edition PengurusandanPentadbiranKenderaanTUDM
10. PU43062nd Edition Peraturan Bahanapi TUDM
11. PU43072nd Edition Pengurusan Rangsum TUDM
12. PU 5310 Manual HANDAU
13. PU 5406 2nd Edition Panduan Pengurusan Pejabat.
14. PU9102 RMAF Logistic Doctrine
15. PU9104-001 Safety Management.
16. PU9104-002 Flight Safety.
17. PU9104-003 GuideLineforOccupationalSafety& Health.
18. PU9203-005 2nd ArahanLatihandanKecekapanMateriel
Edition
19. PU2304 Explosive Regulation
20. PU2205 Arahan Kejuruteraan Bantuan
21. PU2204 Arahan Kejuruteraan Senjata
23. PU2304-003 Explosive RegulationsStorage, Transportation & Inspection of
Explosives
24. PU2304-004 Explosive Ordnance Inspection And Proof Instruction
25. General Regulationsand
PU2304-006
Instructionfo Disposal of Explosive
26. Radio Frequency Hazardto
PU2304-007
Electro Explosives Devices.
27. PU2304-018 Explosive Areaand Danger Building
28. PU 2304-022 Technical Equipment Maintenance Plan (TEMP) – Letupan
29. PU4309 2nd Edition Explosive Ordnance Accounting Procedure
30. PU2304-005 Procedure&RegistersofExplosiveOrdnance Reclassification
31. PU4312 2nd Edition TatacaraPengurusanAsetAlihTUDM
32. PU4313 2nd Edition TatacaraPengurusanStorTUDM
33. PU4315 PeraturanHantaranUdara TUDM
34. PU 4317 RMAF Performance Based Contract (PBC) Handbook
35. PU 4401 Handbook Materiel
36. Perintah Angkatan Tentera (PATJilid III)
37. Dissemination of Higher Authority directives
&Instruction.
38. Arahan MinistryofFinance(MOF)Bil4/2018
Perbendaharaan
39. ManualSATM1 PengurusanStorSenjata
40. ManualSATM2 PengurusanDewanMakanDiKompleksSajian
5.6 – 54 of 55 Interim
RESTRICTED
RESTRICTED PU 9301
3rd Edition
5.6 – 55 of 55 Interim
RESTRICTED